Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Watt’s Up Doc NRG Energy Case Study 1
The Economist & NRG
Energy Case Study:
Optimizing the 21st Century Hospital
Team: Watt’s Up Doc
Abdulkamal Abdullahi
Michael Brown
Jose Poblete
Watt’s Up Doc NRG Energy Case Study 2
Table of Contents
I. Executive Summary
II. Abstract of New Jersey Hospital
a. Hospital Description
b. Location Description
c. State Incentives
III. Technology Summary
a. CCHP, Combined Cooling, Heating, and Power
b. Photovoltaics
c. Battery Storage
IV. Operating Summary
a. Hospital Power Requirements
b. CCHP, PV, Battery Storage Implementation, Operations, and Cost
V. Financial Summary
a. Financing Infrastructure
b. Employment of Cash Flows
c. Financial Metrics
VI. Conclusion
Watt’s Up Doc NRG Energy Case Study 3
I. Executive Summary
People and organizations usually take supply of electricity for granted, but natural disasters
and other threats remind us how dependent modern society is on energy reliability and how
vulnerable the electrical grid can be. Hospitals comprise a subset of systems that can be categorized
as critical infrastructure whose “assets, systems, and networks that, if incapacitated, would have a
substantial negative impact our society”1.
The need for reliability and the opportunity to increase efficiency led Watt’s Up Doc to select
the New Jersey Hospital as its project. Hospitals are on average the most energy-intensive facilities
in the United States, spending more than $8B on energy per year and representing 10% of total
energy used in commercial buildings2. Their operational nature subjects them to high costs of
energy during peak months and hours of the day, without opportunity for taking advantage of
interruptible services for its power and energy needs.
We recommend a CCHP system, Solar PV panels, and battery storage to make the Hospital’s
energy supply independent, reliable and resilient for years to come. Smart grid controls allow our
system to make the best use of electricity and heat generated with natural gas. Solar energy
produced and stored in batteries optimizes fuel consumption and provides ancillary services in-
house and for utilities. The 5MW energy solution will cost $23M in capital investment, and will
pay out in 7 years with an IRR of 12%. Given the debt environment and public status of our
hospital, we elected to finance the project with debt and municipal bonds. Our project is
expected to save the hospital over $100M in efficiency improvements over 20 years, improve
power reliability, and reduce CO2 emissions by 14,564 ton/year.
1 “Combined Heat and Power: Enabling Resilient Energy infrastructure for critical facilities” ICF International, March 2013 2 Energy.gov: Energy Department’s Hospital Alliance Helps Partner Save Energy and Money
Watt’s Up Doc NRG Energy Case Study 4
II. Abstract of New Jersey Hospital
A. Hospital Description
A hospital located in New Jersey presents an attractive opportunity for a renewable
infrastructure upgrade. Our hospital operates a total of 2,000 beds and has energy demands of 5
MW, landing in the top 15% of all US hospitals in terms of size and energy consumption3; with
such a large size, we conclude that the hospital operates in a high population density area on the
New Jersey side of the Philadelphia or New York City metropolitan areas. We also assumed that
the hospital is a general health care facility providing services in emergency care, general
practice, and all standard specialty practices. Therefore, it operates large, energy-intensive
equipment including tomography and MRIs, creating spikes in demand.
At this size, our team carried the assumption that this hospital is a public entity operated like
a VA hospital or large non-profit. Therefore, it has access to financing through bank debt,
municipal bonds, and existing capital. It does not have access to equity capital investments.
B. Location Description
Our hospital is in the Edison township in Middlesex County, New Jersey on the north side
of the Raritan river and New Brunswick. A hospital in this location could serve local townships,
universities and associated research scientists, and cities from Philadelphia to New York by train,
New Jersey is in climate zone 2 meeting requirements for less than 2,000 cooling degree
days (CCD) and 5,500-7-000 heating degree days (HDD)4. The high number of HDD influenced
our decision to provide an energy solution that could meet the high energy demands of a hospital
in such a climate.
3 Energy Information Administration: 2007 Commercial Buildings Energy Consumption Survey 4 Source of Energy consumption in hospitals, by end use, for five U.S. climate zones
https://www9.nationalgridus.com/non_html/shared_energyeff_hospitals.pdf
Watt’s Up Doc NRG Energy Case Study 5
Figure 1: Tentative location of Target New Jersey Hospital
Figure 2. U.S. Climate Zones – Energy Requirement Forecast
Watt’s Up Doc NRG Energy Case Study 6
Utility Service:
Due to the size and location of the hospital and proximity to a large population, utility
service is provided by Public Service Electric & Gas Company (PSEG). PSEG services the
corridor from Philadelphia to Newark. This utility is primarily serviced by nuclear and coal
power systems, and supplemented by gas, steam, and combined cycles during peak periods.
