Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
THE UNIVERSITY OF MISKOLC
FACULTY OF ECONOMICS
INSTITUTE OF MANAGEMENT SCIENCE
The economic impact of energy load shedding on small and medium-sized manufacturers in Richards Bay,
South Africa
Mfihlakalo Vusumuzi Mabuyakhulu
2020
ii
ABSTRACT
South Africa is facing an economic crisis that emanates from the shortage of electricity
supply. This power shortage arises from misguided government policy decisions and poor
management of the South African power utility, Eskom. The power shortage leads to
rotational power interruptions known as load shedding. The electricity supply shortage
remains a challenge as the current power generation infrastructure is aging and getting closer
to the end of life, while the demand in the country keeps rising. Eskom has to renew the
aging power generation plants, however, the utility is facing operational and financial
difficulties. The challenges faced by Eskom have a direct effect on electricity consumers,
particularly businesses in the manufacturing sector. The current study seeks to economic
impact of load shedding on small and medium-sized factories in Richards Bay, South Africa.
A mixed-methods approach was adopted for the research work which produced a qualitative
and quantitative study. Three studies were proposed initially, however, only two were
completed, an open-ended qualitative survey (study 1) and the subjective evaluation
methodology (study 2). The revealed preferences methodology (study 3) was not
implemented due to the unavailability of financial data from the factories, this data was
deemed to be highly sensitive and confidential. Results from study 1 show that the load
shedding has primary and secondary effects on the manufacturers. These effects are captured
on a model that shows the relationship between the effects. Study 2 estimates that the
economic impact of frequent power interruptions on small and medium-size factories is
worth 21% of their total assets. Study 3 was designed to collect data from backup power
generators, about the fuel consumed, energy delivered and maintenance performed to
estimate the true cost of "replacing" the grid supply with a backup generator in Rand.
From the two studies, the researcher recommends that stakeholders such as factory
shareholders, employees, suppliers, and customers work together closely to improve
communication, more especially when it comes to business challenges arising from load
shedding. The morale of the workers is affected by load shedding, professional help is
recommended. Eskom is encouraged to communicate load shedding schedules a week in
advance so that factories can plan their operations accordingly. Factories are encouraged to
consider moving their operating hours to the off-peak electricity demand period, between
22:00–06:00 and to negotiate preferential electricity tariffs for this move. The factories are
also encouraged to explore the possibility of setting a power generation plant jointly.
iii
ACKNOWLEDGMENT
Dr. Habil Berényi László: I appreciate your guidance and support throughout the thesis work
as my mentor. I am truly grateful for your dedication and professionalism.
Tempus Public Foundation: My appreciation goes to the Tempus Public Foundation for
awarding me a scholarship to pursue MBA studies in Miskolc, Hungary.
The South African Government: My sincere appreciation goes to the South African
Government, in particular the Department of Higher Education and Training for their
financial support throughout the studies and for granting me research funding.
Mabuyakhulu Family: From my parents, my siblings and extended family, I truly appreciate
your support and guidance from when I was awarded the scholarship, leaving South Africa
until the end of this work, you have been a source of strength and purpose.
Transnet Freight Rail: I appreciate the opportunity granted to me in the form of sabbatical
leave for two years to pursue my studies abroad, your support has been tremendous.
Zululand Chamber of Commerce and Industry: I appreciate your support provided during
the data collection of the thesis. This could have been a difficult exercise and long exercise,
your interventions made it short and seamless for me.
Thulani Dennis Mnyandu: My singular friend and brother, a very kindest, unpretentious,
affectionate, considerate, and empathetic, who gave me a strong support from start to the
end of our journey.
Laszlo Szasz: I am truly humbled to have worked with you coach on and off the athletics
track. It has been an honor and privilege to be coached by an Olympian. You have helped
me so much to balance my training, social life, and studies. You were not only an athletics
coach but a life coach to me.
God, I'm grateful for the intellect, courage, and blessings you had offered me in my entire
journey.
iv
TABLE OF CONTENTS
ABSTRACT .............................................................................................................................. ii
ACKNOWLEDGMENT .............................................................................................................. iii
TABLE OF TABLES ................................................................................................................. vii
TABLE OF FIGURES ............................................................................................................... viii
INTRODUCTION ....................................................................................................................... 1
1 RESEARCH PROBLEM ................................................................................................ 4
1.1 Research problem statement ............................................................................................. 4
1.2 What are the research objectives? .................................................................................... 4
1.3 Research methodology ...................................................................................................... 5
1.4 Research limitations ........................................................................................................... 6
1.5 Research layout .................................................................................................................. 6
2 LITERATURE REVIEW ............................................................................................... 7
2.1 The current economic situation in South Africa ................................................................ 7
2.2 The current energy situation in South Africa ................................................................... 10
What is Load Shedding? ............................................................................................................... 13
2.3 The impact of load shedding on electricity consumers in general and businesses in
particular ...................................................................................................................................... 13
Societal impact of load shedding ................................................................................................. 14
Indirect commercial impact of load shedding .............................................................................. 16
Direct commercial impact of load shedding ................................................................................. 17
3 METHODS USED TO MEASURE THE IMPACT OF LOAD SHEDDING ON ELECTRICITY
CONSUMERS IN GENERAL AND BUSINESSES IN PARTICULAR .................................................. 18
3.1 Different types of load shedding studies ......................................................................... 18
3.2 Methods for measuring the economic impact of load shedding ..................................... 19
4 CRITICAL ANALYSIS OF THE LITERATURE REVIEW .................................................. 23
5 RESEARCH QUESTIONS ........................................................................................... 26
6 CURRENT LOAD SHEDDING STATISTICS .................................................................. 27
7 RESEARCH METHODOLOGY .................................................................................... 29
7.1 The qualitative impact of load shedding on small and medium-size factories ................ 29
Unit of analysis and population ................................................................................................... 30
Sampling method and size ........................................................................................................... 30
Data collection process ................................................................................................................ 30
Analysis approach ........................................................................................................................ 31
7.2 The direct economic impact of load shedding on small and medium-size factories ....... 31
v
7.2.1 The direct economic impact of load shedding employing the subjective evaluation
methodology ................................................................................................................................ 33
Unit of analysis and population ................................................................................................... 33
Sampling method and size ........................................................................................................... 34
Data collection process ................................................................................................................ 34
Analysis approach ........................................................................................................................ 35
7.2.2 The direct economic impact of load shedding employing the revealed preferences
methodology ................................................................................................................................ 36
Unit of analysis and population ................................................................................................... 36
Sampling method and size ........................................................................................................... 36
Data collection process ................................................................................................................ 37
Analysis approach ........................................................................................................................ 37
7.3 Survey design ................................................................................................................... 37
8 SOCIO-ECONOMIC CONDITIONS IN RICHARDS BAY , SOUTH AFRICA ....................... 39
9 SURVEY RESULTS ................................................................................................... 40
9.1 The qualitative impact of load shedding on small and medium-size factories ................ 40
Major themes ............................................................................................................................... 40
Degree of impact depends on various factors .............................................................................. 41
Operational impact of load shedding ........................................................................................... 42
Costs associated with load shedding ............................................................................................ 43
Revenue loss due to load shedding .............................................................................................. 44
Safety and security issues related to load shedding .................................................................... 45
Mitigation of load shedding impact ............................................................................................. 47
Stakeholders impacted by load shedding ..................................................................................... 48
Second-order effects of load shedding ......................................................................................... 49
Positive outcomes of load shedding ............................................................................................. 50
Graphical representation of major themes .................................................................................. 51
9.2 The quantitative impact of load shedding on small and medium-size factories employing
the subject evaluation methodology ........................................................................................... 52
Results from the survey ................................................................................................................ 52
Direct worth estimates of the impact of load shedding ............................................................... 52
Survey responses .......................................................................................................................... 53
9.3 The quantitative impact of load shedding on small and medium-size factories employing
the revealed preferences methodology ....................................................................................... 63
10 THE DISCUSSION OF THE RESULTS .......................................................................... 64
10.1 What is the qualitative impact of load shedding on small and medium-sized
manufacturing companies in Richards Bay, South Africa? ........................................................... 64
vi
10.2 What is the direct impact of load shedding on small and medium-sized manufacturing
companies in Richards Bay, South Africa? ................................................................................... 68
11 RECOMMENDATIONS .............................................................................................. 69
11.1 Recommendations for the manufacturers ....................................................................... 69
11.2 Recommendations for the power utility .......................................................................... 72
11.3 Limitations of the research .............................................................................................. 73
12 CONCLUSIONS ........................................................................................................ 74
12.1 What is the qualitative impact of load shedding on small and medium-sized
manufacturing companies in Richards Bay, South Africa? ........................................................... 74
12.2 What is the direct impact of load shedding on small and medium-sized manufacturing
companies in Richards Bay, South Africa? ................................................................................... 75
12.3 Limitations of the research and future research recommendations ............................... 76
REFERENCES ......................................................................................................................... 78
APPENDICES ......................................................................................................................... 81
Appendix A – Questionnaire approval ........................................................................................ 81
Appendix B – Survey questionnaire (qualitative) ......................................................................... 82
Appendix C – Survey questionnaire (quantitative) ...................................................................... 83
Appendix D – Pictures of Richards Bay......................................................................................... 87
vii
TABLE OF TABLES
Table 1: Three categories of impact resulting from load shedding (Goldberg, 2015) ....... 14
Table 2: Qualitative servey questionnaire. .......................................................................... 82
viii
TABLE OF FIGURES
Figure 1: The map of Richards Bay showing the strategic location of the town (Michelen, 2020)……………………………………………………………………………………….02 Figure 2: The economic sectors that contribute to the total GDP (Statistics South Africa, 2018)……………………………………………………………………………………….09
Figure 3: The frequency of load shedding stages experienced in Richards Bay from 01 December 2019 until 29 February 2020 (Eskom, 2020)…………………………………....27
Figure 4: The frequency of load shedding on the day of the week for the period 01 December 2019 to 29 February 2020 (Eskom, 2020)………………………………………………….28
Figure 5: Graphical representation of frequency of comments describing the impact of load shedding on factories………………………………………………………………………41
Figure 6: Major themes arising from the qualitative survey looking into the impact of load shedding on manufacturers………………………………………………………………...51
Figure 7: The distribution of responses on the availability of a procedure during a power outage……………………………………………………………………………………...53
Figure 8: Distribution of the working hours of the factories surveyed…………………...…54
Figure 9: The percentage distribution of factories with backup generators………………...54
Figure 10: The distribution of load shedding incidents per day and per week, Monday to Thursday…………………………………………………………………………………...55
Figure 11: The distribution of load shedding incidents per day and per week for Thursday to Sunday……………………………………………………………………………………..55
Figure 12: The percentage distribution of daily revenues lost due to power interruption incidents…………………………………………………………………………………....56
Figure 13: Percentage distribution of the costs incurred during the load shedding incidents…………………………………………………………………………………....56
Figure 14: The percentage distribution of load shedding impact on the equipment and machinery………………………………………………………………………………….57
Figure 15: The percentage distribution of factories that have backup power generators…...58
Figure 16: The percentage distribution of the capacity of backup power generators…….....58
Figure 17: The percentage distribution of the reliability of backup power generators….…..59
Figure 18: The percentage distribution of factories that outsource the backup power generators………………………………………………………………………………….60
Figure 19: The percentage distribution of costs associated with running the backup power generation system………………………………………………………………………….60
Figure 20: The percentage distribution of capacity provided by the backup power generators………………………………………………………………………………….61
Figure 21: The percentage distribution of the number of people who work in these factories……………………………………………………………………………………62
Figure 22: The percentage distribution of the area size of the factories surveyed………......62
ix
Figure 23: The percentage distribution of factories that have insurance as a mitigate against power interruptions………………………………………………………………………...63
Figure 24: Major themes arising from the qualitative survey looking into the impact of load shedding on manufacturers………………………………………………………………...74
Figure 25: The top view of the port of Richards Bay, the town’s export hub…………….....87
Figure 26: The inside of one of the medium factories producing plastic products in Richards Bay (Michelin, 2012)……………………………………………........…………87
1
INTRODUCTION
According to Van der Nest (2015), the immediate problem facing the South African
economy is the structural integrity of the electricity generation system. The lack of power
generation integrity compromises the entire electrical grid, where the demand on the
distribution side far exceeds the supply from the generation side. When the electricity
demand exceeds the supply, the South African power utility company, Eskom, is forced to
implement rolling blackouts to protect the power grid from collapsing known as 'load
shedding'. This is done regularly and the frequent power outages have become a norm for
the South African society and businesses. Nkomo (2005), says that the South African
economy is energy-intensive as the country is industrializing for development and growth.
The rolling blackouts have a devastating effect on the industrial business that are energy-
intensive in their operations. The power generation challenges are not new in South Africa,
they started in late 2007 according to (Goldberg, 2015). Goldberg (2015), further notes that
these power generation challenges are due to a combination of factors which include among
others, the maintenance backlog of Eskom's generation plants, the poor quality of coal
supplied to coal-fired power stations, skill shortages and insufficient generation capacity.
Eskom moved to construct two power stations to increase the generation capacity Medupi
and Kusile power stations (3 600 MW capacity each). However, these are behind the
construction schedule and over budget (Goldberg, 2015). The frequent power outages will
continue until the new power stations come online.
The current electricity supply challenges are not likely to be resolved anytime soon in South
Africa (Wright et al, 2019). The challenges facing the power utility are deep and structural,
they will take years to resolve according to (Wright, 2019). The power utility has a huge
sovereign debt of approximately 500 billion Rand and a host of technical challenges that are
largely related to skill shortages (Goldberg, 2015). Against this background, it is imperative
to understand how this systemic and entrenched problem is affecting businesses and the
economy of the country at large. The economic impact of load shedding on the
manufacturing sector will be studied, with a particular focus on small and medium-sized
manufacturers.
The manufacturing sector is the fourth largest contributor to the South African Gross
Domestic Product (GDP) in 2017, the sector contributed 12.2% to the total GDP (Statistics
South Africa, 2018). The small and medium-sized manufacturers contributed 69% to the
2
12.2% total manufacturing contribution to the country's GDP (Statistics South Africa, 2018).
The small and medium-size factories employ about 65% of the total workforce in the
manufacturing sector (Statistics South Africa, 2018). After mining, the manufacturing sector
is the second most energy-intensive in the country. The manufacturing sector is highly
competitive in South Africa and Southern Africa. The sector depends largely on the
agriculture and mining sectors for primary sources of raw materials (Nkomo, 2015).
Electricity is not only important for factory operations, but it is also important in linking
mines and farms to the coastal factories located in Richards Bay, via railways. Manufacturers
are categorized into three groups based on the annual turnover, small (0 – 15 million Rand),
medium (15 – 51 million Rand) and large manufactures (51 million Rand and above)
(Statistics South Africa, 2018). The sustainability of the manufacturing sector relies heavily
on other stakeholders, such as raw material suppliers, electricity suppliers, and customer
confidence.
This research work aims to understand the economic impact of power interruptions on small
and medium-sized manufacturers in Richards Bay, South Africa. Richards Bay is an
industrial on the north coast of KwaZulu – Natal (KZN) province, South Africa. The town
is the third-largest economy in KZN and hub of small and medium enterprises (SME) in the
province. The economy of Richards's bay is rapidly growing and the town boasts the deepest
Port in Africa that is linked to the country by a state-of-art rail infrastructure, a regional
Airport, smelters, mining giants such as Rio Tinto, Exarro, and a whole host of
manufacturing and processing factories. Figure 1 shows the map of Richards Bay showing
the airport, highway in red and railway lines in yellow & white.
Figure 1: The map of Richards Bay showing the strategic location of the town (Michelin, 2020)
3
Eskom is not solely blamed for the current power shortages currently experienced in South
Africa. The government has been aware of the potential power shortages since 1998 from a
white paper (WP) authored by the Department of Minerals and Energy back then (Goldberg,
2015). The WP noted that the surplus power generation capacity Eskom had at the time
would not be sufficient for the country's energy needs by the year 2007. The WP noted that
the demand in the country was rising rapidly and it recommended that timely action be set
in motion while taking into consideration lead times of some of the interventions required
(Goldberg, 2015). Senior government officials did not act accordingly on the contents of the
white paper regarding the energy forecasts, resulting in chronic power supply shortages
almost a decade later.
4
1 RESEARCH PROBLEM
1.1 Research problem statement
Studies that estimate the cost of power interruptions on small and medium-size
manufacturers are not available in South Africa. Manufacturing is an important driver of the
country's economy contributing over 12% to the total GDP. Key stakeholders in the
manufacturing sector, including factory shareholders, factory employees, suppliers, and
customers, need reliable and scientific estimates of the economic impact that are induced by
frequent power interruptions on them for improved decision making.
1.2 What are the research objectives?
This research work seeks to contribute to the current body of knowledge describing the
economic impact of power interruptions. Three studies will be undertaken, as outlined
below. A mixed-method approach will be followed to carry out the research.
• Study 1: To study the qualitative impact of power interruptions on small and
medium-size manufacturers in Richards Bay, South Africa. The researcher will
design a qualitative survey to be distributed to financial, operational and maintenance
managers of these manufacturers.
• Study 2: To study the quantitative impact of power interruptions on small and
medium-size manufacturers in Richards Bay. Primary data will be collected from the
manufacturers using a survey questionnaire administered online.
• Study 3: To validate the results that will be obtained in study 2. Secondary data
regarding the marginal cost of backup power supply will be collected from the
respondents in study 2. This cost can be thought of as an indicator of the minimum
economic impact the frequent power outages have on manufacturers.
The proposed studies were adapted from Goldberg (2015) in a study that was looking at the
impact of load shedding on the retail sector. This research will build on the work laid by
Goldberg (2015), specifically looking at the impact on manufacturing operations of load
shedding. These will provide a country-specific case for South Africa. Similar studies that
have been done before, were done in developed countries internationally. The qualitative
results of study 1 will provide the soft aspects of the load shedding impact that affects human
beings in particular. The quantitative results of studies 2 & 3 will explain the hard aspects of
the load shedding impact on machinery, production and the bottom line.
5
Pre-millennium (before the year 2000), South Africa had an abundance of electricity supply
that was stable and the electricity was sold at the most competitive tariffs worldwide
(Goldberg, 2015). The abundant and reliable power supply gave South Africa a competitive
advantage and the country attracted foreign, and local investments. Goldberg (2015), noted
that despite the current electricity challenges, South Africa is still an investment destination
as it is positioned strategically on the south coast and it serves as a gateway to Africa. Despite
the current electricity challenges, the country has over 200 years' worth of coal reserves in
Mpumalanga for coal-fired power stations (Goldberg, 2015). According to Goldberg (2015),
there is a huge potential for building up generation capacity fairly quickly in South Africa
as coal reserves are abundant and the gas industry is booming in East Africa.
