The Malaysian Electricity Supply Industry (MESI) – Stakeholders

CISB413 Malaysian Electricity & Power Landscape

Aznan Ezraie Ariffin

System Operation Dept

Transmission Div

[email protected]

Page 2: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

CONTENTS

1. Power System Review2. Malaysian Electricity Supply Industry3. Governance & Institutional Framework4. Smart Grid and New Technologies5. IPPs and PPAs

Page 3: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Part 1:

Power System Review

Page 4: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Electricity Characteristics

Page 5: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Illustration of Power Delivery

Page 6: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Illustration of Generation Sources

Page 7: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Part 2:

Malaysian Electricity Supply Industry

Page 8: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

MALAYSIA ELECTRICITY SUPPLY INDUSTRY (M-ESI)MALAYSIA

MNC

‘WE’VE GOT THE POWER - to serve, to deliver, to excel’

19

Page 9: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Evolution of the MESI

AC Unbundling/Preparation for IBR 2011

Page 10: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Evolution of the MESI (cont)

Page 11: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Introduction to Tenaga Nasional BerhadThree Major Utilities in Malaysia

PENINSULAR

MALAYSIA

SARAWAK

SABAH

Sabah Electricity Sdn Bhd(A 83% TNB Subsidiary)

Sarawak Electricity Board (SEB)

Tenaga Nasional Bhd(TNB)

SINGAPORE

BRUNEI21,060MW*

1,237MW

1,141MW*

695MW

11,506MW

* Includes IPPs

MD: 16,901MW

‘WE’VE GOT THE POWER - to serve, to deliver, to excel’

* Includes IPPs

FY’09 FY’10 FY’11 FY’12 1HFY’13

TNB -Peninsula

Installed Capacity (MW)11,530 11,530 11,530 11,462 11,462

Total units sold (GWh) 87,780 95,197 97,888 102,132 52,129

Total customers (million) 7.59 7.87 8.11 8.36 8.47

Total employees 29,149 30,535 31,935 33,568 34,353

Total assets (RM billion) 71.4 75.9 79.1 88.5 88.3

Page 12: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Customer VS Sales

Page 13: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Tariffs Comparison

Page 14: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

TYPICAL DAILY LOAD CURVE PATTERN

POWERING THE NATION

Page 15: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

TYPICAL DAILY LOAD CURVE PATTERN

POWERING THE NATION

Page 16: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

15,000

15,500

16,000

16,500

17,000

Maximum Demand (MW)

Monthly Peak Demand, MW

FY Highest Month (MW)

Growth (%)

09/10 15, 072 5.8

10/11 15, 476 2.7

11/12 15, 825 2.3

12/13 16, 562 4.7

13/14 16, 901 (YTD) -

MONTHLY MAXIMUM DEMAND (FY09/10 – FY13/14)

POWERING THE NATION

12,000

12,500

13,000

13,500

14,000

14,500

15,000

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug

Maximum Demand (MW)

FY 08/09 FY 09/10 FY10/11 FY11/12 FY12/13 FY13/14

The apparent increase in FY09/10 might be due toThe apparent increase in FY09/10 might be due to El NiñoEl Niño

Page 17: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

THE POLICY DRIVES THE FUEL MIX EVOLUTION FROM OIL

DOMINANT TO GAS DOMINANT OVER A FEW DECADES

Malaysia has been highly dependent on fossil fuels:

Oil (1970s) � Natural Gas (1990s to 2000s) � Coal ??

Coal

Hydro

70%

80%

90%

100%

Import Hydro Coal Natural Gas Distillate

28

Oil

Distillate

Natural Gas

0%

10%

20%

30%

40%

50%

60%

19

76

19

78

19

80

19

82

19

84

19

86

19

88

19

90

19

92

19

94

19

96

19

98

20

00

20

02

20

04

20

06

20

08

20

10

20

12

Page 18: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

DEMAND GROWTH FORECAST

2016

201718,880 MW

201819,492 MW3.18 %

3.24 %

3.27 %

3.31 %

POWERING THE NATION

Note: As Approved by the BOD on 29 Jan 2014

201417,152 MW

201517,697 MW

201618,282 MW

Page 19: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Typical Generation-Demand Scenario

Page 20: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Typical Generation-Demand Scenario

East

North

South

Central

Page 21: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

ASEAN Power Grid – Inception under the ASEAN Ministe r of Energy (AMEM) and implemented under HAPUA

Existing Interconnection

•Peninsular Malaysia –Singapore

(1986, 2 x 200 MW)

