Upload
mavromatidis
View
231
Download
0
Embed Size (px)
Citation preview
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
1/68
2012-2013
edition
Energy WisdomProgrammeImproving Energy Efciency
Reducing Carbon EmissionsMeeting the 2050 Challenges
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
2/68
REPORT AUTHORS
Project Management:Nicola REGA (Advisor Environment & Sustainable Development Policy Unit EURELECTR IC Secretariat)
Project Coordination: Ins REULET
This report was carried out with the contribution of the EWP contact persons in each participating company:
Alliander (NL) Hans NOOTER, Senior Consultant CSR DEI SA (GR) Labrini PATMANIDOU, Strategy Department / Head of section, Environmental branch Electricity Authority of Cyprus (CY) Charalambos MENELAOU, Assistant Generation Manager Energias de Portugal (PT) Pedro PAES, Sustainability and Environmental Ofce
Endesa (ES) David CORREGIDOR, Deputy Director of Environmental and Climate Change Department E.ON (DE) Nicole HENKEL, Political Af fairs and Corporate Communications ESB (IE) Tony CARROLL, ESB Sustainability Manager ewzElektrizittswerk der Stadt Zrich (CH) Gian CARLE, Head of Renewable Energy Trading Fortum (FI) Kari K ANKA ANP, Sustainability Manager, Climate and Environmental Affairs Gas Natural Fenosa (ES) Amado GIL MARTINE Z, Environmental Department / Carbon Management Helsingin Energia (FI) Rauno TOLONEN, Customer Service and Communications / Energy Efciency Manager Iberdrola (ES) Monica OVIEDO CESPEDES, Environmental Stakeholders and Climate Change Head Department PGE SA (PL) Miroslaw NIEWIADOMSKI, Environmental Protection Department Director SWMStadtwerke Mnchen (DE) Beatrix WIDMER, M anager Energy Policy VERBUND AG (AT) Jan CUPAL, Innovation, Research & Development / Sr. Innovation Manager, Coordinator for Environment
and Climate Change Wien Energie, Elisa SCHENNER, Public Affairs
We thank all companies and individual experts for their contribution.
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
3/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 1
Energy efciency will play a fundamental role in attaining
a secure, competitive and sustainable energy future.
Initiatives such as the Sixth Energy Wisdom Programme
represent an excellent contribution to addressing our
energy and climate challenges. I appreciate EURELECTRICs
continued commitment to act as a solid bridge between EU
political priorities and local innovative solutions to bring
more efcient low-carbon energy to our economy.
Our future energy system needs such best practices and
I encourage EURELECTRICs members to continue sending
such positive signals.
GNTHER H. OETTINGER
European Commissioner for Energy
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
4/68
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
5/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 3
Contents
FOREWORD 5
1. EXECUTIVE SUMMARY 9
2. InnOVATIVE PROjECTS 13
On the supply side
2.1. Windoat Development Of Innovative Technology ForOffshore Wid Ex ploratio 142.2. Joint Venture Wid Oshore Activities In Europe And Beyond 152.3. Solar Eergy: Megalopolis PV Project 162.4. Biomass Power Plant in Vienna 172.5. Combied Cycle Gas Turbie (CCGT) Unit 5 182.6. Research Project On CO
2Capture in La Pereda 19
2.7. Less CO2
Project (CCS) 20
2.8. Fuel SwitchigBaleares 212.9. E.ON Pilot Programme PowerTo Gas 222.10. Schlieren District Heatig 232.11. Joensuu CHP-Pyrolasis Project 242.12. Szczecin CHP-Biomass 252.13. Improving Energy Efciency ofA Combied Cycle Power P lat 262.14. Belchatow Power Plant: New Low GHG Emissions Fossil-Fuel 858 MW Unit 27
On the demand side
2.15. Smart Grid Implementation in Amsterdam 282.16. St ar Project : Smart MeterigAnd Network Automation Programme 292.17. Area-Based Retroft Energy Efciency 302.18. Energy Efciency Lighteig System in Storage Buildings and Production Halls 312.19. Gree BuildigEnergy Efciency 322.20. 3E-Houses Project Energy Efciency 332.21. Verbund Smarthome 342.22. Worlds Most Energy Efcient Cloud Computig 352.23. Energy Savig Fuds and Energy Efciency Bous 362.24. E-Carin Ireland: Electric Vehicle Charging Infrastructure 37
3. PARTICIPATInG COMPAnIES 393.1. Alliander n.v. 403.2. DEI Dimossia Epichrissi Illectr ismou 413.3. EAC Electricity Authority of Cyprus 423.4. EDP Energias de Port ugal 433.6. ENDESA 443.7. E.ON 453.8. ESB Electricity Supply Board 46
3.9. ewz Elektr izitts werk der Stadt Zrich 473.10. Fortum 483.11. Gas Natural Fenosa 493.12. Helsingin Energia 503.13. IBERDROLA 513.14. PGE Polska Grupa Energetyczna S.A. 523.15. SWM Stadtwerke Mnchen GmbH 533.16. VERBUND AG 543.17. Wien Energie 55
4. PROjECT FEATURES 57 4.1. Overview 58
4.2. Project Methodology 584.3. Project Eligibility 594.4. Project Results 59
4.5. Projects Abroad 624.6. Project Benets 634.7. Project Barriers 634.8. Future investments 63
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
6/68
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
7/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 5
Foreword
Climate change is one of the major challenges the European Union is facing today. Yet this challengealso represents an opportunity for our industry to undertake appropriate action towards achieving
major technological improvements.
The electricity industr y is strongly committed to delivering carbon-neutral electricity by mid-century,as expressed by sixty -one Chief Executives of European electricity companies in 2009 and supported
by EURELECTR ICs Power Choices study in 2010.
However, the transformation of the energy sector towards a more efcient, low-carbon power supply
will require signicant investment in Europes grid and generation infrastructure. It is therefore
fundamental that the EU provides sound energy and climate policies that are able to promoteinvestments in R&D and innovation a key driver to Europes future competitiveness.
Within this context, the Energy Wisdom Programme (EWP) is an important framework to present the
wide range of activities in which our sector is engaged. Launched in 1998, the programme showspositive examples of electricity companies innovative solutions to reducing carbon emissions andenhancing energy efciency across the whole value chain from electricity generation, transmission
and distribution to end-use energy efciency. The resulting environmental, economic and social
benets could have great potential for pan-European replication.
The EWP has continuously improved its environmental performance: since it was established
electricity companies have saved over 730 Mt CO2
eq. in more than 600 projects across Europe. This6th edition of the EWP report sets out the results for the reporting cycle 2010 to 2011. During thisperiod, over 150 projects have been reported by 16 companies. Thanks to those projects, companies
have reduced approximately 99 Mt CO2
eq. and saved over 24 Mtoe in primary fuel. In addition to CO2
emissions reductions and energy savings, other major co-benets arise from the reported projects:
air quality improvements, waste reduction and increased employment.
EURELECTRIC thus calls for a strong cooperation between EU policymakers and industry stakeholdersto reduce substantial barriers that prevented faster development of climate friendly projects, such aslengthy authorisation procedures and a lack of public acceptance. An investment friendly environment
has to be created through the denition of a predictable and transparent regulatory framework in
addition to a well-functioning European electricity market.
The Commissions recognition that EURELEC TRIC can play a role in promoting and spreading innovative
projects is illustrated by the introductory words of EU Energy Commissioner Gnther Oettinger.I sincerely appreciate those encouraging words and look forward to maintaining the good relationshipbetween EUR ELECTRIC and the European Commission.
I would also like to congratulate the 16 companies that took part in this 6th edition of the EnergyWisdom Programme for their achievements and effor ts towards reaching carbon-neutrality by 2050.I encourage them to continue this good work in the future and hereby invite other electricity companies
to join us in the next edition of the EWP report, to be published in 2014.
Fulvio Conti
PresidentUnion of the Electricity Industry EURELECTRIC
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
8/68
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
9/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 7
Membership 2012-2013
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
10/68
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
11/68
1Executive Summary
9ENERGY WISDOM PROGRA MME 2012-2013 Edition
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
12/68
What is the EWP?
Since 1998, the Energy Wisdom Programme (EWP) has provideda platform for electricity companies to demonstrate how theyare improving energy efciency and reducing greenhouse gas
(GHG) emissions through innovative projects across Europe.
In the context of the EUs 2020 energy-climate objectives andthe industrys goal of moving towards a carbon-neutral power
supply by 2050, this voluntary initiative is the ideal place forelectricity companies to demonstrate how they are tacklingthe challenges ahead. It also encourages the dissemination of
best practices.
Each EWP reporting cycle covers two years. This sixth edition ofthe EWP particularly highlights how electricity companies are
helping to reduce CO2 emissions and enhance energy efciencybeyond the power sector in transport, industry, buildings andconsumer behaviour.
