Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
Table of Contents
Contents
1 INTRODUCTION .................................................................................................................... 8
1.1 Background............................................................................................................................... 8
1.2 Details of EIA Consultant /Accreditation .............................................................................. 8
1.3 Information about the Project Proponent ............................................................................. 9
1.4 Importance and Benefits of the Project ................................................................................. 9
1.5 Purpose of the Report ............................................................................................................ 10
1.6 Scope of the Study .................................................................................................................. 12
1.7 Structure of EIA Document .................................................................................................. 12
1.8 Post Environmental Clearance Monitoring ......................................................................... 13
2 PROJECT DESCRIPTION .................................................................................................. 14
2.1 Identification of the Project................................................................................................... 14
2.2 Products and Capacities ........................................................................................................ 16
2.3 Cost of the Project and Time of Completion ....................................................................... 17
2.4 Infrastructure Facilities in Project District ......................................................................... 17
2.5 Raw Materials ........................................................................................................................ 17
2.6 Material Balance .................................................................................................................... 19
2.7 Total Efficiency of Induction Furnace ................................................................................. 20
2.8 Source of Raw Material ......................................................................................................... 20
2.9 Water Requirement ............................................................................................................... 21
2
2.10 Manufacturing Process .......................................................................................................... 23
Pickling ..................................................................................................................................... 29
3 SITE DETAILS ...................................................................................................................... 31
3.1 General .................................................................................................................................... 31
3.2 Location of the project ........................................................................................................... 31
3.3 Site Selection ........................................................................................................................... 31
3.4 Topography............................................................................................................................. 31
3.5 Coordinates of the land plot .................................................................................................. 32
3.6 Industries within 10 km Radius of Plant .............................................................................. 36
Figure 3-5 ........................................................................................................................................ 36
3.7 Geo-Hydrological Status ........................................................................................................ 36
3.8 Land Use ................................................................................................................................. 38
Figure 3-7 ........................................................................................................................................ 38
Figure 3-8 ........................................................................................................................................ 38
4 BASELINE ENVIRONMENT STATUS ............................................................................. 39
4.1 General .................................................................................................................................... 39
4.2 Methodology ........................................................................................................................... 39
4.3 Study Area .............................................................................................................................. 39
4.4 Environmental Surveys and Studies ..................................................................................... 39
4.5 Physical Environment ............................................................................................................ 40
4.6 Geomorphology ...................................................................................................................... 40
3
4.7 Drainage .................................................................................................................................. 40
4.8 Irrigation ................................................................................................................................. 40
4.9 Geology .................................................................................................................................... 41
4.10 Climate & Meteorology ......................................................................................................... 41
4.11 Test Methodology for Environmental Monitoring & Testing ............................................ 43
4.12 Ambient Air Quality .............................................................................................................. 43
4.13 Ambient Noise Quality ........................................................................................................... 53
4.14 Water Environment ............................................................................................................... 55
4.15 Soil Environment .................................................................................................................... 56
4.16 Flora and Fauna ..................................................................................................................... 65
4.16.1 Forest ............................................................................................................................... 65
4.17 Socio Economic Environment ............................................................................................... 66
5 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES ....... 68
5.1 Introduction ............................................................................................................................ 68
5.2 Air Environment .................................................................................................................... 68
5.3 Impact on Topography and Climate .................................................................................... 68
5.4 Impact on Topography .......................................................................................................... 68
5.5 Impacts on Climate ................................................................................................................ 69
5.6 Air Quality Impact Prediction .............................................................................................. 69
5.7 Model Input Data ................................................................................................................... 70
5.8 Ground Level Concentration ................................................................................................ 71
4
6 ANALYSIS OF ALTERNATIVES (SITE AND TECHNOLOGY) .................................. 77
6.1 General .................................................................................................................................... 77
6.2 Analysis of Alternative Site ................................................................................................... 77
