An IT Application RTO Comparative Analysis Across 12 Industries Session D5 – 11 AM, Monday, April 20, 2015 Robert S. Emmel, Ph.D. – Accenture COAP, CBCP, CBCV, AFBCI, CHS-III © Copyright 2015 Accenture The 13th Annual Continuity Insights Management Conference Presented by: Continuity Insights April 20-22, 2014 Talking Stick Resort ● Scottsdale, AZ Next Generation Resilience

The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

Embed Size (px)

Citation preview

Page 1: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

An IT Application RTO Comparative Analysis Across 12 Industries

Session D5 – 11 AM, Monday, April 20, 2015

Robert S. Emmel, Ph.D. – Accenture COAP, CBCP, CBCV, AFBCI, CHS-III © Copyright 2015 Accenture

The 13th Annual Continuity Insights

Management Conference

Presented by: Continuity Insights

April 20-22, 2014 Talking Stick Resort ● Scottsdale, AZ

Next Generation Resilience

Page 2: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13th Annual Continuity Insights Management Conference: Next Generation Resilience

2

Introduction

• This document presents a comparative study of client IT application RTOs to potentially assist an organization in identifying, comparing and/or quantifying their IT application RTOs.

• This comparative analysis study presents actual rationalized IT application RTOs from 12 clients, each representing a different industry in comparison to an overall average RTO timeline “spread” from the combined IT application BIA RTO data of 44 additional clients.

• The goal of the study was to determine if there was a relationship between a company’s industry and the timing and “spread” of their IT application RTOs.

Page 3: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

3

Study Approach

13th Annual Continuity Insights Management Conference: Next Generation Resilience

• 44 client BIAs representing multiple industries were randomly selected and reviewed to determine if there was a clear view to each of the organization’s IT application RTOs. • RTO results from the 44 clients were then combined to determine a “loose” overall average

of IT application RTOs across 18 time periods (i.e., from 0 – 1 hour to 30 days). • In some instances, client IT application RTOs were grouped with the closest and most

appropriate of the 18 time periods within the study to facilitate easier comparisons (e.g., an 84-hour RTO was grouped with the study’s 96-hour versus 72-hour RTO). • 12 additional clients were then selected to compare their IT application RTOs to the “loose”

average of the 44 client industry average. •A comparative analysis was performed and reflected in two charts for each client’s IT

application RTO “spread” in comparison with those from the combined 44 client average. •A brief description of a client’s RTO findings adjoins the client’s charts.

• Client names were omitted from the study.

Page 4: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

4

Study Approach (cont.)

13th Annual Continuity Insights Management Conference: Next Generation Resilience

IT application RTO data for this study was drawn from BIAs performed across 44 clients representing multiple industries.

Bank - Foreign

Bank - National

Beverage Can Manufacturer

Brewery - Foreign

Cellular Communications Provider

Chemical Processor - Global

College - Small

Computer Services

Direct Mail Catalogue - Women's Apparel

Environmental Controls - Global

Financial Lending Services

Government - Foreign

Government - State

Healthcare Insurance Provider

Healthcare Provider - Regional

Paper Products - Global

Pharmaceuticals - Global

Professional Services Firm - Global

Restaurant and Entertainment

Retailer - Food

U.S. Government Corporation

Utility, Electric - Foreign

Utility, Electric - Regional

Airline Reservations

Bank - International

Bank - International

Bank - National

Communications Manufacturer - Global

Communications Manufacturer - Global

Communications Provider - 4G

Credit Card Processor

Distribution - Mail and Package

Energy - Downstream

Energy - Upstream/Downstream

Government - State

Healthcare Provider - Regional

Healthcare Provider - Regional

Media and Entertainment

Pharmaceutical Manufacturer - Global

Public School System - Large

Retailer - Electronics

Software Developer

Utility, Electric - Regional

Utility, Water - Regional

Page 5: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

5

Study Approach (cont.)