This research work seeks to estimate the economic impact of power interruptions on small
and medium-size manufacturers in Richards Bay, KwaZulu - Natal. A systematic and
rigorous approach that is based on literature and theory will be followed. A descriptive
statistics based methodology will be followed in the study. This research will only be limited
to quantifying the costs of power interruptions on the manufacturing sector, focusing on
small and medium-sized factories in Richards Bay. The recommendations of the research
will be directed to the management of the manufacturers to minimize or mitigate the impact
of power interruptions in this sector. The recommendations will be directed to the power
utility company Eskom and the possibilities of expanding on the current research.
1.3 Research methodology
A multipronged approach will be followed when undertaking the current study. Three
proposed studies will be undertaken to address the set research objectives. The first study
will be qualitative focusing on the soft implications of load shedding on the factories. The
second and third studies will be quantitative focusing on the hard implications of load
shedding on the factories. Small and medium-sized factories will be the focus of this study
as categorized by their annual turnover. These factories generally operate at thin profit
margins, average 5.6% for small factories and 6.8% for medium-sized factories in the
financial year 2017/2018 (Statistics South Africa, 2018). With such profit-margins, any
drastic negative disturbance of these businesses is likely to throw the factories into
profitability challenges that may have huge implications for the employees in the short-run
and the economy of the country in the long-run.
6
The Zululand Chamber of Commerce and Industry (ZCCI) is a chamber of businesses that
sits in Richards Bay, South Africa. It provides a platform for local business to come together
and share information and expertise. Businesses register with the chamber and pay annual
fees for services the chamber renders to them, including training and presenting
opportunities for collaboration. The chamber registers business in different sectors where
the businesses are operating, such as retail, manufacturing, agriculture, and services. Within
the sectors, there are different categories such as small-, medium- and large businesses. The
chamber is then able to link customers who have opportunities with their members in a
particular category. The chamber keeps the contact details of the members. The chamber
will be approached to assist with the data collection, it will serve as a link between the
researcher and the small and medium-size factories operating from Richards Bay.
The qualitative study will be conducted employing a survey questionnaire, that will consist
of ten open-ended questions and the survey will be conducted online. The first quantitative
study will focus on the primary or direct costs arising from a load shedding incident. The
second will seek to estimate the minimum cost of averting load shedding using generators.
1.4 Research limitations
The research work has the following limitations:
• The research work has a time constraint. An interview would have been the preferred
method of collecting data for the qualitative study instead of a questionnaire.
• This research work is limited to measuring the direct or primary costs associated with
load shedding. These costs arise directly from the incident such as loss of revenue.
• Budgetary constraints, ideally, it would be advantageous to carry out the research
countrywide to get a better understanding, as the impact may vary from city to city.
1.5 Research layout
Chapter 1: Introduces the research, sets objectives, outlines the research approach and
presents the limitations of the research. Chapter 2: Presents the relevant literature review
and contextualizes the research. Chapter 3: presents a critical analysis of the reviewed
literature. Chapter 4: outlines the research questions. Chapter 5: presents the current
statistics about the energy situation in South Africa. Chapter 6: shows the design of the
research. Chapter 7: presents the social and economic conditions of Richards Bay. Chapter
8: shows the results. Chapter 9: analysis and discusses the results. Chapter 10: makes
recommendations to various stakeholders and Chapter 11: concludes the research.
7
2 L ITERATURE REVIEW
This chapter presents the South African economy in broad terms, firstly concerning the
global economy, continental economy and national economy. The contribution of the
manufacturing sector in the entire economy of the country will be highlighted. The energy
situation in the country will also be presented, focusing on the provision of electrical energy
to both domestic and commercial electricity consumers. The challenges faced by the energy
sector will be highlighted and discussed in detail. The implications of the challenged energy
sector on electricity consumers will be evaluated. A thorough review of methodologies
previously used to measure the cost of frequent power interruptions on electricity consumers
will be presented. A high emphasis will be placed on the implications of load shedding on
commercial activities.
2.1 The current economic situation in South Africa
Globally, the South African economy is regarded highly, the country is part of the Global
Twenty (G20) forum for economic cooperation (G20, 2020). The G20 comprises of 19
developing and developed countries and European Union (EU). The members of the G20
represent approximately 80% of the economic output in the world, two-thirds of the world
population and accounts for three-quarters of international trade (G20, 2020). The forum has
various committees, with the most prominent one made up of political leaders of member
states such as Prime Ministers, Head of States and Presidents. The leaders committee usually
convenes once annually at the beginning of each year to set the agenda for the whole year.
Thereafter, technical sub-committees made up of Finance Ministers and Central Bank
Governors operationalize the resolutions of the leaders committee. However, impromptu or
extra-ordinary meetings of the leaders can be called at any time when there is a pressing
matter that affects the majority of the major countries, like the special Corona Virus
Pandemic leaders summit, that was convened on 25 March 2020 via video conference (G20,
2020). According to (G20, 20) its main aim is macro-financial and socio-economic matters.
South Africa is also part of an international economic formation of emerging economies
which include Brazil, Russia, India, China, and South Africa (BRICS). The formation is
commonly referred to using the acronym BRICS. South Africa joined this important bloc in
December 2010 and has hosted two BRICS summits, the first one in 2013 and the second in
2018 (BRICS, 2019). According to BRICS (2019) the five countries represent 42% of the
world population, 23% of the world GDP, and 18% of global trade.
8
At the regional level, South Africa is considered one of the most advanced economies in the
continent of Africa. It is part of the African Union (AU) and the Southern African
Development Community (SADC) at the sub-regional level. South Africa is currently the
chair of the AU starting on 09 February 2020, His Excellency President Ramaphosa was
elected chairperson of AU for the year 2020 at the 33rd ordinary session of Heads State and
Government (AU, 2020). According to AU (2020), the primary objective role of the AU is
promoting unity, peace, economic growth, integration and cooperation of African states.
South Africa will be leading in setting the AU agenda for 2020 and linking the AU to the
world through the G20 and BRICS formations. The role of South Africa at the SADC level
is also prominent. Most SADC member states share borders with South Africa and are
largely the biggest trade partners of the country on the continent.
The South African economy is considered to be amongst the largest in Africa and the most
industrialized economy in Africa (Mare, 2011). According to Mare (2011) as one of the
most industrialized economies on the continent of Africa, the South African economy is
energy-intensive, dominated by heavy industries such as mining, processing, and
manufacturing. Even though the country has one of the largest economies on the continent,
there are still massive challenges related to economic growth which has been below 1% for
four years (2014-2018) and the high unemployment rate at 29.1% (Statistics South Africa,
2018). Some of the factors limiting economic growth in the country are external and some
are internal. The external factors related to the global economic slowdown as the
International Monetary Fund (IMF) has lowered the global economic rate forecast to 3.6%
for 2020 (South African National Treasury, 2020). The slow down of the global economy
severely affects the South African export market, as the demand for mineral resources
declines. Trade wars between major economies in the world that result in tariffs being
imposed on certain critical products do not aid the global economy. However, there are also
internal challenges that have stalled the economy from growing rapidly, such as the
weakening currency, energy challenges, and low business confidence.
Since the dawn of independence in 1994, the South African economy was driven by primary
sectors such as mineral resources and agricultural products (Brand South Africa, 2018).
Brand South Africa (2018) notes that the economy has evolved from the early 1990s from
relying heavily on the primary sectors to tertiary sectors such as financial services,
wholesale, manufacturing, and tourism. The economy is mainly based on technology, e-
commerce, and it is a vastly knowledge-economy (Brand South Africa, 2018).
9
The current structure of the South African economy is therefore largely dominated by sectors
such as manufacturing, wholesale, retail, transport, financial services, and tourism. Figure 2
below shows the sectoral distribution of the economy as of quarter three in 2017.
Figure 2: The economic sectors that contribute to the total GDP (Statistics South Africa, 2018).
It can be seen in Figure 2 that manufacturing contributed 13% to the total GDP in the third
quarter of 2017, this within the ball-pack of the 12.2% of the annual contribution of the
sector quoted earlier. The major contributor to the economy is by far the financial services
that are boosted by e-commerce, insurance, and the world-class banking system in South
Africa. The South African Central Bank is playing a critical role in regulating this sector
ensuring healthy competition and fraud detection. Trade comes in third at 15%, this includes
wholesale and retail trade. Statistics South Africa (2018) estimated that the actual trade
contribution is about 1% higher if the informal economy of street vendors is taken into
account. Manufacturing comes in at number 4 with a 13% direct contribution. It is estimated
that manufacturing contributes a further 5% to the South African GDP indirectly, through
tertiary sectors such as trade and financial services (Statistics South Africa, 2018). It is clear
from the statistics mentioned before that manufacturing is a critical sector in the economy.
10
Even though the South African economy has a modern structure and it is highly
industrialized compared to other economies on the continent, the economy is still not
growing at the expected rates. This could be due to some internal factors that will be
considered next.
The weak South African currency, the Rand, is affecting the import and export markets. The
internal factors are related to the structure of the economic policies the country is pursuing
and the management of key national assets, which include state-owned enterprises (SOE).
SOE's are large government-owned corporations in South Africa that are responsible for key
infrastructure and services. They include among others, Rand Water, an entity that is
responsible for ensuring that the country's present and future water needs are catered for and
it reports to the national government through the Department of Water Affairs. There is also
the South African Airways, the national carrier that flies domestically, regionally in Africa
and internationally to other continents. The primary objective of the national carrier is to link
South Africa to strategic partners in the world, prioritizing destinations such as London in
the United Kingdom, New York in the United States, Frankfort in Germany and Shanghai
in China, these countries and cities, in particular, have many people that own and run
businesses in South Africa. There is also Transnet that is responsible for the Ports and the
Railway infrastructure. However, the most critical of all the SOEs is the power utility
company Eskom. An economy cannot grow and be sustainable without a reliable, well-
priced and sustainable electricity supply (Goldberg, 2015).
2.2 The current energy situation in South Africa
Eskom is a South African power utility company that is responsible for the national power
system. The company owns 95% of the installed electricity generation infrastructure in the
country, manages the transmission grid and the reticulation network in non-metropolitan
areas (Eskom, 2020). According to Eskom (2020), the company owns and operations 30
power stations that include the following generation mix, 36 479 MW from coal-fired power
stations, 1 860 MW from a nuclear power station, 600 MW from hydro-stations, 2 724 from
pumped storage schemes, 2 409 from gas-fired power stations and this comes to a total
installed capacity of 44 172 MW of generation capacity. Eskom (2020) notes that the utility
never operates at the installed capacity, because some units are taken out of commission for
maintenance regularly, and the planned maintenance outage is 9 500 MW.
11
On the power transmission and distribution side, the utility owns and operates 387 633 km
of high-, medium- and low-voltage lines and cables (Eskom, 2020). According to Eskom
(2020), the utility has a total of 6.2 million direct customers which include metropolitan
municipalities, mines, smelters, and the general public. The utility has 39 292 employees
spread across three operating divisions, which are power generation, power transmission,
and power distribution including new connections. The utility has a mandate to generate and
supply power to customers in South Africa and the SADC region, it exports power to
Zimbabwe, Botswana, the Kingdom of Lesotho and the Kingdom of Swaziland. Eskom was
regarded as a mighty power utility in the late 1990s and early 2000s, in the year 2005 it was
ranked the 11th best power utility in the world by world energy council (World Energy
Council, 2005). Soon after getting recognition from the World Energy Council in 2005, the
power utility started experiencing power supply shortages leading to rotational power
interruptions in the country in 2007 (Van der Nest, 2015).
According to Van der Nest (2015), the power supply challenges leading to load shedding
were only witnessed in 2007, however, they started much earlier in the late 1990s and early
2000s, approximately seven years before. Energy experts warned the South African
government through the Department of Minerals and Energy in a white paper authored in
1998 that the country's population and electricity demand were rising rapidly (Goldberg,
2015). The white paper forecasted that by the year 2007, the electricity demand is likely to
exceed the installed capacity at the time and this crucial expert advice was ignored by Eskom
and the South African government. Between 1998 when the white paper was given to the
government and 2007 when load shedding was first experienced, there was no investment in
upgrading or strengthening existing power generation infrastructure (Van der Nest, 2015).
This decision taken in 1998 was regretted a few years later when the power cuts started in
2007.
When the load shedding started, South Africa had already won the bid to host the 2010 FIFA
Football World Cup in 2010. The South African government gave the power utility a
mandate to do everything possible to keep the lights "on" to shield the country from
international embarrassment in the build-up to the World Cup in 2010. The already strained
power generation infrastructure was stretched to the limit, leaving almost no room for
periodic maintenance to keep the lights on. The 2008 global economic depression slowed
down the South African economy resulting in reduced energy demand for the years 2008,
2009 (Van der Nest, 2015).
12
The South African economy started rising again in 2010 as the country was building up to
staging the World Cup in June 2010 (The Economist, 2015). However, the rise in the
economy was largely due to the booming tourism and construction sectors at the time, and
both these sectors are not energy-intensive, therefore, the energy demand was still
manageable for the power utility (Goldberg 2015). After the World Cup the South African
economy continued to recover from the 2008 global depression and by 2011 most industries
that had shut down in 2008 were getting recapitalized and starting with operations again
(The Economist, 2015). The implication of this rising economy for the power utility was a
rise in energy demand and by early 2012 load shedding started again (Van der Nest, 2015).
According to Van der Nest (2015), the challenges facing the power utility in 2012 were far
greater than those that faced it in 2007. He further noted that the South African government
was forced to quickly invest in two new state of the art coal-fired power stations, Kusile and
Medupi in 2007. However, the lead times on the construction of these plants meant that they
were not available to come online in 2012 when they were needed the most. Van der Nest
(2015) highlights that the power stations are plagued by design and construction challenges
that caused massive delays, and they went over budget by billions of Rand.
Over and above the problem of load shedding, Eskom had the problem of the two new power
stations that were draining a lot of money and not bringing in any revenue. Both these mega-
projects were financed from money raised in the financial markets backed by a government
guarantee. The cost of servicing the interest on the debt is estimated to cost Eskom over 100
million Rand per month and as of the year 2015, the power utility had a sovereign debt of
approximately 450 billion Rand (The Economist, 2015). These financial difficulties are
coupled with technical challenges, where the current generation plants that were not
maintained properly from 2007 to 2010, are starting to breakdown often. This challenge was
also coupled with leadership instability at Eskom, where there were six different Chief
Executive Officers (CEO) in ten years from 2005 to 2015 (Van der Nest, 2015). All these
challenges and a skills exodus of experienced staff resulted in a deepening load shedding
situation. Whenever a new CEO came, they would change the structure and move employees
around and some employees did not like this leading them to resign. It is against this
background that South Africa is experiencing load shedding that is crippling the economy
and the lives of ordinary South Africans unpleasant with frequent power interruptions. A
deeper look at load shedding will show that this problem is structural, it is embedded in the
power utility. A meticulous approach would be needed to solve this problem at Eskom.
13
What is Load Shedding?
Load shedding is a systematic technique of managing the demand for electricity to prevent
the collapse of the grid. When the demand for electricity far exceeds the generation capacity
at a particular time, power utilities are forced to reduce the load by limiting the number of
supply points, opening circuit breakers that supply certain customers. When there is
insufficient power to meet the electricity demand and the power utility takes no measures to
reduce the load, this has the potential to collapse the grid (nationwide blackout). This would
be catastrophic as it would damage transmission infrastructure and it would take weeks to
restore the power countrywide (Van der Nest, 2015). As the surplus between the electricity
supply and demand reduces, load shedding becomes the only option to protect the grid and
it starts when the demand reaches 90% of the available supply at a time (Eskom, 2020).
Eskom priorities the stability of the national power grid. Therefore, they take preventative
measures when the electricity load rises rapidly, this includes requesting major customers to
reduce their load voluntarily. If this does not yield the required energy supply surplus, the
next step is to request all customers to reduce their demand by switching off all non-essential
electrical appliances and lights. If this call does not yield the required energy surplus in the
power system, Eskom activates peaking plants that open cycle turbines running on diesel to
counteract the rising demand. The diesel plants consume a lot of fuel and they are always
the last resort. If they also do not provide the necessary energy deficit or the demand keeps
on rising, Eskom then resorts to rotational power-sharing, where the available power is
shared rotationally until the demand reduces. There are various stages of load shedding,
depending on the size of the energy deficit between the supply and demand of electricity.
These will be discussed further in the subsequent chapter dealing with load shedding
statistics.
2.3 The impact of load shedding on electricity consumers in general and businesses in particular
Power outages have two main victims in South Africa which are domestic and commercial
electricity consumers. Domestic consumers generally use the electricity for non-commercial
purposes which includes activities to sustain life and for domestic entertainment. The
commercial consumers of electricity use it for business operations. The two victims do not
suffer the same fate from the load shedding and the differences will be outlined in the
subsequent sections of this report.
14
Table 1 shows three categories of the load shedding impact on electricity consumers. The
costs of a load shedding incident are classified according to three types which are the direct,
indirect and societal impacts. A loss in electricity utility qualifies as a loss in the context of
this study when this loss results from a frequent interruption of the electricity supply.
Electricity is such an integral part of people's lives today, the unavailability of the resource
results in mostly economic impact to society. Sanghvi (1991) notes that the nature of the
impact depends on several factors that include, among others, the duration of the load
shedding incident, the magnitude of the incident and the advance notification of electricity
consumers about the incident. When an electricity consumer that suffers from frequent
power interruptions can mitigate or minimize the impact thereof, this is considered when
determining or measuring the total cost of a power outage.
Table 1: Three categories of impact resulting from load shedding (Goldberg, 2015)
Direct commercial impacts Indirect commercial impacts Societal impacts
Loss of production The cost of income being postponed
Uncomfortable temperature Restart costs
Equipment damage The financial cost of losing market share
Loss of leisure time
Raw material spoilage Loss of investor confidence Risk to health and safety
Power interruptions do not only have direct costs they also have indirect costs that are much
more complex and difficult to accurately measure, and quantify. When the United States of
America (USA) government was quantifying the cost of the 1977 New York blackout, they
discovered that looting and arson account for 50% of the costs and they are defined as
indirect costs (Assistant Secretary for Energy Technology, 1978:2).
Societal impact of load shedding
Electricity supply is one of the crucial needs modern societies need daily to use for a variety
of needs. The impact of load shedding on the society depends on the nature and magnitude
of a load shedding event (Goldberg, 2015). The nature of a load shedding event includes the
time of the incident, the day of the incident and whether there was a prior notification about
the incident. The impact of load shedding also depends on the purpose that the society uses
the electricity for like, entertainment, maintaining comfortable temperatures or other home
chores like driving pool pumps, electric gates, energizing the electric fence, alarms,
powering closed-circuit cameras (CCTV), cooking and lighting.
15
In a study performed in Pakistan by Jamil and Faran (2018), they found that safety and
security was the biggest concern for the society they surveyed. The respondents in their study
expressed that they felt unsafe when load shedding occurred at night as the security lights,
the security cameras, and electric fence were not working during the load shedding incident
(Jamil and Faran, 2018). The surveyed respondents expressed that their neighborhood
experienced the most house burglaries during the nights when there is load shedding and this
was their biggest concern about load shedding. Jamil and Faran (2018) performed this study
in a middle-income neighborhood. They also surveyed a high-income neighborhood.
