Upload
greg-williams
View
212
Download
0
Embed Size (px)
Citation preview
10
Greg Williams is a Partner in theWashington, DC, office of the lawfirm of Bracewell & Giuliani LLP,
where he counsels U.S. and Canadianclients in both the electric and natural
gas industries on matters such asmerchant transmission development,RTO development, rate regulation,
industry restructuring, energymarketing, and natural gas pipeline
development. Prior to enteringprivate practice, Mr. Williamspracticed at the Federal Energy
Regulatory Commission for a decadebefore serving first as a trial attorneyand then as an appellate attorney. Heholds a J.D. from the University of
Baltimore Law School.
Andrea R. Robinson is anAssociate in Bracewell and Giuliani’sWashington office, where she works
within the Energy andTelecommunications Markets andRegulation Section, focusing on
regulatory work for natural gas andelectric clients before FERC and fortelecommunications clients before the
Federal CommunicationsCommission.
The authors are extremely grateful toJohn J. Bartus, of counsel at Bracewell
& Giuliani, for crystallizing theirthinking on these issues and helpingto organize the manuscript. The viewexpressed in this article are those ofthe authors and not necessarily thoseof Bracewell & Giuliani or its clients.
1040-6190/$–see front matter # 2005 Els
The Energy Policy Act’sReliability Provisions:Uncontroversial, Yes, butDoomed to Ineffectiveness?
The electric industry grew up and matured under aregulatory regime that fostered reliable service asconsistent with the service providers’ best economicinterests. But changes in the focus and structure of theelectric industry have put strains on that regime – asstarkly revealed in the 2003 blackout. Efforts to adoptenforceable reliability standards depend on the threat ofpenalties to outweigh the profit incentives that underminereliability. It is not clear that those penalties will work.
Greg Williams and Andrea R. Robinson
I. Introduction
Arguably the centerpiece, and
certainly among the least contro-
versial provisions, of the Energy
Policy Act of 2005 is Subtitle A to
the Electricity Title, namely the
‘‘Reliability Standards.’’1 Born out
of the Northeast blackout of
August 2003, the Reliability Sub-
title essentially transmutes what
have been voluntary reliability
evier Inc. All rights reserved., doi:/10.1016/j.
standards into mandatory relia-
bility standards, enforceable by
penalty. This article questions
whether those new mandatory
reliability standards will ade-
quately address the reliability
issues now facing the electric
power industry in the United
States, or whether they will turn
out to be off target or incomplete.
W hile the Reliability Subti-
tle was sold as first aid for
tej.2005.11.005 The Electricity Journal
Figure 1: The Reliability Triangle
Ja
the 2003 blackout, the mission is
broader. The history of the electric
power business in the U.S. sug-
gests that a recent systemic shift in
industry focus was at the root of
the 2003 blackout, and as a result,
the Reliability Subtitle’s pre-
scription for relief may not quite
match the disease. The mandatory
reliability provisions have some
potential for positive effect, but a
potential tempered by the very
shift in industry focus that
engendered the need for these
reliability provisions in the first
place.
II. Historic IndustryStructure
In the early years of the Twen-
tieth Century, Samuel Insull
effected a unique bargain with the
leaders of the city of Chicago: his
company would light the city
with electric power, in exchange
for a broad franchise and regula-
tion of his company’s rates by the
state public service commission.2
That arrangement provided the
structure for the privately owned
electric utility business nation-
wide.3
T hat regulatory structure
formed, in effect, a ‘‘relia-
bility triangle’’ among the utility
provider (which at that time was
vertically integrated to include
generation, transmission, and
distribution functions), the con-
sumers, and the regulator (the
state commission) (Figure 1). The
reliability triangle presumes that
electric consumers are primarily
concerned with reliability, as
n./Feb. 2006, Vol. 19, Issue 1 1040-6190/$–s
opposed to rates: if faced with the
prospect of receiving 10 percent
lower rates in exchange for 10
percent less reliable service, most
consumers would presumably
prefer to pay more for electric
service and not have to worry
whether the lights will come on
when the switch is flicked. The
consumer demands that the reg-
ulator ensure reliable electric
service. The regulator (who is
responsive, directly or indirectly,
to the consumer/voter), in turn,
enforces reliable service by con-
trolling the utility’s purse strings.4
Finally, the utility (anxious as a
profit-making enterprise to max-
imize its returns) makes reliable
service to consumers ‘‘job one.’’5
Significantly, under this
arrangement, reliable electric
service is not an adjunct to prof-
itability for utilities, or an adjunct
to the service demands of consu-
mers, or an adjunct to the self-
perceived responsibilities of the
regulator. The great virtue of the
reliability triangle is that it pro-
motes reliable service as a matter
of foremost self-interest for each
of the principal electric industry
participants—utility, consumer,
and regulator. The result, proven
over 80 years, was the most reli-
able electric grid in the world.6
While, at the industry’s outset,
the utilities’ focus was almost
ee front matter # 2005 Elsevier Inc. All rights
exclusively insular, over time,
inter-utility interconnections
became commonplace. The inter-
connections helped reduce the
cost of generation (via shared
costs) and the cost of reliability
(via lower capacity margins).7 But
the interconnections also raised
the prospect of cascading failures
(blackouts) by propagating failure
in one system to other connected
systems.
