The Implications of CEQA: You Better Plan For It
Trevor Macenski
Director of Environmental Services FirstCarbon Solutions
Outline • What the CEQA are you talking about • Planning for CEQA • Stakeholders • Example Projects
CEQA
What the CEQA are you talking about?
Introduction to CEQA
• 1969: President Nixon signs National Environmental Policy Act (NEPA)
• 1970: Governor Reagan signs California Environmental Quality Act (CEQA)
• CEQA (the Statute): Established by Legislature
…and continuously modified by Legislature …and “interpreted” by the Courts
Who is “in charge” of CEQA?
Lead Agency CEQA is a “Self-executing Statute” meaning it is the Lead-Agency’s duty to determine what is and is not subject to CEQA, and to follow the process. Public can go through the legal process (suing) to challenge decisions
CEQA Key Players
Responsible Agencies
Environmental Consultants
Project Applicants
Trustee Agencies
Courts
Concerned Citizens
Agency W/ Jurisdiction
LEAD AGENCY
Trustee Agencies: 1) CDFG
2) SLC
3) Park & Rec
4) UC
Lead Agency: Principal responsibility carrying out or approving a project. (e.g. City or County)
Responsible Agency: Other than the lead agency that has legal responsibility for carrying out or approving a project. (e.g. Air District)
Planning for CEQA
Perfect planning often has not so perfect impacts….
CEQA and the Public CEQA is the bridge between the hard sciences and the public. Technical studies will need to cater to public understanding Often, site plans, engineering drawings will need to be simplified for CEQA purposes
Common CEQA Projects
Residential Commercial Transportation projects Water and energy infrastructure
Sample of Current Projects
Bridge Crossing- Calaveras County Utility Scale Solar- Merced County Specific Plan- Fremont Prison Expansion- San Diego Hollywood Central Park- Hollywood
Planning Related CEQA Projects
SOI Amendments Annexations Specific Plans General Plans Climate Action Plans Habitat Conservation Plans Regional Transportation Plans Anything with a “plan” after it…
CEQA and Planning
Master or Program EIR Environmental Constraints Analysis
Permitting Thresholds Appendix G Resources Significant Thresholds
Significant Unavoidable Impacts Air Quality - Construction Schedules Traffic Impacts- LOS
Checklist topics
Aesthetics Agriculture Air Quality (GHG) Biology Cultural Geology Hazards Hydrology
Land Use Minerals Noise Population/Housing Public Services/Utilities Recreation Transportation/traffic Urban decay
Appendix G Checklist Question Example
Biological Resources Would the project:
A) Have a substantial adverse effect, either directly or through habitat modifications, on any species identified as a candidate, sensitive, or special status species in local or regional plans, policies, or regulations or by the California Dept of Fish and Game or US Fish and Wildlife?
Stakeholders, Agencies, and Public Participation
Everyone has the right to be heard…
Scoping Process Required for EIR’s not for IS/MND’s Required when: 1) Roadway project 2) Statewide, regional, or areawide
significance If they comment you must address or
discuss why it wasn’t warranted. This must be supported by fact!
EIR Scoping Process During these 30 days, a scoping meeting
may be held to identify key environmental concerns and issues
Identify possible impacts Encourage inter-agency consultation Consult with recognized experts Involve public at an early stage of the
review process (though not required)
Public Comment Process IS/MND
30 Days EIR
45 Days
All comments have to be considered. Respond to those only commenting the EIR not the project.
Common CEQA Challenges
Challenging the Process not the Project
Noticing of hearings Comment periods
Document dump Late comment strategy Disagreement among experts Fair argument mine field
Common CEQA Challenges
Regulatory or Responsible agency choices not to comment during the NOP but then demands more analysis Unwarranted Data Requests Asserting that an EIR is warranted because of “controversy”.
Unique Projects
The good the bad and the impacts
Elk Grove SOI EIR
SOI Amendment South of City Almost exclusively AG. Adjacent to Wildlife Preserve Adjacent to Flood Zone South Sac HCP Incredibly Controversial
Concrete Batch Plant- Merced
Openly Non-Union Contractor Previous Project Challenged and Lost Out of State Consultant Hired to Challenge EIR Five hours of public comments County to prepare Focused EIR Health Risk Assessment
Cold Storage Facility
Large Amounts of Ammonia Commercial Trucking Operations Future Planned Residential Potential Explosion Hazards Fleet Standards and AQ Exposure
Warm Springs SP
Health Risk Assessment Exposure and Hazard Assessment Residential and Industrial Use Conflicts Transit Grants and Bart
Helpful Websites CEQA Statute and Guidelines http://ceres.ca.gov/ceqa/ Land Use Planning Information Network (LUPIN) http://ceres.ca.gov/planning/index.html California Association of Environmental
Professionals (AEP) http://www.califaep.org/
Questions?