PSEG is also the gas utility for our operating area and market prices are available on the Henry
Hub. All primary voltage and gas distribution prices for PSEG were used in our operating and
financial models.
Figure 3. PSE&G Generation Stack5
C. State Incentives
New Jersey offers several incentives that make our investment in CCHP and PV an
attractive solution. As of 2016 the NJ Public Board of Utilities introduced a CCHP incentive
program that rebates on-site power generation that has a proven payback in under 10 years. New
Jersey targets 4.10% of the state’s electricity to be solar by 2028; to achieve this New Jersey and
5 PSE&G Generation Information
Watt’s Up Doc NRG Energy Case Study 7
Pennsylvania have created an SREC market that is now the largest in the country, with 1 MW
now selling for over $2006.
Figure 4. New Jersey SREC Credit Market LTM
III. Technology Summary
A. CCHP, Combined Cooling, Heating, and Power
A combined cooling, heat and power (CCHP) consists of a combination of equipment able to
produce electricity and use the heat generated in the process to deliver heat and cooling solutions.
Hospitals are an excellent fit with CCHP because their energy demand is composed by electric and
large heating and cooling needs. CCHP systems have the same efficiency of electric generation as
utility-scale plants, around 35% but, as a distributed generation resource, achieves approximately
an additional 40% of efficiency by using the heat.
The main element of the system is the gas turbine, which transforms fuel, natural gas in our
case to have a more environmentally friendly fuel, into mechanical energy. We have selected the
Siemens Gas Turbine SGT-1007 for our system, a 5.4 MW turbine. The mechanical energy is then
converted to electricity in a generator. The exhaust heat generated by the turbine is harnessed by a
6 SRECTrade: http://www.srectrade.com/srec_markets/new_jersey 7 http://www.energy.siemens.com/us/en/fossil-power-generation/gas-turbines/sgt-100.htm#content=Technical%20data
Watt’s Up Doc NRG Energy Case Study 8
Heat Recovery Steam Generator (HRSG), transforming it into steam, which is used by our thermal
loads. The HRSG selected is the Cleaver Brook’s Max-Fire8, that includes additional natural gas
burners, which would allow running the CHP at a lower output while meeting the thermal needs
(in the event exporting excess electricity becomes less profitable). Our Heating needs are
comprised mainly by hot water and room heating. Finally, for the Cooling needs we recommend
using steam, instead of additional transfers to hot water, new backup boilers or electricity, to drive
a LG WCSS9 capable of producing approximately 4,000 RT.
This solution offers the opportunity to improve critical infrastructure resiliency, providing
independence and mitigating the impacts of an emergency by keeping critical facilities running
without any interruption of service. Any excess of electricity could be exported to the grid and
additional heat needs could be satisfied with the HRSG burners. The system allows to reduce
carbon emissions in 14,564 tons of CO2 per year10.
Figure 5. CCHP Process Flow Diagram
8 http://www.cleaverbrooks.com/products-and-solutions/boilers/hrsg/max-fire/index.aspx 9 http://www.lg.com/global/business/download/resources/sac/Leaflet_F_LG_Absorption_Chiller.pdf
10 Based on 2014 Electric grid study https://www.epa.gov/energy/emissions-generation-resource-integrated-database-egrid
Watt’s Up Doc NRG Energy Case Study 9
B. Photovoltaics
Solar Photovoltaic panels allow our system to have an additional renewable component and
take advantage of favorable conditions to reduce the systems fuel intake. The rationale behind the
selection of roof-top photovoltaic panels is two-fold: first, installing solar panels reduces the
overall carbon footprint of the hospital by taking advantage of the considerable rooftop space
(137,000 ft2) and offsetting part of the electrical power demand (330 kW). Second, because utility
companies in the state of New Jersey reward customers for clean energy production, via net
metering11, the panels could serve as an additional revenue source for the hospital. In our financial
model we have used the solar production to reduce our natural gas consumption, therefore our
system could have an upside by selling our solar production to the market.