The high neighborhood expressed uncomfortable conditions, such as uncontrolled
temperatures due to lack of air-conditioning, lack of cold and hot beverages during the load
shedding and loss of internet, television and the non-circulation of water in their swimming
pools and fish ponds (Jamil and Faran, 2018). According to Jamil and Faran (2018), the
respondents further stated that the above reasons had health implications for the elderly when
the temperatures were high in the summer months and the were cultural implications, as they
cook lunch every day to enjoy together as family, the load shedding also makes it hard to
achieve this cultural practice. They also reported that the internet, sometimes the cellphone
reception would also get affected by the load shedding and the livelihood of the fish in the
pond would be affected by non-circulating water (Jamil and Faran, 2018).
It can be seen from the study of Jamil and Faran (2018) that the impact of load shedding also
varies depending on the class of society. The upper-class society expressed cultural effects,
health effects and entertainment effects resulting from the loss of internet and electronic
devices. They also expressed that they are unable to enjoy certain beverages when there is
load shedding these include cold beverages and hot beverages, and warm home-cooked
meals. The impact on the upper class can be summarized as cultural, health and leisure.
For the middle-class society, the impact is largely concerning safety matters and can be
described as life-threatening as there are house burglaries reported. This impact is not
directly due to load shedding, the incident does not pose danger to the lives of the society
members, however, it creates conditions that may pose danger to the livelihood of society
members. A similar environment was witnessed in New York during the 1977 blackout
where 50% of the impact was due to looting and arson (Assistant Secretary for Energy
Technology, 1978).
16
Indirect commercial impact of load shedding
For the South African economy, the most significant indirect cost is the loss of investor
confidence that results from unstable power supply or power shortages. Investors become
very skeptical of investing their money in economies where there is an unstable power
supply. A stable electricity supply is a major competitive advantage in attracting greenfield
foreign direct investments. Electricity tariffs and the reliability of electricity supply are a
huge factor when investors assess the viability of an investment destination (The Economist,
2015). Most investors are skeptical of investing in South Africa because of the electricity
challenges. There is no certainty as to what is the extent of the problem causing power
interruptions and the key stakeholders seem to be unable to grapple with the problem and
solve it permanently. The second impact that businesses and the economy face is the
postponement of income resulting in liquidity challenges.
For most small businesses, the biggest challenge arising from load shedding is the
postponement of income due to delayed deliveries of orders (Goldberg, 2015). This plunges
the businesses into liquidity crises where they are unable to meet their short-term financial
obligations such as rent, utility bills, wages and other costs of running their businesses.
Businesses accept sales orders based on their capacity to deliver under normal conditions
and load shedding conditions are not normal. Businesses are forced to consider the costly
option of keeping high product stock levels in warehouses and other storage facilities.
Storage is not ideal for businesses, over and above the cost of storage, there are quality issues
that may develop during storage, depending on the storage conditions. The challenge with
storage, it is difficult to determine the exact time the products are going to spend on the
storage facility as this depends on future orders. The most ideal method of conducting
business is the pull system, where a confirmed sales order activates the production process.
Businesses that can deliver despite load shedding challenges earn a competitive advantage.
When a particular business can stand out and deliver goods and services to customers despite
the challenges of load shedding, it is likely to have an increased market share (The
Economist, 2015). This competitive advantage could be due factors implemented internally
to mitigate against the impact of load shedding or contingency arrangements such as putting
away products in storage facilities. Goldberg (2015) noted that customers have preferred
businesses they are loyal to for many reasons, however, if they are unable to deliver at a
particular time, customers tend to look for alternatives, and this how the market share is lost.
17
Direct commercial impact of load shedding
South African businesses are constrained by the structural shortage in electricity supply and
this is severely affecting business operations (Ateba et al, 2019). The level and severity of
the load shedding impact on businesses is dependent on their core business. Sectors that are
energy reliant such as mining, manufacturing, rail transportation, telecommunications, trade,
and financial services get affected the most according to Nkomo (2015). The major impact
of load shedding results from loss of production or the halting of operations. The stopping
of business operations has direct implications on the business revenues and the costs of doing
business. Other direct costs arise from the load shedding that are industry-specific, however,
the abovementioned are common across many sectors of the economy.
Income revenue is one of the most important key performance indicators most businesses
track periodically to evaluate their performance. At the beginning of each financial year
businesses usually set out objectives and targets for the year ahead. Some businesses even
go further by setting, semi-annual, quarterly, monthly, weekly and daily targets that are
tracked using various tools. When business continuity is affected by load shedding, it affects
the throughput for that particular day. This may lead to the daily target being missed, which
has a direct bearing on the revenues. Targets are set based on forecasts of sales from the sales
& marketing department and the mossed targets have a bearing on the sales for that particular
period thus affecting the business income. Businesses sometimes make certain interventions
to recover from missed business targets. These interventions are usually over and above
provisions made for normal operations and they include extending business hours to cater
for the loss hours during load shedding and this has a cost implication for the businesses
The other major direct impact of load shedding on business is the higher costs of doing
business. The major cost component comes from overheads due to standing time and
overtime costs. The biggest cost component reported by business was overtime payments to
employees for working extra hours to recover the lost production due to load shedding
(Diboma and Tamo Tatietse, 2013). The common method of mitigating against missed order
obligations is to request workers to work extra hours to meet the daily target. However, when
workers work extra time, their employee costs double per hour, this is costly for businesses.
Another major cost component arises from workers being at working, however, not being
able to work because there is no electricity for operations, this is known as standing time.
18
3 METHODS USED TO MEASURE THE IMPACT OF LOAD SHEDDING ON
ELECTRICITY CONSUMERS IN GENERAL AND BUSINESSES IN PARTICULAR
There is a variety of methods in the academic literature that are employed to measure the
economic costs of load shedding. The methods vary according to the nature of electricity
customers being studied and the nature of power interruptions faced by the customers.
Therefore, before embarking on such a study, the researcher has to study the nature of
customers facing the load shedding and also understand the nature of load shedding being
experienced by the electricity customers. This information is crucial for selecting the most
appropriate method for the case that the researcher wishes to study. In the subsequent
sections, the research will review types of load shedding studies in the literature and the
methodologies used to measure the various types of load shedding.
3.1 Different types of load shedding studies
When analyzing the impact of a power outage incident it is important to consider the type of
incident being analyzed. Two categories of load shedding studies were noted in the literature.
The first category pertains to studies performed in high-income countries that have a high
percentage of supply reliability in the order of 99.98% (Sanghvi, 1991). The purpose of this
study was to understand the impact of random, rare and isolated incidents of power outages
in the high-income countries. Power utilities of the various countries commissioned the
studies themselves so that they could refine their operations to improve customer satisfaction
(Goldberg, 2015). Some high-income countries conduct power interruption studies to aid
policymakers in making informed policy decisions (Sanghvi, 1991).
The reliability of power supply in Germany is amongst the best in Europe, however, the
country is actively researching the economic impact of power interruptions. The country is
planning to decommission all nuclear power stations by 2022 and ramp up renewable energy
to 35% of the country's energy mix by the end of 2020 (Growitsch et al, 2014). An increase
in renewable energy sources poses challenges as there is no control of the meteorological
conditions in which the quantum of energy generated by these sources at a particular time.
There exists a serious risk of having energy shortages when the meteorological conditions
are not conducive to produce enough energy to meet the demand. This condition may
potentially lead to power interruptions in Germany, unless otherwise, there a peaking power
plants on standby, such as Gas turbines and Diesel generators, that can be called online when
there is insufficient energy from renewables.
19
The cost of power interruption studies has also been conducted for medium to low-income
countries. It is often difficult to distinguish between outages due to technical faults and the
shortage of power supply. If the power utility company is economical with the truth, it is
difficult to distinguish between the two. Technical faults may affect the generation capacity
temporarily, however, they do not cause systemic power supply shortages. Technical faults
are usually seasonal or occasional while power shortages are not sporadic at all. Oseni (2012)
noted that the power challenges in most African countries are due to poor demand
forecasting, generation efficiency and demand management (Oseni, 2012).
Power outages are a regular occurrence in poor countries and they have become a new
normal. Businesses have to factor in this condition when they plan their operations, the
likelihood of a power interruption is high. Power interruptions have both immediate and
future effects. In the present, they affect the production output of businesses and disrupt
operations. In the long term, this affects both customer and consumer trust as well as investor
confidence. The impact of technical faults can be absorbed by businesses, however, it is
difficult for businesses to absorb the cost of power interruptions. Regular faults usually affect
the profit margins and businesses view these as a once in a while anomaly. While power
interruptions affect the profitability of businesses in the short term, in the long term
sustainability of businesses is threatened by the power interruptions unless certain
interventions are made. Businesses that are struggling due to load shedding lead to a weak
or a declining country economy. Modern economies rely on a stable and reliable electricity
supply if this is not present there are primary and secondary economic effects experienced.
3.2 Methods for measuring the economic impact of load shedding
Various methods can be employed to measure the economic impact of load shedding. These
depend on the scope of the research, the type of electricity customer and the nature of load
shedding incidents. In the previous section, various load shedding types have been discussed.
This section will focus on the various methodologies used in the literature.
The first method that will be reviewed is the analytical methodology that uses secondary
data to estimate the cost of load shedding on electricity consumers. This method is only
applicable where there is historical data about the consumption of electricity for economic
activity. This method seeks to estimate the value of lost load (VoLL) per unit (Linares and
Rey, 2013). The VoLL estimation takes into account the economic sector of the business
being studied, the company size, the geographic location of the company and the nature of
20
the load shedding incident. The VoLL depends highly on the prior notification about the load
shedding incident. By estimating the utility value derived from having electricity supply,
this can be seen as a value lost when there is a power outage. The next methodology to be
reviewed is the revealed preferences methodology.
The revealed preferences methodology model is based on the understanding that businesses
are set up to make profits and pay dividends to shareholders. A company that experiences
load shedding frequently will develop mechanisms to first mitigate or secondly minimize
the impact of power outages, this may include getting a standby power plant. Any action that
a business takes to counteract the effect of load shedding will have financial implications.
Therefore, a thorough analysis of the advantages and disadvantages needs to be undertaken
before a decision is made to invest in any mitigating factor. Adenikinju proposes that
multiple options must be considered at first and after a thorough comparison, the best option
is chosen, which would offer the best total cost of ownership (TCO) (Adenikinju, 2003).
Businesses are always striving to make a profit, deciding on a power generating plant
investment is a managerial decision that considers, the cost of the plant, the power
requirements, the cost of interruptions and the economic value to be derived from the power
plant. Oseni (2012) noted that economics should be the ultimate deciding factor on whether
an investment on a backup generator is economically viable.
If a company purchases a backup generator to counter the effect of load shedding, the
information about acquisition costs would be available in the records of the company.
Modern backup generators log a lot of useful information that can be downloaded for
analysis. The biggest advantage of this methodology is the availability of data that is fairly
accurate as generators are smart to log all the important data themselves (Beenstock et al,
1997). The data collection is relatively cheap and quick, it involves a simple download from
the generator computer box. The data is very accurate as it is electronically logged compared
to survey responses where there is a potential for misrepresentations of facts. The
disadvantage of this methodology is that it is only applicable where there are backup
generators with data loggers installed. The next method to be reviewed is the use of customer
surveys to estimate the cost of load shedding on electricity consumers.
Customer surveys have been widely used in the literature to study the impact of power
interruptions on businesses. Sanghvi (1982) says this is the most widely used methodology
to measure the economic costs of load shedding on industries (Sanghvi, 1982). The onus is
left to the consumer of the electricity to estimate how much a power interruption costs them.
21
The method is referred to as the stated preference method, as the end-users of the electricity
estimate value that is lost due to a load shedding incident. Balducci (2003) says this is the
easiest methodology to measure the economic cost of power outages on the end-users of
electricity. The biggest challenge with this methodology is that it is prone to errors and
manipulation, as electricity consumers may make mistakes when responding to the survey
or deliberately misrepresent facts for some reason (Balducci et al, 2003). Customers are best
placed to determine the economic value of a load shedding incident, as it is something that
consumers experience, however, it is not simple to estimate the cost (Tollefson et al 1994).
The economic impact of load shedding can be measured at a micro-scale (small scale) and
then generalize the results to a larger population at a macro-scale (larger scale) if the sample
is representative of the population. Cheng (2014) says that customer surveys offer the
opportunity to get a statistical sample that spans across a wide range of respondents. The
design and execution of this survey is critical in soliciting the correct data from respondents.
The trick is to make the survey as simple as possible and to get as much data as possible
from the consumers of electricity (Cheng & Venkatesh, 2014). The next method to be
discussed is the conjoint analysis methodology.
The conjoint analysis methodology measures the relative values of attributes. Concerning
the matter of frequent power outages, the conjoint analysis would be used to estimate the
monetary value that the consumer of electricity would be willing to pay for increased
electricity supply reliability. The consumers of electricity are presented with a set of
hypothetical situations about power interruptions and their views are solicited. This is a
contrast to the CVM methodology that asks directly for the WTP and the WTA. The rating
and ranking scales are most preferred when implementing this methodology.
The researcher needs to understand the various kinds of impacts that a load shedding might
have to particular electricity consumer when designing the questionnaire. This will help the
researcher to create the required hypothetical conditions for consumers to rank or rate. If
these are poorly designed this method becomes ineffective and does not yield meaningful
results. The options to rank or rate must cover most, if not all possible scenarios so that each
respondent can be able to have something that is a priority to them or their business (Baarsma
& Hop, 2009). The next methodology to be reviewed is case studies.
22
The case study methodology is based on previous well researched and documented power
interruptions studies. The researcher reviews a practical case that happened in the past and
tries to match the conditions under which it happened to the current conditions to draw
parallels. The most famous case study that deals with the impact of power outages is the
1977 New City blackout. This black was extensively studied with funding from the US
government and a case study was developed from the results. The case study considers both
the economic and social impacts of the blackout (Corwin & Miles, 1978).
This method is extensive and requires a lot of resources and data. It needs the support of key
stakeholders for access to resources and data. The case went beyond the direct impact of the
blackout by looking into the indirect impact of the blackout. The major disadvantage of this
method is that no two power outages are the same according to Blien (2009). The case is
specific to a geographic location under specific conditions that may arise again (Bliem,
2009). The next method to be reviewed is the subject evaluation methodology.
The subject evaluation methodology places the task of quantifying the cost of power outages
on electricity consumers. The consumers use their experience, knowledge and own tools to
quantify the cost of load shedding on their businesses. The researcher presents the
respondents with outage scenarios and the respondents estimate the economic impact of each
scenario based on their experience (Kafeoglu & Lehtonen, 2015). Businesses are requested
to state economic losses suffered due to a specific or a set of power outages of the recent
past (Oseni, 2012). This method is also referred to as the direct worth methodology because,
consumers estimate their direct losses that they recorded (Tollefson, et al, 1994).
This methodology works well when the costs associated load shedding incidents are
quantifiable. The power outages interrupt the provision of services and production of goods
affecting the economic standing of firms and countries where these power interruptions are
experienced (Goldberg, 2015). Some of the important data that informs the subjective
evaluation methodology estimates in industrial operations losses due to load shedding
include idling resources, equipment damage, material spoilage costs, process restart costs
and the health and safety concerns (Sanghvi, 1982). These are usually recorded in the
industrial operations, therefore, industries can estimate these costs.
23
4 CRITICAL ANALYSIS OF THE LITERATURE REVIEW
Chapter two of this report has reviewed academic literature that is relevant to the current
research work. This chapter will provide an independent critique of the reviewed literature,
highlighting major strides made in the research field before and also identifying gaps that
the current research will seek to close. Approaches adapted for this research from the
literature will also be highlighted and contextualized.
The literature review begins by studying the South African economy, in the global, regional,
sub-regional and national contexts. South Africa is considered an emerging economy and
plays a prominent role in world economic forums such as the G20, BRICS, AU, and SADC.
The national context of the South African economy is currently gloom as the economic
growth has been below 1% for four years (2014-2018) according to Statistics South Africa.
This has been due to internal and external factors. It was noted by the National Treasury
(2020) that the global economy had a slower growth than anticipated, however, it was still
2% higher than the South African growth. Therefore, it is evident that the South Africa
economy is facing difficulties. The economy is still described as the most industrialized in
Africa. This is true, however, the challenges concerning economic growth will result in
South Africa losing the status of being an economic powerhouse on the continent. One of
the identified causes of the struggling economy is the management of state assets.
Industrialized economies are underpinned by a stable and reliable electricity supply. The
current energy situation in South Africa is not geared to support the industrialized economy
of the country. This is due to poor planning by the government by ignoring expert advice in
1998 about investments in future power generation and the mismanagement of the utility for
many years. The power utility had political pressure before the 2010 FIFA Wolrd Cup to
keep the lights on at all costs. This started in 2007 when load shedding started breaking out
until the World Cup was staged in June 2010. This meant that critical maintenance could not
be done to keep the lights. Like with any mechanical system, if maintenance is not done on
power plants the efficiency deteriorates which is the case with generation plants in South
Africa. In 2007 the government then rushed through two mega power projects that have been
delayed and over budget. These projects have not aided the energy situation in the country.
They have imposed major financial difficulties for the power utility, as the money used to
build these projects was sourced in the final markets, the power utility has a huge sovereign
debt estimated at 450 billion Rand (The Economist, 2015).
24
The challenges at the power utility have resulted in systemic power interruptions that are
known as load shedding. This severely affects business activities in the country as Nkomo
(2015) noted that there is a relationship stable power supply and economic growth in
industrialized or industrializing economies. With energy-intensive sectors such as mining,
transportation, and manufacturing contributing a significant percentage to the total GDP of
the country, it is imperative to understand the impact of load shedding on the sectors, so that
mitigating factors can be put in place and to guide policy development by policymakers.
The load shedding has different impacts on electricity consumers can be categorized into
three, direct commercial impact, indirect commercial impact, and the societal impact. The
impact on society is mostly associated with conditions that arise from the absence of
electricity such as health issues arising from uncontrollable room temperature and the
unavailability of security systems such as alarms. The conditions make the domestic users
of electricity inconvenienced as they become targets of criminals that place their lives at risk.
This according to the researcher is the major impact of load shedding on domestic electricity
users, which are usually experienced during the night. The other impacts include loss of
electronic devices and the internet connection, this can be described as mild impacts, as other
entertainment options are available that do not use electricity such as board games and
outdoor sport.
Direct and indirect commercial losses due to load shedding can be quite large and complex
to quantify accurately. In South Africa, power outages are not sporadic rather systemic as
alluded to earlier, these power interruptions started in late 2007 and they are still experienced
in 2019. This problem seems to be developing every day and this does not inspire investor
confidence in the South African economy. Currently, the power supply shortages challenges
appear to be worsening. It must be noted that investors do not only consider electricity supply
as the only factor when deciding to invest in South Africa, however, it would help the South
African to have a stable, reliable and reasonably priced energy supply. Although no study
has quantified the losses of both local and foreign direct capital investments in South Africa,
it is not unreasonable to assume that this loss is quite large.
It is not simple nor practical to accurately measure the true cost of a power outage incident.