T he first major blackout
occurred in 1965 in the
Northeast, prompting the crea-
tion of the North American Elec-
tric Reliability Council (NERC).8
NERC is a self-regulatory body
set up by the privately owned
utilities to ensure reliable opera-
tion of the bulk power system –
and hence to prevent future sys-
tem-wide blackouts – without
government mandate.9 NERC
operates through regional coun-
cils that strive to have the utilities
in their region voluntarily imple-
ment reliability standards pro-
mulgated by NERC and the
regional councils.10
III. The IndustryChanges Focus
The 1978 Public Utility Regu-
latory Policy Act (PURPA)11
marked the beginning of a change
of focus of the electric utility
industry. PURPA promoted the
advent of non-utility generators
as competitive suppliers of elec-
tricity in the bulk (wholesale)
market.12 Thereafter, as indepen-
dent (non-utility) generators
began to proliferate, FERC found
reserved., doi:/10.1016/j.tej.2005.11.005 11
Figure 2: The Effect of Order No. 2000 and Other Changes on the Reliability Triangle
12
that because independent gen-
erators exercised no market
power, their bulk sales of electri-
city did not need to be cost-
regulated.13 The result was
further proliferation of indepen-
dent generators.14
R oughly at the same time,
Congress mandated,
in the 1992 Energy Policy Act,
that utilities must provide
transmission service for these
new competitive generators.15
In furtherance of the ’92 Act,
FERC followed with Order No.
888, which required utilities to
provide ‘‘open-access’’ transmis-
sion service.16
Thereafter, wholesale electric
transactions surged. The surge
resulted not only from non-utility
generators, but also from utilities’
affiliates permitted to sell electri-
city in bulk at non-regulated (i.e.,
market) rates.17
These new developments
changed the focus of many utili-
ties. From what had been a single-
minded, profit-driven focus on
reliability, many utilities found
that their profit maximization
objective now had two masters:
profits in retail service were still
subject to the reliability triangle,
but profits in wholesale service, to
varying extents, turned on max-
imizing market sales over the
transmission grid even at the
expense of reliability. At the
extremes, the two masters could
conflict, as market sales might
have to yield to reliable service.
As a result, many utilities became
open to compromising reliability
based on the economic justifica-
tion that it cost less to violate the
1040-6190/$–see front matter # 2005 Els
reliability standards than to fol-
low them.18 As a consequence of
the shift in industry focus – from
reliability toward competition –
many utilities found themselves
of mixed motives, thus clouding
the clear message of the reliability
triangle.19
IV. Change in IndustryStructure
Further change came with
FERC’s Order No. 2000 effort to
foster independent (i.e., non-uti-
lity) operation of the grid. To
maximize the competitive poten-
tial of what FERC hoped to be
regional electricity markets, FERC
encouraged the formation of
region wide independent trans-
mission system operators
(ISOs).20 According to FERC’s
direction, ISOs would have
‘‘functional control’’ of the trans-
mission grid, with ultimate
authority for short-term reliabil-
ity.21 But in practice, the utilities
and the ISOs each had some
imprecise share of control over
the transmission grid and grid
reliability, as ‘‘functional control’’
became the subject of imprecise
(and untested) contract allocation
between the ISOs and transmis-
sion-owning utilities.22
evier Inc. All rights reserved., doi:/10.1016/j.
