Test beam 2004 - crystal tests using E0’ Possibility of new crystal producers for both Barrel and Endcap Need to appraise crystals from these producers Of particular concern: crystal response to irradiation BCTP and SIC have recently produced EE crystals SIC crystals show a 25-30% additional light yield compared to BCTP Apatity (North crystals) to produce a few crystals, by end April Proposal: Use test beam from May 27 th to appraise crystals Construct 1 SC array with Russian and Chinese crystals, mounted on E0’ Crystals to be pre-irradiated and sorted for the SC Read out with 25 channels of MGPA electronics (SM1) from 2003 Irradiate crystals at H4 Follow LY and monitoring response in detail

Test beam 2004 - crystal tests using E0’

  • Upload
    sivan

  • View
    44

  • Download
    0

Embed Size (px)

DESCRIPTION

Test beam 2004 - crystal tests using E0’. Possibility of new crystal producers for both Barrel and Endcap - PowerPoint PPT Presentation

Citation preview

Page 1: Test beam 2004 - crystal tests using E0’

Test beam 2004 - crystal tests using E0’

Possibility of new crystal producers for both Barrel and Endcap

Need to appraise crystals from these producersOf particular concern: crystal response to irradiationBCTP and SIC have recently produced EE crystalsSIC crystals show a 25-30% additional light yield compared to BCTPApatity (North crystals) to produce a few crystals, by end April

Proposal:Use test beam from May 27th to appraise crystalsConstruct 1 SC array with Russian and Chinese crystals, mounted on E0’Crystals to be pre-irradiated and sorted for the SCRead out with 25 channels of MGPA electronics (SM1) from 2003 Irradiate crystals at H4Follow LY and monitoring response in detail

Objectives: To establish whether the crystals meet the CMS ECAL technical requirementsClearance to place contracts for crystals by summer 2004

Page 2: Test beam 2004 - crystal tests using E0’

Basic EE Hardware Needs for Crystal Beam Tests - May 2004

Working assumptions (06-Apr-04):

• 1 EE supercrystal containing 15 SIC, 8 BCTP & 2 Apatity crystals

• The supercrystal will be built at CERN

• We will use (up to) 25 channels of 2003 ECAL Electronics chain

• Beam starts May 27th

• Goal is to have the bare supercrystal ready for HV boards by Apr 26th

• All hardware for one bare supercrystal must be at CERN by the Friday after Easter, 16 April

Page 3: Test beam 2004 - crystal tests using E0’

Preparation

Responsibles:

EA - Etienette Auffray, CERN KWB - Ken Bell, RAL DJAC - Dave Cockerill, RAL DB – David Bailleux, Minn MD - Marc Dejardin, Saclay MH – Maurice Haguenauer, LLR RB – Robert Benetta, CERN PSF - Paul Flower - RAL HFH - Helen Heath - Bristol PL - Pierre Lecomte - ETHZ ABL - Tony Lodge, RAL JR - John Rander, Saclay BJS - Brian Smith, RAL TA1 - CERN-PH TA1 group VP – Vladimir Postoev, INR VG – Viatcheslav Grishin (Slava), IHEP IA – Alexander Inyakin, IHEP

Page 4: Test beam 2004 - crystal tests using E0’

E0’

• E0’ moved to bldg 11 on 30 March to be connected to full ECAL R/O chain

• E0’ currently equipped with one prototype SC – to be replaced

• Work ongoing by MD, RB, AL• Umbilical connected to Motherboard (with the ‘any 5’ trigger ordering)• 25 channels MGPA VFE + FE card (SM1, 2003) = one barrel tower• Blue LED pulses to front of crystals, one at a time • Signals seen in correct order by full readout chain• noise ~ 2 ADC channels, work in progress

Possibility to inject light into each crystal separately from front

Page 5: Test beam 2004 - crystal tests using E0’

Supercrystal assembly

Hardware (needs+spares):

SC crystals

25+5 EE crystals - EA

SC mechanics + VPTs

1+1 Alveoles - 3 already at CERN - BJS/TA1

25+5 Tyveced Front Inserts - 75 already at CERN - BJS/TA1

1+1 sets of Rear Inserts - 3 sets already at CERN - BJS/TA1

1+1 Interface Plates - 3 already at CERN - BJS/TA1

1+1 Housings - 3 already at CERN - BJS/TA1

25+5 VPTs - ~48 already at CERN - DJAC

1+1 calibrated thermistors & cables (what connectors?) - PSF

Page 6: Test beam 2004 - crystal tests using E0’