6.3 Analysis of Alternate Technology ......................................................................................... 77
6.4 Induction Furnace .................................................................................................................. 77
6.5 Reheating Furnace ................................................................................................................. 79
7 ENVIRONMENTAL MONITORING PROGRAM ........................................................... 80
7.1 Monitoring Schedule during Operational Phase ................................................................. 81
8 ADDITIONAL STUDIES ...................................................................................................... 86
8.1 Public Hearing ........................................................................................................................ 86
8.2 Risk .......................................................................................................................................... 86
8.3 Risk Assessment & an Approach to Emergency Preparedness Plan ................................ 86
8.4 Identification of Hazards ....................................................................................................... 87
8.5 Major Hazards ....................................................................................................................... 87
8.6 Accidents ................................................................................................................................. 88
8.7 Risk Assessment ..................................................................................................................... 89
8.8 Risk Prevention Methods ...................................................................................................... 89
8.9 Disaster Management Plan Including Risk Assessment and Damage Control ................ 90
8.10 On-Site Emergency Plan ....................................................................................................... 90
8.11 Objectives ................................................................................................................................ 91
8.12 Basic Contents of Disaster Management Plan (DMP) ........................................................ 91
5
8.13 Purpose & Scope .................................................................................................................... 92
8.14 Preventive Measures & Plans ............................................................................................... 92
8.15 Emergency Management ....................................................................................................... 93
8.16 Infrastructure at Emergency Control Centre ..................................................................... 93
8.17 Health and Safety Measures For The Workers ................................................................... 94
8.18 Safety of Personnel ................................................................................................................. 94
8.19 Emergency Action Plan for Fire ........................................................................................... 94
8.20 Emergency Action Plan For Electric Shock Casualties ...................................................... 94
8.21 First Information .................................................................................................................... 94
8.21.1.1 Declaration of Emergency ......................................................................................... 95
8.21.1.2 Objectives of Onsite Emergency Plan ...................................................................... 95
8.21.1.3 Elements of Onsite Emergency Plan......................................................................... 96
8.21.1.4 Methodology ............................................................................................................... 96
8.21.1.5 Risk Assessment Matrix ............................................................................................ 99
8.22 Heat Stress ............................................................................................................................ 106
8.23 Source .................................................................................................................................... 106
8.24 Occupational Health & Safety ............................................................................................ 108
8.25 Legal Provisions ................................................................................................................... 109
8.26 Role of Management ............................................................................................................ 109
8.27 Accident Record ................................................................................................................... 110
8.28 General Safety at Work ....................................................................................................... 112
6
8.28.1.1 Safe Guards, Signals, Signs ..................................................................................... 112
8.28.1.2 Safety Guards ........................................................................................................... 113
8.28.1.3 Electric Safety ........................................................................................................... 113
8.28.1.4 Hoisting, Loading & Handling ................................................................................ 113
8.28.1.5 Safety Training & Drills .......................................................................................... 114
8.29 Occupational Health Monitoring & Record ...................................................................... 115
8.30 Disasters & its Types ............................................................................................................ 117
8.31 Hazards in Steel Industry & its Effects .............................................................................. 117
8.32 Common Hazards in Industry ............................................................................................ 118
8.33 Disaster Management .......................................................................................................... 119
8.34 Risk Assessment ................................................................................................................... 120
8.35 Disaster Management Steps ................................................................................................ 121
8.36 Incident Control and Command ......................................................................................... 123
8.37 Incident Action Plans (IAP) ................................................................................................ 123
8.38 Incident Command Structures (ICS) ................................................................................. 124
9 PROJECT BENEFITS ........................................................................................................ 127
9.1 Tangible Benefits .................................................................................................................. 127
9.2 Intangible Benefits ............................................................................................................... 127
9.3 Other Benefits ....................................................................................................................... 127
10 ENVIRONMENT COST BENEFITS ANALYSIS ........................................................... 128
11 ENVIRONMENTAL MANAGEMENT PLAN ................................................................ 129
7
11.1 Environmental Management Cell ....................................................................................... 129
11.2 Environment Management Plan ......................................................................................... 130
11.3 Central Pollution Control Board {CPCB} Guide Lines for Steel Industry .................... 134
12 DISCLOSURE OF CONSULTANTS ENGAGED ........................................................... 136
8
1 INTRODUCTION
1.1 Background
M/S Mahalakshmi Profiles Pvt. Ltd., established on Survey. No. 287, 288 & 289 in
Kallakal village, Manoharabad Mandal, Medak District in Telangana state, is already
manufacturing Steel Billets. Presently it has two induction furnaces (one stand by) with 12
tons capacity, with total production of 29,700 tons per Annum. It also has a Strip mill and
Tube mill of 165tonnes per day capacity each. The existing plant is having valid Consent
for Operation from TS Pollution control Board.