This change has had an effect
on the reliability triangle. To the
extent that grid reliability is under
ISO control, the tripartite bond
among utility, regulator, and
consumer is decoupled. Unlike
the utility, the ISO answers to
FERC rather than to the state
regulator. And there is no privity
between the consumer and ISO or
between the consumer and FERC.
If ISO fails to deliver reliable
service, there is no profit incentive
at work that might be utilized to
bring ISO into line, nor are FERC
regulators’ careers so directly at
stake. Thus, the new structure
creates a detour from the straight-
line reliability-driven relation-
ships that previously existed
(Figure 2).
In addition, a potential
‘‘reliability gap’’ is created by the
new structure. The insertion of the
ISO into the grid operation equa-
tion means that there are two
entities potentially responsible for
making critical reliability deci-
sions. Under Order No. 2000,
FERC required that ISO have
operational authority for the grid,
including exclusive authority for
maintaining the short term relia-
bility of the transmission grid
under its control.’’23 But FERC was
fuzzy about the ISO’s actual exer-
cise of that operational control,24
tej.2005.11.005 The Electricity Journal
Given the changesin industry focusand structure,the August 2003blackout washardlysurprising.
Ja
and the implementing agreements
between the grid operator (the
ISO) and the transmission owners
reflect that fuzziness.
F or example, in New England,
the Transmission Owners
Operating Agreement between
the transmission owners and the
ISO provides that the ISO shall
take necessary actions to plan and
maintain short-term reliability
and system security, but the
transmission owner shall direct,
operate, and maintain its trans-
mission facilities and local control
centers.25 The NYISO Transmis-
sion Owner’s Agreement
describes two classes of trans-
mission facilities: those under
which the ISO has day-to-day
operational control and those
where the transmission owner is
responsible for notifying the ISO
with respect to action.26 The
NYISO Agreement provides that
the ISO shall ‘‘direct the operation
and coordinate the maintenance
of certain facilities . . .’’27; while
the transmission owners ‘‘shall
operate and maintain the facilities
. . . in accordance with the terms of
the Agreement . . . and ISO
Procedures.’’28 The MISO RTO
Transmission Owner’s Agree-
ment provides that MISO shall
have functional control of the
transmission facilities, and that
the transmission owners shall
physically operate the facilities,
subject to MISO direction.29
Unless the delineation of
responsibility is absolutely clear,
a ‘‘reliability gap’’ potential exists
in the fuzzy boundaries between
the utility and the ISO. When a
reliability crisis occurs, even the
n./Feb. 2006, Vol. 19, Issue 1 1040-6190/$–s
slightest hesitancy caused by
fuzzy lines of responsibility could
lead to a reliability cascade.30
G iven those changes in
industry focus and struc-
ture, the August 2003 blackout
was hardly surprising.31 Utilities
in the affected area had economic
incentives to lean on neighbors
and evade compliance with
voluntary reliability standards.32
Lines of responsibility between
the utilities and the ISOs were
vague.33 And the ISOs involved
were subject to no regulator-
imposed sanction.34 All these
factors contributed to the black-
out, and they persist.
V. The 2003 BlackoutReport
The 2003 Blackout Report failed
to address the changes in the
electric industry, discussed
above, that were at the root of the
problem.35 The Blackout Report
did identify ISOs (primarily
MISO) as contributing to the
problem.36 But the Blackout
Report did not suggest any
ee front matter # 2005 Elsevier Inc. All rights
change in or elimination of the
ISOs’ reliability role or, for that
matter, any sanction whatsoever
directed to the ISOs for their role
in the Blackout.37 Instead, the
Report focused primarily on the
need for mandatory, rather than
voluntary, reliability standards.38
The conclusions of that Report led
directly to the legislation that now
appears in the Reliability Subti-
tle.39
VI. The Energy PolicyAct of 2005
The Reliability Subtitle estab-
lishes a system of mandatory and
enforceable reliability standards
in a new Section 215 of the Federal
Power Act.40 Under Section 215,
FERC will certify a single
nationwide Electric Reliability
Organization (ERO).41 The ERO
may, pursuant to FERC rule,
delegate authority to a qualified
Regional Entity for the purpose of
(1) proposing reliability standards
to the ERO, and also (2) enforcing
those standards.42 While FERC
has not yet certified the ERO,
NERC, and the various NERC
regions are likely candidates to be
the ERO and the Regional Enti-
ties.
