Texas Nodal Program Update. Jerry Sullivan. Overall program status remains amber. Cost. Nodal Delivery. Schedule. Scope/ Quality. Nodal Delivery. Scope / Quality. Schedule. Cost. Green. Amber. Amber. Amber. Summary. Currently fully aligned with protocols. - PowerPoint PPT Presentation
Citation preview
September 10, 2007TPTF Meeting
Texas Nodal Program Update
Jerry Sullivan
2Texas Nodal Program UpdateSeptember 5, 2007 2
CostScheduleScope / Quality
Legend
Summary
Overall program status remains amber
Green
Additional costs (Integration, Release Management, MMS, BL 1 & 2, and
Internal Allocation) exceeding existing contingency and savings
Amber AmberCurrently fully aligned with protocols.
15 NOGGRs identified with no
impact. Remaining 15
being reviewed for cost and
schedule impact
Red
Amber
Green Estimate at Complete = <$263m
Estimate at Complete = < $263m + 10%
Estimate at Complete = >$263m + 10%
Go-live = 12/1/08
Go-live = <30 days+
Go-live = >30 days+
Program is aligned with current protocols
Program is aligned to previous protocol version
Program is not aligned to protocols
Current EDS 1-3 milestones being achieved and are on track. Significant amount of work taking place in next 3
months.
EDS 4 milestones at risk due to MMS schedule.
Scope/Quality
Nodal
Cost
ScheduleScope/Quality
Schedule
Cost
Nodal Delivery
Nodal Delivery
Amber
Current product quality is not sufficient for Nodal launch
Most Nodal products currently achieve quality standards
All Nodal products currently achieve quality standards
Significant design issues still open
with MMS solution.
100% Success Rate in EDS3 R5
QA plans for EMS, MMS, OS still need
work
3Texas Nodal Program UpdateSeptember 5, 2007 3
Tactical deliverables and actions
# Topic Solution/Action
1 MMS • Vendor high-level schedule puts the Nodal Program schedule at risk.• Critical design issues need to be addressed rapidly by ERCOT/vendor – 75% “high” and “medium” category items resolved by 9/6. Focusing on the
remaining 25% this week. Possible schedule impact qualified by 9/7.• Commercial implications to follow• Mutual detailed plan is being developed to sustain viability of work going forward
2 Sandbox (8/31)Priority 2 Web Services
• Milestone met; market notice sent on 8/30
3 EDS 2 (9/4)State Estimator and Telemetry
• Release of EMS 2B and 2C to EDS environment planned for 9/6 (we’ll make this date)• FAT Testing: Transformer Tap Estimation may need major fix from AREVA – necessary to support SE performance requirements by October• Interim solution for delivery of SE Reports being developed (reports required in Oct/Nov)
4 EDS 1 (10/1) • Confidence in achieving the milestone is High: 79% complete with P2P• All QSEs will be completed and tested by 10/1, except for Austin Energy (currently upgrading their EMS)• Working to train Grid Ops to backfill for summer students returning to school• Fail-over test to occur in September; drafting requirements for MPs
5 EDS 3 (11/1)EMS interfacing with SCED
• Confidence in achieving the milestone is Medium• EMS integration code delivered; FAT testing this week• MMS delivery of interfaces, confidence is High as result of EMS interface status • Delivery of SCED reports, confidence is low – cross-project effort launched to expedite delivery • Developed consolidated list of data elements, assigning responsible parties for delivery (Network Model, Registration, EMS, MMS)
6 EDS2 R4 (11/1)NMMS NOMCR
• Confidence in achieving the milestone is Medium, with known challenges (data reconciliation and validation, AREVA load capabilities, MP availability)
• Phase 1c delivery at end of Sept 2007 being pushed to Mid-Oct; Defining testing approach to leverage system functionality in the order it’s delivered
4Texas Nodal Program UpdateSeptember 5, 2007 4
Time line update
Energy Management System (EMS)
EDS
Market Management System (MMS)
Congestion Revenue Rights (CRR)
Market Information System (MIS)
Network Model Management System (NMMS)
Commercial Systems (COMS)
ERCOT / MP Readiness & Implementation
Enterprise Integration (EIP)
Enterprise Data Warehouse (EDW)
Infrastructure (INF)
CIM
RT FAT
FAT
CMM
S&B Build S&B FAT
FAT
EDS 1
EDS 3EDS 4
Single Entry Model3/31/
RT Market12/01
DA Market12/08
168 Hour Trials
DAM, RUC, SASM S&B Interfaces Build and FAT
SCED, CRR Interfaces Build and FAT
Currently re-planning
Currently re-planning
Readiness Metrics
Start MP Registration
Build Dev Environments
Build ITest & EDS1/2 Build EDS 3
Build ITest
Build EDS 4 and Fail-Over Env
SCED Interfaces, RLC LFC
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
RPP, LF Study Apps
SE & TelemetryICCP Upgrade
DAM, RUC, SASM Build and BL 1 & 2 changes DAM, RUC, SASM , CIM FAT VDI, DC Tie
Financial Transfer FAT Disputes FAT
UI, NOMCR EDS 2 FAT
CIM Importer
EDS 2
CRR Auction10/15
Today
Key
Milestone Complete √
FAT Start
FAT end
EDS Start
EDS End
Go-Live
Acronym KeyFAT – Factory Acceptance Testing
EDS – Early Delivery System
I test – Integration Testing
√√
√√ √√√√
√√
√√ √√
√√
√√
√√√√
√√