D E P E N D A B L E N A T U R A L G A S
TGP OutagesFebruary, March, and AprilCustomer WebexFebruary 17, 2015
2
Review of Upcoming OutagesFebruary/MarchApril
Q&A
3
Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary.Unless otherwise stated, all scheduled dates represent gas days as defined in the Tennessee Gas Pipeline tariff to mean a period of twenty‐four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).
4
Scheduled dates are subject to change.Projects may be added, altered, delayed or cancelled. TGP will provide notice of such additions or changes via DART postings.Dates as posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates within this presentation.
5
GreenNo Impact Anticipated
YellowRestrictions are possible, but not likelyWith extended duration, restrictions could be necessary from time to time(M) denotes that meter(s) may be impacted, refer to EBB posting
RedRestrictions are probable
6
Zone 0 – February/March
Unit MaintenanceSta. 409 (2/23/2015 ‐ 3/6/2015)
Capacity of 537,000 reduced to 360,000 (seg. 490)Sta. 409A (2/23/2015 – 3/7/2015)
Capacity of 300,000 reduced to 185,000 (seg. 492)
Trap ModificationsMLV 1‐2 to 2‐2 (2/10/2015 ‐ 3/3/2015) (M)MLV 1‐1 to 2‐1 (3/5/2015 ‐ 3/26/2015) (M)Capacity of 650,000 reduced to 425,000
Pipe Inspection/RepairMLV 705‐1 to 706‐1 (2/9/2015 ‐ 3/15/2015) (M)
MLV 701‐1 (3/15/2015 ‐ 4/30/2015) (M)
7
Zone L – February/March
ILI/Cleaning PigMLV 507‐1D to 516‐1
(3/3/2015 ‐ 3/10/2015 and 3/16‐3/17, 3/18‐3/19, 3/23‐3/24) (M)
8
Zone 1 – February/March
Pipe ReplacementMLV 545‐3 (1/16/2015 ‐ 3/14/2015)MLV 545‐2 (3/15/2015 – 5/15/2015)
Capacity of 940,000 reduced to 870,000 (seg. 542)
Bi‐Directional Station WorkStation 860 (8/18/2014 ‐ 3/16/2015)
Capacity of 650,000 reduced to 455,000 (seg. 847)Capacity of 996,000 reduced to 890,000 (seg. 548)
9
Zone 2 – February/MarchBi‐Directional Station Work
Sta. 200 (8/4/2014 ‐ 3/15/2015)
Anomaly Remediation MLV 96‐1D to 106‐1S (3/15/2015 ‐ 4/3/2015)MLV 96‐2D to 102‐2R (3/31/2015 ‐ 4/30/2015)
Capacity of 1,737,000 reduced to 1,270,000 (seg. 187)
Station ReversalSta. 96 (3/15/2015 ‐ 9/30/2015)
Capacity of 1,737,000 reduced to 1,270,000 (seg. 187)
Station ReversalSta. 110 (3/15/2015 ‐ 9/30/2015)
Capacity of 1,737,000 reduced to 1,270,000 (seg. 187)
10
Zone 4 – February/March
Anomaly Remediation Various valve sections from Sta. 200 to Sta. 209,
Lines 1, 2, and 3(4/28/2014 – 10/31/2015)
Station MaintenanceSta. 204 (3/16/2015 – 3/20/2015)Sta. 209 (3/23/2014 – 3/27/2015)
11
Zone 5 – February/March
Unit MaintenanceSta. 245 (8/11/2014 – 8/14/2014)
Unit MaintenanceSta. 245 (3/23/2015 – 3/27/2015)
Capacity of 1,067,000 reduced to 1,042,000 (seg. 245)
12
Zone 6 – February/March