However the EWP is much more than a report. The dedicatedwebsite ww w.eurelectric.org/ewp provides an interactive mapwith details of all projects reported in this edition.
How does the EWP work?
The EWP establishes a reporting and monitoring system that
evaluates and documents the environmental performance ofthe reported projects. The method measures energy efciency
and GHG emissions reductions for each of the projects. The
savings are then aggregated in order to provide a global gure.
In this sixth reporting cycle, sixteen participating companiesfrom eleven European countries repor ted 155 projects that led to
energy savings and/or GHG emissions reductions. The projectswere carried out between 1990 and 2011, but the report onlypresents results obtained between 2010 and 2011. The ve
previous reporting cycles cover the period 1990 to 2009.
In the year 2011, the 16 participating companies totalled over90 million customers and 249,081 employees, a turnover of
133.25 billion euros. They accounted for 258.57 GW of installedgeneration capacity and 473.41 TWh of generated electricity.They also owned almost 1.2 million km of transmission and
distribution lines.
What are the key achievements in 2010-2011?
In this reporting cycle, participating companies reduced oravoided emissions of 99 MtCO
2eq as of result of implementing
projects that delivered GHG emissions reductions (Figure 1).
Figure 1: GHG emissions without project and with project
(Europe, 2010-2011)
The greatest emissions reductions or offsets were achieved bythe following project types: New Generating Capacity: FossilFuel (44%) and New Generating Capacity: Renewables
(22%). See Figure 2 for more details.
Figure 2: GHG emissions reductions per project type (Europe,
2010-2011)
0
50
100
150
200
250
2010 2010/20112011
With project Without project
Mt CO2 eq
GHG Emissions With Project and Without Project
Reduction in GHG Emissions per Project Type
Efficiency Improvement7%
Fuel Switching2%
New GeneratingCapacity: Renewables22%
New Generating Capacity:
Fossil Fuel44%
New GeneratingCapacity: Nuclear3%
New Generating Capacity:CHP
3%
Other ElectricityGeneration Projects
5%
Construction ofNew Transmission
and/or Distribution Lines7%
Upgrade Transmission and/orDistribution Line Voltage
7%
Executive Summary10
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
13/68
Participating companies reduced primary energy fuel use in
electricity generation by around 24 Mtoe, and by 2573 GW/hamong energy end-users (Figure 3).
The projects that saved most primary energy were reported
under New Generating Capacity: Fossil Fuel (34%), NewGenerating Capacity: CHP (23%) and Other Transmission andDistribution Projects (18%).
Figure 3: Primary energy savings per project type (Europe,
2010-2011)
What are the main ndings?
Ivestmet in the electricity sector was driven by three mainchallenges:
- Reducing fuel import dependency,- Creating secure long-term energy supplies, and- Limiting the risks from climate change and habitat loss.
The climate change challenge in particular triggered actions
in research, development and innovation, aimed at thedevelopmet of low-emissio techologies.
Companies have recognised that electricity grids and storagefacilities must be rapidly extended to best use the increasingshare ofpower from reewables. To this end, they are carry ingout research into different technologies for storage and
load compensation.
New smart technologies will enable companies to feed
large volumes of renewable energy into the energy infra-
structure, provide their customers with more eergy
savig opportuities and encourage large-scale adoption ofelectric transportation.
Customers will play a maor role in driving changes in society,but only if they are able to study their consumption andimprove their energy usage. Companies have supported them
for many years by offeringeergy advisory services.
Engaging with customers gives companies the opportunity
to underline their environmental awareness and enhance
their corporate image and public recognition.
Which conclusions can we draw?
The ogoig ecoomic crisis has also impacted electricitycompanies, particularly hitting their cash ows and access to
capital. This has made the investment climate extraordinarily
difcult, and several projects have had to be delayed or cancelled.
Conicting policy instruments at EU level remain a challenge
when it comes to deciding on future investments. New
approaches, going beyond simple target-setting, need tobe explored, as does the interaction between various policyinstruments aiming to promote renewable energy sources,
energy efciency and CO2
emissions reduction.
The developmet of parterships across the whole electricit y
value-chai is needed to manage societys energy transition.
Involvement is needed from generators to end-users,passing through grid operators, local authorities, and othermarket players.
To get the ivolvemet of ed-users right, the new and growingeld of energy innovation urgently eeds trasparet rules to
clarify the roles ad resposibilities of the many par ticipants
involved. Many open issues still need to resolved, includingdata management, the role of household and industrialend-customers, and the role of third parties delivering new
services to those end-customers.
How is this EWP report structured?
The following section (Section 2) highlights one or two
particularly innovative projects per company, includingremarks by the project managers who are working daily to
reduce the environmental footprint of our sector.
Section 3 portrays all participating companies. CEOs havethe opportunity to explain their visions and actions towards
greening the electricity sector.
In Section 4, the results of all projects submitted by partici-pating companies are analysed in detail. More information on
all projects can be found at ww w.eurelectric.org/ewp
Energy Savings per project Type
New GeneratingCapacity: Nuclear4%
New Generating Capacity:CHP23%
New Generating Capacity:Fossil Fuel34%
Construction ofNew Transmission
and/orDistribution Lines
7%
Efficiency Improvement3%
New GeneratingCapacity: Renewables
4%
Upgrade Transmissionand/or Distribution
Line Voltage7%
Other Transmission andDistribution Projects
18%
ENERGY WISDOM PROGR AMME 2012-2013 Edition 11
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
14/68
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
15/68
2Innovative Projects
13ENERGY WISDOM PROGRA MME 2012-2013 Edition
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
16/68
Innovative Projects14
proect reported by
The deep offshore windtechnology, in particularthe WindFloat, will allow
us to harness stronger and
more stable winds, and in
the medium term deliver
sustainable energy into our
electrical system.
This is an historic moment
that takes my breath away.
This is probably the mostchallenging project in which
Ive been involved. My rst
word is to thank the team
and partners as this was
the result of a tremendous
team work involving several
EDP areas and National and
International collaborations.
I guess no one was expecting
a project like this to come
from Portugal , yet we have
proven the capabilities ofthe Portuguese maritime
industry to adapt and provide
the necessary resources to
successfully fabricate and
deploy an offshore structure
of this scale.
Now it is time to make
extensive testing and
validation moving forward
in the development of the
WindFloat technology.
Contact Person:Mr. Joao MacielTechnology DevelopmentDirector at EDP InnovationTel: [email protected]
Windfloat Development ofInnovative Technology forOffshore Wind Exploration
Project DescriptionThe WindFloat Project, led by EDP in partnership with Principle Power, A Silva Matos and Vestas,developed an innovative technology that will allow the exploitation of the wind potential at sea, at depthsof more than 40m.
The innovation focus of the project is the development of a oating foundation for multi-MW windturbines, based on the experiences from the oil and gas industr y.
The oating foundation is a semi-submersible and is anchored to the seabed. Its stability is due to the useof water entrapment plates, associated with an innovative ballast system. WindFloat adapts to any typeof offshore wind turbine. It is built entirely on land, including the installation of the turbine - thus avoidingthe use of scarce marine resources.
The WindFloat project encompasses the design and construction of a demonstration unit, including a2 MW turbine. The unit has been installed off the Portuguese coast, close to Aguadoura, and connected
to the grid in the end of December 2011. Pre-commercial and commercial phases are also planned,depending on the performance of the demonstration phase.
The project is the rst offshore wind deployment worldwide which did not require the use of any heavylift equipment offshore. Also, this is the rst offshore wind turbine in open Atlantic waters and the rstdeployment of a semi-submersible structure supporting a multi-megawatt wind turbine. Furthermore,it will form the basis of a future ocean energy cluster in Portugal.
Project ReasonThe existing energy paradigm is being strongly impacted by demographics, scarcity of resources andgrowing environmental concerns and mandatory targets. These three main drivers lead to two maintrends: cleaner generation (on the supply side) and energy efciency (on the demand side).
The WindFloat project addresses the supply side of the global solution as it implies cleaner energy generation.Wind Energy has already proven to be the most mature and competitive renewable energy option, eitheronshore or offshore, where the wind is stronger and more stable. However, shallow water deployments,using bottom xed structures, are only limited to specic regions (e.g., North Sea in Europe), so oneshould look at deep offshore wind using oating foundations as the way to explore the offshore winds inthe medium term.
The WindFloat was selected because of its key differentiating characteristics highlighted above.
Project Appraisal and Estimation MethodsWith an installed capacity of 2 MW, the offshore wind turbine produced, in 2011, about 25 MWh,corresponding to just 12 days of conditioned operation (namely with turbines capacity limited to 1.2 MW),during the commissioning process. During the demonstration phase, the wind turbine is expected toproduce between 4.4 and 5.3 GWh/year, i.e., 25 to 30% capacity factor (in offshore wind commercialproject, one could expect capacity factors above 40 to 45% ).
