Upload
aulani
View
54
Download
2
Embed Size (px)
DESCRIPTION
TFTR D&D ALARA PLAN FY00 thru FY02. December 3, 1999 Presented By: James H. Chrzanowski. TFTR D&D ALARA PLAN. This presentation will review for the ALARA committee those D&D activities being planned for the three year plan, including: Assumptions made in determining dose estimates - PowerPoint PPT Presentation
Citation preview
TFTR D&D ALARA PLAN FY00 thru FY02
December 3, 1999
Presented By: James H. Chrzanowski
TFTR D&D ALARA PLAN
• This presentation will review for the ALARA committee those D&D activities being planned for the three year plan, including:– Assumptions made in determining dose estimates– General task descriptions– Estimated personnel exposure for each D&D task– Controls which will be used
• The safety and protection of the work force will be the primary concern during the D&D Removals
• Integrated Safety Management (ISM)
TFTR D&D ALARA PLAN
• The TFTR D&D Project Mission is to:– Surgically remove items which can be re-used
within the DOE complex– Remove Tritium contaminated and activated
systems for disposal– Clear the Test Cell of hardware except for the
Neutral Beams and their sources– Reclassify the D-site complex as a non-nuclear
facility as defined in DOE Order 420.1 (“Facility Safety”)
– Provide data on the D&D of a large magnetic fusion facility
TFTR D&D ALARA PLAN
• How dose estimates were developed:
• Dose rates based upon surveys performed this Summer and Fall.
• Man-hours were based upon estimates developed by engineering for the D&D Project
• Estimates were conservative
• No credit was taken for the use of shielding, even though shielding will be used wherever possible
• Activities whose estimated dose were less < 1.0 mrem were discounted from totals
TFTR D&D ALARA PLAN
SURVEY DATA - Top of umbrella structure 0.8-1.0 mrem/hr. - Midplane adjacent to TF coil 5.0 mrem/hr. - At edge of 102-ft. elevation 0.8 mrem/hr. - Vacuum Vessel on contact 25-35 mrem/hr.
- At yellow fence 0.16 mrem/hr.
TFTR D&D ALARA PLAN
Activity No. Task Description FY Estimated Exposure Dose Rate Total Estimated
Activity Man-Hours mrem/hr. Exposure (mrem)
2.4.1 - TOKAMAK REMOVAL241-2010 Remove upper cable trays,conduits & junction boxes FY01 480 hrs. 1.0 mrem/hr 480 mrem241-2020 Remove all conduits &cables below Umbrella Structure FY00 160 hrs.241-2060 Disconnect & remove coil/bus cooling lines FY00 80 hrs. 1.0 mrem/hr 80 mrem241-2030 Disconnect/remove all cooling lines/flow meters FY00 240 hrs. 5.0 mrem/hr. 2400 mrem241-2040 Remove VV Heating/Cooling pipes FY00 500 hrs. 1.0 mrem/hr 500 mrem241-2050 Remove MIRI Structure FY00 240 hrs. 1.0 mrem/hr 240 mrem241-2070 Remove upper PF/TF Bus runs and supports FY00 320 hrs. 1.0 mrem/hr 320 mrem
Primavera Activity No.
Man-hours to complete task
Dose-Rate/Hour
Sample Dose Estimating Table
TFTR D&D ALARA PLAN
• Steps Taken to Minimize Exposure– Experienced personnel will be used for critical tasks such as
vacuum interface/line breaks
– Lead shielding will be used whenever possible
– Disassembly sequence
– Special tools
– Pre-job Briefings
– Post-job Briefings
TFTR D&D ALARA PLAN
• Contamination Issues
– Personnel shall wear protective clothing/equipment as determined by Health Physics
– Elephant trunks, gloveboxes, etc. shall be used to contain airborne contamination
– Each procedure requires HP to survey/smear area prior to starting work to determine working condition
TFTR D&D ALARA PLAN
• FY BREAKDOWN• FY00 -Area preparation, initial diagnostic removals, Tokamak
removals on top of umbrella structure
– Minimal expected personnel dose• FY01- Majority of Diagnostic line breaks, pump duct removals,
vacuum vessel entry, start of contaminated basement vacuum line removals, prep and concrete fill VV
– Highest expected personnel dose• FY02 – Umbrella structure removal, Diamond cutting of VV and
close vessel work
– Reasonably high personnel dose
TFTR D&D ALARA PLAN
• PROJECTED DOSE SUMMARY• (Conservative estimates)R1
• FY00 …………………. 4.1 Rem• FY01 …………………. 13.9 Rem• FY02 …………………. 6.6 Rem • D&D Projected Total= 24.6 Rem
TFTR D&D ALARA PLAN
• ESTIMATED DOSE COMPARISON
• D&D Project……………………….. 24.6 Rem
• 1996 TFTR Outage (requested) ….. 13.7 Rem
• 1996 TFTR Outage (actual) ………. 5.05 Rem
– (internal & external values)