The loss of investor confidence impact is not easily quantifiable. However, direct losses such
as revenues and cost escalations are measurable. These indicators can give a minimum
indication of the impact of load shedding on businesses and these can measured or estimated.
25
There is a variety of methods reviewed in the literature that are used to measure the impact
of load shedding on businesses. These have advantages and disadvantages and this section
seeks to highlight these and to recommend the most preferred methodology to be followed
in the current study.
Analytical methods offer an advantage of simplicity and cost-effectiveness when the
secondary data is readily available for analysis. Cheng et al (2014) noted that this
methodology uses historical energy consumption data to perform economic analysis of
energy load shedding. The major shortfall of this methodology is that it makes some
simplistic assumptions that are often invalid in reality and ignores indirect costs (Cheng &
Venkatesh, 2014:1). According to Balducci (2003), the secondary data is usually presented
at an aggregated level and cannot be used to make findings at the unit level, for example to
one factory or industry (Balducci, Roop, Schienbein, Desteese, & Weimar, 2003). Particular
details such as size, power consumption patterns, operational strategies and type of industry
are also important and this methodology does not have room to factor these into the model.
The revealed preferences methodology is reliable and cheaper than most methodologies that
are used to estimate the cost of a power outage (Beenstock et al, 1997). The disadvantage of
this methodology is the complexity that arises when the backup power plant does not supply
all the energy requirements during a power outage, where only a certain portion of the plant
is the backup power supply, the methodology becomes highly mathematical.
The case study methodology is not suitable for measuring the cost of power interruptions,
however, it is important to use it in demonstrating the importance of supply security, it gives
a good indication of how severe a power interruption can be (Chowdhury & Koval, 1999).
The most preferred methodology is the subjective evaluation methodology. This
methodology is ideal for this study, as there are financial and time constraints. In this
methodology, respondents will be the ones that estimate the impact of load shedding on
them. This methodology has disadvantages like any other methodology. The respondents
may misrepresent their losses or the impact of the load shedding to claim from insurance or
to get support from the government. The respondents may genuinely be unable to accurately
measure and report the losses from the load shedding, which is a possibility if they are not
experienced enough with the measurements. The researcher needs to be careful to guard
against bias and request further particulars where results seem to have outliers.
26
5 RESEARCH QUESTIONS
As previously mentioned, South Africa is suffering from load shedding due to the
constrained power generation capacity of Eskom. The limitations arise as the power
generation plants are aging and getting closer to the end of life. They have been poorly
maintained over the years leading to the 2010 FIFA World Cup. The power shortages have
an impact on both the society and businesses. This impact is not well understood, particularly
in the manufacturing sector. An individual factory may the impact on their business,
however, there is no sectorial analysis that details the impact across the sector. There is
consensus in the reviewed literature that load shedding hurts the economy, however, the
extent of the impact remains a point of debate in academia and society. A study was
formulated that consists of two studies to study the impact of load shedding. There is a
qualitative and a quantitative aspect of the study to better understand the impact of frequent
power interruptions. The results of this study will aid the captains of the manufacturing
sector and policymakers in making wise decisions. This research work seeks to add to the
current academic knowledge by answering the following questions.
The qualitative objective of the research will be addressed by answering question number 1
below and the quantitative aspect will be addressed by answering question number 2.
1. What is the qualitative impact of load shedding on small and medium-sized manufacturing companies in Richards Bay, South Africa?
2. What is the direct impact of load shedding on small and medium-sized manufacturing companies in Richards Bay, South Africa?
27
6 CURRENT LOAD SHEDDING STATISTICS
In South Africa, load shedding has various stages that are determined based on the energy
shortage at the time. Eskom has an installed capacity of 42 000 MW including peaking diesel
turbines. The nominal outage due to planned maintenance is 9 500 MW, meaning that at a
point in time, 9 500 MW is not available as the units are out of commission for maintenance.
Therefore, at a point in there is 36 500 MW available to meet the demand of the country.
Peaking diesel turbines account for 5 500 MW of the installed capacity, in essence, there is
31 000 MW available to power supply the country's energy requirements. South Africa has
a base load of 25 000 MW throughout the year. This rises in winter to about 28 000 MW due
to heating load and 26 500 MW during the summer due to air-conditioning load (Eskom,
2020).
When the generation system is healthy, there is a surplus of at 3 000 MW available and
Eskom exports this power to neighboring countries. The challenges start when there are
breakdowns and the system loses over 7 000 MW, load shedding begins to protect the
network. Anything under 7 000 MW, the peaking plant can provide. When the system is
short of 1 000 MW it is referred to as stage one load shedding. When the system is of 2 000
MW it is known as stage two and so forth. Figure 2 shows the frequency of load shedding
stages experienced in Richards from 01 December 2019 until 29 February 2020. Stage 3 is
not so frequent and it is the most devastating stage. The time of the day during which the
stage occurs is also shown in Figure 3 below.
Figure 3: The frequency of load shedding stages experienced in Richards Bay from 01 December 2019 until 29 February
2020 (Eskom, 2020).
28
When stage one occurs approximately 8% of the customers are affected by load shedding.
Major industries and factories are requested to reduce their demand first before the power
cuts ultimately are initiated. The worst stage of load shedding is stage 8 where the generation
system is 8 000 MW short (Eskom, 2020). This affects approximately 40% of the customers
are affected according to Eskom. The main challenge in South Africa is not the severity of
the power cuts, however, it is the frequency of power cuts that causes challenges for
manufacturers.
Figure 4: The distribution of power interruption incidents on the day of the week for the period 01 December 2019 to 29 February 2020 (Eskom, 2020).
Figure 4 shows the frequency of occurrence of each stage of load shedding on a particular
day of the week for the period 01 December 2019 to 29 February 2020 in Richards Bay. It
can be seen that stage 3 has only been experienced on Tuesdays, Wednesdays, and
Thursdays. This is when most businesses ramp up their operations and the demand rises in
the country. Therefore, the power grid becomes constrained when the generation capacity
cannot match the demand. To protect the grid, load shedding begins and the level rises when
the demand does not drop. Richards Bay experiences the highest number of load shedding
incidents from Thursday until Sunday. This is due to the heavy industries ramping up their
operations heavily starting on Thursday night into the weekend until Sunday night.
29
7 RESEARCH METHODOLOGY
The proposed methodology is multipronged consisting of three studies. The first study deals
with the qualitative impact employing the survey methodology, the second study deals with
quantitative aspect employing the subjective evaluation methodology through a customer
survey and the third study deals with the quantitative aspect employing the revealed
preferences methodology through a customer survey.
• Study 1: To study the qualitative impact of frequent power outages on small and
medium-size factories in Richards Bay, South Africa. A qualitative survey was
shared with managers of the sampled factories in Richards Bay.
• Study 2: To estimate the direct economic cost of frequent power outages on small
and medium-size manufacturers in Richards Bay, South Africa. This study will be
carried out using the direct worth methodology employing a survey questionnaire
that will be administered online. This study focuses on the direct costs of a load
shedding incident. Indirect costs are not covered in the current research scope.
• Study 3: To validate the results from study 2, secondary data will be collected from
backup power systems of the factories that have standby generators installed. The
results of this study will be compared with the results from study 2. The sampled
factories will be requested to share information about the total cost of ownership
(TCO) of their backup generators. This will provide the minimum estimate of what
the factories are willing to pay (WTP) to avoid load shedding.
7.1 The qualitative impact of load shedding on small and medium-size factories
There are no existing studies in the literature that look at the qualitative impact of load
shedding in the manufacturing sector in a developing country such as South Africa. The
literature was then used as a basis upon which an independent study was designed which
would apply to the South Africa context. There are two methods of implementing a
qualitative study, it can be in exploratory or inductive format. The exploratory format
explores situations to find out more about them and the inductive format studies existing
data to interpret (Saunders & Lewis, 2012). The inductive approach is appropriate to the
current research work because the operational and financial data is already available in the
factories, the load shedding incidents have happened. Grounded theory will be used to
extract major themes from the data collected during the qualitative survey.
30
Unit of analysis and population
Data will be collected at the factory-level, therefore, the unit of measure for this research is
a small or a medium-size factory that is operating in Richards Bay, South Africa. These
factories will be represented by management. The population is all small and medium-size
factories operating from the Richards Bay area with an annual turnover below 51 million
Rand. All factories with an annual turnover below 51 million Rand are regarded as small or
medium-size. Small factories have a maximum turnover of 15 million Rand.
Sampling method and size
A collection of all small and medium-sized factories in Richards Bay was not available from
the relevant authorities. An effort was made to gather a list of all factories in Richards Bay
operating from Richards Bay. It was not possible to get to all the factories, because some are
not listed companies, their turnover is not published. The next best bet was the Zululand
Chamber of Commerce and Industry, they have a unit for small and medium-sized
businesses, where some of the factories operating from Richards Bay are registered. These
factories were targetted as the sample of the study. Therefore, probability sampling was not
a possibility and as such non-probability sampling was used.
Purposive non-probability sampling was used to determine the sample. This kind of
sampling ensured that the final sample is representative, with an even distribution of small
and medium-sized factories represented in the final sample. When deciding on the sample
size for qualitative research, it is important to consider the saturation point, where no new
themes arise from more data collection. The researcher had a sample of 38 managers from
both small and medium-size factories who were requested to participate in the qualitative
study. There were 12 medium-size factories and 26 small size factories that were to take part
in the survey.
Data collection process
The data collection process was done employing a survey questionnaire. The qualitative
survey questionnaire was administered electronically online. The questionnaire consisted of
ten open-ended questions. Table 3 shows the sample of the questions that were shared with
the factory managers to solicit qualitative data. The survey had ten questions in total. As
previously mentioned 38 managers from both small and medium-size factories were
approached to complete the survey.
31
Table 2: Qualitative research survey questions (Self-creation, 2020)
What is the impact of load shedding on your business and operations and brand?
How are the revenues of your business affected by load shedding?
How are the costs of doing business affected by load shedding?
How is safety in your factory affected by load shedding?
How does load shedding affect your staff morale and attitude?
What is the impact of load shedding on the Administration side of the factory?
If you have installed backup power supply, what challenges do you still experience, if any,
despite having backup generators in place?
Are there any opportunities that result from load shedding?
What are the knock-on effects experienced due to load shedding?
What do you do to manage and mitigate the load shedding risk?
Analysis approach
The data for the qualitative part was analyzed manually to get the various themes and this
was possible as the number of responses was only 22. For a high number of responses,
typically a software package like Atlas Ti would be required to analyze the responses to
identify common concepts and cluster them for analysis. For this analysis, the most common
themes were grouped manually. This made it possible to understand the most pertinent issues
arising from load shedding from a qualitative perspective.
7.2 The direct economic impact of load shedding on small and medium-size factories
These two quantitative studies are designed to be descriptive, to allow respondents to
describe their experience of load shedding. These two studies are quantitative and they seek
to estimate the direct economic impact of power outages on the factories. The studies are
designed to be descriptive to enable the factories to describe the economic impact they suffer
because of load shedding. Saunders and Lewis (2012) say that a descriptive study produces
an accurate account or representation of persons, events, and situations (Saunders & Lewis,
2012). This study will provide a systematic and scientific approach to estimating the direct
economic impact of load shedding on small and medium-size factories in Richards Bay.
32
The main aim of these quantitative studies is to come up with a numerical value that will
represent the cost of power outages on the small and medium-size factories operating from
Richards Bay, South Africa. These two studies will have as a financial result a numerical
value or a percentage representation of the economic impact of load shedding on factories.
From the various methodologies reviewed from the literature, two important considerations
were noted when a methodology is chosen for the studies. The first consideration is the type
of power outages and the various types of impact arising from the outage.
In a country that has frequent power interruptions, there are two categories of victims, the
first are businesses and the second is the society in general. The types of impacts that a load
shedding incident may have various electricity consumers are listed below.
• Direct economic impact
• Indirect economic impact
• Societal impact
The costs associated with indirect economic costs and societal costs are significant, their
study is beyond the scope of this research work. These would require a separate methodology
to estimate and a case study is best suitable for this kind of research work according to
(Corwin & Miles, 1978). Due to the limited resources in terms of time and financial
limitations, the case study is beyond the scope of the current research. It will be
recommended for future research work. The total costs of power interruptions will be higher
than what will be measured by these two studies as they will only focus on the direct costs.
The other important consideration when studying the economic impact of power outages is
their nature and their frequency. In South Africa power outages are experienced daily,
however, the stages vary as previously mentioned. This depends on the power deficit
between the generating capacity and the demand at a particular time. During the high peak
periods, the higher stages of load shedding are usually experienced which are mornings and
evenings, when household activity is at the highest. South African society has accepted that
load shedding is a part of their lives and business operations. When there is a prior
notification of the load shedding, it is possible to plan alternative activities that do not require
the use of electricity or to organize alternative power supply for the continuation of activities
that require the use of electricity. Several studies looking into the cost of power interruption
have noted that the impact of a power outage significantly reduces when there is a prior
notification of the electricity consumers about the load shedding incident (Kim et al, 2015).
33
There are four studies from the literature that will be used as a basis upon which this study
will be developed. All these four studies use electricity consumer surveys to estimate the
economic impact of load shedding on consumers. Below is a list of the studies, countries
where they were performed and the people who performed the studies (Goldberg, 2015).
• Cameroon (2013), Diboma and Tamo Tatietse employed the direct worth methodology
to estimate the economic impact of power outages on industrial consumers employing a
customer survey.
• Various African countries (2012), Oseni employed the secondary data from a World
Bank survey to estimate the economic cost of power interruptions in 12 countries in
Africa.
• Nigeria (2003), Adenikinju employed customer surveys to estimate the economic impact
of frequent power interruptions. The marginal cost of the backup power supply was also
estimated from the data from customer surveys.
• South Korea (2016), Nam et al employed customer surveys to estimate the direct cost of
power interruptions on heavy industrial electricity consumers. The direct worth
methodology was used for the estimations.
The studies mentioned above make use of customer surveys to solicit information required
for the economic cost estimation of power interruptions. This technique is widely used in
similar circumstances to the current research estimate the economic impact of power
outages. The subjective evaluation method is used to estimate the direct costs and the same
method will be adopted for this research. The marginal cost of backup systems is estimated
using the revealed preferences method, and this approach will also be adopted in the current
research. The environment where the above methods have been applied is similar to the
Richards Bay case. A structural shortage of electricity is common to all four studies and this
is also the case experienced in Richards Bay by factories.
7.2.1 The direct economic impact of load shedding employing the subjective evaluation methodology
Unit of analysis and population
Data will be collected at the factory level. It will either be a small or medium-size factory
that is operating from Richards Bay, South Africa. A customer survey with quantitative
questions will be sent to the factories electronically for them to estimate the economic impact
of energy load shedding. The impact of load shedding will be normalized to cost per hour.
34
Where load shedding incidents lasted for part of an hour, the impact will be normalized to
one hour, assuming that the impact is linear over the total load shedding period. This
assumption is not accurate for industries dealing with steel and other metals, where the
processes involve molding and turning of the metals, longer load shedding periods results in
much higher costs.
The population for this survey is 38 small and medium-sized manufacturers in Richards Bay,
which are registered with the Richards Bay Chamber of Commerce. Load shedding patterns
are not the same in summer months (October – March) and the winter months (April –
September). The electricity demand rises in South Africa during winter, due to increased
heating loads and this increases the frequency and severity of load shedding (Eskom, 2020).
It would have been ideal to do this research in winter, however, the only opportunity
available was the summer, between December 2019 and February 2020, in South Africa.
The results from the study do not represent the worst-case conditions.
Sampling method and size
Purposive non-probability sampling was used for this study. The population is 38 small and
medium-sized factories. The entire population was taken as the sample. This was done to
ensure that the sample is representative of both small and medium-sized factories. The
purposive non-probability sampling was used together with stratified random sampling
because there are two groups within the population. The literature suggests stratified random
sampling for studies of this nature when there are different groups within the population,
like households, some are wealthy and others are not wealthy (Kjolle et al, 2008).
Since the population of small and medium-size factories operating from Richards Bay is
38 according to the Zululand Chamber of Commerce and Industry (ZCCI). There are
26 small size factories and 12 medium-size factories. A minimum of 13 small-size
manufacturers' responses and a minimum of 6 medium-size manufacturers responses' are
required for the stratification principle to be satisfied (Kjolle et al, 2008).
Data collection process
An online administered questionnaire was employed for data collection. The electricity
consumer was requested to assess how load shedding impacts their factory financially and
economically. The survey was designed to be flexible to allow the consumer to explain their
estimations or provide a methodology of how they arrived at a particular estimation. This is
necessary to test and evaluate the methodology to understand the assumptions that factories
35
make when they do their estimation. This methodology is known as the direct worth
approach to studying the economic impact of power outages.
There are costs associated with volume production losses and costs associated with
overheads and related expenses and some savings made due to the disturbance of the
operation. This is captured by equation 1 below (Godberg, 2015).
�� = ��� + � − �� Equation 1
DW is the total estimate of a power interruption cost. VLP represents the losses incurred to
production disturbances. ORC referrers to other VLP is the value of lost production, and
ORC and ORS is the outage related costs and outage related savings respectively (Godberg,
2015). The subjective evaluation methodology presents the consumer with options that
represent certain scenarios that they may have experienced in the past. The researcher must
have a good understanding of the industry and possible impact when designing the scenarios.
Analysis approach
The factories provided details of a particular load shedding incident, including the time it
started and duration. The impact was then broken down into intervals of one hour. This is
illustrated below using an example, where an incident starts at 10:00 until 13:00.
• 10:00 – 11:00
• 11:00 – 12:00
• 12:00 – 13:00
Where a load shedding incident lasted less than one hour or a certain number of hours and
part of an hour, the part was normalized to a cost per hour using equation 2, instead of cost
per minute. Let the impact of experienced by a business as a result of a power outage for a
part of an hour be I. Let the cost be denoted C and the time in minutes be donated TM.
Therefore, the normalized impact will be as follows.
=�
��∗ 60�������/1ℎ� Equation 2
After determining I in equation 2, it is then possible to determine the percentage of revenue
lost per day in hours. The revenue lost per day in hours is called the Revenue Loss Per Hour
(RLPH) and it is calculated using equation 3.
��� = !"#$%'("%)*+%!,-%!(.(/0(-12)#11!.3
45,6#"(/7(5"+!.2$#.-"!( Equation 3
36
The RLPH is considered with other factors to come with a Customer Damage Function
(CDF). The CDF varies with factors that make up the nature of the load shedding incident
experienced. The factors are the hour of the day, day of the week Duration of the load
shedding incident, the hour of the week (Goldberg, 2015).
The CDF changes as any one or more of the previously mentioned factors change. This
function makes it possible to track and trace the changes as the factors change. The factors
are independent variables and the CDF depends on them. An assumption was made that a
factory's revenue could be affected by load shedding during trading hours only, i.e. hours
when there is production in the factory. Of course, some factories that do not run production
24 hours a day and 7 days a week, however, they do have refrigerated storage facilities that
operate 24 hours a day and 7 days a week from the electricity supply and are affected by
power outages outside of production hours. This effect is beyond the scope of the current
research, it will be recommended for future work.