•Peninsular Malaysia – Thailand

•HVAC Bukit Ketri – Sadao (1981, 85

MW)

•HVDC Gurun – Khlong Ngae

(2001, 300 MW)

Potential Interconnection

32

MALAYSIAMNC

‘WE’VE GOT THE POWER - to serve, to deliver, to excel’

• Sarawak and Sumatera interconnections are viable op tions to increase energy security• The Singapore & Thailand Interconnections enhanced system security for all parties

Potential Interconnection

•Peninsular Malaysia – Sarawak (2022)

•Peninsular Malaysia – Sumatera (2018)

•Peninsular Malaysia – Thailand

(2015, 2nd 300MW HVDC)

•Rantau Panjang – Sg. Kolok (under

discussion)

Note: HAPUA – Head of ASEAN Power Utilities and Authorities

Page 22: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Part 3:

Governance & Institutional Framework

Page 23: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

ESI Structure in Peninsular Malaysia

� Current ESI structure remains the same with TNB and IPPs as the key players in the generation sector

� However, the business activities of TNB is segmented into 5 business entities in anticipation of full implementation of Incentive Based Regulation (IBR) in 2015

TNB Generation- Thermal plants- Hydro planrs- Generation

SPV

IPPs

‘WE’VE GOT THE POWER - to serve, to deliver, to excel’

Regulation (IBR) in 2015

� The System Operator and Single Buyer are in the process to be ring-fenced to enhance transparency, independence and fair play in generation scheduling and dispatch

Source: • Energy Commission’s Peninsular

Malaysia Industry Outlook 2013

34

TNB Transmission (Grid Owner)

Grid System Operator Single Buyer

Franchised Retailers

TNB Distribution

Retail

Page 24: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Industry Regulatory Framework

Page 25: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Institutions in the Sector

Page 26: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Key Energy Policies

Page 27: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

The Energy Commission:

Regulatory Process • To advise the Minister on all matters concerning the national

policy objectives for energy supply activities.• To implement and enforce the energy supply laws.• To regulate on safety matters relating to the electricity

supply industry and gas supply industry (reticulation stage).• To regulate on technical matters in order to promote • To regulate on technical matters in order to promote

efficiency in the electricity supply industry and gas supply industry (reticulation stage).

• To regulate on economic matters so as to promote and safeguard competition and fair and efficient market conduct or, in the absence of a competitive market, to prevent the misuse of monopoly or market power in the ESI and the GSI (reticulation stage)

• Sarawak is regulated separately

Page 28: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Historical Development of MESI

Structure

Page 29: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Part 4:

Use of Information Technology in

Power Utility

Page 30: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Tesla vs Bell

41

Page 31: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Disruptive Forces

Page 32: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Intelligent Grid

43

Page 33: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

• "Smart Grid" is today used as a marketing term, rather than atechnical definition. For this reason there is no well definedand commonly accepted scope of what "smart" is and what itis not.

• The general understanding is that the Smart Grid is theconcept of modernizing the electric grid. The Smart Grid

What is Smart Grid

© 2014 TNBR. All rights reserved 44

concept of modernizing the electric grid. The Smart Gridcomprises everything related to the electric system inbetween any point of generation and any point ofconsumption. Through the addition of Smart Gridtechnologies the grid becomes more flexible, interactive andis able to provide real time feedback.

http://www.iec.ch/smartgrid/

Page 34: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Smart Grid Drivers & Technology Options

© 2014 TNBR. All rights reserved 45

Source : Bloomberg New Energy Finance 2012

Page 35: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Smart Grid Drivers & Technology Options

© 2014 TNBR. All rights reserved 46

Source : IEA Smart Grid Survey

Page 36: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Issues & Challenges – Customer Acceptance

© 2014 TNBR. All rights reserved 47

Page 37: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

© 2014 TNBR. All rights reserved 48COTO – cut over to operation

Page 38: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

B

Community Briefings & Engagemen

tPre

Installation Letter

Bill Inserts

Video/Advert

Web & Mobile

Incentive Campaign

Phone & Post Survey

Post-installation

survey

▪ Continuous

customer

engagement

▪ Localised

events

▪ Community

engagements

▪ Voluntary

participation

▪ Customer

benefits

Pilot Smart Meter Deployment in Melaka - Customer Experience

B Advert

Door Hanger

Social Media

EngagementInstallation

Survey

Smart Meter Help

Desk

Smart Meter Web

Portal

Mobile Tools

▪ Improved

efficiency and

availability.