Emissions with project: no CO2
emissions from windpower.
Emissions without project: calculated assuming the electricity produced by the generation unit, had itnot been implemented, would have been generated by the companys thermoelectric plants, with anemission intensity of 635.3 tCO
2
/GWh. In 2011, the project avoided 16 tCO2
. When fully operational, weestimate the Windoat project to avoid around 3000 tCO2/year.
Fuel/Energy savings: calculated by converting the electricity production of t he wind turbine into primaryenergy, using the average net heat ratio of the companys thermal power plants. In 2011, energy savingsamounted to 198 TJoule.
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
17/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 15
Project DescriptionFrom planning to realising a project two frontrunners in the eld of renewable energy have combined
their know-how and nancial strength. A project developer and an energy supplier are following a new path
while concentrating competences and bringing projects from planning to realisation. With the sustainable
joint venture star ting only last year, the actual CO2
reduction is still comparat ively small (70,000t in 2011).But this sustainable project has impressive mid-term prospects: the exponential growth shows savings
of 108,000t in 2012, 363,100t in 2013 and reduced greenhouse gas emissions in 2020 of 3 million t/a.
SWM has a 33% share in the wind onshore activ ities of wpd Europe. The joint venture covers internat ionalwind-onshore activities in Europe and Canada.
The common goal is now to implement the activities planned and to plan, build and operate more wind
parks with some thousands of MW.
Project ReasonThe wpd AG, as leading designers and operators of wind energy, and the Stadtwerke Mnchen (SWM) havean expansion strategy in the eld of wind power. The common goal: developing wind energy cooperation
between European countries. The partners combine experience in the areas of onshore wind energy andenergy supply strongly supported by f unds.
By participating in the project development company operating throughout Europe, SWM is deliberatelygoing upstream, underlining in addition that any energy policy based on 100% renewables must be
European. Currently, wind energy has the biggest potential among renewables. Wind onshore is the mostcost-efcient and will be cheaper than fossil fuels in the next decade.
The joint venture represents an economically meaningful way of achieving the desired objective to supply
power by 2050 mainly from renewable energy sources.
Further advantages include: earlier, faster and more economic access to wind onshore projects for a local utility like SWM;
a strategically important reaction towards a new market structure in the eld of renewables;
the possibility for SWM to open up for new renewable generation portfolio;
important instrument in the Renewable Expansion Strategy to reach its goal of 100% by 2025 in a
cost-effective and economical way;
intensied cooperation for SWM with a powerful and well established partner;
stabilising the role of SWM as a player in the renewable market;
projects will play an important role on the renewable generation path the goal is 7.5 billion kWh/a,
of which the joint venture contributes 1.2 billion kWh/a.
Project Appraisal and estimation methodCO
2reduction of the wpd-cooperation: 3,000,000 t/a (2020)
A sample calculation to illustrate the CO2
savings: With an onshore wind capacity of 1,000 MW, anaverage of 800,000 households can be supplied with green electricity annually and 1.7 million tons ofCO
2could be saved.
Contact Person:Dr. Bernhard BoeckProject ManagerTel: +49(0)[email protected]
So far, it is unusual thata local utility is active in theeld of europe-wide wind
energy project development.
Due to the fact that SWM is
consequently going upstream
to ensure a sustainable
competitive position in the
relevant areas of energy
production and energy
supply, we established this
exclusive joint venture with
wpd as a strong and reliablepartner in the eld of wind
onshore development. The
cooperation makes it possible
to bundle the companies
core competencies and
to act quickly and exibly
on the European wind
onshore market. For SWM,
it is important to focus
on economic projects in
regions where the best
natural, legal and regulatory
conditions prevail. Thelogical consequence is to
act even as a local utility
on a European basis. A
further benet for SWM is
the possibility to build wind
onshore portfolios without
having to participate in
bidding contests a huge
draw-back for local utilities
at the moment. In addition,
with our portfolio approach
we reduce the dependence on
single market uncertainties
and price developments
signicantly. I am looking
forward to the possibility to
steer those new projects
for SWM.
proect reported by
Joint Venture Wind OnshoreActivities in Europe and Beyond
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
18/68
Innovative Projects16
Project descriptionThe project is expected to be one of the largest PV plants in Europe. PPC Renewables, a 100% subsidiaryof PPC S.A., is in charge of completing its implementation. PPCR is in the process of implementing a 50MW photovoltaic project near the city of Megalopolis located in the Arcadia prefecture in Peloponnese.
The project is to be developed as two single PV plants by two PPC Renewables 100% owned SPVs:Arkadikos Ilios I (39 MW) and Arkadikos Ilios II (11 MW). The PV plants will be installed at the location of adepleted lignite mine, previously used by PPC to extract lignite for electricity production. The photovoltaic
power plant installation area will cover up to 2.03 sq. km. The annual electricity generation is expectedto be 70,000 MWh.
Project reasonPPCs strategy for renewable energy sources is based on the development of all categories and the growth
of PPC Renewables portfolio. The Megalopolis PV power plant is included among PPC Renewables mostimportant projects.
Project appraisal and estimation methodsemissions with project (2013)The CO
2emissions from electricity generation of the project are zero.
Emissions without project (2010)With an average CO
2coefcient for the companys Interconnected System of 1.057 kg/ kwh (year 2010)
for 70,000 MWh energy generation, the expected CO2
emissions are 74,000 tonnes or 74 kt.
Emissions reductions
Emissions reductions=emissions without project-emissions with projectCO
2emission reductions (2013) = 74 ktCO
2- 0 ktCO
2= 74 ktCO
2
Fuel savingDuring 2010, PPCs thermal plants produced 27,440 GWh from lignite, 113 GWh from heavy fuel and6,042 GWh from natural gas. The average specic consumption of PPCs thermal plants is estimated at
2.264 kcal/kwh. Therefore, the amount of thermal energy to be saved with the project for 70,000 MWh is158.48 Gcal or 15.85 toe of the mixture.
Contact Person:Mr. Georgios MarkouProject ManagerTel: [email protected]
The Megalopolis PVProject will be the biggestsolar park in Greece, and the
rst solar park among a large
port folio of about 360 MW
to be constructed by
PPC Renewables.
The project is fully licensed
and, after a public
tendering procedure for the
construction of a turnkey PVpower plant, PPC Renewables
has recently selected the EPC
contractor. Construction is to
begin within the next months.
The project enjoys high levels
of irradiation as well as a
very attractive feed-in tariff
regime. PPC Renewables
expects that, following the
notice to proceed to the EPC
contractor, the project will
be fully operational within14 months. The project will
consist of 212,740 PV panels,
36 central inverter stations
and also includes the
construction of a high
voltage substation.
proect reported by
Solar Energy:Megalopolis PV Project
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
19/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 17
Project descriptionTurning wood into watts and warmth briey describes the key task and benet of the large-scale forest
biomass power station located in the cit y of Vienna in the southeastern district of Simmering. The wood-red cogeneration plant (combined heat and power generation/CHP) was launched as a agship project
to reduce greenhouse gas emissions, boost renewable energy technologies and maximise the efciency
of energy conversion, all at the same time. The plant is a joint project undertaken by Wien Energie (themunicipal energy provider of Vienna) and the sterreichische Bundesforste AG (Austrian Federal Forests).By combining the use of a local green energy source the plant is almost exclusively red with wood
chips from forest residue with advanced CHP-technology, the plant contributes to an efcient and
environmentally sound supply of heat and power to Austrias capital.
In order to realise the project, favourable framework conditions were pivotal, such as subsidies via a xed
feed-in tariff for green electricity and the availability of an ideal plant location. Hence, an existing Wien
Energie thermal heat and power generation site was selected to utilise existing infrastructure such as thedistrict heating and power grid, rail and road connections and qualied staff. Given the respectable size
of the plant, which requires a signicant biomass input, logistics and long-term contracts regarding fuel
supply played an important role. The relatively short transport distances more than 80% of the wood issupplied from the surrounding area within a radius of 100 km or less save costs and bring added valueto the region. The woody biomass is either transported to the biomass power plant directly or indirectlythrough the central transshipment site (Albern Port).
The biomass is incinerated in a circulating uidised bed boiler producing high pressure steam. It is
simultaneously converted into electricity and district heat by u sing an extraction condensing turbine withintermediate super heating. High efcient cogeneration raises the fuel efciency of the biomass power
plant up to 80%. The installed capacity is 24.5 MW electric output (16.2 MW electric and 37 MW thermalare generated in CHP-operation). The plant supplies the equivalent of 48,000 households with electricityand 12,000 households with district heating.