7.2.2 The direct economic impact of load shedding employing the revealed preferences methodology
Unit of analysis and population
The energy delivered in kilowatt-hour (kWh) from the back power generating systems or
plant will be used as a unit of analysis in this study. The revealed preferences methodology
will be used to estimate the cost of a kWh of energy from a backup power plant relative to
the cost a kWh from the power utility company Eskom. The population is the small and
medium-size factories that have backup power systems. This included only those small and
medium-size factories that are registered with the Zululand Chamber of Commerce and
Industry as Chamber's database was used to identify and contact the relevant factories.
Sampling method and size
The population of small and medium-size factories operating from Richards Bay that have
backup power generators are limited, therefore, purposive sampling employed to identify
those factories in the small and medium-size category, which have backup power systems or
plants installed. With purposive sampling, it is possible to ensure that the sample covers both
the small and medium-size factories. No definite financial data was obtained, all
manufacturers deemed this data confidential and highly sensitive. However, comparative
figures (backup power plants costs vs utility power costs) in percentage were supplied. The
size of the sample was 12 factories in total, 8 are small size and 4 are medium size.
37
Data collection process
The data was collection carried out by approaching the manufacturing organizations
electronically employing a survey questionnaire. Acquiring financial data from all the
factories was a huge challenge. Again absolute figures proved to be sensitive for most
factories, therefore a percentage system was used. The survey asked specific questions
regarding backup power systems.
Analysis approach
This study will analyze the cost of investment in a backup power system taking into
consideration the acquisition costs and the running costs. A calculation will be performed
that will come with the cost of supplying a kWh from a backup system and it will be
compared with the cost of a kWh supplied by the power utility. The total cost of ownership
of the backup power system will be determined and this shall serve as the minimum cost of
load shedding on that factory. This exercise becomes highly mathematical and complex
when the backup power system supplies a certain of the factory, further information is
required to make the calculation and estimations.
7.3 Survey design
The questionnaire was prepared initially and pre-tested using a small number of factory
managers in Richards Bay. The survey provided factory representatives with possible
scenarios relating to load shedding incidents and they were requested to estimate how these
affected their business before it was experienced or how it would affect their business.
During the pre-testing of the survey with five factory managers, the following was
discovered.
The representatives of the five factories that were chosen to pre-test the questionnaire were
only comfortable to estimate losses that they had experienced. The hypothetical scenarios
did not apply to some of their factories and they could not imagine the impact if they had to
experience the scenario. No scenario was common to all the five factories that took the pre-
testing questionnaire. It was discovered during the pre-testing that giving respondents a set
of scenarios was not the best option for the current research work. It was then decided that
the respondents would be requested to pick a load shedding incident from the recent past and
estimate the economic impact it had on their factory.
38
For an accurate estimation, the respondents were asked to recall a recent power interruption
incident that they had recently experienced. Respondents were requested to briefly describe
the incident, the stating the time, the time it ended, the day on which it happened and to
estimate the impact in terms of revenue losses and costs escalation. The biggest advantage
of this approach was that the factory representatives still had the incidents fresh in their
minds as they had experienced and could remember the incident well, meaning their direct
worth estimate was likely to be accurate.
The respondents consider the revenue losses associated with production losses to be of
utmost importance compared to other losses related to the power outage. The qualitative part
of the survey in study 1 provides a deeper understanding of other elements that can be
affected by load shedding other than revenues. In a factory setting, the highest loss will come
from the loss of production. Equation 1 shows that the VLP is the first variable to consider
when computing the CDF, it has the highest contribution to the total losses. The emphasis
was put on measuring the revenue losses associated with a power outage.
Factory managers experienced a difficulty in spelling out in monetary value the cost of
power interruptions, a percentage estimation was decided to be accurate enough. This
information is considered highly sensitive by all the trial respondents. The next best measure
to absolute values is the percentage estimation and all respondents were comfortable with
this proposal. It proved to be a challenge to secure managers for a physical interview to
understand the qualitative aspect load shedding has on manufacturing, therefore, it was
decided that the qualitative part will form part of the survey in the form of open-ended
questions.
After taking into consideration the concerns raised during the pre-testing of the
questionnaire, a final questionnaire was developed. Based on the subjective evaluation
methodology the survey questionnaire asked factory managers to think of a recent power
outage incident that they have recently experienced, which is perhaps still fresh in their
memory. The managers were also asked to estimate the direct economic loss associated with
the incident. The qualitative impact of load shedding on the manufacturing business was
captured using part 2 of the survey shown in Appendix A. Section 3 of the questionnaire
considers the quantitative impact of the load shedding scenario. Section 4 of the survey
pertains to the backup power generation system where applicable and section 5 covers
particulars of the company such as demographics, size and staff complement.
39
8 SOCIO-ECONOMIC CONDITIONS IN RICHARDS BAY , SOUTH AFRICA
Richards Bay is a coastal town on the North Coast of KwaZulu-Natal Province, South Africa.
The town started as a small town for fishing for people on holiday. It has since evolved to
be a major economic hub, not only in the Province of KwaZulu-Natal but in the whole of
South Africa. The port of Richards Bay is a key national asset that is owned by the South
African government. The port has a world-class coal terminal for coal export and six other
terminals that are used for import and export of other various commodities and cargo. Some
of the commodities that are exported include ilimite, rutile, zircon and pig iron (Nel, 2018).
The port also services a host of farmers that export various fruits, vegetables, and timber to
the foreign markets. The area around Richards Bay is fertile for timber plantations and
sugarcane farms. These are the largest agricultural feeds. The evolvement of the town is a
result of the government policy on industrial decentralization that enacted in 1998. This
down is considered to be one of the most successful government projects on industrial
decentralization (Arinuth & Barns, 1998). The development of the deepwater port and the
state of the art railway system linking the port to various economic activities inland was a
major game change for Richards Bay. The town has several international corporations setting
up manufacturing operations around it, because of the convenience of export finished goods
or the import of raw material. This has seen the economy of the town rise rapidly over the
past few decades. Richards Bay is now the city with the third-largest economy in KwaZulu-
Natal and the tenth in South Africa. The future of the town looks bright as the local
government is trying, by all means, to attract more investments into the town.
UMhlathuze Local Municipality that houses Richards Bay and the nearby town of
Empangeni is home to 1 600 000 residents (Nel, 2018). According to Nel (2018), the
unemployment rate in Richards Bay is 22%. The port of Richards Bay is a major export hub
in the KwaZulu – Natal Province. Many people who are employed in Richards Bay, work
for the industries that are located around the port. These industries process agricultural
products from inland into finished goods and export them into the foreign market. They also
receive imported raw material that is processed into finished products and then distributed
to the country for consumption using the railway system linked to the port. The major
industries have a huge impact on the local economy, however, the small factories, employ
more people compared to the big factories or smelters as mentioned in the introduction.
Therefore, the impact of power losses on these small industry players affects several people
and has a far-reaching implication for the GDP of the Municipality as well as the Province.
40
9 SURVEY RESULTS
9.1 The qualitative impact of load shedding on small and medium-size factories
Qualitative data was collected using a survey with open-ended questions that were
administered online. This survey was sent to factory managers to solicit the data, they were
requested to describe the impact of load shedding in open-ended questions.
Major themes
When a qualitative study is undertaken with a larger group, meaning that there is no focus
group, the analysis technique involves identifying themes emanating from the data. It is
highly recommended that the data should reach a saturation point for accurate research.
When new themes do not appear from the analysis of the data, the data is deemed to be
saturated. In the current research work, the sample and population could not provide enough
data to reach saturation. However, the collected can still be analyzed to get a view of the
factories surveyed. The outcome of this study cannot be generalized as the available data is
not sufficient. The analysis of the qualitative data yielded nine major themes that are going
to be described further to understand the qualitative impact of frequent power interruptions
on manufacturers. The major themes are the following:
The above themes are discussed in the subsequent sections. The major themes emanate from
the analysis of the qualitative survey questionnaire responses. These themes will be further
explained in the following subsections. Where appropriate, a survey questionnaire responses
will be quoted to help explain the theme.
41
Degree of impact depends on various factors
The economic impact of power outages varies from factory to factory and it depends on
measures each factory takes to mitigate against the impact of power outages. A Likert scale
was used to graphically represent the responses of factories on the level of impact the power
outages have on them. The scale starts from negative 5 to positive 5. Negative 5 represents
the worst impact and positive 5 represents a positive impact of the load shedding incident or
event. A rating of '0' means that there is a neutral impact of load shedding on that particular
factory. Figure 5 on the next page shows the graphical representation of the frequency of
responses stating either positive, neutral or negative impact of a power outage.
Figure 5: Graphical representation of the frequency of comments about the impact of power outages on factories.
The severity of the impact of a power outage incident is largely dependent on two factors,
internal and external to the factory. The internal factors relate to actions and measures that
the factory takes to mitigate and minimize the impact of a load shedding incident. They
include checking the published load shedding schedules from Eskom and setting up internal
mechanisms to deal with load shedding incidents. The comments from factories below give
some examples of the measures factories take. The external factors have to do with the
notification about the incident, duration, and stage of the load shedding incident.
• Survey Response: We are in the business of molding steel, we melt it and then mold.
If the energy goes out, the melting has to be done all over again and it is energy-
intensive, our electricity bill shoots up while the production does not.
There are critical processes in manufacturing that have a devastating effect if they are
stopped midway. Over and above production losses, there are significant energy costs
associated with rework of what was already done or in progress during the load shedding
incident for some factories.
4
6
3 3
1
2
1
2
1
0 00
1
2
3
4
5
6
7
-5 -4 -3 -2 -1 0 1 2 3 4 5
42
• Survey Response: Our factory is largely affected by the loss of production during a load
shedding incident. The raw material is largely not affected as we producing wood-chips
from timber. We are just crushing it to make chips. Our crushers suffer the most from
the stop and start. If are notified on time about the load shedding, we suspend our
operations before the load shedding starts and switch off our equipment.
Some factories are not impacted by rework, however, they are affected by loss of production
mostly. Unplanned load shedding poses a lot of challenges for their equipment. It is possible
to take precautions and reduce the impact on the plant when the load shedding is
communicated well in advance.
• Survey Response: Load shedding usually hits us in the morning when our staff is
energic and eager to push to meet our daily target. It demotivates them as they have to
potentially work longer hours. In the afternoon, the workers tend to think they can just
go home if the load shedding is anticipated to last until knock-off time. We always have
to negotiate with our staff and offer them transport home and overtime pay.
The time of the day during which a load shedding event happens has a huge implication on
the attitude of employees. Employees are more productive in the morning or at the beginning
of their shift.
Operational impact of load shedding
Electrical systems form the backbone of any manufacturing business enabling operations to
be carried out using electrical machinery. An electricity outage does not only affect the
production of goods, it has administrative and safety implications for manufacturers. The
halting of operational processes was the major operational impact expressed by factories.
• Survey Response: We plan our operations around the published load shedding
schedule. We halt our operations during the outages.
• Survey Response: We center our operations around the load shedding schedule.
• Survey Response: We plan our operations, even start or knock-off times based on the
load shedding schedule.
• Survey Response: We only do what we can. Something that doesn't need electricity.
• Survey Response: Try to plan around the load shedding schedule and replenish diesel
in the backup generator after every load shedding incident.
43
• Survey Response: We try to schedule our operations around the announced load
shedding schedule, sometimes it is not followed and we experience unplanned load
shedding which is catastrophic.
• Survey Response: We are producing perishable dairy products, our storage facilities
need energy all day and every day. Therefore, we have a backup power plant for our
storage facility.
Above 90% of the surveyed factories plan their operations the published load schedule by
the South African power utility company, Eskom. If the load shedding is communicated well
in advance and the load shedding is carried out as per the published schedule, the factories
try to minimize the impact, by starting work later than usual if the incident is early in the
morning. If the incident is anticipated in the late afternoon, work commences earlier than
usual. If it happens around midday, the company finds training activities for the employees
to do that do not require electricity. Backup power generation is used to minimize the impact
of a power interruption.
Costs associated with load shedding
A power outage has several costs associated with it for factories that experience it. The costs
are associated directly with a particular power outage or the phenomenon of frequent power
outages. A power outage increases the overtime costs, in terms of extra overtime worked,
damage to equipment and spoilage of raw materials. Costs associated with the phenomenon
of power outages include investments in emergency lights and alternative energy sources.
• Survey Response: The costs of doing business are rising rapidly. We have raw material
spoilage costs that have shot up. We can recycle some of the half processed products,
however, this is energy intense and pushes up our utility bill.
• Survey Response: We have decided to commission a professional firm to perform a
study on the alternative energy sources available and the nature of capital that could be
required. Backup generators consume a lot of diesel, we cannot have sustainable
operations if the generators are to be run very often and for long periods.
• Survey Response: The overhead costs on standing time and overtime are reaching
unsustainable levels. This is a major cost contributor for us arising from load shedding
incidents.
• Survey Response: The costs are rising, most products that are produced during load
shedding do not pass our internal quality testing mechanisms. The cost of rework is
44
rising, we are pondering completely halting operations during load shedding incidents
to cut down on the rework costs.
• Survey Response: We are paying penalties from left, right and center, our clients are
penalizing us heavily for missed deliveries. We have had to renegotiate a lot of our
service level agreements with clients. They also have obligations to their clients, it is a
precarious situation. We are more careful about which contracts we take on, typically it
is far less than our capacity. We are losing business to our competitors if you cannot
deliver clients tend to take the business elsewhere.
• Survey Response: It is so difficult to contain costs, they are running away. We have
decided together with our management team to invest in a backup power plant. This will
require a huge capital investment. We are going to have to train our maintenance team
on the maintenance of the plant, fuel costs and we need to justify the investment to the
board of directors. Our bottom line has to improve after this investment.
The costs of load shedding on business can be classified into two categories, fixed and
variable costs. The fixed costs can often be associated with large capital outlay required
which is difficult for small and medium-size factories. If a factory can afford the initial
capital outlay to provide backup power generation, there are still operational costs associated
with load shedding. The variable costs associated with the running and maintenance of
generators increase significantly with increasing load shedding incidents. Labor costs are
one of the most significant for most factories, as they have to pay employees for not doing
any work as long as they are at work. The overtime bill also increases for some factories, as
they have to extend hours to meet production targets.
Revenue loss due to load shedding
Manufacturers rely on a stable and reliable power supply for production, air-conditioning,
administrative activities, lighting and for security reasons. The major contributor to the
economic impact of load shedding on small and medium-size factories is the loss of revenues
as a result of production losses.
• Survey Response: Revenues are down by 28% per week, we simply cannot afford to
take a huge number of orders. The uncertainty around the electricity supply makes it
difficult to make commitments to our customers. Customers do not take excuses they want
us to deliver and when we don’t they lose confidence in our abilities and capabilities.
45
• Survey Response: About 20% of revenues would come from non-traditional customers,
that we do not have contracts with. They would just call and ask for the availability of
the product, request a quotation and buy. When these customers enquire, we always have
to tell them, sorry we do not have shelf stock. We are barely meeting the obligations of
contracted orders.
• Survey Response: The revenues are declining so quickly. It is so devastating when we
get hit by a sporadic load shedding incident that was not on the published schedule. It
sometimes leads to the cancellation of some of our customer orders, which is the most
unfortunate thing for any business to do. We have built good relationships with our key
customers, however, it is more difficult to manage the relationship now because of the
load shedding resulting in reduced production output.
• Survey Response: They have been plummeting down and the situation is becoming
untenable. We need solutions to this problem and we need it quickly. My factory barely
gives 70% of the design capacity, it is a sorry state of affairs.
• Survey Response: The revenues are declining mainly due to lower production volumes
and the number of rejected products. After a load shedding incident, the quality of the
first few products is bad. We have to recycle these products and this also eats on our
throughput, the number of products that leave our factory daily is declining and this
affects our revenues heavily.
The inability of certain factories to continue with production during load shedding incidents
affects their throughput and consequently the revenues decline. Factories are unable to
produce at full capacity due to power outage incidents. Factories endeavor to plan for load
shedding incidents that are announced on the schedule by the Power Utility, Eskom.
However, when an unplanned incident occurs, it has that element of surprise to factories and
they become reactive instead of being proactive. When factories produce less than what they
used to produce before, they tend to sell less, and the revenues decline compared to before.
Safety and security issues related to load shedding
Administrative systems are critical for tracking orders, deliveries, and production
monitoring. The processing of payments to suppliers is done through an electronic system
for most manufacturers. Sensormatic and closed-circuit television (CCTV) systems get
affected by load shedding, this exposes the factory to looting and theft by criminals. Electric
46
fences also get de-energized during the load shedding making the premises less secure, this
is a huge concern for manufacturers dealing with high valued products.
• Survey Response: The impact of load shedding on security is quite severe, all security
systems like electric gates, automated clocking of employees, electric fences do not
function putting both our employees at risk and our facility in its entirety.
• Survey Response: We need ventilation to keep our factory habitable. We use extractor
fans to circulate the air within the building. Load shedding makes it impossible to
continue operating as the PPE of the employees is not enough and natural ventilation is
not enough.
• Survey Response: Safety is compromised when there is an electricity outage. We have
an automated assembly bay that has limited human involvement and a manual assembly
bay that requires 100% human involvement. The manual assembly bay requires
vigilance as there are mechanical hand tools used to assemble the furniture.
• Survey Response: We need ventilation in our factory, it is the most major form of safety
precaution over and above personal protective equipment. We use the extraction
mechanism for our ventilation system that is electrically driven. Lighting does affect
security more especially our stockpile area.
• Survey Response: It is difficult to maintain safety without electricity, actually the whole
factory environment becomes hazardous when there is an electricity outage. We
immediately withdraw our personnel and turn-off all equipment from supply points
during a power outage.
• Survey Response: Safety is a huge concern for us. We have electric sensors that
measure gas concentration levels throughout the factory when there is a power outage
these become dysfunctional and it is dangerous to occupy the factory space when the gas
levels are not known. As a precaution, we send our employees semi-annually for medical
check-up. This has a cost implication for us, however, our people come first.
Safety and security gets compromised during load shedding incidents in most factories.
Some even state that their factories become a health hazard when there is insufficient
ventilation and lighting in their factories. Employees have to be withdrawn until the power
is restored and the environment is made suitable again for human occupation. Routine
medical check-ups of employees are carried out to ensure that the health of the employees
does not deteriorate because of the working conditions.
47
Mitigation of load shedding impact
Richards Bay factories are exploring and putting in place a few measures to combat the
economic impact that power interruptions have on their factories. These are difficult business
decisions that require financing and consultation with various stakeholders. This is a tough
balancing act that involves looking at the pros and cons of each scenario. The ultimate goal
is to reduce the costs and increase revenues, which in turn increases the profit.