Now the company have proposed to expand the existing plant by installing 12TPH x 6
more (total 8 No. 12TPH) Induction Furnaces along with CCM for making 621 TPD
(2,04,930 TPA) of MS Billets and New roughing stand/Modernization activities for
making 534 TPD (1,76,220 TPA) of MS Skelp and installation of 3 new ERW Tube mills
for production of 835 TPD (2,75,550 TPA) of MS Pipes and installation of scaffolding
workshop for production of 50 TPD (16,500 TPA) of Scaffolding. It will also Install
continuous coil Galvanizing unit for manufacturing of 300 TPD (99,000 TPA) of
Galvanized Strips /Coils and installation of Hot Dip Galvanizing unit for manufacturing of
300 TPD (99000 TPA) of Hot Dip Galvanizing of MS ERW Tubes.
As per the Environmental Impact Assessment (EIA) notification S.O. 1533 issued on 14-
09-2006 by Ministry of Environment and Forests (MoEF&CC), New Delhi, the proposed
expansion project for manufacturing MS Billets and TMT Bars is categorized as Category
B project under 3(a) Secondary Metallurgical Industries and is mandated to obtain prior
Environmental Clearance from State Environmental Impact Assessment Authority
(SEIAA), under Ministry of Environment & Forests, Govt. of India. Since the state
committee is not yet formed the case is put up at center.
Accordingly EIA studies in and around 10 Km range of project site has been carried out by
NABET Accreditated Global Management & Engineering Consultants International,
Jaipur, Rajasthan as per the terms of reference stated above and the EIA report has been
compiled based on the data collected during the study and details about the project
provided by the proponents.
1.2 Details of EIA Consultant /Accreditation
The EIA consultants have accreditation with Quality Control of India (QCI)/National
Accreditation Board of Education and Training (NABET) as per office memorandum dated
26th December 2009 of MoEF&CC. Disclosure of the Consultant is given in Chapter 12.
9
Table 1-1: Brief Information about Consultant
EIA Consultant Organization Global Management and Engineering
Consultants International
Saharan Tower, 308, Officers Campus Extension,
Sirsi Road, Khatipura, Jaipur-302012
Environmental coordinator Dr. Meena Bhaduri
Contact Information E-mail: [email protected]
QCI/NABET NABET Accredited EIA Consultant
Organization
Certificate No. NABET/EIA/1619/IA007
An ISO 9001:2008 Certified company
Laboratory Engaged in EIA Project Nakshatra Enviro Services 66/40, Heera Path,
Mansarovar, Jaipur Certificate Number:- 2018-
12-08
Status of Laboratory NABL Accredited Laboratory
An ISO 9001:2008 Certified Laboratory
1.3 Information about the Project Proponent
M/S Mahalakshmi Profiles Pvt. Ltd. is a Private Limited Company. The Directors of the
company are as under:
Directors: The company is promoted by: Mr. Ramniranjan Agarwaland Mr. Vinod Kumar
Agarwal.
Address: Mahalakshmi Profiles Pvt. Ltd. Private Limited has its registered office at 1-9-8,
I.D.A, Azamabad, Hyderabad, Telangana.
1.4 Importance and Benefits of the Project
Iron and Steel industry forms the backbone of the economy. Iron and steel helps to
manufacture machines that support other producing units. The level of per capita
consumption of steel is treated as one of the important indicators of socio-economic
development and living standard of the people in any country.
India is the third largest steel producer in the world. The Indian Steel industry is organized
in three categories i.e., main producers, other major producers and the secondary
producers. The main producers and other major producers have integrated steel making
facility with plant capacities over 0.5 MT and utilize iron ore and coal/gas for production of
steel. The main producers are Tata Steel, SAIL, and RINL, while the other major producers
are ESSAR, ISPAT and JVSL etc. The secondary sector is dispersed and consists of: (1)
Forward linkage with about 120 sponge iron producers that use iron ore and non-coking
10
coal, providing feedstock for steel producers; (2) Approximately 650 mini blast furnaces,
electric arc furnaces, induction furnaces that uses iron ore, sponge iron and melting scrap to
produce steel; and (3) backward linkage with about 1,200 re-rollers that roll out semis into
finished steel products for consumer use. In 2015-16, production of finished Steel is 90.98
million tones. The share of secondary steel producers is 67% of total steel production in the
country. Due to its growing demand, India has been identified as one of the hottest
destination of steel exports from all over the world.
Secondary steel producers play vital role in reaching end customers in the country.
Induction steel melting and rolling mills are growing at rapid rate due it’s accessibility to
small and medium users, housing sector, infrastructure, transportation etc., This demand is
further boosted by the demand from foreign countries. The Indian Market is exporting the
steel products to more than 51 countries and earning valuable foreign exchange to the
country. In view of the above, the proposed expansion project would contribute in meeting
the increasing demand for steel in both domestic and export markets.
