38
THE NEW PARKLAND HOSPITAL Presented by: Chuck Armstrong – Corgan Associates, Inc. Jeff Haber – W&W Glass, LLC A Case Study on the Design-Assist Process for the Structural Glass Façade

The New Parkland Hospital Presentation

Embed Size (px)

DESCRIPTION

Design-Assist Delivery Process for a Structural Glass Facade: The New Parkland Hospital - Jeff Haber of W&W Glass, Chuck Armstrong of Corgan and Mic Patterson of Enclos - Facades+ Dallas 2014

Citation preview

Page 1: The New Parkland Hospital Presentation

THE NEW PARKLAND HOSPITAL

Presented by: Chuck Armstrong – Corgan Associates, Inc. Jeff Haber – W&W Glass, LLC

A Case Study on the Design-Assist Process for the Structural Glass Façade

Page 2: The New Parkland Hospital Presentation

¨  Architect: ¡  HDR & Corgan Associates, Inc. (Joint Venture), Dallas, TX

¨  CM at Risk: ¡  BARA (Joint Venture), Dallas, TX

¨  Structural Glass System: ¡  Pilkington, St. Helens, UK

ú  Manufacturer - Structural Glass Fabrication & Fittings ¡  W&W Glass, LLC, Nanuet, NY

ú  Engineering & Design ¡  Tripyramid Structures, Waterford, MA

ú  Manufacturer - Plate Beams, Tension Rods & Fittings ¡  Harmon, Inc., Lewisville, TX

ú  Installation

Page 3: The New Parkland Hospital Presentation

Video Tour of The New Parkland Hospital

Page 4: The New Parkland Hospital Presentation

¨  In the Beginning…

Page 5: The New Parkland Hospital Presentation
Page 6: The New Parkland Hospital Presentation
Page 7: The New Parkland Hospital Presentation
Page 8: The New Parkland Hospital Presentation

Cable  Wall                    vs.  Tension  Rod/Plate  

Beam  Wall  

Pros   -­‐          Higher  Transparency   -­‐  Less  Load  on  Boundary                Structure  

-­‐          No  Horizontal  Metal   -­‐  Good  Transparency  

-­‐  Less  Expensive  Boundary                Structure  

-­‐  VerAcal  Rods  Smaller  Than  Cables  

Page 9: The New Parkland Hospital Presentation

Cable  Wall                    vs.  Tension  Rod/Plate  

Beam  Wall  

Cons   -­‐  Higher  Loads  on  Boundary  Structure   -­‐  Steel  Blades  May  Block  

View  (Inside  to  Out)  

-­‐  AddiAonal  Steel  Required….$$$  

-­‐  ConnecAons  to  Columns  Visible  

-­‐  Large  ConnecAons  at  Head  and  Sill  

         (If  Exposed  =  $$$;  If    Concealed,  Perimeter              Detailing  Can  Be  Challenging)  

-­‐  IGU  Glass  DeflecAons  Are  Higher,  Requiring              Significant  AddiAonal  Restraint;  Can  Result                  in  Higher  Loads  into  Building  and  Larger              Dia.  Cables  =  $$$  

Page 10: The New Parkland Hospital Presentation

¨  Cable Wall ¡  Reaction Loads

ú  45 Kips Tension per Cable (Tension Load at Head and Sill) ­  1” Stainless Steel Cables

¡  Steel Sizing at Head ú  W24 x162

¨  Tension Rod/Plate Beam Wall ¡  Reaction Loads

ú  4 Kips – Dead Load ­  3/8” Stainless Steel Rods

ú  3.7 Kips per Plate Beam (7.4 Kips per Column @ 30’ O.C.) – Wind Load ­  ¾” x 10” Plate Beams

¡  Steel Sizing at Head ú  W16x57 - Savings of 16,650 Pounds of Steel!

Page 11: The New Parkland Hospital Presentation

Architect

+ Structural Engineer + Façade Contractor

Affordable Solution to Meet the

Design Intent and Satisfy the Budget

Page 12: The New Parkland Hospital Presentation
Page 13: The New Parkland Hospital Presentation
Page 14: The New Parkland Hospital Presentation

¨  Desired Performance: ¡  VLT: 0.50 ¡  Rf: 0.10 ¡  SHGC: 0.28 ¡  SC: 0.32 ¡  U-Value: 0.24/0.26 (Summer/Winter)

¨  IGU Lami was requested for Acoustics & Safety

Page 15: The New Parkland Hospital Presentation

¨  Meeting the architect’s design intent while satisfying the Owner’s budget restraints.

¨  Looking for cost reductions in the boundary structure as a result of modifications to the glazing system.

¨  Finding an IGU/spacer that was capable of meeting the aesthetic requirement of a 5’ x 9’ panel with only four corner support.