Investment in backup power generators remains one of the most popular mitigating move by
the majority of the factories. In most cases, the backup power generator is not sufficient to
supply the entire factory's energy needs, therefore, an improvision is made to prioritize the
high impact sections. Sometimes it is not possible to mitigate the impact entirely, therefore,
factories try to minimize the impact by planning their operations around the published load
shedding schedule, the start of production is delayed if load shedding is anticipated in the
morning. Some factories had manual production processes before moving to automation.
They did not decommission the manual production means, during load shedding they revert
to manual production process. Some factories organize other activities for employees to do
that do not require electricity, like coaching, training and workshop housekeeping.
• Survey Response: Firstly, we plan our operations around the published load shedding
plan. Secondly, we have a backup power plant. Thirdly, we are incorporating the risk of
load shedding when negotiating and signing contracts with our clients, and we strive for
a mutually beneficial outcome for all parties.
• Survey Response: We center our operations around the published load shedding
schedule. If we have to suspend operations, we do it before the load shedding starts or if
we have to delay the start, we also do that to minimize its impact.
• Survey Response: Our operations are linked to the load shedding schedule, we have
even set our working hours to coincide with the published schedules.
• Survey Response: Unfortunately we halt our primary operation during a load shedding
incident. However, we then do other activities that do not require the use of electricity.
• Survey Response: We try to schedule our operations around the announced load
shedding schedule, sometimes it is not followed and we experience unplanned load
shedding.
48
Most small and medium-sized factories in the Richards Bay area, schedule their production
operations based on the published load schedules. In this case, they switch off and disconnect
their equipment before the power falls away, and they start it once the power has been
restored and stabilized. This protects the equipment and makes the planning manageable. In
cases where there is an unplanned load, the implications are catastrophic for the
manufacturers, as they are caught unaware and tend to be reactionary.
Stakeholders impacted by load shedding
The survey responses gave rise to four major stakeholders in the manufacturing sector that
are directly impacted by power outages incidents. The first stakeholder is the owners of the
factory who are shareholders. The second stakeholder is the customers or clients of the
factory who buy the products of the factory. The third stakeholder is the employees of the
factory, from top management to the lowest employee. The fourth stakeholder is the
suppliers of the raw materials to the factory.
• Survey Response: Our staff is demoralized as the work stops and starts more often due
to the load shedding. We more often than not, fail to meet our daily targets that have an
implication on the employee incentives and bonuses.
• Survey Response: Staff morale is at an all-time low for us. The workers feel the effects
of load shedding on their pockets, we are used to having production bonuses and lately,
we never meet our targets.
• Survey Response: Load shedding has hit us the most on our people. Our staff are the
most precious resource we have in this factory. The morale is declining at an alarming
rate, we have sought to find professional help from psychologists. All our future is
uncertain under these conditions.
• Survey Response: We, as the management of the factory, have had serious discussions
amongst ourselves about going off-grid. This would have both short & long term
implications. The short-term implications include the huge capital outlay required from
the shareholders and the costs associated with the maintenance of the plant until we
break-even.
• Survey Response: We have developed a transparent relationship with our clients, where
we keep them informed of the disturbances we experience and give them evidence to back
up everything assertion we make. We are upfront with the challenges load shedding is
causing for us and we highlight these during our contract negotiation process.
49
• Survey Response: Our suppliers are big stakeholder and the success of our business
relies heavily on their ability to deliver. We have established an open and transparent
line of communication with our suppliers. We have a unit that focuses on our suppliers
and supports them when they encounter challenges. Some suppliers need support.
• Survey Response: In the next few days, we will be taking a proposal to our shareholders,
where we want to explore the use of LPG for energy generation. We are busy finalizing
the business and technical case. We have the space in our premises and the LPG is
available closeby in Mozambique.
• Survey Response: We have open ourselves up, our clients can see our capacity in terms
of equipment, expertise and staff compliment. They are convinced without a doubt that
if we fail to deliver it is due to external factors, internally good systems.
Second-order effects of load shedding
The frequent power interruptions are experienced by everyone and everywhere in South
Africa. This a national problem in South Africa which lowers the risk of brands having their
names tarnished by the load shedding as it is a reality for everyone in South Africa. Therefore
a factory's brand being damaged by load shedding is low from a public perception point of
view. These load shedding incidents are deemed to be beyond the control of the factory or
manufacturer. The brand is enhanced if a particular factory can stand out and be proactive
to avert or minimize the impact of load shedding. This makes the factory distinguished
among the competitors and drives a lot of business towards it. The ability to provide backup
power during load shedding gives a factory a lot of competitive advantage amongst
competitors who are not able to produce during this time. This increases the market share.
• Survey Response: Our clients tell us that they come to us because our competitors are
not able to deliver the volumes they require because of load shedding related incidents.
• Survey Response: We have been making surveys, asking our customers to rate our
service and getting their thoughts on our brand. The majority think that our brand is still
intact, load shedding is something that is not within our control and ambit. We are only
in a position to mitigate or minimize its impact, we cannot stop it.
• Survey Response: I do not think that our brand is tarnished by the load shedding
incidents. Generally, brands are tarnished by a lack of honesty and trust and matters
within our purview. This is a national problem that is beyond our ambit. We suffer from
the loss of market share as customers take their business elsewhere, where they have
means of production even during load shedding.
50
• Survey Response: We have recently invested aggresively on backup power systems and
this will surely have a positive impact on our brand, market share, and competitiveness.
There is a huge pressure from our shareholders to ensure that we break-even as possible
on the investments on backup power generators. It costs a lot of money to keep a brand
shining and to maintain reputation.
Load shedding invokes a lot of conflicts between various stakeholders and this poses a lot
of complications for businesses. Some factories have a single customer that they supply and
it is easier to re-negotiate contracts as and when conditions of trade change. However, most
factories that play in the open market have to note what competitors are doing to gain a
competitive advantage. The South African economy is struggling to grow, therefore markets
are price sensitive. It is difficult to pass on the effect of load shedding to the consumer and
the manufacturers cannot afford to absorb the cost entirely. It is a tough balancing act that
requires a meticulous approach.
Positive outcomes of load shedding
The economic impact of power outages on factories is severely negative. However,
respondents were able to identify some positives arising from the power outages in their
factories. The identified positives can be grouped into categories which are increased
competitiveness in the manufacturing sector and robust learning by factories as they tackle
the reality and challenges of load shedding.
• Survey Response: We have learned to appreciate every kWh that is available to us for
use. We have developed procedures of disconnecting electrical equipment when not in
use. We have upgraded all our lights to energy-saving ones. We are looking in the market
for more efficient motors that consume less energy. In the long run, I think these load
shedding challenges will bring about positive change, even though it is not entirely
voluntary change.
• Survey Response: This challenge has forced us to think outside the box as
manufacturers, and have realized that it cannot be business as usual. We now working
on a collaboration with what would be “our competitors”, however, we are now having
conversations about a local power generating plant in the Richards Bay area that will
have the capacity to supply all of us.
• Survey Response: We are asking ourselves what else could go wrong on the same scale
as load shedding. Our risk analysis has changed and we now consider all, and all
51
possible eventualities and we try to at least plan what to do when the challenge
experience. Crisis moves fast and there is no time to plan during a crisis, one has to
move with the crisis or play catch up later. Load shedding has to teach us to think ahead
and be anticipatory in running our business.
• Survey Response: We are always imagining that the worst will happen, which has
brought some innovation in our business. We try to foresee what would ordinarily be an
unforeseen circumstance or event.
• Survey Response: As a Maintenance Manager, I struggle to get the plant out of
commission to maintain it during non-load shedding times, production takes priority.
Therefore, any load shedding incident provides an opportunity maintenance window for
me. My equipment is in a far more healthy state now than before, as I would only get to
maintain it once a week, now I get at least two hours a day to work on the machine for
maintenance.
• Survey Response: Another interesting thing is that we are looking at various methods
of powering electrical appliances and equipment. They putting solar panels on the top
of their roofs and getting solar lights. This is on a minor scale, it is not for production
purposes but it does help lower the utility bill at the end of the month.
Graphical representation of major themes
When a qualitative study is undertaken with a larger group, meaning that there is no focus
group, the analysis technique involves identifying themes emanating from the data. It is
highly recommended that the data should reach a saturation point an accurate result. The
collected data did not saturate, however, it analyzed and summarised in a model in Figure 6.
Figure 6: Major themes arising from the qualitative survey looking into the impact of load shedding on manufacturers
(Self-creation, 2020).
52
9.2 The quantitative impact of load shedding on small and medium-size factories employing the subject evaluation methodology
Online surveys were conducted where factory managers were requested to quantitatively
estimate and describe the impact of power interruptions on their factories. This method of
collecting data cost estimations from the factories is known as the subject evaluation
methodology, because the subject or the person who has experience on what is being studied,
gives an opinion based on experience. This methodology has three components in the
manufacturing sense and these are described below.
• VLP: The value of losses in production
• ORC: Power outage related costs
• ORS: Power outage related savings
The above information can be used to construct a customer demand function (CDF) that
shows how the impact of load shedding varies with certain factors (Goldberg, 2015).
Results from the survey
The electronic survey was distributed to 38 small and medium-sized manufacturing
companies that are registered with the Zululand Chamber of Commerce and Industry
(ZCCI), in Richards Bay, South Africa. Over two months, 22 responses were received
electronically. The distribution of the survey responses was 8 medium-sized and 14 small
manufacturers. The survey was completed by senior management of the factories, like
Managing Directors, Financial Directors, and Technical Directors. More factories are
operating in the Richards Bay area that are small or medium size, however, they do not reveal
this information. Therefore, they were not approached to be part of the survey to protect the
integrity of the data. This could have potentially created a bias in the data, as only those
manufacturers with a known size status were approached.
Direct worth estimates of the impact of load shedding
The survey asked factory managers to recall a specific power outage incident that they had
experienced in the recent past. They were requested to describe the incident, the day on
which the incident happened and the duration of the incident, stating the start and end times.
The survey further asked the respondents to estimate the impact on the daily revenues of the
load shedding incident. The estimates of factory managers were normalized to hourly
impact. Where a power outage incident lasted for less than one hour, this was normalized to
53
hour impact assuming linearity. The customer demand function is then constructed using the
hourly estimates. Consider a three-hour power outage incident on a Friday as an example.
• Friday 10:00 to 11:00
• Friday 11:00 to 12:00
• Friday 12:00 to 13:00
The entire three-hour incident is broken down into three incidents of one hour each. The
impact was assumed to be linear over three hours. A measure of the hourly impact is defined
and named "Revenue Loss Per Hour" (RLPH). The RLPH estimates the revenue lost per
hour due to a particular load shedding incident. When solving the above example using the
defined RLPH, it can be seen that a revenue decrease of 30% over three hours gives rise to
a 10% RLPH for each of the three hours. The RLPH is defined by equation 3.
��� = !"#$%'("%)*+%!,-%!(.(/0(-12)#11!.3
45,6#"(/7(5"+!.2$#.-"!( Equation 4
Survey responses
Respondents were presented with a quantitative survey with a predetermined set of outcomes
and they had to choose one that best describes their situation. During the pre-testing of the
survey, it was discovered that most manufacturers were uncomfortable to give exact figures
to questions, therefore, percentage estimations were preferred. These following results will
be interpreted in this section, however, an analysis of the results in the context of the research
follows on in section 8.
Figure 7: The distribution of responses on the availability of a procedure during a power outage.
54
It can be seen from Figure 7 that 50% of the respondents have a procedure that is followed
during a power interruption. This shows a proactive approach from the manufacturers, as
load shedding is a big part of their operations, it is wise to have a procedure that everybody
would under and follow during load shedding. It is also encouraging that 41% of respondents
are planning to develop a procedure for load shedding incidents. The remaining 9% that does
not have a procedure and is not planning on developing on, it is wise to develop one.
Figure 8: Distribution of the working hours of the factories surveyed.
Figure 8 shows the distribution of business operating hours of the factories surveyed. It can
be seen that the majority of the factories work between 6 – 8 hours per day, with 45.5% of
the factories surveyed falling into this bracket. The second bracket of factories operate for
9–12 hours per day, these factories account for 27.3% of the total factories surveyed. The
third bracket of factories has operations that run for 20 – 24 hours per day and these account
for 27.3% of the factories surveyed.
Figure 9: The percentage distribution of factories with backup generators.
55
Figure 9 summarises the percentage distribution of factories that have a backup power
system installed in their factories. From Figure 8 it can be seen that only 18.2% of the
surveyed factories have backup power systems available and 81.8% of the factories do not
have backup power plants. Perhaps the initial investment required to install a backup power
plant is the hindrance for most factories as they are operating in difficult economic times.
Figure 10: The distribution of load shedding incidents per day and per week, Monday to Thursday.
Figure 11: The distribution of load shedding incidents per day and per week for Thursday to Sunday.
Figures 10 & 11 show the distribution of load shedding incidents experienced by the
surveyed factories in the months between December 2019 and February 2020. The color-
coding in Figure 9 shows the time of the day during which the incident occurred. A glance
at the two charts shows that either the factories experience more load shedding during the
week (Monday to Friday) or some factories do not operate during the weekend, therefore,
the weekend load shedding incidents are not experienced by these factories. The most likely
explanation for the drop in load shedding incidents during the weekend, is the low demand
as most businesses do not operate during the weekend. Most incidents are experienced in the
morning or after, this is when the load demand is highest in the country.
56
Figure 12: The percentage distribution of daily revenues lost due to power interruption incidents.
Figure 12 shows the percentage distribution of revenue lost due to various load shedding
incidents by the surveyed factories. About 41% put the revenue losses between 11-20%,
which compares well with a global trends at 22% (Oseni, 2002). The 27.3% of factories that
have less than a 10% revenue loss either have backup generators or they worked extended
hours and they incurred an extra cost. About 4.5% of the factories surveyed experienced a
catastrophic loss of over 51% of their daily revenues, this was most likely unplanned load
shedding incidents that had such a devastating effect.
Figure 13: Percentage distribution of the costs incurred during the load shedding incidents.
57
Figure 13 shows the distribution of costs arising from load shedding incidents. The costs are
due to raw material spoilages, overtime payments to employees, penalties arising from
missed contractual obligations, standing time payments, re-start costs. About 31.8% of the
surveyed factories had a cost escalation of 0 – 10%. About 27.3% of the suffered between
11 – 20% losses. About 4.5% of the factories suffered catastrophic losses in the region of
31 - 50% of the losses. The major cost drivers are the cost of backup power systems and the
penalties suffered from contractual obligations.
Figure 14: The percentage distribution of load shedding impact on the equipment and machinery.
Figure 14 shows the percentage distribution of the estimated life cycle reduction of the
machinery due to load shedding. Certain production machinery is not designed for frequent
starting and stopping. The stopping and starting of the machinery frequently affects the life
expectancy of the machines. Most factories, at 45.5%, estimate that the life cycle of their
machines is reduced by 6 - 10% per year. About 40.9% of the factories estimate that the life
cycle of their machines is reduced 0 – 5% per year. About 4.5% of the factories estimate that
the life cycle will be reduced by 11 – 15%. The remaining 9.1% of the factories estimates a
catastrophic life cycle reduction of equipment of above 16%. The biggest contributor to the
life cycle reduction of manufacturing machinery is unplanned load shedding and the
frequency of stopping and starting the machines.
58
Figure 15: The percentage distribution of factories that have backup power generators.
Figure 15 shows the percentage of factories that have backup power generators installed in
their facilities. It can be seen that only 40.9% of the factories do have power generating
plants installed in their factories. The rest of the factories do not have backup power
generators installed, however, 40.9% of these factories are planning to install the backup
power generators. The biggest hindrance in setting up backup power generating plants is the
initial capital required and the running costs. The generators consume a lot of diesel and they
cannot be run as a primary source of energy, they can only be run for a short time.
Figure 16: The percentage distribution of the capacity of backup power generators.
Figure 16 shows the distribution of various backup power system capacities in factories that
have backup power generators installed. The capacity ranges from a 10kW generator that is
used to power the administration area and for lighting purposes. The capacity of backup
power generators goes up to 45 000 kW which powers production areas and storage facilities
59
that require refrigeration. Six of the nine surveyed factories have backup capacity that is
beyond 1 000 kW which is quite significant for small or medium-size factories. The bigger
the backup power plant, the higher is the running costs as they consume more fuel. However,
in the long run, the massive power plants tend to be efficient as they are not operated at full
capacity, usually, they are operated at 80% of the full capacity. This is the most optimal
region for the best efficiency in terms of fuel consumption and this ensures the life cycle of
the power plant is not shortened by overuse.
Figure 17: The percentage distribution of the reliability of backup power generators.
Figure 17 shows the percentage distribution of how reliable are the backup power systems
installed by the factories surveyed. The reliability is estimated based on how frequently the
backup plant fails to come online in the anticipated time when it is required to come online.
The majority of the factories, at 55.6% find their backup power plants to be between 81
- 100%. This compares well with international trends, as most back up power systems have
a reliability of 78% (Sangvhi, 2008). About 22.2% of the factories estimated the reliability
of their backup power plants at 61 - 80%, a portion of this still falls within the international
trends, albeit partially according to Sagvhi (2018). The rest of the factories sited issues such
as the inability of a power plant to come online automatically when there is a power outage.
This required the factory to contact the service provider supplying the backup power plant
to dispatch a Technician to manual start the generator. Crucial production time was lost
during the waiting period and 22.2% of the surveyed factories estimated the reliability to be
between 41 – 60%.
60
Figure 18: The percentage distribution of factories that outsource the backup power generators.
Some factories manage their backup power system and some outsource this service to an
external provider. About 66.7% of the surveyed factories are outsourcing this service to a
service provider. The only reason this service is preferred, the factories do not need to
develop skills and expertise in the operation and maintenance of the backup power plant.
However, the downside of this arrangement is that there is a potential for huge delays when
the service provider is not onsite and the power plant has to be operated. The liability rests
with the service provider and the factory only pays for the service. The rest of the factories
invest in the training of staff in the operation and maintenance of the power plant. The
biggest advantage of this move is that skills reside in-house and the reaction time is much
smaller compared to the activation of a service provider who does operate offsite.
Figure 19: The percentage distribution of costs associated with running the backup power generation system.
61
Figure 19 shows the percentage distribution of the cost estimations associated with the
running of backup power systems. Factories were asked to do a cost estimation of running
their factory using a backup power plant versus the utility supply. The respondents were
given a set of pre-determined options and all factories estimated that the cost of running the
backup power system costed more than the utility supply when comparing the cost of a kWh.
About 22.2% of the factories estimate that the backup power system costs them between
21 – 30% more to run compared to the utility supply. The majority of factories, 55.6%
estimated that the backup power supply costs them between 31 – 40% more and this
compares well with international trends, with an average of 32% (Sangvhi, 2018). Some
factories estimated that the backup power system costs them between 51 - 100%, this is an
abnormally and the backup plant is not sustainable.
Figure 20: The percentage distribution of capacity provided by the backup power generators.