Project ReasonThe idea to build a large biomass power plant goes back to the end of the 1990s when the politicalwill to signicantly increase renewable energy production and reduce CO
2emissions gained importance
in Austria and the EU as a whole. Wien Energie has always been committed to the protection of theenvironment and the efcient use of resources. Wien Energie has longstanding experience in operating
high efcient CHP plants and is increasingly investing in renewable energy. The biomass cogeneration
plant represents the synthesis of these two sustainable approaches. Since 2006, the biomass plant hasbeen making a signicant contribution to reaching the emission abatement targets set in the Kyoto Protocol
and the renewable targets required by the Renewable Energy Directive (2001/73/EC). Furthermore, socialbenets are triggered through creation of regional employment and increased security of supply.
Project appraisalBy using forest biomass to produce electricity and district heating, the amount of fossil fuel needed
could be reduced by the equivalent of around 44,000 tonnes of heavy oil per year in comparison to aconventional power plant with the same efciency factor.Compared to conventional electricity (ENTSO-E mix from fossil fuel) and heat production (from AustrianCHP plants), the biomass power plant in Simmering emitted 149,000 tonnes of CO
2eq less in 2010,
147,000 in 2011 and projected 154,000 in 2012.
Contact Person:Mr. Thomas StraussWien Energie Fernwrme /ManagerTel: +43 (1) 4004 [email protected]
A mix of innovativesolutions is the key to asustainable energy supply
tomorrow. The forest
biomass power plant in
Vienna presents a role
model in this respect. It is
embedded in Wien Energies
large energy production and
supply system. It combines
the use of renewable energy
sources with advancedCHP technology.
However, it not only
contributes to environmental
benets such as the
reduction of fossil fuel
consumption and CO2
emissions but also enriches
the region with social and
technological benets. The
citizens of Vienna benet
from improved air qualit y,
the creation of employment
in the region and increased
autonomy as the fuel (wood)
is homegrown in arborous
Austria . Our project proves
that caring for nature can
benet both, the environment
and the citizens.
proect reported by
Biomass Power Plantin Vienna
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
20/68
Innovative Projects18
Project DescriptionVasilikos Power Station of the Electricity Authorit y of Cyprus is situated on the southern coast of Cyprus.Phase I was commissioned in 2000 and consists of two 130 MW heavy fuel oil steam units (Units 1 & 2)and one 38 MW diesel oil red gas turbine. Phase II consists of one 130 MW heavy fuel oil steam unit (Unit3). Phase III consists of a CCGT block in a conguration of two gas turbines and one steam unit (Unit 4)with a maximum continuous rating (MCR) electrical output of 220 MW.
The Vasilikos Power Station Phase IV project consists of a CCGT block in a conguration of two gasturbines and one steam unit (Unit 5) with a maximum continuou s rating (MCR) electr ical output of 220 MW.The CCGT will initially operate on distillate fuel oil and will switch to fuel gas once natural gas becomesavailable at the site. Due to recent developments involving the possible discovery of natural gas reservesin Cypruss Exclusive Economic Zone, the initial plans to supply liqueed natural gas (LNG) and developthe necessary infrastructure for regasication of the LNG have been suspended. EAC is now awaiting apolitical decision as to how and when natural gas will be made available in Cyprus. The distillate fuel
oil is a low sulphur fuel, containing a maximum of 0.1 per cent sulphur. This compares favourably to theheavy fuel oil used on-site for the other three steam units, which has a typical sulphur content of less orequal to 1.0 per cent. The rst fuel ring of gas turbine GT51 of unit 5 took place on 14 April 2011 andthe respective ring of gas turbine GT52 on 10 May 2011. The performance tests were then carried outand the two gas turbines operated in an open cycle mode. Full commercial operation was scheduled totake place towards the end of 2011. Unfortunately on 11 July 2011, due to an explosion at the adjacentMari Naval Military Base, Vasilikos Power Station suffered extensive damage which caused the completeinterruption of its operation. Unit 5 suffered damages as well and the EAC is currently proceeding with itsrestoration along with the stations other four units. It is expected that Unit 5 will be back in service in anopen cycle in July 2012.
The 170 MW minimum electrical output will be achieved on both distillate and gas red operation. Theconversion of the CCGT plant from distillate fuel operation to gas-red operation was included within theGas Conversion Works of the EPC (Engineer Procure Construct) Contract. The plant has been supplied withbypass stacks. It will opera te continuously throug hout the year and has been designed to have a minimum
net operational life of 30 years. During natural gas ring emissions of oxides of nitrogen (NO x) will becontrolled by the use of Dry Low NO
xburners. The ue gases from each gas turbine will be discharged
via a dedicated 75m stack. A 25m blast stack will also be provided for each gas turbine. During distillatefuel oil ring the emissions of NO
xwill be controlled by water injection. Unit 5 is expected to be ofcially
commissioned in the second half of 2012.
Project ReasonsThe investment is part of the generation expansion plan of the Electricity Authority of Cyprus for securingthe islands power supply taking into account the latest global developments in the energ y, environmentaland electricity sector as well as the necessity to fully implement the European Directives and Regulations.
Project Appraisal and Estimation MethodsApart from the obvious economic benets, it is expected that the project will result in signicantenvironmental benets (e.g. lower CO
2-emissions, lower NO
xemissions), economic benets (less fuel
consumption) and improved system reliability.
Other InformationThe cost of No.5 Unit is expected to reach 239 million, excluding any cost for its restoration due to thedamages suffered from the e xplosion.
Contact Person:Mr. Polyvios PolyviouGeneration DevelopmentManagerTel: [email protected]
Vasilikos Power StationPhase IV consists of onecombined cycle unit with a
capacity of 220 MW (Unit
5). The contract for the
construction of the unit
was awarded to the joint
venture J&P Avax / Hitachi
Power Europe in 2009.
A separate contract was
awarded for the maintenance
of the gas turbines for a
period of six years fromthe date of commercial
delivery of the turbines. The
contract was awarded to
the manufacturer of the gas
turbines, General Electric
USA. The contract covers the
planned maintenance of the
gas turbines as well as the
provision of spare parts. At the
same time a strategic stock
of spare parts will be kept on
site in order to avoid delays in
case of unexpected defects.
During the rst years ofoperation the unit will operate
on distillate oil until the arrival
of natural gas in Cyprus.
Thereafter it will operate
on natural gas as the main
fuel. The new CCGT unit will
provide electricity to the local
grid in the most efcient,
reliable and environmentally
acceptable manner currently
commercially possible,
providing the Electricity
Authority of Cyprus with the
exibility to meet the growing
demand and thus securing
the electricity supply
on the island.
proect reported by
Combined Cycle Gas Turbine(ccgt) unit 5
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
21/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 19
proect reported by
With its 2009-2013Technology Plan Endesa hasstrengthened its researchactivities, technologicaldevelopment and innovationin order to achieve the highestefciency levels while seekingsolutions to a sustainableenergy model. In this model,Endesa is committed to takingleadership in CO
2reduction
technologies throughdeveloping CCS projects.Endesa is actively taking
part in the European Unionsenergy policy, whichhighlights CCS as a prioritytechnology, as set out inthe Seventh ResearchFramework Programme.
Among the different CCSprojects in which Endesa isinvolved, we would highlightthe following: Compostilla-OXY-CFB-300
project, to develop theoxy-combustion technologyin circulating uidised bedboilers with CO
2storage in
deep saline aquifers. "Less CO
2in Compostilla"
project, to capture CO2
usingchemical absorptionby amines.
La Pereda project, asdescribed here.
CO2
capture pilot plant withalgae, developed in thethermal power plantin Almera.
The objective of these projectsis to validate the selectedcapture technologies at acommercial scale. This willallow the renewal of existing
fossil fuel power plants whilereducing CO
2emissions into
the atmosphere as part of theght against climate changein the near future.
Contact Person:Mr. Andrs Sanchez-BiezmaR&D Unit Project ManagerTel: [email protected]
Research Project on co2
capture in La Pereda
Project DescriptionEndesa, in collaboration with Hunosa and the National Agency for Scientic Research Council (CSIC), has
carried out the construction of a 1.7 MW pilot plant for CO2
capture in La Pereda (Mieres, Asturias), closeto the modern thermal power station of La Pereda, owned by Hunosa. The plant has been designed for
the development of the cycle carbonation technology for CO2
capture, using limestone as sorbent.
The plant has two circulating uidised bed reactors with 15 metres interconnected. In the calcination
reactor, the limestone will decompose into calcium oxide and highly concentrated CO2. The calcium oxide
is then sent to the carbonation reactor where it reacts with the combustion gases by capturing the CO2
tocreate limestone again.
The plant is designed to treat up to 2,600 m3/h of ue gas and has a capture capacity of 8 tonnes of CO2
per day with efciencies of around 90%. The implementation began at the end of 2011; the testing
period of CO2 capture began in early 2012.
This plant is the largest in the world with this CCS technology, and is also the rst time that this technology
has been integrated into a thermal plant to treat real combustion gases.
Project ReasonsCarbon capture and storage (CCS) is a powerful tool to mitigate climate change. Endesa therefore support stechnological leadership through the development of a number of different CCS projects.