The ERO will develop reliabil-
ity standards, subject to FERC
approval.43 Either the ERO/
Regional Entity or FERC can
impose a penalty on a ‘‘user,
owner, or operator of the bulk
power system’’ for a violation of
the FERC-approved reliability
standards.44 FERC can also order
compliance with a reliability
reserved., doi:/10.1016/j.tej.2005.11.005 13
The Section215 penalty
mechanism mayfall short in two
respects related tothe likelihood of
enforcement.
14
standard for violation, or antici-
pated violation, of that stan-
dard.45
I n late summer, FERC issued a
Notice of Proposed Rulemak-
ing to implement Section 215.46
On the subject of penalties,
FERC’s NOPR discusses both
monetary penalties and non-
monetary penalties. FERC offers
that non-monetary penalties
could include ‘‘limitations on
activities, functions, operations,
and other appropriate sanctions,
including the establishment of a
publicly available watch list
composed of major violators.’’47
While FERC does not specifically
say so, presumably the non-
monetary penalties could apply to
any entity subject to its jurisdic-
tion under Section 215 (i.e., users,
owners, and operators of the
grid). That would include RTOs
and ISOs.
In connection with enforce-
ment, FERC’s NOPR recognizes
the need to strike a balance
between protecting the due pro-
cess rights of entities being pro-
secuted on the one hand, and
preventing further compromise to
reliability on the other. The
NOPR’s discussion about the
process (e.g., what constitutes
adequate notice to the violator,
what should be the notice to
FERC, how public the proceeding
should be, what should be
the internal appeal process
within the ERO, and what
should be and what should
trigger the appeal process to
FERC) makes it apparent that
Section 215 enforcement will
come at a high cost.48
1040-6190/$–see front matter # 2005 Els
VII. Analysis of Section215’s RemedialMechanism
Essentially, Section 215’s
response to the 2003 Blackout is to
attempt to compel electric service
providers to ensure reliability by
means of a standard government
command-and-control mechan-
ism – i.e., imposition of standards,
and penalties for violations of
those standards. On the premise
that governmental objectives
are best achieved if they are
aligned with the subjects’ pre-
dispositions, Section 215’s
remedy addresses part, but not
all, of the problem.
Under the electric industry’s
‘‘reliability triangle’’ paradigm,
all interests were aligned in
favor of assuring reliable service.
The relatively recent electric
industry paradigm shift has
altered that alignment in three
respects:
(1) Some electric service provi-
ders are no longer single-mind-
edly focused on providing retail
service. Now, electric service
providers, more and more, derive
evier Inc. All rights reserved., doi:/10.1016/j.
profit from providing wholesale
services that are outside of the
state commission’s reliability-first
scrutiny. Thus, utility profit
motives that had once been
clearly and solely aligned with
reliable service are now con-
flicted. When reliable service col-
lides with the economic potential
of a wholesale service, reliability
may be compromised.
T he Section 215 penalty
mechanism attempts to
address the service providers’
conflicted profit motives. The
mechanism should work for that
purpose if the penalty is large
enough to outweigh any profits
from efforts that conflict with
reliable service. However, if the
penalty is perceived as too small,
or unlikely to be enforced or
invoked, the penalty will not
work to forestall the predisposi-
tion to profit from the non-relia-
bility driven activity. The Section
215 penalty mechanism may fall
short in two respects related to the
likelihood of enforcement.
The likelihood of a penalty’s
implementation is a function, at
least to some extent, of the ‘‘due
process’’ surrounding enforce-
ment. The greater the ‘‘process,’’
the less likely a meaningful pen-
alty will be imposed. In addition,
as has been recognized in other
contexts, a deficiency of com-
mand-and-control regulation is
the cost to administer it.49 Sub-
stantial costs for enforcement
tend to mitigate against enforce-
ment. FERC’s decisions in its
NOPR regarding enforcement
‘‘process’’ could have a significant
bearing on the likelihood of
tej.2005.11.005 The Electricity Journal
Ja
reliability standards enforcement,
which could, in turn, erode
reliability.