13th Annual Continuity Insights Management Conference: Next Generation Resilience

The 12 clients selected for comparison purposes represented the following industries:

• Airline Reservations • Communications • Consumer Products • Electric Utility • Energy • Financial Services

• Healthcare • Manufacturing (High Tech) • Media • Mobile Communications • Natural Resources • Retail

• 0 – 1 hour • 1 – 2 hours • 2 – 4 hours • 4 – 8 hours • 8 – 12 hours • 12 – 24 hours • 24 – 36 hours • 36 – 48 hours • 72 hours

• 4 days • 5 days • 6 days • 7 days • 10 days • 14 days • 15 days • 21 days • 30 days

The timeframes selected for RTO placement and comparison purposes included:

Page 6: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

6

Data Presentation Format – Example Charts

• Two charts were developed for each industry grouping represented in the RTO comparative study:

‒ Percentage (%) of IT applications recovered by RTO (see upper chart) as compared to the combined industry percentage (%)

‒ Cumulative percentage (%) of IT application recovery by RTO showing progression of the overall application recovery process versus the combined industry percentage (see lower chart)

• The “rust” bars within each chart represent the percentage (%) of IT applications recovered by RTO time period within the combined industries.

• The “gray” bars within each chart represent the current recovery rate of client IT RTOs.

13th Annual Continuity Insights Management Conference: Next Generation Resilience

Percentage of Applications Recovered by RTO (combined industries) % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO (combined industries) % of

Applications

RTO Timeframes

Combined industries % Client %

Combined industries % Client %

Page 7: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

7

RTOs by Client – Airline Reservations

13th Annual Continuity Insights Management Conference: Next Generation Resilience

Percentage of Applications Recovered by RTO – Airline Reservations % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Airline Reservations % of

Applications

RTO Timeframes

• This industry’s overarching goals are the accurate and timely maintenance of a traveler’s reservation, ticketing, baggage handling/routing, commerce and scheduling experience so a traveler arrives safely at their destination and is not stranded along the way.

• Tiering within the IT application recovery process is easily identified:

‒ Tier 1 recovery activities typically focus on ticketing, scheduling, fare collection and baggage handling with an RTO of 2 – 4 hours

‒ Tier 2 recovery activities encompass the restoration of back-office support applications within an RTO 12 – 24 hours

• All applications are targeted to be completely recovered and operational within 12 – 24 hours of an IT outage.

Combined industries % Client %

Combined industries % Client %

Page 8: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

8 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Communications

Percentage of Applications Recovered by RTO – Communications % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Communications % of

Applications

RTO Timeframes

• In an IT outage situation, this industry’s primary goal is to get back-office support as well as call tracking, routing and payment capabilities “up” as soon as possible.

• Recovery tiering is not readily identifiable from an overall industry view.

‒ The size of the particular company within the industry does make somewhat of a difference in application RTOs.

‒ Larger organizations typically recover applications more quickly (e.g., faster than 24 – 36 hours)

• Irrespective of company within this industry, the vast majority of applications (approximately 98.5%) are recovered within five (5) days.

Combined industries % Client %

Combined industries % Client %

Page 9: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

9 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Consumer Products

Percentage of Applications Recovered by RTO – Consumer Products % of

Applications

Cumulative Percentage of Apps Recovered by RTO – Consumer Products % of

Applications

RTO Timeframes

• From a consumer products perspective, an IT outage typically impacts headquarters functionality before individual manufacturing plant locations are affected.

• Plant locations have their own IT processing capabilities and can potentially function for up to five (5) days without HQ-refreshed product manufacturing, inventory or shipping information.

• As these graphs represent a single company within the Consumer Products industry, recovery Tiering is easily identified: ‒ Tier 1 applications (e.g., SAP, Manugistics,

Exchange, etc.) are recovered within five (5) days.

‒ Tier 2 applications (e.g., Hyperion, Brand websites, etc.) are recovered within 14 days.

‒ Tier 3 applications (e.g., employee self-service, SharePoint, WebSphere, etc.) are recovered within 21 days.

RTO Timeframes

Combined industries % Client %

Combined industries % Client %

Page 10: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

10 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Electric Utility

RTO Timeframes

Percentage of Applications Recovered by RTO – Electric Utility % of

Applications

Cumulative Percentage of Apps Recovered by RTO – Electric Utility % of

Applications

RTO Timeframes

• When an electrical utility’s main IT environment goes down, the individual power generation plants are not typically impacted as each plant has a separate IT environment just for that facility. (That doesn’t mean, however, that plant IT capability is not connected to the primary data center for relevant data.)

• In an IT outage situation, one of this industry’s primary goal is to get power trading systems back online in as little as one (1) hour following an IT disruption.