The CSIC has been collaborating with Endesa in dif ferent research projects for years. Since 2000 it has
been developing the application of carbonation-calcination cycles for CO2
capture processes from coalcombustion. These tests have obtained promising results in the laboratory, showing a great potentialto reduce the cost of CO
2capture. This system is applied to existing and newly constructed coal plants
because the high energy consumption required for the regeneration of the sorbent (calcination) isrecovered in heat sources at high temperature, facilitating its use in a steam cycle power plant. The
construc tion of the La Pereda pilot plant is the next milestone towards the development of this type of CO2
capture. The object ive of this project is to demonstrate the technical feasibility of this capture technolog y,at a lower cost than other alternatives.
Project Appraisal and Estimation MethodsThis project is at a pilot phase so it is not yet possible to estimate the real emissions reductions that it
could generate. However, the reduction potential is clear as it would allow the capture of CO2
emissionsgenerated in the operation of power plants.
In addition to the construction and start of the pilot plant in 2011, we have worked in the laboratory with30 KWt, stably and continuously achieving efciency ratios above 90%. Based on these efciencies, we
have developed an integration analysis of this technology in a real plant. First results show that the plantefciency would be reduced by merely 7-8 percentage points, compared to the 10-12 points of other, more
developed technologies that were considered, such as post-combustion with amines or oxy-combustion.
During 2012, we will try to validate the previous laboratory results at a pre-industrial scale.
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
22/68
Innovative Projects20
proect reported by
Why was biomass chosenas the project fuel?The carbonator needs a
high volatile fuel, and
biomass meets perfectly
this requirement. On the
other hand, biomass is a
natural way to reduce the
CO2
concentration in the
atmosphere, therefore CO2
capture and storage frombiomass combustion is a way
to reduce CO2
concentration
in the atmosphere and
to produce energy at the
same time, so the concept
'negative emissions' comes
up. The process requirements
will be perfectly met by
using another high volatile
fuel, but in this scenario we
wont be able to talk about
negative emissions but only
emissions reduction. That is
why biomass adds an extra
value to the Project. In fact,
Gas Natural Fenosa obtained
the patent for 'Procedure
and device for the CO2
free
biomass combustion'.
Contact Person:Mr. Carlos Perez RosLess CO
2GNF
Project ManagerTel: +34 [email protected]
Less CO2
Project (CCS)
Project DescriptionThe Less CO
2Project studies the technical viability of capturing carbon dioxide (CO
2) in a cost- effective
way through carbonation and calcination technologies. The 300kWt demonstration plant, the rst of itskind worldwide, is located next to the La Robla coal power plant in the Spanish province of Len.
The plant commissioning work began under the CENIT CO2
framework, and was carried out from 2006 to2009. A National Consortium for Technical Investigation was in charge of the programme, and as a resultof Gas Natural Fenosas active membership in the CENIT CO
2, the plant was commissioned in 2010. Since
then, several tests and studies have been conducted to set operational and design parameters whichwould allow the commissioning of a 5MWt plant in the near future.
The carbonation and calcination technology is based on the reaction between CO2
and calcium oxide (CaO)to produce calcium carbonate (CaCO
3). The industr ial facilit y consists of two interconnected reactors ,
a carbonator and a combustion chamber, both running at atmospheric pressure and at temperaturesof 650- 700C and 850-950C respectively. In the carbonator, the fuel combustion (biomass) produces
CO2, which reacts with the CaO added to the combustion to produce CaCO3. The combustion emissionsare therefore CO
2-free. The CaCO
3is then burned in the combustion chamber to produce CaO, which is
re-introduced into the carbonator, closing the cycle. Overall process efciency is determined by thecombustion temperature, which is therefore a key factor to manage. Theoretically, the carbon captureefciency of this process is 100%, however experimental results so far show 80% efciency.
The development of carbon capture and storage technologies is considered as one of the measures witha high potential of reducing greenhouse gas emissions.
Project ReasonThe challenges associated with climate change are driving actions by the energy sector in research,development and innovation. Following this trend, and in accordance with Gas Natural Fenosas businessstrategy on climate change, the Less CO
2Project addresses Gas Natural Fenosas commitment through
research and development on carbon capture and storage technologies.
Main objectives:
Develop Carbon Capture Technology through R&D projects. Test a new sort of power plant, able to produce electricity and to remove CO
2from the atmosphere at
the same time.
Project Appraisal and Estimation MethodsProject Appraisal: Optimize the 300 kWt plant and study the technical and economical viability in a 5MWt plant. Develop an experimental programme in order to study: operation parameters, potential fuels and sorbents. Track different sorts of reactors in order to interpret the experimental data obtained.
Estimation Methods:
CO2
emission factor of cellulose: C6H10O5 + 6O2 6CO
2+ 5H
2O; which implies 1,623 kg CO
2/ kg of cellulose
NCV of biomass: 15 MJ/kg Installed Capacity: 300 kWt Full Load Equivalent Hours: 4000 hours/year Capture Efciency: 80%
Electricity generation efciency: 40% Biomass Consumption: (300 kW x 4000 hr/yr) / (15 MJ/KG) = 288 tons of biomass/year Absorbed Emissions: 0.8 x 288 tons of biomass/yr x 1.623 tCO
2/ton of bioma ss =374 tCO
2/yr
Electricity Generation: 0.4 x (300 kW x 4000 hr/yr) = 0.48 GWhe Emissions Factor: - 374 tCO
2/0.48 GWhe = -780 tCO
2/GWhe
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
23/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 21
Project DescriptionEndesa is committed to developing projects that improve energy efciency, thus reducing the environmentalimpact of its projects. Therefore, Endesa, anticipating the arrival of natural g as to the Balearic system, hasbeen meeting the needs of new production capacity by incorporating new combined cycle.
The plants included in this project are the power plants Cas Tresorer and Son Reus, both located in themunicipality of Palma de Mallorca. Cas Tresore has two combined cycle with a total installed electricalpower of 477,4 MW. Son Reus has two combined cycles for a total of 457,6 MW while the t wo gas turbinesand two diesel motors from the Ibiza plant that have been converted to add a power of 88,4 MW. Up tonow the plants have been operated as combined cycles fueled by diesel. However, these were developedto consume gas when this was available in the islands after incorporating certain modications. Aftercompletion of the pipeline in 2010 which supplies natural gas to the Balearic Islands, Endesa beganworking for the conversion to natural gas of the combined cycle plants Cas Tresorer and Son Reus inMajorca, and Ibiza power plant. Dur ing 2011 the conversion of the different groups included in the project
took place and the groups are already operating with natural gas, making it possible to convert a total of1023 MW for the use of natural gas.
This is a very ambitious project, not only because its objective is to get the gasication of two islands,but also because from a technical perspective to adapt the combined cycle (gas turbines based on GEtechnology 6FA / FA + e) and diesel motors (MAN 48/60) so it can operate with t wo combustibles, throughthe use of gasoil (combined cycle) or fuel oil (diesel motors) to natural gas, is a wor ld premiere. This has ledto some technical difculties due to lack of technical expertise, as there are no similar experiences to drawupon. This conversion, which represents an investment of 45 million Euros has involved the installation ofa regulating and metering station of gas at each plants and equipment modications to the combustiblesupply, combustion chambers and systems control to t the new operation.
Once these modications have been implemented, the natural gas is considered as the principalcombustible, while diesel fuel becomes the reserve combustible to be used only during periods ofunavailability of natural g as to ensure electricity production.
Project reasonAnticipating the arrival of natural gas to the Balearic system, Endesa has built and started during the 2002-2010 period four combined cycle, the most efcient and with the lowest environmental impact technologythat currently exists in the eld of power plants. The use of natural gas as combustible for electricityproduction in the Balearic power plants implies a diversication of energy supply sources. It also impliesan lengthening of the components lifetime and at the same time a very important simplication isachieved in the management of fuel due to the elimination of truck trafc for the transport of gas oil. Thisfuel switching has resulted in a increase of the energy efciency of the power plants and also a signicantreduction in CO
2, S
2O and particulate matter emissions has been achieved. Also the arrival of natural gas
to island systems enables a substantial reduction of operating more polluting equipment.
Project appraisal and Estimation MethodsThe introduction of natural gas as fuel in combined cycle plants of Mallorca offers signicant environmental andtechnical benets that are specied in a substantial reduction in greenhouse gas emissions to the atmosphere: 31.34 % reduction in carbon dioxide emissions (CO
2) 58.3% reduction of nitrogen oxides (NO
x)
100% reduction of sulfur dioxide (SO2) 100% Particle Reduction
The above percentages mean a reduction of emissions into the atmosphere, with reference to the year 2009(when it had not yet begun the process of transformation), about 282098 tons of CO
2, 2478 tons of nitrogen
oxides, 701 tons of SO2
and nearly 69 tons of particulate mat ter each year.