C. Battery Storage
Battery Storage systems are quoted as a 1 MW power per 4-hour energy service (4MWh),
and is scalable up to optimize load requirements. NEC’s GSS system provides the necessary
elements for our system, although other providers offer storage, control software or both in
different types of business models that could be beneficial. For example, Tesla and BYD provide
scalable battery solutions, and STEM provides a SaaS12 option that doesn’t require storage
investment. Storage control algorithms have advanced at a fast pace during the past years and the
systems can provide peak demand correction, dynamic load learning for frequency and voltage
regulation13, provide black-start capability, among other applications. Additionally, the smart
grid control can route energy generated by the solar panels or the generator to the storage, or
discharge energy to the hospital or the grid, allowing an optimization and flexibility of resources.
11 New Jersey Clean Energy Program: Net Metering and Interconnection | Net metering in New Jersey 12 STEM would own the batteries and provide the service of energy management for the goals the Hospital requires. 13 https://www.linkedin.com/pulse/nigeria-electric-grid-spinning-reserve-inadequate-control-igbokwe provides an illustrative
example of the voltage/frequency problem. Utilities pay for these services in addition to the energy it is consumed during the
service, so our solution would also benefit from cheaper generation.
Watt’s Up Doc NRG Energy Case Study 10
A 2014 study on Hospital equipment14 indicates Computed Tomography (CT) and Magnetic
Resonance Imaging (MRI) operate frequently in a narrow range of Power, but maximum Power
demand can be 17 times more in CTs and almost 5 times more in MRI machines. The study also
shows that these peaks can last from seconds to 45 minute intervals, and have random
occurrences between days, allowing only to separate similar behavior among weekdays and
holiday/weekend days. These situations translate to unexpected demand for the CHP system and
can stress the system by inducing voltage and frequency variations that can eventually shut down
generation or cause heating in wiring or equipment and overcharge certain circuits.
Figure 6. Power Surge Frequency and Size
In Figure 7 we can observe the basic function of the peak correction. If the imaging
equipment produce a peak in demand, the battery storage would provide the excess power and
energy above a predetermined threshold. In hospitals certain machines are highly predictable, for
example most MRIs and CTs are usually scheduled in advance (except emergency room
machines), which allows the algorithm to optimize readiness for charge and discharge. For the
14 “Healthcare Energy End-Use Monitoring”, Michael Sheppy, Shanti Pless, and Feitau Kung, National Renewable Energy
Laboratory, Technical Report, NREL/TP-5500-61064, August 2014
Watt’s Up Doc NRG Energy Case Study 11
solar panels the algorithms can consider the weather and adapt to take part of the charging load
from the solar panels.
Figure 7. Battery Peak Demand Correction Example
IV. Operating Model Summary
A. Hospital Power Requirements
Power and Steam: The power requirements for a hospital can be divided into 5
consumption categories. Figure 8 indicates the energy each category consumes a percentage of
total energy and utilizes either steam or electricity or steam to operate.
Figure 8. Hospital Energy Consumption (% of total)
12.5%
4.5%
18.1%
10.4%
54.5%
64.9%
Fans Imaging Equipment Light, Offices Chiller Heat & HW
Watt’s Up Doc NRG Energy Case Study 12
Calendar Demand Adjustments: Our 5MW New Jersey hospital was modelled over a 12-
month period to account for seasonal changes in steam and electrical consumption. Our CCHP
system has been sized to address the entire demand of power and energy and not as a complement
to the grid connection. In sizing the system, we have assumed a 10% security factor for the
Hospital’s energy demand. The power and steam requirements were then sized using industry
standards for efficiency: 40% steam capture, and 35% electrical capture to determine the nominal
demand of our technology solution. Our annual power requirements are shown below in Figure 9.
Figure 9. Hospital Calendar Seasonal Demand (MMBtu)
Our 12-month projection of hospital power demand is detailed in Exhibit 2.
B. CCHP Operations and Costs
Given the higher efficiency of the steam and heating component (40%) of the CCHP, the
equipment is designed to provide head most efficiently. Electricity can be more easily exported
(sold to grid) or any shortfall is supplied by storage or acquired (purchased) to provide adequate
electricity. This design methodology also minimizes cost of equipment. The capital cost of
$3,000/MW represents the high range of capital costs assuming this is a greenfield installation and
-
500
1,000
1,500
2,000
2,500
3,000
3,500
1 2 3 4 5 6 7 8 9 10 11 12
MM
BTU
Heat & HW Fans Chiller Imaging Equipment Light, Offices
Watt’s Up Doc NRG Energy Case Study 13
leveraging a $3MM project rebate from the NJBPU. Installed costs represent engineering design,
procurement, installation, and commissioning of all major equipment.