• Similarly, as can be seen from the upper graph, approximately 70% of the business management applications are to be recovered within a 4 – 8 hour timeframe, with the majority of the remaining applications (26.53%) recovered within 12 – 24 hours of an IT disruption.

Combined industries % Client %

Combined industries % Client %

Page 11: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

11 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Energy

RTO Timeframes

Percentage of Applications Recovered by RTO – Energy % of

Applications

Cumulative Percentage of Apps Recovered by RTO – Energy % of

Applications

RTO Timeframes

• Similar to headquarters/plant data center strategies in other industries, upstream and downstream oil processing facilities are typically not impacted by a primary data center outage at an Energy industry headquarters location.

• In an IT outage situation, this industry’s primary goal is to get business management support applications (e.g., SAP, etc.) “up and running” within the first 8 – 12 hours (if not sooner) following an IT outage.

• Recovery tiering is readily identifiable from an overall industry view.

• Irrespective of companies within this industry

study, all applications are recovered within seven (7) days.

Combined industries % Client %

Combined industries % Client %

Page 12: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

12 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Financial Services

Cumulative Percentage of Apps Recovered by RTO – Financial Services % of

Applications

RTO Timeframes

Percentage of Applications Recovered by RTO – Financial Services % of

Applications

RTO Timeframes

• Overall, this industry prides itself on being able to quickly (i.e., within a couple of hours) recover the majority of its IT and data center capabilities in the event of a disastrous data center interruption.

• Of all the Financial Services industry clients within this study, this one client example is provided to highlight a relatively “slow” data center recovery capability.

• The client is a very large retail and commercial financial services firm in Europe, and a large commercial bank within the boundaries of the U.S.

• Upon a data center outage scenario in the headquarters location in the Northeast U.S., the recovery data center (which resides in a co-location facility in the Southwest U.S. and primarily “runs” in an active/passive mode) can restore approximately 68% of production data center operations (e.g., trading, brokerage, loans, etc.) within 2 – 4 hours of a disaster event.

Combined industries % Client %

Combined industries % Client %

Page 13: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Healthcare

RTO Timeframes

Percentage of Applications Recovered by RTO – Healthcare % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Healthcare % of

Applications

• The Healthcare industry focuses on recovering critical patient care IT applications within 8 – 24 hours of a data center outage.

• However, the Healthcare industry also is typically supported by proven departmentally-based manual procedures in the event of an extended IT or facility power outage.

• Recovery tiering is somewhat readily identifiable in the upper chart:

‒ Tier 1 applications (e.g., critical patient care – McKesson, Cerner, testing, imaging, etc.) are typically recovered within 4 – 24 hours of an IT event

‒ Tier 2 applications (i.e., non-emergency care) within 72 hours

‒ Tier 3 applications (i.e., billing, pharmacy, (some) medical records, etc.) after five days

Combined industries % Client %

Combined industries % Client %

Page 14: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

14 13th Annual Continuity Insights Management

Conference: Next Generation Resilience

RTOs by Client – Manufacturing (High Tech)

RTO Timeframes

Percentage of Applications Recovered by RTO – Mfg (High Tech) % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Mfg (High Tech) % of

Applications

• Within the Manufacturing industry there are multiple data center strategies whereby the various plants will either share all or part of IT processing capabilities with the primary (e.g., headquarters) data center, or each plant can function in a standalone fashion with hourly/daily updates from HQ.

• Data from the upper chart highlights an example of a manufacturer that shares primary and plant IT capabilities, and recovers approximately 88% of their overall IT data center processing capabilities (e.g., Tier 1 applications - SAP, PeopleSoft, logistics, materials management, sales, etc.) within 24 hours of a data center disaster event.

• Tier 2 applications such as inventory management, Siebel and reporting within 72 hours of a data center disaster event.

• The remaining (Tier 3) applications (e.g., legal, training, and certification, etc.) are recovered within five (5) days.

Combined industries % Client %

Combined industries % Client %

Page 15: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13th Annual Continuity Insights Management Conference: Next Generation Resilience

15

RTOs by Client – Media

RTO Timeframes

Percentage of Applications Recovered by RTO – Media % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Media % of

Applications

• This Media industry example is the only client group within the study population whereby immediate/quick revenue recognition and tracking is not the primary driver of the business.