Contact Person:Mr. R. Fortuny ZafortetaProject Manager of the switchto natural gas in the Balearics
Tel: +34 [email protected]
Contact Person:Mr. I. Pescador ChamorroDirector - Powergeneration IslandsTel: +34 [email protected]
For Endesa, energyefciency means transformingand using energy in the mostintelligent and optimum waypossible throughout its valuechain while maintaining thesame quality of the servicesit offers its customers. Theenergy efciency Endesaachieves in using the naturalresources at its disposalis a key parameter for thecompanys generationbusiness. Efciencyimprovements in thegeneration business directlyimpact the consumption ofprimary energy and helpslash CO
2emissions, as a
high percentage of fossilfuels are used to produceelectricity. The project "FuelSwitching Baleares" uses thebest available technology forits business, analysing and
anticipating the availability ofnew, more efcient resourcesin the territory where
it operates.
proect reported by
Fuel Switching Baleares
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
24/68
Innovative Projects22
proect reported by
If Europe increases theproportion of uctuating windand solar energy in power
generation as planned over
he next years and decades,
hen todays electricity grids
and available storage capacity
will no longer be sufcient.
Electricity grids and storage
acilities must be rapidly
extended to make the best use
of the increasing quantity ofpower from renewables. For
his reason, E.ON is carrying
out research into different
echnologies for storage and
oad compensation. The most
promising type of storage for
arge quantities of energy is
he extraction of hydrogen
rom excess regenerative
electricity. This hydrogen will
be fed into the existing natural
gas network. In this way, largequantities of energy can be
tored and transported. In
he medium to long term this
torage technology, which is
eferred to as power to gas,
ould provide the required
balance between supply and
demand. In principle, a mass
torage facility and hence a
very large part of the required
nfrastructure is already
available with the natural gas
networks. We will intensively
est and develop this
echnology at our Falkenhagen
pilot plant.
Contact Person:Dr. Urban KeussenSenior Vice PresidentTechnology & InnovationTel: +49 211 4579 [email protected]
E.ON Pilot ProgrammePower to Gas
Project DescriptionE.ON is building an energy storage plant in Falkenhagen, Germany, to convert excess wind power intohydrogen by electrolysis. The hydrogen will be carried via pipeline to a connection point on the naturalgas grid, where it will be injected into ONTRAS/VNGs high-pressure transmission pipeline.
Through this project, E.ON will become one of the rst companies worldwide to demonstrate how
surplus renewable energy can be stored within the natural gas grid, essentially removing the linkbetween generation and demand. There will also be opportunities to establish the potential for
converging electricity and gas grids, determine the optimum mixture of hydrogen within natural gas, andinvestigate the possibility of using the hydrogen-rich gas to generate electricity using combined heatand power plants.
Project ReasonsPower-to-gas is a highly efcient way of storing surplus energy from renewable sources, such as solar
and wind power, until it is required, balancing long-term uctuations in generation. The conventional
conversion process involves using electricity to electrolyse water, producing hydrogen. Alternatively, CO2
from bio-energy facilities can be converted to bio-methane, which can then be fed into the natural gasgrid without any blending limitation.
Project appraisal and Estimation MethodsUsing innovative technology, the Falkenhagen storage plant will produce up to 360Nm/h of hydrogenfrom 2 MW of wind power through electrolysis. The hydrogen will be fed into the natural gas pipeline
at around 2 percent by volume, at a maximum operating pressure of 55bar(g), effectively storing andtransporting surplus renewable energy.
The work scope will include the engineering, construction, commissioning and start-up of a containerised
2 MW electrolyser and compression plant. In addition the project will provide a power substation,metering station, hydrogen pipeline and natural gas grid access station. The diverse programme of workwill encompass conceptual design, detailed engineering, project management, tendering, construction,
commissioning, operation, optimisation and standardisation of the plant, right through to negotiationswith all relevant authorities, as well as gas and electrical grid operators.
Although proven electrolysis technology will be used to get the power-to-gas plant up and running,
the project will enable E.ON to gain a greater understanding of the technical and regulatory challengesinvolved in the set-up and operation of such storage plants, and to acquire valuable practical experiencefor application in future multiple or larger installations. The knowledge and experience gained will allowE.ON to dene sound business models and place it in a strong position to win business in countries
looking for proven, cost-effective and environment-friendly ways to store renewable energy.
Above all the project will demonstrate the effective storage of renewable energy within the gas grid.
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
25/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 23
Project DescriptionSchlieren, a municipality in the canton of Zurich, is a former industrial zone that has been transformedinto a new residential district.
The supply of district heating and cooling is typically cost-effective in areas of high-energy demand. Incooperation with the City of Schlieren and the Swiss Post, ewz (Elektrizittswerk der Stadt Zrich) hascreated a major energy net work that takes advantage of locally available heat sinks and sources and localdemand for heating and cooling.
The energy net work exploits the proximity of environmentally friendly waste heat arising from the coolingprocess for heat generation purposes. Treated wastewater from the nearby sewage plant is used tobalance out the network's heating and cooling needs. If the demand for cooling produces surplus heat,the system is cooled with water from the plant. This is a highly efcient cooling process, since the wateris typically colder than outside temperatures in summer. If the demand for heating produces surplus
cooling, water from the plant is used as a source for the heat pumps. The Schlieren energy network is oneof Europes largest facilities using treated wastewater as an energy source.
ewz submitted this project as part of its bid in a public tender in 2005. The energy plant for the SwissPost distribution center was rst realized in 2006. Today, a number of heating and cooling power stationsmeet the heating and cooling needs of ofce buildings, a shopping center, a Do-it-yourself market andapartment blocks. Zurich Insurance's central computing center feeds additional heat into the network.The energy supply includes a large-scale heat pump that operates on ammonia, an environmentallyfriendly substitute with a low climate change impact.
The success of this project is testimony to how energy-efcient and competitive solutions can be createdusing an innovative combination of energy systems. The Schlieren energy network is a prime example ofhow heating and cooling demand can be met by a large-scale, environmentally friendly, cost-effectivesystem that uses treated wastewater as an external energy source.
Contact Person:Mr. Christoph DeissHead of SalesTel: +41 58 [email protected]
As an energy contractor,we develop environmentallyfriendly and competit ive
solutions in order to provide
our customers with a reliable
supply of heating and
cooling energy.
In the town of Schlieren
we have several major
customers with heating and
cooling needs, such as theSwiss Post's distribution
center and a new residential
district. By means of a district
heating and cooling grid, ewz
has connected the heat sinks
and sources in a two-stage
project that uses wastewater
from the nearby sewage
plant to balance out the
system's heating and cooling
needs. ewz submitted this
solution in its bid as part of
a public tender in 2005. The
cost-efcient solution with
tailor-made contracts for all
partners involved guarantees
heating, cooling and power
supply 24x7, 365 days a year.
This carefully developed,
state-of-the art project is
worthy of repetition as it
brings about a considerable
reduction in the amount
of energy required not to
mention CO2 emissions.
proect reported by
Schlieren District Heating
post centre Mlligen Entire Schlieren network
heat requirement per year 9,500 MWh 52,000 MWh
Cooling requirement per year
Heat pump (NH3)
Refrigerant machine (NH3)
8,400MWh
5.6MW
4.3MW
21,800MWh
11.1MW
9.0MW
Gas/oil-red boilers ( peak load)
Ecology
Saving of fossil fuels per year
corresponding CO2
reduction per year
6,100MW
6,100MWh
1,200t
17.0MW
48,700MWh
8,100t
Existing energy network using waste heat.
9100 MWh natural gas/oil
22 400 MWh wastewater
purication plant
9100 MWh electricity
Gas/Oil-redboilers
Heatingunits/refri-gerationplants
8200 MWh
29200 MWh 54200 MWh 52000 MWh hea t
16800 MWhwaste heat used
2200 Mwhloss to network
8000 MWh waste heat unused
22500MWh 21800 MWh cooling
700 MWhloss to network
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
26/68
Innovative Projects24
Project descriptionThe aim of the project is to build the worlds rst commercial-scale demonstration plant based oncombined heat and power (CHP) integrated fast pyrolysis of biomass, producing bio-oil to replace heavyfuel oil. The plant will be constructed at the Joensuu CHP plant in eastern Finland. Fortum will implementthe project in cooperation with Metso and VT T.
The consortium (Fortum, Metso, UPM and VTT) has developed a pyrolysis process which integrates aconventional uidised bed boiler. In this CHP-integrated bio-oil production process solid biomass ispyrolysed and condensed into liquid form.
This so-called fast pyrolysis bio-oil is derived from biomass by a thermal process without the presence ofoxygen. The produced bio-oil is a complex organic mixture with a high energy density compared to forestbiomass. It is a suitable fuel for district heat production and the processing industry, and has a greatpotential to replace fuel oils.