The CCHP will be run at maximum availability, with scheduled 4000-hour preventative
maintenance services. We expect a 94% run time efficiency, and flat fixed and variable O&M
costs. The primary cost driver of the CCHP is natural gas price. Gas consumptions was calculated
based on monthly demand, unit efficiency, and market price.
Table 1. Cost Model for CCHP
Cost Line Total Unit
CCHP Installed Cost 3,000 $/MW
CCHP Fixed O&M 15.37 $/kW/year
CCHP Variable O&M 3.27 $/MWh
C. Solar PV Operations and Costs
Our PV installation was modelled using an assumed roof surface area of the hospital,
seasonal efficiency, and operating costs. Efficiencies ranged from 12%-18% of capacity
depending the month of the year. Even though PV installations using already acquired land cost
less than $2,500 per MW, we modeled our installation cost on the high end of the spectrum
considering additional equipment to make a smart grid, appropriate operational expense, and
SREC credits.
Table 2. Sizing Model for Solar PV
Beds 2,000 beds Roof area 137,143 ft^2
Size 960,000 ft^2 Solar PV Space 60% availability
ft^2/bed 480 ft^2/bed Roof area 1.89 acres available
Floors 7.0 floors PV Capacity* 5.50 acres/MW
Floor size 137,143 ft^2 PV Installed 0.34 MW
PV Efficiency* 18% Capacity factor
Solar PVHospital Data
Watt’s Up Doc NRG Energy Case Study 14
Table 3. Cost Model for Solar PV
D. Battery Storage
Battery storage will be available to curb equipment peak power loads, provide backup power, and
serve to sell solar PV at optimal market time. The battery system will provide 1MW for 8 hours of
service. Our electrical requirements are primarily for Imaging equipment but could serve to power Fans
and lights/offices as well.
Table 4. Cost Model for Battery Storage
From our estimate of the imaging equipment in a 2,000 bed Hospital, the peak power
demand for a simultaneous use of all the equipment, with every equipment demanding its
maximum load, would be 1.4 MW. Our system has a 2MW storage system able to provide 8
MWh, which covers the maximum expected peak and allows our solution to provide Ancillary
Services to our Utility (frequency and voltage regulation, peak energy demand during
weekends/holidays) and open a new revenue stream. In our financial model, we assumed a
revenue stream the provided a 7.0% IRR for the storage system investment.
Table 5. Peak Demand Model Assumptions
Cost Line Total Unit
Solar PV Installed Cost 2,500 $/MW
Variable O&M ($) 19 $/kW/year
SREC Revenue 0.01 $/kWh
Description Total Unit
Batter Installed Cost 60,000 $/MW
Service 8 hrs.
Capacity 8 MWh
Equipment Type Peak Demand (kW) Avg Demand (kW) # Units Max Average
CT Scan 115 7 9 1035 63
MRI 55 12 7 385 84
Total 170 19 16 2720 304
Aggregate Demand
Imaging Equipment Power Demand
Unit Demand
Watt’s Up Doc NRG Energy Case Study 15
V. Financial Summary
The 3-solution project to construct a CCHP, install solar PV and battery storage will cost
$23 million including financing fees, has an internal rate of return (IRR) of 11.7% and 7-year
payback. As a municipal project, we will leverage bank debt and the municipal bond market to
secure long term fixed rate financing.
Bank Debt: Local bank debt will finance $8M of the project. The project will incur a 3%
financing fee and be 100% amortized over 5 years. Bank debt and cash on hand will be
withdrawn to pay for planning, front-end engineering design, (FEED), and permitting.
Municipal Bond: We will work with a bank to syndicate $15M of municipal debt. The
project will incur a 5% financing fee and be redeemed at maturity of 15 years. Coupon rates for
municipal bonds for NJ Healthcare systems range from 4%-5%. Proceeds will be put toward
procurement and general construction.
Risks: A fixed rate long maturity bond presents several risks. If interest rates fall the project
could pay financing costs above the market. Bonds contain covenants that may restrict the
hospital's overall capital structure for the duration of the bond life. Bank debt is senior secured,
which may negatively influence the coupon rate the project can secure. Interest payments will be
required prior to full realization of savings. We have increased our exposure to gas price
volatility by increasing our consumption, this should be mitigated by futures contracts. There are
no contract costs considered in our model.