In sum, while the section 215
mechanism appears to be direc-
tionally correct to address service
providers’ conflicted motives,
whether it is sufficient for that
purpose will depend upon the
penalty’s deterrent effect, based
on both the size and likelihood of
the penalty. For now the jury is
out—at least until completion of
FERC’s NOPR—on whether Sec-
tion 215 will suffice.
(2) The electric industry para-
digm shift has added, in many
areas, a new entity into the mix of
ensuring reliable service. Under
FERC’s direction, an ISO has pri-
mary responsibility for short-term
reliability within the ISO’s sphere
of grid influence. In practice, all
existing ISOs operate on a not-for-
profit basis. All costs incurred by
the ISO are ultimately passed on to
its transmission customers. It is
difficult to understand how a
monetary penalty potential in
connection with a reliability fail-
ure would have any serious
deterrent effect upon a non-profit
ISO. The monetary penalty would
be socialized and passed along to
system customers, who bear all
ISO-incurred costs. The penalty
would have no direct connection
to the compensation of the ISO
employees responsible for the
reliability failure.
FERC’s NOPR does discuss the
possibility of non-monetary
penalties. It is possible that non-
monetary penalties could be
fashioned to establish a clear
nexus between the assurance of
n./Feb. 2006, Vol. 19, Issue 1 1040-6190/$–s
reliable service by an ISO and the
foremost objective of the ISO
leaders: job preservation. Perhaps
reliability failures by an ISO could
trigger ISO personnel dismissals.
Thus, a ‘‘sword of Damocles’’
would hang over the ISO, much as
it does over the state commissions
under the reliability triangle.
While such a result might
logically be appropriate, its
realistic prospects appear dim.
The 2003 Blackout Report cited
MISO with three separate NERC
violations contributing to the
blackout.50 Nevertheless, the
Blackout Report’s recommenda-
tions included no sanctions
against MISO.
(3) The command-and-control
reliability enforcement model is
confounded in an additional way
by the ISO. While ISO is nominally
ultimately responsible for short-
term reliability, in fact, as dis-
cussed above, reliability is a
shared function – between the ISO
and the transmission-owning uti-
lities. In these circumstances, pre-
cise responsibility for a blackout
will almost surely be cloudy, and
penalties for reliability infractions
ee front matter # 2005 Elsevier Inc. All rights
cannot be clearly targeted to the
responsible entity. Targeting
penalties to wrongdoing is made
even more difficult where, as in
NYISO and ISO-New England,
for example, contractual indem-
nities might immunize the
wrongdoers. Both the NYISO and
ISO-New England Transmission
Owners Operating Agreements
contain broad indemnity
provisions that require the ISO
to indemnify the transmission
owner for actions taken in
response to the ISO direction.51
These indemnity provisions might
enable a penalty to be shifted from
transmission owner to ISO, and
thence socialized to transmission
customers. In order for reliability
penalties to have the desired
deterrent effect, there must be a
unity of responsible and
penalty-liable entities. When both
Alphonse and Garcon share
responsibility for the blackout,
what is the proper deterrent
penalty for each?
VIII. Conclusion
The electric industry grew up
and matured under a regulatory
regime that fostered reliable ser-
vice as consistent with the service
providers’ best economic inter-
ests. Recent changes in both the
focus and structure of the electric
industry have put some strains on
that reliability-regime. Those
strains contributed to the 2003
blackout.
T he Blackout Report, and its
progeny the Reliability
Subtitle (Section 215), attempt to
reserved., doi:/10.1016/j.tej.2005.11.005 15
16
address the 2003 Blackout by
means of enforceable reliability
standards. That command-and-
control mechanism fosters relia-
bility to the extent the penalty and
its likelihood of enforcement are
perceived to outweigh conflicting
profit incentives. It is not clear
that will be the case.
M oreover, the Section 215
remedy does not appear
to address at all the industry’s
structural change—i.e., the
advent of ISOs. Section 215’s
financial penalties (1) have no
deterrent effect on non-profit
ISOs, and (2) do not bridge the
communications gap resulting
from multiple arbiters of grid
reliability. FERC may address the
former in its rules implementing
Section 215, but not the latter.&
Endnotes:
1. Domenici-Barton Energy Policy Actof 2005, Pub. L. No. 109-58, § 1211, 119Stat. 594 (2005) (EPAct of 2005).
2. THOMAS P. HUGHES, NETWORKS OF
POWER 205–207 (Baltimore: JohnsHopkins University Press 1993) (1983).