The planned annual capacity of bio-oil is 50,000 t/a corresponding to about 200 -250 GWh of fuel. Primar yraw material is forest residues. Pyrolysis bio-oil can be produced from almost any organic material, butto ensure a sustainable and a renewable product, only 100% renewable biomass will be used as rawmaterial. In order to increase demand for pyrolysis oil in local fuel markets, the target is to promote thestandardisation of bio-oil.
Project reasoningFortum's long-term aspiration is to be a CO
2-free power and heat company. Climate change mitigation is
one of the core areas in the company's strategy and the company wants to provide sustainable solutionsfor the society. At least in the beginning, the bio-oil can be used in Fortum's own energy productionplants. In addition to business benets, the replacement of fossil fuels with renewable and sustainablefuels is one of Fortum's actions towards CO
2-neutral production.
By utilising domestic forest biomass as raw material for bio-oil, Fortum wants to ensure that the raw
material does not compete with food production. Fortum has recently established guidelines and criteriafor sustainable use of bioenergy in its energy production.
Project Appraisal and Estimation MethodsThe EUs RES Directive sets sustainability criteria for biomass-based fuels. Based on our analyses,replacing fossil fuels with pyrolysis oil reduces greenhouse gas emissions by more than 70% comparedto fossil fuels, therefore clearly fullling the Directives requirement of 60% emissions reduction.Using 210 GWh (50,000 tonnes) of pyrolysis oil to replace heavy fuel oil, the CO
2-emission and SO
2-
emission reductions will be about 59,000 t and 320 t respectively.
Project timescheduleThe investment decision was made in February 2012 and detailed engineering began immediately.Commissioning of the pyrolysis plant is planned for autumn 2013.
Other benets of the projectIn addition to reducing CO2
emissions, replacing fuel oil with pyrolysis oil will also reduce SO2
emissions,as the bio-oil is almost sulphur-free.The project will provide considerable local employment benets and the impact is estimated to be about60-70 man-years. Employment during construction phase is about 2,200 man-days.
Contact Person:Mr. Jukka HeiskanenHead of R&D, Heat DivisionTel: [email protected]
Being involved inthe development of aninnovative new technological
solution for sustainable
use of resources is utmost
challenging, but also
rewarding", says Jukka
Heiskanen, Head of R&D
in Heat Division. "Fortum,
Metso and VTT (Technical
Research Centre of Finland)
each being leadingorganisations in their
business area are in an
excellent position to create
a robust new technology
concept for biomass
utilisation. Our project is
a good example of joint
interests of political decision
makers who need a solution
for climate change and
companies that can create
opportunities for futurebusiness. If this project is
successful, the developed
pyrolysis technology can be
used extensively providing an
important addition to climate
change mitigation toolbox.
This is one of our solutions to
create energy that improves
life for present and future
generations.
proect reported by
Joensuu CHP-Pyrolysis Project
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
27/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 25
Project DescriptionZEDO is one of 11 divisions of PGE PGE Grnictwo i Energetyka Konwencjonalna S.A.. ZEDO consists ofthree plants. Activity of the branch is heat and power generation. The main fuel is hard coal, but alsobiomass is used in the combined cycle. In Szczecin Plant the largest biomass boiler in Poland was put intooperation in Dec. 2011. New biomass fueled unit have replaced 5 exploited carbon units (2 pulverized-fuel boilers and 3 stoker-red boilers). The installation consists of 1 uidized bed biomass boiler and 1small emergency boiler based on heating oil bioester. The new unit supplies green electricity and heatto one third of citizens in Szczecin.
The parameters of the biomass installation are: Total green energy generation is 440,000 MWh/a. Heat generation is 1,900,000 GJ/a. Annual biomass consumption is at the level of 550,000 Mg/a. Power heat generation - 183 MWt,
Steam generation 230 t/h, steam temperature 535 C, steam pressure 70 bar.The unit will fulll EU criteria for high efcient cogeneration. The project realization brings positiveimpact on environment, improves energy conversion level and decreases GHG emissions. This projectallowed the displacement of high emitting sources (old fashioned coal red boilers) by a new green unit.Comprehensive ecological effects are as follows: CO
2emission reduction as a consequence of cool replacement with biomass,
SO2
emission reduction of 69% Dust emission reduction of 63% Reduction of 80% of waste/by-products with reference to current level.
Project reasonsThe investment was voluntary undertaken by the company but inuenced by EU/national regulations.
Project Appraisal and Estimation Methods:The project resulted in signicant environmental (e.g. lower CO
2emissions, lower power consumption)
economic (e.g. power savings) and social (e.g. improvement of the power plants image) benets.
For the estimation of CO2 emissions reductions, the following calculation was made:Emission with project:
Emission with project comes f rom biomass burning and is recognized as avoided emission. CO2
reductionshave been estimated on the basis of avoided emission for the same production level previously based onhard coal in Szczecin CHP. The estimation has been made for one month (December 2011) and forecastedfor next (2012) year. Emission with project (biomass): ECO
2= recognized as non emitted = 0 [tCO
2]
Emission without project:
Calculation is based on chemical energy of used coal, that would have been burned to achieve the samegeneration level. Example for December 2011: fuel (coal) consumption = 18,000 [Mg] Do;
heating value = 0.025 [TJ/Mg] Dz;
Emission without project (coal): ECO2
= Do x Dz x WeCO2
x WuECO
2= 18,000 [Mg] x 0.025 [TJ/Mg] x 93.97 [MgCO
2/TJ] x 0.985 = 41,652 [MgCO
2].
Achieved CO2
emission reduction in December 2011: 41,652 [MgCO2].
Forecasted CO2 emission reduction in 2012: 500,000 [MgCO2].Fuel savings:Coal consumption for heat generation in Szczecin CHP before project implementation was at the level of18,000 [Mg] per month. Fuel saving results from coal switch to non-emissive biomass. Fuel saved inDec. 2011: 18,000 Mg of hard coal.Forecasted fuel savings in 2012: 216,000 [Mg of coal].
As the biggest lignite, heatand power producer in Poland,we feel responsible both forthe countrys energy securityand natural environmentprotection. PGE GiEK SA iscommitted to conducting itsabove-mentioned businessactivities in a sustainablemanner and in compliancewith high ecological standardsand the principles of corporatesocial responsibility. Power
generation companies andCHPs of PGE Group havelong followed an emissionsreduction programme.Signicant power generationefciency improvement hasbeen achieved on existingunits and considerable amountof biomass co-burning andbiomass dedicated units havebeen implemented. CHPsbest results are related toreplacement of old-fashionedcoal-red units by high
efcient combined cycle units.Our generation assetsmodernisation programmehas been running step bystep since 2004. It results inreduced CO
2emissions and
efciency improvement. Ourunits efciency is amongthe highest in Polish powercompanies based on lignite.Our projects submitted to theEWP Report are only examplesof PGEs involvement in GHGemissions reduction. Thehighest available techniquesin biomass, both within Polandand the European Union, havebeen applied for the SzczecinCHP project.
proect reported by
Szczecin CHPBiomass Contact Person:Miroslaw NiewiadomskiPGE EWP ProjectsTel: +48 [email protected]
oxidation factor = 0.985 Wu;
CO2
emission factor = 93.97 [MgCO2/TJ] WeCO2;
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
28/68
Innovative Projects26
Project DescriptionThe energy production at Helsingin Energia is based on combined heat and power generation (CHP) withoverall efciency rate of energy generation exceeding 90%. The Vuosaari B CHP plant has two V94.2
gas turbines supplied by Siemens. The original electric power output of the gas turbines at ambient
temperature of 0C was 163 MW and the efciency rate approx. 33.7%. Siemens has developed a blade
modernisation pack (Si3D) for the gas turbine type, which raises the gas turbine output and efciency
rate. The modernisation involves tting the turbine with new type of blades and vanes, with modied ow
geometry and improved cooling, whereby the ow of cooling air required may be reduced. The seals of
the turbine section have also been improved in order to reduce losses. Ceramic coatings are used on theblades and the inner casing, which also permits a higher combustion temperature than was previously
possible.
The pack was installed in the rst two stages of Vuosaari B gas turbine 4 at the annual overhaul in 2009
and in all four stages of gas turbine 5 at the annual overhaul in 2011. Performance test were carried out
on the turbines before and after each overhaul. After the tests, the combustion temperature of bothturbines was set at 1065C.
Project ReasonHelsingin Energia has signed up to an Energy Efciency Agreement, and has set as its goal to further
improve the efciency of its energy production, already at a good level. Energy efciency is part of
Helsingin Energias development programme towards carbon-neutral energy production by 2050.
Energy audits have been carried out at all the power plants and energy efciency measures implemented
based on their results. The turbine blade modernisation of Vuosaari B plant has proved to be one ofthe most effective energy efciency measures.