Supercrystal assembly + umbilical

SC mechanics + VPTs (contd)

Glue for Rear Inserts - already at CERN - BJS/DJAC

Glue dispensors for Rear Inserts - already at CERN - BJS/DJAC RTV Glue for VPTs - on order in the UK - BJS Glue dispensors for VPTs - ??? - BJS/DJAC

2 Glueing Jigs for VPTs to crystals - already at CERN - DJAC

10 Centering tubes/weights for glueing - already at CERN - BJS/DJAC Bar-code reader for crystal serial numbers (or temporary labels???) - DJAC

Jig for manipulating alveolar during construction – ETH-Z/PL

Supercrystal lifting "handle" - already at CERN - DJAC

SC umbilical 5+2 HV boards - presently at RAL - ABL 1+1 umbilical signal looms - ABL 1+1 umbilical HV (SHV) cable pairs - ABL

Test gear for supercrystal soak test at CERN - ABL/HFH/DJAC/KWB/VP/VG/AI

Page 7: Test beam 2004 - crystal tests using E0’

E0’

Monitoring 50 Porte-Ferrules - already at CERN - BJS/DJAC Tooling for Porte-Ferrules - already at CERN - BJS/DJAC 1 Level-1 EE fibre optic harnesses - 1 presently on E0’ at CERN - BJS/JR Laser(s)/photo-diodes/MEMs/mating-pieces-to-photo-diodes etc etc - JR???

E0’ mechanics 1+1 positional spacers - already at CERN - DJAC E0prime support backplate & related ironmongery & cooling plates - already at

CERN - DJAC Mounting bolts & shoulder bolts - already at CERN - DJAC E0prime thermal enclosure, already at CERN, extra insulation – TA1 Support to mount E0prime system onto test beam turntable - TA1 design/ fabricate

Readout HV system for beam tests - KWB EE Mothercard/connectors/pigtail - ABL

Full readout chain, LV system, MEM, etc - MD 1 set of EE cooling bars & related mechanics etc - already at CERN - JAH

Page 8: Test beam 2004 - crystal tests using E0’

Test beam meetings/H4

Wed 14 April

Test Beam Mtg, Yves Sirois

- follow on from PRS, at ~ 16.00

- choice of crystals

- irradiation procedure

» Use of 6 days of beam for 25 crystals

» Start up requirements (DAQ setup, laser setup)

» Beam size, rate, calibration points

» Shift list + test beam web page for 2004

• Laser system at H4 – expected to be ready by Mon April 19

• Optical cables from CR to area – currently those from 2003

• Cooling system + interlocks – to be discussed

• 10 SHV cables to be laid from CR to area

Page 9: Test beam 2004 - crystal tests using E0’

Test beam

SPS MD 10.00 Wed 26 May – 10.00 Thu 27 May

Beam 10.00 Thu 27 May – 10.00 Wed 2 June (~ 6 days)

25nsec beam 08.00 Mon 7 June – 08.00 Mon 14 June

Shutdown 08.00 Mon 14 June – 08.00 Sat 19 June

Beam 08.00 Sat 19 June – 08.00 Wed 30 June (~10 days)

Page 10: Test beam 2004 - crystal tests using E0’

E0’ – corresponding SCs in CMS

6,45,4

5,5 6,5

Spacer numbering

Column, Row

Page 11: Test beam 2004 - crystal tests using E0’

Angles at CMS

737.67mm

587.31mm

o

3179 mmIP to front of EE

= 38.526 o

IP

Page 12: Test beam 2004 - crystal tests using E0’

Angles for E0’, Y-Z plane

Y

Z

= 10.47o

587.31mm

3179 mmIP to front of EE

Beam

Page 13: Test beam 2004 - crystal tests using E0’

Angles for E0’, X-Z plane

X

Z

= 13.06o

737.67mm

3179 mmIP to front of EE

Beam

Page 14: Test beam 2004 - crystal tests using E0’

E0prime backplate & SCs

352mm

250mm

Position of middle of array, 390mm forwards from backplate, with respect to backplate edges