Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Copyright of Royal Dutch Shell plc
Testing the Effect of Different Optimization Parameters on Layout
Design Using openWind®: A GIS Based Wind-Modeling Platform
Meagan Krawczyk, Wind Resource Analyst, Shell Wind
Nick Robinson, Director of openWind®, AWS Truepower
Sara Tyler, Wind Resource Manager, Shell Wind
ESRI Petroleum User Group Conference, Houston, TX
April 18th 2011
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 1
Copyright of Royal Dutch Shell plc
Overview
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 2
What is openWind®?
Optimizing wind farm layouts
Wind farm layout design basics
Test results / conclusions
Copyright of Royal Dutch Shell plc
openWind® and ArcGIS: Compatible, not competitive
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 3
openWind®:
Software developed by AWS Truepower, LLC
A tool for the design, optimization, and assessment of wind power projects
Open-source platform
Patterned after Geographical Information Systems (GIS)
Identical computations to those of other leading wind farm design programs
openWind® GIS functionality:
Create and display vectors and rasters
Clip vector layers
Edit attributes
Edit vectors
Label features
Export vectors/rasters to Google Earth
Add/Subtract rasters
Perform Vegetated and Non-Vegetated viewshed analysis (ZVI)
Copyright of Royal Dutch Shell plc
Approaches to wind farm layout design
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 4
Standard industry practice is to optimize turbines for maximum production
openWind® Enterprise has the capability to optimize layouts using the Cost of Energy Optimizer (COE)
Takes into account some project cost metrics
COE Testing: Hope to find a way to more automate the process of optimizing wind farm layouts for project valueTested whether or not the COE process had measurable impact on the resulting turbine layout
Plant Cost
Estimates
Financial
Assumptions
Site
ConditionsOptimization
Wind
Conditions
Turbine
Layout
Site
ConditionsOptimization
Wind
Conditions Turbine
Layout
Copyright of Royal Dutch Shell plc
Wind Farm Layout Design Basics: Create a wind map
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 5
Inputs to openWind®
Digital Elevation Model (DEM)
Roughness (RGH) – Values assigned to land cover for the site
Meteorology data (TAB file) – Historical, representative met data for the site in the form of wind speed and direction
(wind frequency)
Output (.WRG)
A grid containing probability (P) and wind speed (U) at each pixel in the grid
Defines wind conditions for the site.
Site Land cover (RGH) Elevation Data (DEM) Wind Rose (TAB file)
Wind Map (.WRG)
Copyright of Royal Dutch Shell plc
Wind Farm Layout Design Basics: Capture site constraints
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 6
Constraints:
Each site will have specific considerations to avoid, i.e. roads, rivers, steep slopes, etc.
Constraints are defined and mapped in order to create a buildable area in raster form
In Shell Wind, constraints are handled within ArcGIS
Copyright of Royal Dutch Shell plc
Wind Farm Layout Design Basics: Define Turbine Specifications
Date 9 May, 2011 ESRI PUG Presentation - openWind COE Optimizer 7
Turbine Specifications:
Hub height – The height of the turbine at the center of the hub
Rotor Diameter – The diameter of the circular path which the turbine blades rotate within
Cut in/out – The wind speed in which the turbine will start spinning (cut-in), and discontinue spinning
(cut-out)
Power Curve – The relationship between power production of the turbine and incoming wind speed
Thrust – Used to estimate impact of turbine on downstream wind flow
RPM – Rotational speed of the turbine rotor
* Photos courtesy of Vestas V100 Turbine Brochure
Side View of Turbine NacelleTurbine Hub Height Turbine Rotor Diameter
Copyright of Royal Dutch Shell plc
Wind Farm layout Design Basics: Choose a spacing
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 8
Spacing : Turbines need to be properly spaced from each other to lessen wake effects
Dominant Wind Direction
Max. Rotor SpacingMin. Rotor Spacing
Horns Rev Wind Farm : Photographed by
Christian Steiness
Copyright of Royal Dutch Shell plc
Wind Farm Layout Design Basics: Choose an optimizer
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 9
Optimize Layouts: There are 3 main ways to optimize layouts:
Gridded
Energy
Cost of Energy
1. Gridded Layout Optimizations – Turbines are packed into a linear array defined by angles, spacing and an area
Copyright of Royal Dutch Shell plc
Wind farm Layout Design Basics: Optimize for energy
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 10
2. Optimize for Energy (maximum capacity factor):
Inputs:
Wind Resource Grid
Turbine Specifications
Turbine Spacing
Number of Turbines
Constraints
Output:
Turbine Layout
Capacity Factor:
The ratio of estimated actual
output of energy over a
period of time and it’s output
if it had operated at full
capacity
Copyright of Royal Dutch Shell plc
Wind Farm Layout Design Basics: Optimize for cost of energy
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 11
Inputs: Same as energy optimizer AND:
Costs:
Roads
Cables
Turbine
Financial
Files:
Existing roads
Water bodies
Existing Cables
Cost Multipliers
Starting points (nodes) for cables
and roads must be defined
Should be as centrally located as
possible
Road start node should connect to
an existing main road
Outputs:
Turbine Layout
Road Design
Collection System
Copyright of Royal Dutch Shell plc
Wind Farm Layout Design Basics: Assess your design
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 12
Generate layout-specific producible energy estimates based on:
Input wind map (WRG)
Wind speed distribution (.tab file)
Turbine model specifications
Site specific air density
Site reference height
Estimates Include:
Gross Energy : Energy before wake effects
Net Energy : Gross Energy – site specific losses (i.e. wake effects)
Capacity Factor : Net Energy / (#MW *8760)
Example: 10 Turbine – 2 MW Machine:
Cost of energy
Copyright of Royal Dutch Shell plc
Testing Methodology: COE vs. Energy
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 13
Two test sites were selected to run both the energy optimizer and the COE optimizer
Inputs were kept the same for both optimizers, other than inputs specific to COE
COE inputs were defined by engineers within Shell Wind
Each optimization was run for the same number of iterations
Reports were run for each scenario and results compared
Reported conclusions are based on averaged results from 2 sites (4 scenarios)
Each of the 4 scenarios had a different total number of turbines/MW : 100, 250, 400 and 380 MW scenarios
This methodology was chosen to see if an increase in available land (by decreasing the number of turbines)
would increase the difference between costs
Copyright of Royal Dutch Shell plc
Results: COE vs. Energy
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 14
Designs were compared on basis of the following parameters:
Across the board, COE optimized layouts were lower in each category than energy optimized layouts
Scenarios with a higher ratio of land to turbines had a higher difference between energy and cost between the COE and
energy optimized layouts
Gross
Energy Net Energy
Capacity
Factor
Array
Efficiency Cost/MWh Total Cable Cost Total Road Cost
Total Cable
Length
Total Road
Length
COE
~0.08%
lower
COE
~1.41%
lower
COE
~1.40%
lower
COE
~0.61%
lower
COE ~1.90%
lower
COE ~17.7%
lower
COE ~30.9%
lower
COE
~12.0%
lower
COE ~17.7%
lower
Copyright of Royal Dutch Shell plc
Results: 100 MW Vestas V112 Scenario:
Energy Optimization Cost of Energy Optimization
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 15
Road NodeTurbine
Cable Node
Copyright of Royal Dutch Shell plc
Results: 400 MW Vestas V112 Scenario:
Energy Optimization Cost of Energy Optimization
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 16
Road Node TurbineCable Node
Copyright of Royal Dutch Shell plc
Results: 250 MW Vestas V100 Scenario:
Energy Optimization Cost of Energy Optimization
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 17
Road NodeTurbineCable Node
Copyright of Royal Dutch Shell plc
Results: 380 MW SWT 101 Scenario:
Energy Optimization Cost of Energy Optimization
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 18
Road NodeCable Node Turbine
Copyright of Royal Dutch Shell plc
Testing Methodology: Sensitivity to DEM resolution and start nodes
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 19
50 meter and 10 meter resolution DEMs were tested
Start nodes for cables and roads were shifted
The start nodes were shifted from the 1st location to different locations that were still feasible for the project
*Red circle represents Cable Start Node (Substation), Yellow circle represents Road Start Node
50 m DEM, 1st set start nodes 10 m DEM, 2ND set start nodes
Copyright of Royal Dutch Shell plc
Results: Sensitivity to DEM resolution and start nodes
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 20
Comparison 1: Variable is DEM
Site 1: 50 m DEM, 1st set start nodes (base case)
Site 2: 10 m DEM, 1st set start nodes (comparator)
Comparison 2: Variables are DEM and start nodes
Site 1: 50 m DEM, 1st set start nodes (base case)
Site 3: 10m DEM, 2nd set start nodes (comparator)
Comparison 3: Variable is start nodes
Site 2: 10 m DEM, 1st set start nodes (base case)
Site 3: 10m DEM, 2nd set start nodes (comparator)
ComparisonGross
Energy Net Energy
Capacity
Factor
Array
Efficiency Cost/MWh
Total
Cable Cost
Total Road
Cost
Total Cable
Length
Total Road
Length
1 + 0.16% - 0.14% Negligible -0.34% + 0.32% -1.52% + 4.38% -2.02% + 1.02%
2 + 0.11% - 0.17% - 0.28% - 0.34% - 0.04% - 4.83% - 0.26% - 3.32% - 2.18%
3 - 0.05% - 0.03% Negligible Negligible - 0.35% - 3.26% - 4.85% -1.28% - 3.24%
Copyright of Royal Dutch Shell plc
Results: Sensitivity to DEM resolution and start nodes
250 MW Vestas V100 sensitivities:
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 21
10 m DEM, 2ND set start nodes50 m DEM, 1st set start nodes 10 m DEM, 1st set start nodes
Copyright of Royal Dutch Shell plc
Conclusions:
Date 9 May, 2011 ESRI PUG Presentation - openWind ® COE Optimizer 22
The COE optimizer produces layouts that are more linear and less like the energy optimized layouts for sites that are less
constrained (or have more available land)
Based on the cost calculator within openWind®, COE optimized layouts cost less to build than energy optimized layouts per MW
installed capacity
COE optimized layouts produce less energy per MW installed than energy optimized layouts
Energy optimized layouts are optimized for energy, and therefore tend to be more spread out to minimize wake effects
COE optimized layouts minimize the cost of energy rather than maximizing the energy capture and tend to be more tightly packed
COE optimized layouts are generally more linear in their design, which could make construction and maintenance easier
Using a higher resolution DEM impacts COE optimized designs, indicating that the highest resolution of DEM available to the user
should be used
Shifting the start nodes for cables and roads has shown to affect the outcome of the COE optimized layout. The user should be
aware of this relationship and test various scenarios to see what fits best for the site