Project Appraisal and Estimation MethodsPerformance test showed that the efciency rate of gas turbine 4 increased by 1.19 percentage points
and that of gas turbine 5 by 1.52 percentage points. As the combined effect of the modernisation and the
increase in combustion temperature, the output of gas turbine 4 increased by approx. 11.5 MW and thatof gas turbine 5 by approx. 13 MW.
The Vuosaari B performance data at reference point 0C changed after modernisation as follows:
Year 2008 2009 2011
Overall electric power output 460 MW 471 MW 486 MW
Back-pressure mode power production efciency rate 47.9% 48.6% 49.2%
Power-to-heat ratio 1.07 1.098 1.125
District heating output has remained the same at the reference point following the modernisations.
The savings in fuel volumes and reduction in CO2
emissions were estimated by scaling so that the plantwould produce the same volume of power before modernisation and after it.
This gives the result of an annual saving of fuel energy of approx. 210 GWh and a reduction in CO2
emissions of approx. 43 kt after both modernisation phases.
Contact Person:Mr. Jyrki HaniojaPower Plant ManagerTel: [email protected]
The greatest productioncost of a combinedcyclepower plant is the fuel it
uses. The CO2
emissions
are directlyproportionate
to the volume offuel
used. Therefore, every
measure that reduces fuel
consumption also reduces
the environmental impacts
of the powerplant. The
actual increase in the power
production efciency could
be described by saying
that on an annual level, we
manage to produce the same
amount of electricpower as
before the modernisation,
butby consuming as much
less natural gas as we
previouslyconsumed in
9 days. Atthe same time,
we produce no nitrogen
oxides orcarbon dioxideduring those 9 days.
proect reported by
Improving Energy Efciency ofa Combined Cycle Power Plant
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
29/68
ENERGY WISDOM PROGR AMME 2012-2013 Edition 27
proect reported by
As the biggest lignite, heatand power producer in Poland,we feel responsible both for
the countrys energy security
and natural environment
protection. PGE GiEK SA is
committed to conducting its
above-mentioned business
activities in a sustainable
manner and in compliance
with high ecological standards
and the principles of corporatesocial responsibility. Power
generation companies and
CHPs of PGE Group have
long followed an emissions
reduction programme.
Signicant power generation
efciency improvement has
been achieved on existing
units and considerable amount
of biomass co-burning and
biomass dedicated units have
been implemented. CHPs
best results are related toreplacement of old-fashioned
coal-red units by high
efcient combined cycle
units. Our generation assets
modernisation programme
has been running step by
step since 2004. It results
in reduced CO2
emissions
and efciency improvement.
Our units efciency is among
the highest in Polish power
companies based on lignite.
Our projects submitted to the
EWP Report are only examples
of PGEs involvement in GHG
emissions reduction.
Belchatow Power Plant:New Low GHG EmissionsFossil-Fuel 858 MW Unit
Project DescriptionThe new 858MW power unit working in the Bechatw Power Station is the biggest generation unit in the historyof the Polish power industry and the most advanced power unit in Poland. It was commissioned in September2011. Its advanced technology determines new standards in the Polish industrial power generation. It is themost efcient lignite-fuelled power unit in the country, with the net efciency reaching 42%. Its structure andtechnical parameters allow to generate more power and comply with the European environmental standards.The power unit meets all the requirements of the European Union directives regarding emission of pollutantsinto the atmosphere and is compatible with carbon capture and storage installations.
The new 858 MW power unit, as in the case of the remaining power units of the Bechatw power stationis fuelled with lignite from the nearby lignite mine. The power unit as an independent generating unit hasbeen furnished with all the necessary systems and basic/supporting installations.
Except of widely known technologies, raising the power units efciency as low- and high pressurerecovery and steam overheating, the following systems were applied additionally:supercrit ical steam system I modern systems of the turbine blades I heat recover y from ue gas.
Above mentioned innovations result in the gross efciency exceeding 42%.
Technical ParametersSO
2< 200mg/Nm
3I NO
X< 200mg/Nm
3I dust < 30mg/Nm
3I CO
2< 200mg/Nm
3(5,5 mln t/a)
Project reasonsThe investment was volontary undertaken by the company but inuenced by EU/national regulations.
Project Appraisal and Estimation Methods:The project resulted in signicant environmental (e.g. lower CO
2emissions, lower power consumption)
economic (e.g. power savings, fuel savings) and social (e.g. improvement of the power plants image)benets. For the estimation of CO
2emissions reductions, the following calculation was made:
Emission with project
Calculation is based on CO2
emission factor, comparing old units and the new high efcient one, for the
same production level. Example for year 2011:CO
2emission factor = 0,887 MgCO
2/MWh I power generation = 1.935.200 MWh
Emissions with project are calculated multiplying power generation by CO2
emission factor:1.935.200 MWh x 0,887 MgCO
2/MWh = 1.716.522 MgCO
2
Emission without project:
Calculation is based on CO2
emission factor for the old units for the same production level.
Example for 2011:CO
2emission factor = 1,095 MgCO
2/MWh I power generation = 1.935.200 MWh
Emissions with project are calculated multiplying total power generation by CO2
emission factor:= 1,095 MgCO
2/MWh x 1.935.200 MWh = 2.119.044 MgCO
2
Emission reduction in 2011:2.119.044 1.716.522 = 402.522 Mg CO
2
Forecasted CO2
emission reductions:
Based on 4 month of operation and 402.522 MgCO2 avoided emission in 2011, the new unit will saveabout 1.100.000 MgCO
2each year of operation.
Fuel savings:Calculation is based on factor of chemical energy consumption per generation unit for new and old units.Fuel savings in 2011: 1.935.200 MW h x (9,500 8,145 GJ/MWh) / 7,798 GJ/Mg = 336.265 Mg
Contact Person:Miroslaw NiewiadomskiPGE EWP ProjectsTel: +48 [email protected]
8/2/2019 The EURELECTRIC Energy Wisdom Programme (EWP): Improving Energy Efficiency Reducing Carbon Emissions Me
30/68
Innovative Projects28
Project descriptionWithin Amsterdam New West, an urban area of about 3 by 6 kilometres was selected for this rst iNet
implementation in the Netherlands. It contains approximately 9,000 households and requires 9 MVApower supply. In this area the existing 10 kV radially operated mid-voltage grid has been transformed
into a 20/10kV ring-shaped bidirectional g rid (see pict ure). To achieve this, a 20 km long 20 kV backbonecable was twined into the existing grid, with both ends connected to the primary substation. Existing 10kV cables were transformed into 10 kV secondary rings, with both ends connected to the backbone. Both
the 20 kV backbone and the 10 kV secondary rings are fully bidirectional. All substations within this gridare equipped with advanced substation automation technology. Furthermore a bre optic/GPRS network
was implemented to connect all substations within this grid to the central control department.
The resulting intelligent grid provides:
complete transparency of the grid (current, voltage, power quality, etc. in all stations involved arevisible in the central control dpt.);
full remote control (all substations can be controlled from the central control dpt.);
automatic fault localisation and self-healing functions.
The uniqueness of this smart grid concept lies in the large percentage of reuse of existing assets (>90%)
which makes this concept nancially feasible. Furthermore, this leads to the least cumbersome outcome
for the public domain: less cable to roll out or renew, and few substations to build or replace.
Project Reasons In the Amsterdam New - West Area a lot of solar energy is generated. Many houses in this area are
equipped with solar panels on the roof. Furthermore, the City of Amsterdam is planning to install evenmore solar panels and also wind turbines in the next years. To be able to integrate these renewableenergy resources an in efcient way an intelligent exible grid is required.
As a result of the complexity and age of Lianders grid in Amsterdam the number of outage minutes per
year is substantially higher then in the rest of the area serviced by Liander. Therefore Alliander wants toreduce the number and length of outages in this area by implementing an intelligent self healing grid.
Amsterdam is promoting the use of electrical vehicles. To enable a massive penetration of electrical
vehicles and provide required recharging facilities the underlying electricity grid needs to be intelligentand exible.
iNet results in a far better use of existing assets thereby avoiding massive investments in new andexpensive cables and components, while facilitating both the Citys and Lianders ambitions to reachsustainability goals.
Project appraisal and estimation methodsThe implementation of iNet within the Amsterdam area is above all an enabler facilitating other projects
with a direct positive impact on the reduction of CO2/NO
x. For example, the iNet enables the integration
of solar and wind energy in the traditional grid, and has created opportunities for enlarging the amount ofelectrical vehicles. These initiatives contribute directly to Amsterdams 20-20 objectives.
The reduction of outage minutes on the other hand is a clear direct objective: the initial 35 yearly outageminutes within this area should be reduced by at least 50% as a result of the implementation of iNet.
Contact Person:Mr. Bert HeerbaartProgramme ManagerSmart GridTel: + 31 6 11034291bert.heerbaart@allia