Figure 20 shows the distribution of load that is supplied from backup power systems. The
factories were then asked to estimate at what capacity they can operate on the backup power
plant. It must be noted that all factories derive some form of operation from the backup
power system. The majority of the factories, 66.6%, operating at a capacity of between 21 –
60% on the backup power. This highlights the cost of backup power, it has been noted in
Figure 16 that it costs more to run on the backup power system. The majority of the factories
do not even operate at full capacity when operating from the backup power plant. Therefore,
it is not desirable to operate on the backup generators, it costs more and there is less
production output. Perhaps, the benefits of meeting contractual obligations and preserving
the company's brand outweigh the costs of operating on backup power.
62
Figure 21: The percentage distribution of the number of people who work in these factories.
Figure 21 shows the percentage distribution of the workers employed by the surveyed
factories. The smallest factory has only 5 workers and the largest factory has 1232 workers.
The factory with only five people is highly automated and outsources most of its services.
The factory is owned by Italian nationals and uses highly sophisticated technology. The
largest factory runs 24-hour operations with three shifts of eight hours.
Figure 22: The percentage distribution of the area size of the factories surveyed.
Figure 22 summarises the percentage distribution of the size of the factories surveyed. The
factories supplied the size of their main production area, for example, the smallest factory
has a production area of about 100 square meters. However, the total area of the factory
premises is much bigger. The largest factory has over 67 000 square meters of space.
63
Figure 23: The percentage distribution of factories that have insurance as a mitigant against power interruptions.
Figure 23 shows that only 9.1% of the surveyed factories have purchased insurance to
mitigate the impact of load shedding. The impact of load shedding is felt but not yet
understood, factories are not sure how the insurance will protect them. However, 50% of the
factories intend to get insurance in the future. The rest must be encouraged to consider the
insurance option.
9.3 The quantitative impact of load shedding on small and medium-size factories employing the revealed preferences methodology
Information about the financial implications of having backup power generators was not
made available to the researcher. This information was deemed to be highly confidential and
sensitive information by the factory managers. The data from the qualitative and quantitative
studies show that the cost of operating from the backup power supply is much higher
compared to the utility electricity supply. Factories tend to use the backup power supply for
essential elements of their operations. The factories can apply the revealed preferences
methodology internally to determine the cost of substituting the utility supply with the
backup power supply.
64
10 THE DISCUSSION OF THE RESULTS
This research work had three objectives that were set out in the objectives section at the
beginning of this report. The first objective was to understand the qualitative aspect of the
economic impact of power interruptions on small and medium-sized manufacturers in
Richards Bay, South Africa. The second objective was to estimate the direct economic
impact of power interruptions on factories using the subjective evaluation methodology. The
third objective was to validate the estimates in objective two by using backup power data to
estimate the minimum economic impact of load shedding using the revealed preferences
methodology. All objectives were achieved except for the third one.
Study 1 consisted of a qualitative survey of open-ended questions administered online.
Physical interviews were the preferred method of collecting qualitative data, however, due
to the timing being a festive season, most managers were not available for physical
interviews. Therefore, the next best solution was an electronic survey questionnaire. The
survey was probing the qualitative impact of frequent power outages on the factories.
Study 2 focused on estimating the direct economic impact load shedding has on the small
and medium-size factories in Richards Bay. The subjective evaluation methodology formed
the basis for this study and the analysis of the results.
Study 3 was not implemented as the factories deemed this data to be highly confidential and
they were not willing to share it with the research. Even after proposing to sign non-
disclosure agreements and only sharing the analysis of the results, not the results. The
factories were unable to provide this data. However, a methodology was developed and an
attempt was made to collect the data. The revealed preferences methodology was found to
be suitable for this kind of analysis, as it is widely used in literature.
10.1 What is the qualitative impact of load shedding on small and medium-sized manufacturing companies in Richards Bay, South Africa?
The pie-chart in Figure 4 shows how often a particular comment appears in the responses
describing the impact of power interruptions on the factories. It can be seen from the
responses that the impact is overwhelmingly negative on the factories. A small margin of
the respondents considered the impact to neutral and surprisingly, a positive impact has been
identified that led to new business opportunities for the factory concerned. The cases where
neutral or positive impact has been experienced are quite rare and the factories concerned
65
have a unique advantage. One factory has a huge piece of land on-site that is unused and
they are planning to explore the possibility of setting a renewable energy system on site.
Figure 6 shows the outcome of an analysis that was performed in study 1. Nine major themes
came out of the analysis resulting in the model shown in Figure 5. The themes describe the
various challenges that factories experienced due to power outages. The degree of impact
was found to vary according to the primary product that the factory is producing. Factories
dealing with steel are the ones that suffer the most when there are load shedding incidents,
usually, these factories are energy-intensive and the steel is melted before molding. Re-
melting cost is one of the biggest costs experienced by steel factories.
Power outages disrupt manufacturing operations. Before the frequent power outages were
experienced, South Africa had an abundance and a stable supply of electricity. Factories are
designed and built for a stable and reliable power supply. Factories rely on electricity supply
for production and the manufacturing equipment is not designed for frequent restarting. The
most frequently cited operational challenge was the raw material spoilage and the need for
recycling the spoiled products into raw material again. The reduction of life expectancy of
the machinery was also cited as a major concern for most factories. As the machines are not
suitable for frequent restarting. The operations are planned around the load shedding
schedule that is published by Eskom. This influences the starting and the stopping of the
operations. If the schedule is not followed, this has a devastating impact on the factories.
Power outages have an effect of pushing costs of doing business for manufacturers. From
the qualitative model shown in Figure 6, it can be seen that the 'costs associated with load
shedding' occupy a big block in the graphical model. The biggest cost driver was the
overhead costs arising from working overtime and paying employees while they are not
productive. The second major cost component was the raw material spoilage. Some factories
mention that if the load shedding lasts for two hours or less, the costs remain within a
manageable region. If the load shedding period goes beyond two hours, it becomes difficult
to salvage anything from the spoiled raw material. For factories that have the backup power
supply, the costs of this energy was also cited as a major cost. The costs rising from missed
contractual obligations are also a cost component factories face.
The most catastrophic economic impact of power interruptions on factories is the loss of
production that results in revenue loss. It can be seen from the qualitative model in Figure
66
that 'revenue loss' has a bigger block compared to the other themes. Revenue losses have
more impact when manufacturers produce less than what they can produce, in other words,
there is an investment in capacity but the volumes do not match the installed capacity. When
factories produce less, they able to sell less. Due to the constrained capacity arising from
load shedding, factories sign fewer contracts with customers which affects the revenues.
Existing contracts are also renegotiated in terms of volumes.
Some factory environments become hazardous when there is load shedding as they rely
heavily on electrical ventilation to keep the factory habitable. Therefore, personnel are
withdrawn immediately when there is a power interruption. Security systems such as closed-
circuit television cameras (CCTV) and Sensormatic systems get affected during a load
shedding incident. Lighting becomes a huge problem and this exposes factories to theft.
Over 90% of the factories rely heavily on the published load shedding schedule to plan their
operations. Scheduling their operations around the load shedding incident minimizes the
impact as there is no element of surprise when the power outage occurs. Factories can plan
and prepare for the outage. The factories can plan other activities the employees can do while
there is load shedding, like training or coaching or housekeeping activities in the workshop
or cloakrooms. This keeps employees active while there is a power outage and prevents the
possibility of having zero activity for the duration of the load shedding incident. Some
factories resort to manual production using mechanical means to keep the production line
going, like the furniture assembly factory. A small percentage of factories have backup
power generators installed in their premises that are activated when there is a power outage.
The challenge with backup power is that it costs significantly more than the utility supply.
Four major stakeholders came out from the analysis of study 1. Firstly it is the shareholders
of factories, secondly, it is the employees of the factories, thirdly it is the customers of the
factories and fourthly the suppliers of the factories. The shareholders of factories are the
final decision-makers on issues about investments into the backup power supply,
investments into developing suppliers to cope with load shedding and deciding on staff
requirements depending on the business direction. The second stakeholder is the employees.
The employees are the most important assets of the factories. They are the ultimate drivers
of production and they suffer the most when a power interruption is experienced. Employees
always wish to meet their daily targets because it has a bearing on their wages, incentives,
and bonuses. Some employees are loyal and work for one factory for a very long time, they
67
always want their factory to succeed, therefore they put in extra hours to ensure that the
business meets its obligations. They get demotivated when they cannot work because of load
shedding and factories have been getting professional help to keep the morale of the
employees high, despite the challenging circumstances.
Customers of the factories surveyed are usually other businesses that sell the products to
consumers. Sometimes the products of the surveyed factories act as raw material for other
factories. They ultimately have obligations to their customers or consumers to deliver,
therefore, they are under a lot of pressure when load shedding is experienced. They are
restructuring the contracts with factories to protect themselves and their consumers. The
final stakeholder identified was the suppliers to the factories.
Suppliers play a critical role in enabling factories to meet their production targets and
objectives. Factories closely monitor the impact of load shedding on their suppliers and offer
support where possible. The supplier relationship management is more critical as factories
cannot afford to stop production due to load shedding and possibly lack of raw material or
other critical supplies. Some factories that have the possibility of stockpiling raw materials,
go for this option. However, this comes with challenges of theft and looting.
Most of the factories surveyed tended to focus mostly on the direct impact of power
interruptions. The second-order effects were not a major concern for most factories, it has a
small weighting on the model in Figure 6. The major concern for most factories is the effect
of load shedding on the manufacturer's brand. Most manufacturers think that the frequent
power outages affect their credibility and ultimately their brand. This is because they are
unable to meet some of their obligations to customers. Some factories mentioned the loss of
market share as one of the second-order effects, as customers take their business elsewhere
if one factory cannot deliver. A small number of factories mentioned that their customers
understand that frequent power interruptions are not within their control.
The positive outcomes arise as factories change the way they operate where it is business,
power interruptions disrupt this and cause discomfort. This discomfort forces factories to be
innovative and think out of the box. These skills of innovation are then only used to combat
the impact of load shedding, however, they are used in business to improve operations and
risk analysis. The factories that can stand out and provide products during the difficult period
of severe power interruptions, they tend to experience a surge in new customers and their
revenues increase sharply. The factories view the experience of dealing with power
68
interruptions as a positive thing, as they can use the similar tools learned or develop during
the power interruption crisis to solve other business problems.
10.2 What is the direct impact of load shedding on small and medium-sized manufacturing companies in Richards Bay, South Africa?
The subjective evaluation methodology is the most prevalent methodology that employs
customer surveys to study the economic impact of power interruption on consumers of
electricity. This methodology is particularly applicable in environments that have frequent
power outages. The biggest disadvantage of this methodology is the credibility of
information provided by the factories. Sometimes factories do not answer honestly to avoid
overstating their challenges or not portray a picture where they are almost immune to load
shedding (Kufeoglu & Lohtonen, 2015:591).
However, this methodology was able to estimate that the impact of load shedding on
manufacturers at 21% of their total assets, on average. The total value of the assets is not
known, therefore a numerical value is not given. This takes into account the revenue losses
and cost escalations. The impact varies with the size and resources of the factory. The
challenge with the current estimates is that they ignore the primary product of the factory
and assume that each day of the week contributes the same losses to the weekly losses of
revenues and costs. In reality, each day of the week has to be assessed individually as the
revenue losses are not uniform per day. This will be further discussed in the next section.
The survey population was 38 small and medium-sized factories. A total of 22 responses
were recorded. To perform a more accurate study more responses would be required. One of
the major disadvantages of the study of this nature is the time and cost associated with
carrying out such a study. Kahneman (1979) notes that some respondents are sometimes not
exactly sure of the impact they are meant to describe in the surveys.
69
11 RECOMMENDATIONS
This section presents recommendations arising from the research for key stakeholders
affected by the load shedding. These are the manufacturers and the South African power
utility. Limitations of the research and the possible future expansion of the work are also
proposed, which is aimed at improving the current contribution.
The load shedding situation in South Africa is a huge challenge for all electricity consumers.
The power interruptions arise from the poor planning by the power utility company Eskom
and the South African government. The country has noted growth in population and
economic activity, however, the electricity generation capacity remained the same. This has
resulted in inherent power interruptions that severely affect business operations and
profitability. The impact of power interruptions is felt by all consumers, however, very few
consumers know the exact impact or able to accurately quantify the impact. This is also true
for factories operating from Richards Bay, they are impacted by load shedding as well. This
study has sought to determine the impact of load shedding from a mixed approach
considering both the qualitative and quantitative aspects.
The manufacturing sector in Richards Bay employs over 200 000 people and the sector
nationally contributes over 12% to the total GDP. Richards Bay is an export town and
producing from here makes the export logistics cheap as the port is also in Richards Bay.
Most manufacturing companies that are servicing the export industry are moving to Richards
Bay and setting up factories here. The availability of state of the art railway infrastructure
linking the port and major hubs inland remains a competitive advantage for the port as those
products not destined for the export market find market inland, and the railway system
connects the factories with consumers. South Africa has an aspiration of becoming the most
industrialized economy in Africa. This aspiration is unlikely to be realized if the electricity-
related challenges are not addressed aggressively and speedily by all stakeholders including
the South Africa government and industry captains.
11.1 Recommendations for the manufacturers
Manufacturers take the impact of power interruptions and it is a difficult task dealing with
this impact as there are few options available to the manufacturer to deal with this challenge.
The manufacturer has the option of passing the higher costs of production arising from load
shedding challenges to the consumer. The factories can try to minimize the impact of power
interruptions and absorb the minimized impact that reduces their profits. The third option is
70
for the factories to collaborate with all key stakeholders in the sector to come up with a set
of sustainable and long-lasting solutions.
It is a fact that it costs factories more to produce the same quantum of goods when there is
load shedding compared to producing the same quantum when there is no load shedding.
The cost of production per item increases, also known as the unit cost. The costs arise from
several contributors including overtime payments, standing time payments and standby
power where there are backup generators installed. The factory has to carefully consider how
to deal with the increased cost. It is recommended that factories should not pass 100% of the
extra costs to the consumer or customers, as this may be unsustainable and reduce market
share. It is recommended that the factory absorbs a certain portion of the costs. This should
be done while ensuring that the profitability of the factory is not compromised, which may,
in turn, affect the sustainability of the factory and possibly affecting the workforce which is
not desirable at all. The risk of the factory absorbing all the extra costs is unprofitability and
unsustainability of the business. This may likely reduce the market share if the competitors
do not increase prices significantly.
Factories are advised to develop a comprehensive load shedding procedure if it has not been
developed already. The procedure should be comprehensive taking into account planned and
unplanned load shedding circumstances. The procedure should be a blueprint that is clear to
the employees that have to implement it. It must have clear roles and responsible persons.
The plan should take into consideration the different stages of load shedding. The load
shedding plan should ultimately reduce the impact and cost of load shedding to a point where
the factory can absorb without compromising profitability on their bottom line. This would
give factories the benefit of keeping customers and keep delivering to their expectations.
The major risk of this approach is short-term losses while the plan is still on the trial phase.
However, the plan must be modeled and tested with different scenarios in a simulation first.
Factories that do not have 24-hour operations are advised to consider changing their
operating hours to the following period or part of the following period, 22:00 – 06:00. During
this period the frequency of load shedding is at the minimum, according to the statistics from
Figure 3. This period would ensure a long period of uninterrupted production for
approximately 8 hours. Before the decision can be made, the following must be taken into
consideration, the basic conditions of employment act, the occupational health and safety
act, and the cost of changing operational requirements. The condition of employment act
outlines the rights of employees and the minimum basic conditions under which they must
71
execute their duties. If the working times of the employees have to change, they must be
consulted individually or in a union. The necessary shift or night working allowances must
be applied. Heightened safety and security measures should be taken into account. The risks
of working during the night are many, employees may be fatigued after not having rested
enough during the day. This could be because other family members are active during the
day, including children where applicable. Employees may be tempted to steal certain
company assets because the night presents an opportunity. The safety and health of
employees may be at risk if they work on heavy-duty machinery while fatigued. The cost of
operating during the night may be higher than that of operating during the day after taking
all consideration into account including the load shedding, in this case, the operating hours
should not be changed. The factories could consolidate their efforts and come up with plans
to minimize the impact of load shedding.
One of the measures factories in Richards Bay can take collectively, is to approach the power
utility to negotiate preferable energy tariffs to operate during the off-peak period. These
tariffs should be able to offset the costs that will arise from operating during the offpeak
period. This would require the small and medium-size factories to collectively lobby the
power utility company. The security of production is a huge factor in this option of operation.
The factories could explore this option immediately. A detailed cost-benefit analysis has to
be developed. Another option is to build a generation plant in Richards Bay.
Some factories are proposing a collaborative effort in building a power generation station
that will supply factories locally in Richards Bay. This would require a huge capital budget
and probably have a complex ownership structure, depending on the investment level of each
factory. The power generation facility would be set up such that it can supply all the small
and medium-size manufacturers in Richards Bay. There is a huge natural gas storage facility
available in Richards Bay. Mozambique which is 300km North of Richards Bay has an
abundance of natural gas. It is possible to set up a gas power generation plant in Richards
Bay. It must be noted that this a huge project that would require huge capital and carry a lot
of risks for the factories. The financing and ownership structure would be complex and
would require a lot of negotiations. The operation of the plan would also pose challenges, as
there would be operational costs to sustain the power plant. Necessary approvals would be
required from the government for self-generation of energy. The returns on investment in
this kind of project would take a long time, this could compromise the liquidity of the small
factories.
72
11.2 Recommendations for the power utility
The power utility is facing a multitude of challenges that include capacity, operational and
financial difficulties. The resultant of the aforementioned challenges is the load shedding
that is experienced in the country. The following set of recommendations are proposed for
the power utility to assist in minimizing the impact of load shedding. The first suggestion
arises from Figure 2 the daily load shedding frequencies. The second proposal arises from
the planning and communication of load shedding schedules.
From Figure 3 it can be seen that the frequency of load shedding is at the lowest between
22:00 – 06:00. This is a period when the demand on the national grid is at the lowest. Most
small and medium-sized factories are closed during this time, corporate businesses are also
closed during this time. Most households are only using electricity for lighting,
entertainment purposes such as television sets, desktops and other electronic devices.
Usually, around this time, the high energy-consuming components such as geysers, pool
pumps, electric gates, electric stoves, and kettles are not working. This significantly lowers
the demand on the national grid. The mining and other heavy industries ramp up their
operations during this time. These industries can run their operations largely unconstrained
by power supply and power interruptions. These industries get preferential electricity tariffs
from the power utility for operating at peak during the off-peak period.
The preferential electricity should be extended to small and medium factories if they are to
operate during the off-peak period of power demand. This would help ease the pressure and
demand on the grid during the day. This applies to those factories that do not have 24-hour
operations. For example Figure 7 shows that 73.7% of the surveyed factories operate
between 6 – 12 hours per day. The off-peak period is approximately 8 hours. The factories
that operate for 12 hours could schedule their operations such that the 12 hours includes the
8 hours of off-peak. The incentive given to mining companies and heavy industries may
prove to be unsustainable if it is extended to small and medium factories. The power utility
would have to make estimates to determine the feasibility of this option. The power utility
must also consider the possibility or the risk of having the demand curve shifting
significantly if this incentive were to be extended. The second suggestion that emanates from
the responses of the survey is regarding the planning and communication of load shedding
incidents.