• 60% of IT production operations and conversion support capabilities (e.g., film to digital format conversion) is recovered within 24 – 36 hours due to a number of factors including film fragility.

• The Remaining 40% of applications (e.g., PeopleSoft Financials, imaging, contract management, AP/AR. etc.) are recovered within a timeframe equal to or greater than 72 hours.

Combined industries % Client %

Combined industries % Client %

Page 16: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13th Annual Continuity Insights Management Conference: Next Generation Resilience

16

RTOs by Client – Mobile Communications

RTO Timeframes

Percentage of Applications Recovered by RTO – Mobile Communications % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Mobile Communications % of

Applications

• Similar to the terrestrial communication providers within this study, an example Mobile Communications firm’s primary goal is to get back-office support as well as call tracking, routing and payment capabilities “up” as soon as possible (i.e., 8 – 12 hours), with credit management and other business operations applications “up and running” within 36 – 48 hours of a data center disaster.

• History and data warehouse-based applications would be recovered within 30 days.

Combined industries % Client %

Combined industries % Client %

Page 17: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13th Annual Continuity Insights Management Conference: Next Generation Resilience

17

RTOs by Client – Natural Resources

RTO Timeframes

Percentage of Applications Recovered by RTO – Natural Resources % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Natural Resources % of

Applications

• This Natural Resource (mining) client example requires approximately 12% of its IT applications be “up and running” within 0 – 1 hour of a data center outage to support highly time-sensitive communications and mine site operations (i.e., Tier 1).

• Tier 2 application recovery (35% of applications) occurs within a 36 – 48 hour timeframe and focuses on mine site business and production management.

• Tier 3 application recovery (13% of applications) occurs at 14 days and encompasses activities such as data warehousing and fixed asset management.

• Lastly, Tier 4 application recovery (40% of applications) occurs at 21 days and includes actuarial reporting, asset recovery, badging, sales, risk management, etc.

• Interesting note: this client tends to use extensive DR tabletop testing versus executing actual physical DR tests.

Combined industries % Client %

Combined industries % Client %

Page 18: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13th Annual Continuity Insights Management Conference: Next Generation Resilience

18

RTOs by Client – Retail

RTO Timeframes

Percentage of Applications Recovered by RTO – Retail % of

Applications

RTO Timeframes

Cumulative Percentage of Apps Recovered by RTO – Retail % of

Applications

• The Retail Industry’s overall recovery capability is somewhat mixed, and driven by not only the size of the company (i.e., number of stores, etc.), but by the company’s culture and type of goods sold.

• In general, approximately 30% of a retailer’s IT capability is targeted for recovery within 12 – 24 hours of a data center outage to keep its stores open, ensure revenue generation (sales) and item tax management, as well as customer retention and inventory management.

• However, after that initial recovery window, recovery timeframes can be spaced out over the remaining 29-day timeframe.

Combined industries % Client %

Combined industries % Client %

Page 19: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

19

High-Level Findings

13th Annual Continuity Insights Management Conference: Next Generation Resilience

• There were some readily identifiable differences in RTO timing between industries. •When checked with appropriate client personnel, some RTOs from three years ago have

been accelerated (shortened) due to significant changes in business requirements. •Not all clients with the same industry recover within a similar RTO spread.

• In most cases, client’s recover a majority of their IT applications within 72 hours.

•While the RTO timeframes shown within this analysis had been rationalized, most were not

validated through an actual test. Therefore, please note the IT application RTO shown within the study may “slip” to the right (i.e., get longer) following a physical test. • It is anticipated the provided information can be used by organizations and their DR/BCP

planning staff to help in guiding internal RTO confirmation meetings.

Page 20: The 13th Annual Continuity Insights Management Conference · PDF file•A brief description of a client’s RTO findings adjoins the client’s charts. ... Public School System - Large

13th Annual Continuity Insights Management Conference: Next Generation Resilience

20

Questions?

Additional ResourcesRobert S. Emmel

Senior Manager

Accenture161 North Clark StreetChicago, IL 60601- 3200

Mobile: (630) 913-8319Email: robert.emmel

@accenture.com

Additional ResourcesRobert S. Emmel

Accenture161 North Clark StreetChicago, IL 60601-3200

Mobile:(630) 913 8319Email: [email protected]