Benefits: By financing with debt, we will increase our savings by eliminating a PPA that
floats on an index. However, service contracts must be established under our estimated variable
costs to manage the facility.
Watt’s Up Doc NRG Energy Case Study 16
A. Employment of Cash Flows
The project’s cash flows consider the amortization of the bank loan starting at year 1, generating
$16.6M in cash flow extinguishing the bank debt in year 5. Through year 6 until the payment of
the municipal bond the project generates $45.5M in cash flow paying the municipal bond in year
15.
Table 6. Consolidated Statement of Project Cash Flows
B. Financing Infrastructure
Bank debt and municipal bonds offers stable long term financing for our CCHP, PV, ad
Battery storage solution. Construction is expected to take 18 months and will be handled by a 3rd
party developer.
C. Sensitivity Analysis
As we have said before, by projecting higher installation costs and low divergence of natural
gas to electricity prices, we believe our base scenario is conservative. We have performed a
sensitivity analysis that captures the impact of different scenarios.
First, looking at our financial costs, our base scenario considers a weighted average interest
rate of 4.1% (3.5% for bank loan 35.9% and 4.5% for bond 64.0%). Increasing interest rates have
an average 0.3% IRR decrease per 50 basis point. It is important to mention that this is a general
conclusion due to the different structure of our financing option.
Condensed Statement of Cash Flows 2018-2022 2023-2032 2033-2037 Total
Project EBIDA (no taxes paid) $ 20,825,061 52,069,086 32,452,391 105,346,538
Interest Expense $ (4,184,770) (6,599,475) 0 (10,784,245)
Debt Ammortization $ (8,240,000) (14,665,500) 0 (22,905,500)
Project Free Cash Flow $ 8,400,290 30,804,111 32,452,391 71,656,793
Watt’s Up Doc NRG Energy Case Study 17
Table 7. IRR CAPEX vs Interest Rates
Approximately 30% of our ROI relies on savings from a higher growth in utility rates
(PSE&G) compared to gas price growth rates. Our base scenario considers gas prices growing at
2% from $ 2.5 per MMBTU and electricity rates growing at 3% (total). Our analysis shows that
our project’s IRR is more sensitive to PJM energy prices, approximately 0.9% IRR per 50 basis
point change, and less sensitive to Gas prices, approximately 0.3% IRR per 50 basis point
change.
Table 8. Gas vs. Utility Growth Rates
A detailed operating and financial model are included below in Exhibits 1, 2, and 3.
11.7% 4% 4.000% 4.500% 5.000%
150000.0% 21.2% 21.1% 21.0% 20.9%
1750 19.2% 19.1% 19.0% 18.9%
2000 17.4% 17.3% 17.2% 17.1%
2250 15.8% 15.7% 15.6% 15.6%
2500 14.3% 14.2% 14.2% 14.1%
2750 13.0% 12.9% 12.9% 12.8%
3000 11.7% 11.7% 11.6% 11.6%
3300 10.4% 10.3% 10.3% 10.2%
Weighted Avg Project Interest Rate %
CH
P C
apit
al In
vest
me
nt
$/k
W
11.7% 2% 2.500% 3.000% 3.500% 4.000%
2% 9.8% 10.7% 11.7% 12.6% 13.5%
2.5% 9.5% 10.5% 11.5% 12.4% 13.3%
3.0% 9.2% 10.3% 11.2% 12.2% 13.1%
3.5% 8.9% 10.0% 11.0% 11.9% 12.9%
4.0% 8.6% 9.7% 10.7% 11.7% 12.7%
Power PJM/PSE&G Growth
Gas
Pri
ce G
row
th
Watt’s Up Doc NRG Energy Case Study 18
VI. Conclusion
The selection of a comprehensive CCHP, solar and battery solution will not only provide the
hospital’s daily energy needs, but is flexible and robust enough to adequately manage anticipated
power demand spikes and feed electricity back to the grid during times of excess production.
Financing this project using a combination of bank loans, NJBPU grants, and municipal bonds
will yield a payback period of <7 years and create value for the hospital in the long run.