Page 16: The New Parkland Hospital Presentation
Page 17: The New Parkland Hospital Presentation
Page 18: The New Parkland Hospital Presentation

¨  Approx. $100,000 reduction in steel costs!

¨  Additional savings

from decrease in concrete reinforcement in the floor and columns.

Cable Wall

Plate Beam Wall

6” Narrower Beam

8.5” Shorter Beam

Page 19: The New Parkland Hospital Presentation

DESIGN CRITERIA

   9 ft span

   20 psf wind load

Edge  Defl.  

Limit   Req’d  Glass  Thickness   Glass  Cost    Increase  

L/175   3/8”  -­‐  Air  -­‐  3/8”  -­‐  SGP  -­‐  3/8”   +  50%  L/140   3/8”  -­‐  Air  -­‐  3/8”  -­‐  SGP  -­‐  5/16”       +  43%  L/100   3/8”  -­‐  Air  -­‐  5/16”  -­‐  SGP  -­‐  5/16”   +  35%  L/50   3/8”  -­‐  Air  -­‐  1/2”   -­‐  

Page 20: The New Parkland Hospital Presentation

  Surface 1: Contracts

  Surface 2: Stretches

Page 21: The New Parkland Hospital Presentation

Typical IGU Construction

PIB Seal Degradation

Page 22: The New Parkland Hospital Presentation

PIB Seal Failure PIB Seal Degradation

Page 23: The New Parkland Hospital Presentation

¨  Typical insulating unit manufacturers allow L/175 edge deflection. Some of the highest quality manufacturers allow a maximum IGU edge deflection of L/140.

¨  IGU Lami Glass Make-up:

¡  3/8” Optiwhite w/ HP 50/27 low-e on #2 – 5/8” Air – 1/4” Optiwhite – .060” PVB – 1/4” Optiwhite

¨  Only Pilkington could provide an IGU that could deflect + 2” and - 2” at the edges and still remain completely sealed without failure. This equals L/50.

Edge  Defl.  Limit   Req’d  Glass  Thickness  @  5’  Wide  x  9’  Tall   Glass  Cost    Increase   DeflecFon  

L/175   3/8”  -­‐  Air  -­‐  3/8”  -­‐  SGP  -­‐  3/8”   +  50%   0.62”  L/140   3/8”  -­‐  Air  -­‐  3/8”  -­‐  PVB  -­‐  3/8”     +  45%   0.77”  L/100   3/8”  -­‐  Air  -­‐  5/16”  -­‐  SGP  -­‐  5/16”       +  35%   1.08”  L/50   3/8”  -­‐  Air  -­‐    1/4”  -­‐  PVB  -­‐  1/4”   -­‐   2.2”  

Page 24: The New Parkland Hospital Presentation
Page 25: The New Parkland Hospital Presentation

7’ x 14’ Panels Deflect Up to 4” In and 4” Out!!!

Centre Square Deflection Video

Page 26: The New Parkland Hospital Presentation
Page 27: The New Parkland Hospital Presentation

5’2” x 7’5” Panels Deflect Up to 4 5/8” In / 4 5/8” Out!!!

City Creek Center Deflection Video

Page 28: The New Parkland Hospital Presentation

¨  The Pilkington Planar IGUs were put through accelerated weather and dew point testing to determine if there were any seal failures (condensation forms inside the unit showing a failure) after the extreme deflections the IGUs were put through.

¨  The IGUs were then retested and put through

the full process again and PASSED.

Page 29: The New Parkland Hospital Presentation

IGU Construction Failed Condensation Test: Unit PIB Seal Compromised

ASTM E-546

Standard Test Method for Frost/Dew Point of Sealed Insulating Glass Units

Page 30: The New Parkland Hospital Presentation

¨  Pilkington’s Large Deflection Spacer Design ¡  300% increase in amount of butyl for the primary

seal. ¡  Unique corner conditions for discontinuous spacers

to keep unit sealed under shear stress at the edges.

STANDARD SPACER LARGE DEFLECTION SPACER

Page 31: The New Parkland Hospital Presentation

CONSTRUCTION Erection of the Structural Glass Wall

Page 32: The New Parkland Hospital Presentation
Page 33: The New Parkland Hospital Presentation
Page 34: The New Parkland Hospital Presentation
Page 35: The New Parkland Hospital Presentation
Page 36: The New Parkland Hospital Presentation
Page 37: The New Parkland Hospital Presentation
Page 38: The New Parkland Hospital Presentation

THE NEW PARKLAND HOSPITAL

Presented by: Chuck Armstrong – Corgan Associates, Inc. Jeff Haber – W&W Glass, LLC

A Case Study on the Design-Assist Process for the Structural Glass Façade