3. See Rudy Perkins, ElectricityDeregulation, EnvironmentalExternalities, and the Limitations of Price,39 B.C. L. REV. 993, 999–1000 (1998).
4. State regulatory commissions havebroad discretion within which toregulate utility rates. The SupremeCourt has held that the onlyconstitutional limitation on theexercise of that authority by a statecommission is that the net effect of arate decision may not be confiscatory.Duquesne Light Co. v. Brasch, 488 U.S.299, 310 (1989).
5. Directionally, the regulatorymechanism—cost-of-service rates—also fostered reliable service. Undercost-of-service regulation, utilitieshave a financial incentive to maximize
1040-6190/$–see front matter # 2005 Els
infrastructure because the more theyinvest in the system, the more theyreceive in return. The more robust theinfrastructure, the more profitable theutility.
6. See Robert E. Burns, et al., After theLights Went Out, ELEC. J., Jan./Feb.2005; Eugene P. Coyle, Economists’Stories, and Culpability in Deregulation,ELEC. J., Oct. 2002; Michael T. Burr,Power Flux: Generators Struggle to Planfor the Future as They Cope with anUnstable Present, PUB. UTIL.FORTNIGHTLY, Dec. 2003, at 22.
7. Jose Delgado, the Blackout of 2003and its Connection to Open Access 2(2005) (white paper produced for theU.S.-Canada Power System OutageTask Force Technical Workshops onCompetition and Reliability in NorthAmerican Energy Markets, held inWashington, DC, Sept. 15 andToronto, Sept. 28.
8. U.S.-CANADA POWER SYSTEM OUTAGE
TASK FORCE, AUGUST 14TH BLACKOUT:CAUSES AND RECOMMENDATIONS 104(2004) (hereinafter ‘‘Blackout Report’’).
9. Charles G. Stalon, State-FederalRelations in the Economic Regulation ofEnergy, 7 YALE J. ON REG. 427, 442(1990); see also Scott Heck, Lights out forNew Jersey: The August 2003 Blackoutand the End of Electricity Regulation inNew Jersey, 29 SETON HALL LEGIS. J. 279,282 (2004).
10. Id., at 10–12.
11. Public Utility Regulatory PolicyAct (PURPA), 16 U.S.C. 824a-3(h)(2004).
evier Inc. All rights reserved., doi:/10.1016/j.
12. Hon. Richard J. Cudahy, PURPA:The Intersection of Competition andRegulatory Policy, 16 ENERGY L. J. 419,421–422 (1995).
13. Promoting Wholesale CompetitionThrough Open Access Non-Discriminatory Transmission Services byPublic Utilities; Recovery of StrandedCosts by Public Utilities and TransmittingUtilities, Order No. 888, FERC Stats. &Regs. � 31,036, at P31,643 (May 10,1996) (Order No. 888).
14. Id.
15. Energy Policy Act of 1992, 42U.S.C. 2297, et seq. (2004).
16. See generally Order No. 888, supranote 13.
17. Regional TransmissionOrganizations, Order No. 2000, FERCStats. & Regs. � 31,089, PP30,996-30,999 (Jan. 6, 2000) (Order No. 2000).
18. David N. Cook, General Counsel,NERC, Prepared Testimony before theU.S. Senate Governmental AffairsCommittee (June 28, 2001), S. Hrg. 107-156, at 515.
19. As the president of AmericanTransmission Co. recently put it: ‘‘Theattention of the industry – utilities,marketers, regulators and customers –was focused [now] on ensuring fairaccess to transmission capacity andpromoting robust competition in theenergy markets, rather than onreliability.’’ Delgado, supra note 7, at 4.
20. Order No. 2000, supra note 17, atPP30,992-30,995.
21. Id., at P31,103.
22. See, e.g., MISO and NYISOtransmission operating agreements forfirm point-to-point transmissionservice, available at http://www.midwestiso.org/emt/docs/Attachments.pdf and http://www.nyiso.com/public/webdocs/documents/tariffs/oatt/att_a.pdf.