The power utility has tools that predict or anticipate the change in demand and the
availability of generating capacity. The utility can predict with a good degree of certainty as
73
to when will load shedding be required and which areas will be affected, and for how long.
The utility does weekly and monthly forecasts of both the demand and generation capacity.
Only the weekly plan is shared with electricity consumers like smelters, mining companies,
and other heavy industries for them to plan around it, they are the ones that are required to
reduce demand first when the grid is strained. The rest of the customers only get a two-day
plan that is supposedly more accurate according to the power utility. This does not give the
factories enough time to adjust and plan around the load shedding incidents. However, they
still plan, even though it is not the most optimal planning. The incidents are better managed.
The power utility should try to minimize as much as possible unplanned power interruptions.
If these were unforeseen, they should rather be directed to domestic customers in residential
areas as most of them do not have economic activity. Their loss is only comfort and leisure
time. About 90% of the surveyed factories plan their operations around the load shedding
schedule of the power utility, any deviation has a devastating impact on the factories.
11.3 Limitations of the research
There are small and medium-sized factories in the whole of South Africa. However, due to
resource limitations, only a specific population was considered, which are factories operating
from Richards Bay. Ideally, for a study to be represented as possible, the entire population
of small and medium-size factories in South Africa would have to be considered. This would
require considerable resources and time to accomplish this task. This research was limited
in terms of the population from which the sample was drawn, only the factories registered
with the Zululand Chamber of Commerce and Industry (ZCCI) were considered for the
sample. ZCCI has a database of small and medium-size manufacturers operating from
Richards Bay. Some factories may be small or medium operating from Richards Bay,
however, their status is not known because it is not declared anywhere publicly. These
factories could be approached individually to ascertain if they are small or medium size to
increase the population.
The second major limitation of the research was the unavailability of data necessary to
implement the revealed preferences methodology to estimate the impact of load shedding on
the factories. This was because this data was deemed highly sensitive and confidential by
the factories. This methodology would have been used to compare and contrast with the
results from the subject evaluation methodology that was implemented. It is expected that
the revealed preferences methodology was going to confirm the estimations of the subject
evaluation methodology.
74
12 CONCLUSIONS
South Africa is currently facing systemic power interruptions that are due to constrained
generating capacity and rising demand for electricity. The impact of power interruptions on
business entities is complex and this is true for manufacturers as well. The manufacturing
sector contributed 12.2% to the South African GDP in 2018. The sector employs 17% of the
total workforce in the country directly and creates a 5% jobs for the suppliers and retailers.
Research has been undertaken to understand the qualitative, as well as the quantitative
economic impact of power interruptions on small and medium-size, manufacturers in
Richards Bay. Initially, three studies were proposed, however, only two were undertaken
due to the unavailability of the third study which was deemed highly sensitive and
confidential by the respondents.
12.1 What is the qualitative impact of load shedding on small and medium-sized manufacturing companies in Richards Bay, South Africa?
An open-ended questionnaire was shared with managers of factories electronically to solicit
information about load shedding that affects their businesses. The qualitative study was
undertaken to understand the soft impact of load shedding on the factories, from employees,
external clients, and their brand. Figure 23 below shows the major themes that emanated
from the analysis of the qualitative results. The block size depicts the size of impact as
described by the respondents and the position shows the interaction of the blocks, as an
example revenues interacts with operations.
Figure 24: Major themes arising from the qualitative survey looking into the impact of load shedding on manufacturers
75
The impact of power outages on the factories was found to vary according to factors such as
the primary product being produced and the nature of the power outage incident. Advance
notification was found to significantly reduce the impact of power outages on the factories.
Factories were better prepared when notified in advance. The longer the duration of a power
outage incident, the more severe was the impact. Load shedding severely affects the
operational activities of factories which are essentially production activities in the main. The
factories are unable to harness the full capacity of their factories as there is frequent stopping
of production due to load shedding.
The other two major themes at the core of the model are the cost escalations and the revenue
losses. Costs have a direct implication for the bottom line of any business. Cost escalations
and the revenue losses were found to be also major themes following closely from
operational losses. The operations have a direct bearing on the costs and revenues. This
negatively affects the profitability of the factories. The two major cost drivers are overhead
costs arising from extended working hours and the cost of having a backup power system
for those factories that have it installed. Revenues depend on the quantum sold, and the
quantity of the sold products depends on the volume of production, when the factory
produces less, they sell less and have less revenues.
The primary stakeholders affected by load shedding include factory shareholders,
employees, customers, and suppliers. All these stakeholders need to support each other to
survive the impact of load shedding, shareholders have to approve investments into
developing skills of workers and suppliers. Employees need to be prepared to put in long
and extended hours. Suppliers need to be transparent and upfront with challenges faced and
let the factories know in time, with actions they are taking or proposing to remedy the
situation. Customers need to understand some challenges are beyond their control.
12.2 What is the direct impact of load shedding on small and medium-sized manufacturing companies in Richards Bay, South Africa?
The subjective evaluation methodology was applied to estimate the impact of load shedding
on small and medium-size manufacturers in Richards Bay. It is estimated that the impact on
manufacturers is worth 21% of their total assets, on average. The revenue losses suffered by
factories due to a load shedding incident are not linear, therefore, a more accurate estimation
would be non-linear. The estimation would also have to take into consideration the primary
product of the factory and seek to quantify the indirect costs of load shedding such as loss
76
of credibility. A larger population and sample would help to reinforce the findings and
perhaps reveal other dimensions that the current study may have not revealed.
The revealed preferences methodology was not implemented due to the unavailability of
data. Factories deemed this data highly sensitive and confidential. Generators provide
accurate information about the delivered kWh, fuel consumed and other consumables are
taken over time to keep the machine running. It is fairly simple to accurately work out the
cost of running a backup power supply and use this cost to estimate the impact of load
shedding. This method gives a more accurate estimation as generators are intelligent, they
record the fuel intake, power delivered and the service intervals, based on hours of
operations. This information can be consolidated to determine the cost in numerical terms
that would represent the impact of a power interruption on the factory.
12.3 Limitations of the research and future research recommendations
One major constraint of both studies is the sample size. A bigger sampled size would have
revealed more dimensions and perspectives. The qualitative data did not reach saturation,
however, it still provided an interesting analysis. This can either be solidified or questioned
by commissioning another study with a larger sample. The study was focused on the
Richards Bay area and presents a biased view of the Richards Bay factories, the same may
not be true for other factories throughout the country. This was done due to the time
constraints and the limitations of the budget. The revealed preferences methodology could
not be implemented because data could not be obtained from the factories.
The overwhelming majority of factories surveyed mentioned that load shedding has a
severely negative impact on them economically. The frequency and the severity of load
shedding are unlikely to come to an end soon, therefore, a plan has to be developed to
mitigate against load shedding or minimize the impact. Study 1 shows that the revenues,
costs, and production is affected the most.
Stakeholders in the manufacturing sector need to understand that it is possible to
quantitatively estimate the economic impact of frequent power interruptions. The performed
study followed a widely accepted methodology that has been used extensively in similar
environments to measure the economic impact of power interruptions on electricity
consumers. The subjective evaluation methodology was employed to estimate the economic
impact on factories, by factory managers. Key stakeholders need to understand the true
impact of power interruptions to effect mitigating mechanisms.
77
An expansion of this work would include the implementation of the revealed preferences
methodology, after reaching an understanding with factories regarding data privacy. The
impact of the load shedding should be analyzed at the level of the product produced and not
at an aggregated cost level. A larger sample is recommended to countrywide view of the
load shedding impact to avoid the bias of the study. The data collection could be extended
countrywide to reach saturation for the qualitative study.
The two main objectives of the research were to understand the qualitative and quantitative
impact of the frequent power interruptions in Richards Bay. Two studies were undertaken,
it was found that the qualitative impact of load shedding affects the brand of the organization
and the morale of the employees of the factories. Quantitatively, the economic effect load
shedding is devastating as it negatively affects production, revenues and increases the cost
of doing business. This affects the profitability and sustainability of the factories.
The qualitative model in Figure 23 summarises the results of study 1. The model shows the
most pertinent issues facing the manufacturing sector in Richards Bay as a result of frequent
power outages. The quantitative results of study 2 show that the impact is estimated at 21%
of the total asset of the factories. The revealed preferences methodology was not
implemented due to the unavailability of data that was deemed to be highly sensitive and
confidential. It is hoped that this work will aid stakeholders in making informed decisions in
the future.
78
REFERENCES
Adenikinju, A. F. (2003). Electric infrastructure failures in Nigeria: A servery-based analysis
of the costs and adjustment responses. Energy Policy, 31(14), 1519 – 1530.
African Union (2020). What who we are. Available online at https://au.int/en/au-nutshell
(accessed 15/04/2020)
Assistant Secretary for Energy Technology. (1978). Impact Assessment of the 1977 New York City Blackout. New York City: The U.S. Department of Energy.
Ateba, B., Prinsloo, J., and Gawlik, R., (2019). The significance of electricity supply
sustainability to industrial growth in South Africa. Energy Reports 5 (2019), 13-18
Baarsma, B. E., & Hop, J. P. (2009). Pricing power outages in the Netherlands. Energy,
34(9), 1378 – 1386.
Balducci, P., Roop, J. M., Schienbein, L. A., Desteese, J. G., & Weimar, M. R. (2003).
Electric Power Interruption Cost Estimates for Individual Industries, Sectors, and the
U. S. Economy. Proceedings from the twenty-Fifth Industrial Energy Technology
Conference, (109 – 118). Houston. Bliem, M. (2019). Economic Valuation of Electrical Service Reliability in Austria – A
Choice Experiment Approach. Institute for Advanced Studies Carinthia.
Brand South Africa (2018). SA’s key economic sectors. Available online at
https://www.brandsouthafrica.com/investments-
immigration/business/investing/economic-sectors-agricultural (accessed 9/11/2019)
BRICS (2019). What is BRICS?. Available online at
http://brics2019.itamaraty.gov.br/en/about-brics/what-is-brics
(accessed 15/04/2020)
Cheng, D., & Venkatesh, B. (2014). Literature Survey and Comparison of Consumer Interruption Costs in North America and Europe. Electrical & Computer
Engineering, 1-7.
Chowdhury, A., & Koval, D. (1999). Value-Based Power System Reliability Planning. IEEE
Transcation on Industry Applications, 35(2).
Diboma, S., & Tamo Tatietse, T. (2013). Power interruption costs to industries in Cameroon.
Energy Policy,, 582 - 592.
England, A. (2015). Power crisis knocks South African Economy. Retrieved on 28 October
2018 from The Financial Times: http://www.ft.com/intl/cms/s/0/dcbd1bda-d77f-
11e4-849b-00144feab7de.html
79
England, A. (2015). Worsening electricity crisis adds to South Africa’s economic woes.
Retrieved on 28 October 2018 from The Financial Times:
http://www.ft.com/intl/cms/s/0/dcbd1bda-d77f-11e4-849b-00144feab7de.html
Eskom (2020). Company information overview. Available online at
http://www.eskom.co.za/OurCompany/CompanyInformation/Pages/Company_Info
rmation.aspx (accessed 14/11/2019)
Goldberg. A., (2015). The economic impact of load shedding on retailers in
South Africa. Retrieved online from https://repository.up.ac.za/handle/2263/52398
(accessed 18/10/2019)
Growitsch, C., Malischeck,, R., Nick, S., & Wetzel, H. (2014). The Costs of Power
Interruptions in Germany: A Regional and Sectorial Analysis. German Economic
Review, 1-17
Jamal, M., and Faran, M., (2018). The impact of electricity and gas load shedding on social
Economic and psychological well being of factory workers. International Journal
Research in Humanities and Social Studies, Volume 5, Issue 12, 2018, PP 34-43.
Kahneman, D., & Tversky, A. (1979). Prospect theory: An Analysis of Decision under Risk.
Econometrica, 47(2), 263 – 292.
Kim, K., Nam, H., & Cho, Y. (2015) Estimation of the inconvenience cost of a rolling
blackout in the residential sector: The case of South Korea. Energy Policy, 76, 1-8
Kjolle, G., Samdal, K., Singh, B., & Kvitastein, O. (2018). Customer costs related to
interruptions and voltage problems: Methodology and Results. IEEE Transactions
on Power Systems, 23(3), 1030 – 1038.
Kufeoglu, S., & Lehtonen, M. (2015). Electrical Power and Energy Systems Interruption
costs of service sector electricity customers, a hybrid approach. Electrical Power and
Energy Systems, 64, 588-595
Linares, P., & Rey, L. (2013). The costs of electricity interruptions in Spain: Are we sending
the right signals? Energy Policy, 38(4), 1665 – 1671.
Maré, J.H., (2011). Economic diversification in Africa: a review of selected countries.
Michelin (2020). The Map of Richards Bay. Available online
at https://www.viamichelin.co.uk/web/Maps/Map-Richard_s_Bay-3900-
KwaZulu_Natal-South_Africa (accessed on 05/01/2020)
Mogajane, D., (2020). Budget Review 2020-2021 National Treasury of South Africa.
http://www.treasury.gov.za/documents/National%20Budget/2020/review/FullBR
(accessed 18/10/2019)
80
Nam, K, Choi, S., Ryoo, H., Jeong, S., Lee, J., & Kim, D. (2006). A survey on interruption
costs of Korean industrial customers. Proceedings of the IEEE Power Engineering
Society Transmission and Distribution Conference, 781-787.
Nel, E., (2018). Local Economic Development: A review and Assessment of its
Current Status in South Africa, Urban Studies, 38 (7), 1003-1024
Nkomo, J., (2006). Energy and economic development. In: Winkler, H. (Ed.), Energy
Policies for Sustainable Development in South Africa: Options for the Future.
University of Cape Town Energy Research Centre, Cape Town.
Oseni, M. (2012). Power Outages and the Costs of Unsupplied Electricity: Evidence from
Backup Generation among Firms in Africa. Proceedings of the USAEE 2012. Austin:
Internation Association of Energy Economics. Retrieved October 15, 2019, from
http://www.usaee.org/usaee2012/submissions/OnlineProceedings/IEEE%20PAPER
%20FRST%20YEAR%20EDITED%20LAST%201%20LATEST.pdf
Sangvhi, A. (1982). Economic costs of electricity supply interruptions. Energy Economics,
4(3), 180 – 198
Saunders, M., & Lewis, P. (2012). Doing Research in Business & Management. Essex,
England: Prentice Hall.
Statistics South Africa (2018). Gross Domestic Product (Fourth quarter 2018 statistical
release p0441). Available online at: www.statssa.gov.za/publications/
P0441/P04414thQuarter2018.pdf (accessed on 21/10/2019).
Trading Economics, 2018. South African GDP from utilities
The Group of Twenty (2020). About the G20. Available online at
https://g20.org/en/about/Pages/whatis.aspx (accessed 15/04/2020)
Van der Nest, G., (2015). The economic consequences of load shedding in South Africa
and the state of the electrical grid. Available online at
https://www.tralac.org/discussions/article/7000-the-economic-consequences-of-
load-shedding-in-south-Africa-and-the-state-of-the-electricalgrid.html (accessed on
13/04/2020)
World Energy Council (2005). World Energy Council Power Utilities Conference 2005.
Available online at https://www.worldenergy.org/experiences-events/past-events
(accessed on 13/04/2020)
Wright, J., Bischof-Niemz, T., Caltiz, J., Mushwana, C., and Van Heerden, R., (2019).
Long-term electricity sector expansion planning: A unique opportunity for a least
cost energy transition in South Africa. Renewable Energy Focus 4(30), 180 – 205
81
APPENDICES
Appendix A – Questionnaire approval
82
Appendix B – Survey questionnaire (qualitative)
Table 2: Qualitative servey questionnaire.
What is the impact of load shedding on your business and operations and brand?
How are the revenues of your business affected by load shedding?
How are the costs of doing business affected by load shedding?
How is safety in your factory affected by load shedding?
How does load shedding affect your staff morale and attitude?
What is the impact of load shedding on the Administration side of the factory?
If you have installed backup power supply, what challenges do you still experience, if any, despite having backup generators in place?
Are there any the opportunities that result from load shedding?
What are the knock on effects experienced due to load shedding?
What do you do to manage and mitigate the load shedding risk?
83
Appendix C – Survey questionnaire (quantitative)
Do you have a standard procedure that is followed during load shedding in the
factory? * • Yes • No • No, but we plan to develop it.
How long is your daily business operation in hours? * Less than 6
• 6 - 8 • 9 - 12 • 13 - 15 • 16 - 19 • 20 – 24
Have you ever experienced load shedding while in operation with no backup
generators available? * • Yes • No • Other:
Please think of particular load shedding incidents that you recently experienced. Please mark when it happened! Please mark only once, e.g Sunday – Night
84
Please describe how long did it take and what was the main challenge of the incident! *
Please estimate the percentage revenue that was lost due this load shedding
incident on the day? * • 0 - 10% • 11 - 20% • 21 - 30% • 31 - 40% • 41 - 50% • 51% and above
Please estimate the percentage costs that were incurred due to the load
shedding incident on the day? Raw material spoilage costs, disposables costs,
restart costs, etc. *
• 0 - 10% • 11 - 20% • 21 - 30% • 31 - 40% • 41 - 50% • 51% and above
Please estimate in percentage, how much load shedding reduces the life cycle of
your production equipment in one year? * • 0 - 5% • 6 - 10% • 11 - 15% • 16% or above • Other:
What is the power (kW) requirements for your business to operate at full
capacity? *
Does your factory have backup power generator(s)? * • Yes • No
• No, however, planning to install
What is the capacity (kW) of the your backup system? *
85
What is the reliability of your backup power generation system in percentage? * • 0 - 20% • 21 - 40 % • 41 - 60% • 61 - 80% • 81 - 100% • Other:
Do you manage your own power backup system or this service is outsourced? *
• Managed Internally • Outsourced Service • Other:
In percentage, how does the cost of running your factory on back up supply for
two hours compare to the cost of running it from the utility supply for two hours?
The cost of running on backup is usually higher, please indicate how high it is for
your factory. *
• 0 - 10% • 11 - 20% • 21 - 30% • 31 - 40% • 41 - 50% • 51% and above • Other
Please explain how did you make the estimation above!
Please describe which parts of your factory are powered by the backup power system during load shedding? e.g. administration area, production area, storage area, warehouse, etc *
Please estimate at what capacity are you able to operate your factory on the
backup power system? * • None • 1 - 20% • 21 - 40% • 41 - 60% • 61 - 80% • 81 - 100%
86
How may people work in your factory? *
What is the size of your factory (in square meters)? *
What are your main products? *
Is your factory categorized as small or medium-sized? * • Small • Medium
Do you have insurance to mitigate the impact of load shedding? * • Yes • No • No, however, I am planning to purchase one • Other
Is there any other information that you would like to share with the researcher?
87
Appendix D – Pictures of Richards Bay
Figure 25: The top view of the port of Richards Bay, the town’s export hub (Michelin, 2020).
Figure 26: The inside of one of the medium factories producing plastic products in Richards Bay (Michelin,2012).