ILI/Cleaning PigMLV 270A‐101.1 to 270A‐102 (3/30/2015 ‐ 3/30/2015) (M)MLV 270C‐301 to 270C‐302 (3/24/2015 ‐ 3/24/2015) (M)
13
Zone 0 – April
Unit MaintenanceSta. 409 (4/1/2015 ‐ 4/16/2014)
Capacity of 537,000 reduced to 360,000 (seg. 490)
14
Zone L – April
Pipe Inspection/RepairMLV 823‐1 (4/1/2015 ‐ 4/30/2015)
MLV 825‐1 to 826‐1 (4/1/2015 ‐ 4/30/2015)
15
Zone 1 – April
Pipe ReplacementMLV 545‐2 (3/15/2015 – 5/15/2015)
Capacity of 940,000 reduced to 600,000 (seg. 542)
Hydrotest/Valve ReplacementMLV 542‐2 to 546‐2 (4/15/2015 –
5/15/2015)Capacity of 940,000 reduced to 600 ,000
(seg. 542)
ILI/Cleaning PigMLV 876‐1 (Station 106) to 200‐3
(4/1/2015 ‐ 4/30/2015) (M) *dates to be determined
16
Zone 2 – April
Station ReversalSta. 114 (4/1/2015 ‐ 6/30/2015)
Capacity of 1,737,000 reduced to 1,560,000 (seg. 187)
HydrotestMLV 90‐5 (4/4/2015 ‐ 5/16/2015)
Capacity of 1,737,000 reduced to 1,560,000 (seg. 187)
Anomaly Remediation MLV 96‐1D to 106‐1S (3/15/2015 ‐ 4/3/2015)MLV 96‐2D to 102‐2R (3/31/2015 ‐ 4/30/2015)
Capacity of 1,737,000 reduced to 1,560,000 (seg. 187)
Station ReversalSta. 96 (3/15/2015 ‐ 9/30/2015)
Capacity of 1,737,000 reduced to 1,560,000 (seg. 187)
Station ReversalSta. 110 (3/15/2015 ‐ 9/30/2015)
Capacity of 1,737,000 reduced to 1,560,000 (seg. 187)
17
Zone 4 – AprilStation Maintenance
Sta. 317 (4/14/2015 ‐ 4/17/2015)Capacity of 1,710,000 reduced to 1,605,000
(seg. 315)
Anomaly Remediation Various valve sections from Sta. 200 to Sta. 209,
Lines 1, 2, and 3(4/28/2014 – 10/31/2015)
HydrotestMLV 206‐4 (4/1/2015 ‐ 4/30/2015)
18
Zone 5 – April
Unit MaintenanceSta. 245 (8/11/2014 – 8/14/2014)
ILI/Cleaning PigMLV 237‐1 to 245‐1 (4/28/2015, 4/30/2015 , 5/5/2015)Capacity of 1,030,000 reduced to 770,000 (seg. 245)
Unit MaintenanceSta. 241 (4/13/2015 ‐ 4/24/2015)
Capacity of 1,030,000 reduced to 990,000 (seg. 245)
19
Zone 6 – April
ILI/Cleaning PigMLV 270C‐303 to 270C‐401 (4/2/2015 ‐ 4/2/2015) (M)
Anomaly Remediation MLV 261‐1 to 267‐1 (4/20/2015 ‐ 10/31/2015)
Capacity of 985,000 reduced to 855,000 (seg. 261)Capacity of 518,000 reduced to 390,000 (seg. 266)
Station MaintenanceSta. 265E (4/11/2015 ‐ 4/25/2015)
20
100 System
Station 87 (TBD)
Station 106 (TBD)
200 System
300 System
MLV 321‐2 to 325‐2 ILI/Cleaning Pig (July)
MLV 325‐1 to 329‐1 ILI/Cleaning Pig (July)
MLV 329‐1 to 336‐1 ILI/Cleaning Pig (July)
MLV 342‐1 to 343‐1 Hydrotest (August)
500 System
500 Reversal (will include both lines and compressor stations)
800 System
MLV 834‐1 and 842‐1 Pipe Replacement (TBD)
MLV 847‐1 Hydrotest (TBD)
21
Suggestions for improvements to this meetingAre the meetings beneficial?Is additional information needed?Questions after the meeting?Other?
Email to one of the following:Your schedulerDART Portal