Watt’s Up Doc NRG Energy Case Study 19
Exhibit 1. Operating Model
Installed Cost Gas Turbine Solar PV Battery
Min $/kW 1,200$ 2,493$ Capacity (hrs) 8
Max $/kW 3,000$ 2,500$ Cost $/kWh 600 60000
Demand (MW) 5.5 0.3 Capacity kWh 8000
CAPEX 16,547,143$ 860,000$ 4,800,000$
Month 1 2 3 4 5 6 7 8 9 10 11 12
% of Peak 94% 94% 97% 86% 66% 69% 69% 69% 62% 86% 100% 94%
Demand (MW) 6.29 6.29 6.50 5.78 4.40 4.61 4.61 4.61 4.15 5.78 6.70 6.29
Hours 730 730 730 730 730 730 730 730 730 730 730 730
kWh 4,590,886 4,590,886 4,742,726 4,221,281 3,211,354 3,363,194 3,363,194 3,363,194 3,026,552 4,221,281 4,894,566 4,590,886
1 LMP ($/kWh) 0.02955 0.02677 0.02394 0.02768 0.02323 0.02565 0.03221 0.03178 0.02896 0.02821 0.02573 0.03192 Cap ($/kW) 20.1095 20.1095 20.1095 20.1095 20.1095 29.7275 29.7275 29.7275 29.7275 20.1095 20.1095 20.10952 T&D ($/kWh) 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342 0.0342
O&M ($/kWh) 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011 0.011
Cost ($/kWh) 0.064$ 0.061$ 0.058$ 0.062$ 0.057$ 0.060$ 0.066$ 0.066$ 0.063$ 0.062$ 0.060$ 0.066$
Utility Cost ($) $419,000 $406,000 $406,000 $377,000 $273,000 $338,000 $360,000 $359,000 $314,000 $380,000 $428,000 $430,000
3 CCHP Operating Cost ($) $88,000 $88,000 $91,000 $80,000 $59,000 $62,000 $62,000 $62,000 $55,000 $80,000 $95,000 $88,0003 Solar PV Operating Cost ($) $240 $240 $170 $170 $90 $90 $90 $90 $170 $170 $240 $240
3. Refer to CCHP Operating Model
PSE&G Monthly Cost Forecast 2017
Infrastructure CAPEX
1. PJM Historical Monthly Average of Day-Ahead LMP
2. PSE&G Primary Voltage Service Costs
Watt’s Up Doc NRG Energy Case Study 20
Exhibit 2. Infrastructure Engineering Model
Safety Factor (demand) 1.1
Month 1 2 3 4 5 6 7 8 9 10 11 12
Relative CCD 1 1 2 3 3 4 4 4 4 3 3 1
Relativd HHD 9 9 9 7 4 4 4 4 3 7 9 9
35.1% A Electricity 1,409 1,409 1,409 1,409 1,409 1,409 1,409 1,409 1,409 1,409 1,409 1,409
12.5% A Fans 502 502 502 502 502 502 502 502 502 502 502 502
4.5% B Imaging Equipment 181 181 181 181 181 181 181 181 181 181 181 181
18.1% C Light, Offices 727 727 727 727 727 727 727 727 727 727 727 727
10.4% D Chiller 152 152 304 456 456 607 607 607 607 456 456 152
54.5% E Heat & HW 3,030 3,030 3,030 2,356 1,347 1,347 1,347 1,347 1,010 2,356 3,030 3,030
Month 1 2 3 4 5 6 7 8 9 10 11 12
A+B+C 1.9 MW Electricity 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9
G CCHP Electrical Efficiency 35% 35% 35% 35% 35% 35% 35% 35% 35% 35% 35% 35%
F/G 5.5 Total (MW) 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5
CCHP Steam Efficiency 40% 40% 40% 40% 40% 40% 40% 40% 40% 40% 40% 40%
Total Steam Recovery (MW) 3,182 3,182 3,333 2,812 1,802 1,954 1,954 1,954 1,617 2,812 3,485 3,182
Fuel Demand (Mmbtu/mo.) 27,140 27,140 28,436 23,987 15,372 16,668 16,668 16,668 13,796 23,987 29,731 27,140
Price Gas ($/MMBtu) 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50
Fuel Cost ($) 67,851 67,851 71,089 59,969 38,431 41,669 41,669 41,669 34,490 59,969 74,327 67,851
Fixed O&M ($) 7,065 7,065 7,065 7,065 7,065 7,065 7,065 7,065 7,065 7,065 7,065 7,065
Variable O&M ($) 13,167 13,167 13,167 13,167 13,167 13,167 13,167 13,167 13,167 13,167 13,167 13,167
Total Variable Cost ($/yr) 88,082 88,082 91,320 80,200 58,662 61,901 61,901 61,901 54,721 80,200 94,558 88,082
Solar PV Efficiency 12% 12% 15% 15% 18% 18% 18% 18% 15% 15% 12% 12%
Energy production (MWh) 30.09 30.09 37.61 37.61 45.13 45.13 45.13 45.13 37.61 37.61 30.09 30.09
O&M Cost ($) $544 $544 $544 $544 $544 $544 $544 $544 $544 $544 $544 $544
SREC Revenue (0.01 $/kWh) $301 $301 $376 $376 $451 $451 $451 $451 $376 $376 $301 $301
Total Variable Cost ($/yr) 243 243 168 168 93 93 93 93 168 168 243 243
Imaging Equipment (MW) 0.248 0.248 0.248 0.248 0.248 0.248 0.248 0.248 0.248 0.248 0.248 0.248
NJ Hospital Total Demand demand of Hospital
CCHP Sizing
Solar PV
Battery Storage
Assumes Solar PV panels in roof, production is substracted from CHP's fuel demand.
