Upload
buidat
View
217
Download
0
Embed Size (px)
Citation preview
MOO
The M & V Guided Recommissioning Process
Energy & Water Conservation ProgramSeptember 2015
MOO
EWCAgenda
• EWC Overview• Our approach• Progress
• Fault Detection• Zone & customer feedback• Variance reporting• Rogue zone diagnostics
• Existing Building Commissioning • Selection Process• GDC• BME
• M&V Plan for New Construction • EUI & 3PIM Benchmarking • BAS Trend Review
EWC
• Behavior Programs• Campus-Wide Scheduling, Resets, & Economizing• Campus-Wide Fault Diagnostics• System Component Replacements• Existing Building (EB) Commissioning• Measurement & Verification
Our Approach
Campus Distributed E&G Building EUI
Bi-Monthly Variance Report
Most Recent Two Weeks Steam UsageCampus Average Increase in Steam Usage
Previous Two Weeks Steam Usage
Fault Detection Tools
Pre-Heat Set Point: 50oF Actual Temp: 110oF
Townes Hall AHU-08 BAS Graphic
• Improperly installed and leaking preheat steam valve• Steam costs increased $400 per day due to leak-by steam• If left unaddressed, problem would have resulted in annual utility cost
increases of $140,000• Short term solution: Steam to AHU was valved off• Long term solution: Correct faulty installation of valve stem
Summary of our Investigation
TNH Steam Consumption
Fault Detection ToolsRogue Zone Diagnostics
• Reheat valve is open above 80%
• Space temp is 2oF less than heating set point
• Space temp is 2oF greater than cooling set point
• Damper position is above 95%
Rogue Zone Diagnostics
Rogue Zone Diagnostics
Chill
ed W
ater
(Ton
-Hou
rs)
Date
4/28/20154/28/2014 11/7/2014
Impact of Rogue Zone Program at GDC
• EUI Ranking
• EUI change over year before
• 4 PIM modeling – baseload and controllability
• BAS control level and potential for success
• Service request frequency and maintenance personnel feedback
• Validated Utility Data
EWC EB Commissioning Selection Process
Top 30 EUI Buildings
0
0.05
0.1
0.15
0.2
30 50 70 90 110
Ton-
hrs/
day/
sq-ft
Average Daily Temp
Slope (performance efficiency)Scatter (controllability)
Base load
Pivot Temp 65 degrees
Three Parameter Inverse Modeling, Dr. Kissock, University of Dayton
Example 3 PIM Chilled Water Model
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
30 40 50 60 70 80 90
Ton-
hr /
Day
/ S
q-ft
Average Daily Temperature
3PIM Chilled Water Campus Averages
Campus Average
Campus Lab Average
Campus Office/Academic Avg
Three Parameter Inverse Modeling, Dr. Kissock, University of Daton
3PIM Chilled Water Campus Average
AHU Resets Supply air temp reset based on zone loads• Air is pretreated by a dedicated OAU with chilled water and hot water/ steam coils• Supply air temperature feedback and set-point in BAS• All zones have room temp feedback in BAS• All zones have terminal box damper feedback in BAS• Return air humidity feedback in BAS• Sensitive areas are evaluated and monitored
Water-Side Resets Hot water supply temperature set-point reset based on outdoor air temperature• Building has a heating hot water loop in place• Supply temperature of hot water loop is tied into the BAS• Outdoor air temperature is available for use in the reset schedule• Hot water pump serves only HVAC loads
BAS Control Level and Potential for Success
1. Baseline Validation –Verify Metering & Billing
2. Reviewing documents• As-builts (Mechanical Schedule,
MEP Drawings)• Sequence of Operations (SOO)• Test and Balance (T&B)• Commissioning Report• Building Automation Systems
(BAS)
GDC Re-Commissioning Process
3. Verify and resolve operational discrepancies • Repaired/ replaced minor equipment – sensors & actuators• Rewrote and reprogrammed vague static pressure reset SOO• Rewrote and reprogrammed outside air flow control• Programmed supply air temperature reset• Corrected inconsistent minimum air flow values
4. Optimize for energy conservation• Optimized supply air and space temperature set-points• Improved supply air temperature reset• Added economizer programming • Added rogue zone programming
GDC Re-Commissioning Process
VAV
HW
Val
ve P
ositi
on %
Date (Day/Hour)
Nov. 6th, 2014 Returned Room Temp Set-point to 70-74F Nov. 7th, 2014
Reduced Air Flow Min.
VAV 3.506 Reheat Valve Position
Nov. 6th, 2014 Demand control ventilation sequence utilizedFa
n Sp
eed
Perc
enta
ge
Date (Day/Hour)
GDC OAU-1 Fan Speed Percentage
10/6/13 – 9/30/14
10/1/14 – 12/9/14
GDC 4 PIM Model After start of EB Cx but before tuning
Generated using Energy Explorer
Temperature (oF)
CW (kBTU/day)
10/6/13 – 9/30/14
12/10/14 – 5/6/15
GDC 4 PIM Model After tuning
Generated using Energy Explorer
Temperature (oF)
CW (kBTU/day)
Chilled Water Electricity Steam Total Measured (10/6/14-5/6/15) Daily Avoidance Annual Estimate46% 5% 51% 37% 173,508.91$ 814.60$ 297,327.48$
Cost Avoidance% Avoidance
BME Re-Commissioning3. Verify and resolve operational discrepancies
• Correct fume hood controller CFM calculation• Add schedule for motion sensors• Adjust motion sensor ultrasonic sensitivity• Correct AHU-3 return air CFM set-point calculation• Replace CO2 sensors and enable demand controlled ventilation
MOOOffset = General Exhaust + Hood Exhaust – Supply Air
BME Motion sensors not fully operational• Design requires that ventilation rates reduce and lights turn off during
unoccupied periods • Programming was partially complete and motion sensors were installed• Ultrasonic sensitivity was not adjusted • Occupancy schedule was not programmed • Located in higher hazard labs and not teaching labs• If utilized, potential energy cost avoidance >$30,000 (ROI < 1 year)
M&V Plan for RBRH• EUI & 3PIM Comparisons
• Against itself at 1, 2, 3, and 5 years from SC• Campus averages• National benchmarks• Energy model
• BAS Trend Comparisons • Against expected operation at 6 to 8 months after SC• Set-up trending in system groups• Use in preparation for enhanced commissioning • Record anomalies and discrepancies
Energy Conservation Measure Trended Point to ReviewAHU static pressure reset Static pressure set point, actual static
pressure, fan speed feedback
AHU supply air temperature reset Supply air temp set-point, actualsupply air temp, relative humidity
AHU set-back schedule Fan speed feedback, valve position
Terminal box set-back Damper position, reheat valve position
Demand Control Ventilation Return air, space, and outside air CO2 value, outside air flow
Economizer Outside air flow, Outside air & return air damper position, CHW valve position, mixed air temperature
Building Automation Trend Review
MOO
The M & V Guided Recommissioning Process
Energy & Water Conservation ProgramSeptember 2015