Upload
adi-susilo
View
394
Download
23
Embed Size (px)
DESCRIPTION
The Karns Oil Company is deciding whether to drill for oil on a tract of land the company
Citation preview
The Karns Oil Company is deciding whether to drill for oil on a tract of land the company
owns. The company estimates the project would cost $8 million today. Karns estimates
that, once drilled, the oil will generate positive net cash flows of $4 million a year at the
end of each of the next 4 years. Although the company is fairly confident about its cash flow
forecast, in 2 years it will have more information about the local geology and about
the price of oil. Karns estimates that if it waits 2 years then the project would cost $9
million. Moreover, if it waits 2 years, then there is a 90% chance that the net cash flows
would be $4.2 million a year for 4 years and a 10% chance that they would be $2.2 million
a year for 4 years. Assume all cash flows are discounted at 10%
a. If the company chooses to drill today, what is the project’s net present value?
b. Using decision-tree analysis, does it make sense to wait 2 years before deciding
whether to drill?
Answer:
Initial Investment: $ 8 Million
Cash Flow: $ 4 Million
Life Project: 4 Years
Discounted Rate : 10% (1+0,10)= 1,10
Problems: If the company chooses to drill today, what is the project’s net present value?
Year PV
1 4/(1+0.10)1=4/(1,100) 3,694
2 4/(1+0.10)2 =4/(1,210) 3,3058
3 4/(1+0.10)3 =4/(1,331) 3,0053
4 4/(1+0.10)4 = 4/(1,464) 2,7321
Total 12,6795
NPV=-20 + 12,6754 =4,6795 Million
Answer B:
Cost Project: 9 Million
Low Cash Flow Prob 10%= 2,2 Million for 4 years
High Cash Flow Prob 90%= 4,2 Million for 4 years
Discounted Rate= 10% (1+0,10)= 1,10
Wait for years= 2 years
Problems: Using decision-tree analysis, does it make sense to wait 2 years before deciding
whether to drill?
Wait 2 Years
Low 10% Prob High 90% Prob
Year NPV NPV
0 0 - 0 -
1 0 - 0 -
2 -9 Million -9 Million -
3 2,2/(1,10)1 2 4,2/(1,10)1 4
4 2,2/(1,10)2 1,818 4,2/(1,10)2 3,471
5 2,2/(1,10)3 1,653 4,2/(1,10)3 3,156
6 2,2/(1,10)4 1,503 4,2/(1,10)4 2,869
Total 6,974 Total 13,313
Low CF scenario: NPV = (-9 + 6.974)/(1.1)2 = -$1.674
High CF scenario: NPV = (-9 + 13.313)/(1.1)2 = $3.564
Expected NPV = .1(-1.674) + .9(3.564) = 3.040
If the cash flows are only $2.2 million, the NPV of the project is negative and, thus, would
not be undertaken. The value of the option of waiting two years is evaluated as 0.10($0) +
0.90($3.564) = $3.208 million.
Since the NPV of waiting two years is less than going ahead and proceeding with the project
today, it makes sense to drill today.