TERMINAL REPORT DURING THE RSU MECHANICAL ENGINEERING REVIEWEE VISIT AT ALCORCON ENGINEERING REVIEW CENTER IN MANILA
August 28-29, 2015
The undersigned wrote a letter to the VPAA of the University, Dr. Elvin F. Gaac if he could visit the Mechanical Engineering reviewees since the group texted that their pre-board exam will nearly come on September 29-30, 2015. The VPAA granted the request of the undersigned.
On Aug. 28, 2015, the undersigned boarded through Montenegro shipping lines to go to Manila to accomplish his task. On the next day, he went to Alcorcon Engineering Review Center located at Sampaloc Manila to talk with staff and reviewers regarding on the status of the RSU Mechanical Engineering reviewees batch 2015. We have discussed the percentage passing of the group during their weekly exams and some of the RSU BSME reviewees had some difficulty in passing the exams. But of course, the results were not the basis of the actual passing on the actual exams. We even talked on the possibility of not allowing students to take exam if their status on the review sessions will not meet on the 80% passing of the review center.
At 9:00 P.M., Aug. 29, 2015 the undersigned visited also the lodging houses where the group stayed. Fortunately, one of the lodging was located few walks at the review center but others would have to ride jeepney for their sessions. He observed that the lodging was overcrowded and no enough table for them to have study well. On the other hand the room was good and clean for lodging purposes.
The reviewees and the undersigned have had conversations regarding their problems on the subject matter in the review sessions as well as the accommodation of the review center. They were very happy that a University sent a faculty representative to visit them as well as to give regards to them. Before we end up the conversations they requested the undersigned to visit the group next time during their actual board exam to be given on September 29-30, 2015.
Prepared by:
Engr. Virne B. Dalisay
RSU MECHANICAL ENGINEERING REVIEWEE VISITS
ALCORCON ENGINEERING REVIEW CENTER4th Floor, Anacleta Building, 891 Galicia Street, Corner Espana Blvd.,
Sampaloc, ManilaAugust 28-29, 2015
REIMBURSEMENT REPORT
DATE ORIGINDESTINATION
TRANSPORTATION/SERVICES
COST
AUG. 28 MAYHAPOCTOY PORT
TRIBIKE70.0
0
SHIPPING TICKET842.00
TERMINAL TICKET15.0
0
PORTERAGE120.00
AUG. 29BATANGAS
ALABANG BUS127.00
ALABANG
ESPANA MANILA
TAXI350.00
AUG.30 ESPANA ALABANG TAXI350.00
BUS128.00
SHIPPING TICKET842.00
TERMINAL TICKET24.0
0
PORTERAGE120.00
POCTOY MAYHA TRIBIKE120.00
TOTAL3108.00
Prepared by: ENGR. VIRNE B. DALISAY Faculty