▪ TNB

SmartLiving

enabled

programs

▪ Online

community

engagement

▪ Personalized

engagement

Page 39: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Challenges & Critical Enabler - Interoperability

• As information technology (IT) and operations technology (OT)converge in the smarter grid of the future, network interoperability willbe the starting point and precondition for all.

• Interoperability in multiple network technology must support end-to-end data quality and security, network system performance andapplication service provisioning and management.

© 2014 TNBR. All rights reserved 50

Mission : To accelerate the implementation of interoperable Smart Grid devices and systems

Page 40: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

© 2014 TNBR. All rights reserved 51

Page 41: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Challenges & Enabler – Infrastructure Development

• Shared vision for the smart electricity among stake holders

• Widespread deployment of Intelligent Electronic Devices (IED)– Retrofitting of existing components are required to make them

“smarter” as well as keeping the cost lower

• Infrastructure for integrated communications need to be fullydeveloped

© 2014 TNBR. All rights reserved 52

developed

South Korea Smart Grid Test-bed with budget allocation of $200 million has been made ($68 mil public funds, $170 mil private investment)

Page 42: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Host of New Technologies

53

Page 43: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Part 5:

IPPs and PPAs

Page 44: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

IPP’s Beginning

� Beginning 1993, IPP license was awarded to a total of 15 IPPs tobuild and operate generating plants in Peninsular Malaysia.

1993• YTL• GSP• SEV• PDP• PTEK

1998 - 1999• TNB

Janamanjung• TTPC• NUR• Pahlawan

2001 - 2003• Prai Power• GB3 Sdn Bhd• Panglima• Kapar Energy

2003 – 2005• Tanjung Bin• TNB

Janamanjung• Jimah Energy

First Generation IPPs

Third Generation IPPs

Second Generation IPPs

Strictly Private & Confidential 55

Page 45: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

Independent Power Producers

IPP Capacity (MW)

Type of Plant

Fuel Owner

First Generation IPPs

YTL Power Sdn Bhd 1,170 CCGT Gas YTL

SEV Energy Ventures Sdn Bhd 1,303 CCGT Gas Malakoff

Genting Sanyen Power Sdn Bhd 762 CCGT Gas Genting Group

Powertek Bhd 434 OCGT Gas Tanjong

PD Power Sdn Bhd 436.4 OCGT Gas Sime Darby

Second Pahlawan Power Sdn Bhd 322 CCGT Gas TanjongSecond Generation IPPs

Pahlawan Power Sdn Bhd 322 CCGT Gas Tanjong

Kapar Energy Ventures Sdn Bhd 2,420 CSP,OCGT

Coal, MFO, Gas

60% TNB/40% Malakoff

Panglima Power Sdn Bhd 720 CCGT Gas Tanjong

GB3 Sdn Bhd 640 CCGT Gas Malakoff

Prai Power Sdn Bhd 350 CCGT Gas Malakoff

Teknologi Tenaga Perlis Consortium Sdn Bhd (TTPC)

650 CCGT Gas JatiCakerawala

Third Generation IPPs

TNB Janamanjung Sdn Bhd 2,070 CSP Coal TNB

Tanjung Bin Power Sdn Bhd 2,100 CSP Coal Malakoff

Jimah Energy Ventures Sdn Bhd 1,400 CSP Coal Jimah TeknikNote: CCGT (Combined-Cycle Gas Turbine), OCGT (Open Cycle Gas Turbine), CSP (Conventional Steam Plant)

Page 46: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

PPA :Product & Payment

Capacity & Energy

Capacity & EnergyMinimum Take or Pay (Energy)

(YTL only)

Product

Product

Product

Payment

Energy Payment Only (YTL only)

Capacity & Energy Payment

1st Generation

1998 2002PPA Signed

Capacity & Energy

Capacity & Energy Payment

2nd Generation

Capacity, Utilisation &Energy Payment

3rd Generation

Payment

Payment

Page 47: The Malaysian Electricity Supply Industry (MESI) · PDF fileThe Malaysian Electricity Supply Industry (MESI) –Stakeholders CISB413 Malaysian Electricity & Power Landscape Aznan Ezraie

PPA: Product and Payment (2)

� Capacity Payment

Payment made to IPPs

Capacity Payment (for being available)

Energy Payment(for energy generated)

Daily Utilisation Payment

� Capacity Payment� for availability & performance of the plant� Payment is based on availability regardless of whether the plant is

despatched or not. � Daily Utilisation Payment (for Jimah & Tanjung Bin only)

� introduced to encourage IPP to share demand risks and to reduce fixed capacity payment when plant is not utilised.

� Energy payment� Payment for energy despatched from the plant� covers fuel & variable operating costs