Hospital Energy consumption (MWh)
Steam
Watt’s Up Doc NRG Energy Case Study 21
Exhibit 3. Financial Model
Operating Assumptions:
CHP+Fuel Cell CAPEX $22,207,143 Power Inflation 3%
Percent Funded with Debt 100% Gas Inflation 2%
TOTAL FINANCING $22,905,500
PPE Useful Life 20.00
Source of Funds
Funding Source Leverage Total Rate Fee Amor. Maturity
BANK LOAN SENIOR NOTE $ 8,240,000 3.50% 3% 100.00% 5 4%
NJ HEALTHCARE FAC MUNI NOTES $ 14,665,500 4.50% 5% 0.00% 15
TOTAL DEBT $ 22,905,500 4.14%
0 1 2 3 4 5 6 7 8 9 10
Cash Flow Statement 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Earnings (Cost Savings) $ 3,926,069 4,041,781 4,161,194 4,284,425 4,411,592 4,542,819 4,678,231 4,817,961 4,962,141 5,110,912
Interest Expense $ 948,348 894,566 838,903 781,291 721,663 659,948 659,948 659,948 659,948 659,948
Depreciation 1,110,357 1,110,357 1,110,357 1,110,357 1,110,357 1,110,357 1,110,357 1,110,357 1,110,357 1,110,357
Debt Amortization $ 1,536,607 1,590,388 1,646,051 1,703,663 1,763,291 0 0 0 0 0
Free Cash Flow $ -22207143 1,441,115 1,556,827 1,676,240 1,799,471 1,926,638 3,882,871 4,018,284 4,158,013 4,302,194 4,450,964
CASH FLOWS FROM FINANCING ACTIVITIES:
Payments on Bank Debt $ $1,536,607 $1,590,388 $1,646,051 $1,703,663 $1,763,291 $0 $0 $0 $0 $0
Payments on Bonds $ $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Other Financing Items: $
CASH FLOW for INTEREST REPAYMENT
BANK LOAN SENIOR NOTE $ 288,400 234,619 178,955 121,343 61,715 0 0 0 0 0
NJ HEALTHCARE FAC MUNI NOTES $ 659,948 659,948 659,948 659,948 659,948 659,948 659,948 659,948 659,948 659,948
Balance Sheet 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027
Assets 16,547,143 16,451,651 16,418,090 16,448,279 16,544,087 16,707,433 20,590,304 24,608,588 28,766,601 33,068,795
Project Cash 0 1,441,115 2,997,942 4,674,182 6,473,653 8,400,290 12,283,162 16,301,445 20,459,458 24,761,652
Net PP&E 16,547,143 15,010,536 13,420,149 11,774,097 10,070,434 8,307,143 8,307,143 8,307,143 8,307,143 8,307,143
Liabilities
BANK LOAN SENIOR NOTE $ 8,240,000 6,703,393 5,113,006 3,466,954 1,763,291 0 0 0 0 0 0
NJ HEALTHCARE FAC MUNI NOTES $ 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500 14,665,500
Net Debt: $ 22,905,500 19,927,779 16,780,564 13,458,273 9,955,139 6,265,210 2,382,338 1,635,945 5,793,958 10,096,152
Finacial Summary
Capital Investment 22,207,143
Payout (years) 7
IRR 11.7%