23. Order 2000, supra note 17, atP31,103.
24. Id.
25. ISO-NE Transmission OperatingAgreement, � 3.02 and � 3.06.
26. Agreement between NYISO andTransmission Owners, � 2.01.
tej.2005.11.005 The Electricity Journal
Ja
27. Id., � 3.01.
28. Id., � 2.02.
29. MISO Transmission OwnersOperating Agreement, Appendix E.
30. Blackout Report, supra note 8, at109.
31. To quote one industryobserver: ‘‘The specific conditionsthat led to the blackout of 2003were only one more bad day in asequence of steadily worsening daysin network operations. The blackoutcould have happened earlier or later,there or elsewhere.’’ Delgado, supranote 7, at 4.
32. Cook, supra note 18.
33. Hughes, supra note 2, at 109.
34. Blackout Report, supra note 8, at20, 140–170. ISOs are subject toexclusive FERC jurisdiction, and FERChas no mechanism currently in placethat operates to induce the ISOs tobehave in ways that encouragereliability.
Conference Date
4th Annual Strategic Supply
Chain Management for Utilities
Jan. 18–20, 2
The 11th Annual Conference on
Buying & Selling Electric
Power in the West
Jan. 19–20
North American
Energy Infrastructure Forum
Jan. 30–31
6th Coaltrans Americas Jan. 31–Feb.
Middle East Electricity
Exhibition and Conference
Feb. 5–8
Utility Regulation and
Market Design: Entry, Exit,
and Competition Strategies
March 13–24
Electric Power 2006 May 2–4
15th Annual Latin American
Energy Conference
May 16–17
Power-Gen Europe May 30–June
n./Feb. 2006, Vol. 19, Issue 1 1040-6190/$–s
35. See generally Blackout Report,supra note 8.
36. Id., at 20.
37. Id., at 140–170.
38. Id.
39. See, e.g., Senate Consideration ofConference Report, CONG. REC. PS9335(July 29, 2005).
40. EPAct of 2005, supra note 1, at §1211.
41. Id.
42. Id.
43. Id.
44. Id.
45. Id. Section 215 does not promptstate action to ensure reliability withinthe state not inconsistent with Section215. § 215(i)(3).
46. Rules Concerning Certification of theElectric Reliability Organization; andProcedures for the Establishment,
Place Sponsor C
006 Ft. Lauderdale,
FL
Platt’s W
P
Seattle Law Seminars
International
h
s
Ottawa, Ontario The Conference
Board of Canada
h
j
1 Miami Coaltrans h
a
Dubai, United
Arab Emirates
IIR Middle East h
Washington Institute for
Public-Private
Partnerships, Inc
h
t
Atlanta Trade Fair Group h
La Jolla, CA Institute of the
Americas
h
h
1 Cologne, Germany Pennwell h
ee front matter # 2005 Elsevier Inc. All rights
Approval, and Enforcement of ElectricReliability Standards, 112 FERC � 61,239(Sept. 1, 2005).
47. Id., at P 66.
48. Id., at PP 58–73.
49. Jeffrey M. Hirsch, EmissionsAllowance Trading under the Clean AirAct: A Model for Future EnvironmentalRegulations?, 7 N.Y.U. ENVTL. L.J. 352(1999). See also Byron Swift, EmissionsTrading and Hot Spots: A Review of theMajor Programs, BNA ENVIRONMENT
REPORTER, Vol. 35, No. 19 (2004) (‘‘[Theacid rain program under Title IV] hasbeen called one of the most effectiveemissions reduction programs,principally because it achievessignificant and permanent reductionsat very low compliance costs’’).
50. Blackout Report, supra note 8, at22, fn 2.
51. Agreement between NYISO andTransmission Owners, � 5.03; ISO-New England Transmission OperatingAgreement, � 9.01.
ontact
eb: http://www.platts.com/Events/
C601/index.html
ttp://www.lawseminars.com/
eminars/06BSEWA.php
ttp://conferenceboard.ca/conf/
an06/energy-infra/overview.htm
ttp://www.coaltrans.com/default.
sp?Page=11&eventid=ECK121
ttp://www.middleeastelectricity.com/
ttp://www.ip3.org/t2006/
_workshops_1603.htm
ttp://www.electricpowerexpo.com/index.asp
ttp://iamericas.org/events/event.
tml?eid=2006-2301E&isnw=1
ttp://pge06.events.pennnet.com/
reserved., doi:/10.1016/j.tej.2005.11.005 17