The project would provide direct employment and indirect business and service
opportunities in the region. Also the project contributes to economic development in the
region and revenues to Government.
The Company has its registered office at 1-9-8, I.D.A, Azamabad, Hyderabad, Telangana.
The Company is engaged in Manufacturing of Hot Rolled Strip, MS ERW Pipes & Tubes.
MPL stands on a foundation of skill and enterprise with experience of over five decades.
The founder Late Shri Mohanlal Agarwal is the first promoter of the steel industry in
Andhra Pradesh. Over the last fifty years we have combined technology with expertise to
manufacture a wide range of steel products geared to serve a variety of needs. With a
modest turnover of Rs. 13.97 Crores for the year ended March 2002, the Company has
registered a turnover of around Rs. 269.85 Crores and net profit of 5.02 Crores for the year
ended March 2018, and has targeted a turnover of Rs. 500 Crores for the year 2020. The
company has manufacturing at Kallakal village, Manoharabad Mandal, Medak Dist,
Telangana. The company now proposes expand the existing plant by modernization of
Strip mill and Induction Furnace in existing plant premises, setting up of new tube mill
division along with strip galvanizing and hot dip galvanizing facilities.
They are committed to bring around a major change in the society through its quality
products and by implementing global best practices, adopting efficient technologies,
developing R&D and promoting CER activities.
1.5 Purpose of the Report
M/S Mahalakshmi Profiles Pvt. Ltd., established on Survey. No. 287, 288 & 289 in
Kallakal village, Manoharabad Mandal, Medak District in Telangana state, is already
manufacturing Steel Billets. Presently it has two induction furnaces (one stand by) with
12 tons capacity, with total production of 29,700 tons per Annum. It also has a Strip mill
11
and Tube mill of 165tonnes per day capacity each. The existing plant is having valid
Consent for Operation from TS Pollution control Board.
Now the company have proposed to expand the existing plant by installing 12TPH x 6
more (total 8 No. 12TPH) Induction Furnaces along with CCM for making 621 TPD
(2,04,930 TPA) of MS Billets and New roughing stand/Modernization activities for
making 534 TPD (1,76,220 TPA) of MS Skelp and installation of 3 new ERW Tube
mills for production of 835 TPD (2,75,550 TPA) of MS Pipes and installation of
scaffolding workshop for production of 50 TPD (16,500 TPA) of Scaffolding. It will also
Install continuous coil Galvanizing unit for manufacturing of 300 TPD (99,000 TPA) of
Galvanized Strips /Coils and installation of Hot Dip Galvanizing unit for manufacturing
of 300 TPD (99000 TPA) of Hot Dip Galvanizing of MS ERW Tubes.
As per the Environmental Impact Assessment (EIA) notification S.O. 1533 issued on 14-
09-2006 by Ministry of Environment and Forests (MoEF&CC), New Delhi, the proposed
expansion project for manufacturing MS Billets etc. categorized as Category B project
under 3(a) Secondary Metallurgical Industries and is mandated to obtain prior
Environmental Clearance from State Environmental Impact Assessment Authority
(SEIAA), under Ministry of Environment & Forests, Govt. of India.
Since the State Appraisal Committee was dissolved hence, Project proponent has
submitted application in the prescribed Form-I along with Pre- Feasibility Report and
other required documents, to obtain Terms of Reference (TOR) for conducting
Environmental Impact Assessment study for the proposed expansion project to EAC,
Ministry of Environment and Forests (MoEF&CC), New Delhi.
The Proposal No IA/TG/IND/96524/2019 was considered by the “Re constitute Expert
Appraisal Committee (Industry-I) “meeting held between 27th – 29th March, 2019 .After
detailed deliberations, the Committee recommended specific ToR on 3rd May 2019, for
undertaking detailed EIA and EMP study in addition to the generic ToR enclosed at
Annexure I read with additional ToRs at Annexure-2, for the project proposal, the same
is attached in the report. The committee also desired that public consultation should be
done by the SPCB and final outcome of the same be incorporated at the time of final EIA
report. Accordingly this final EIA report has been prepared by incorporating Public
Hearing outcomes.
Accordingly EIA studies in and around 10 Km range of project site has been carried out
by NABET Accreditated Global Management & Engineering Consultants International,
Jaipur, Rajasthan as per the terms of reference stated above and the EIA report has been
compiled based on the data collected during the study and details about the project
provided by the proponents.
12
1.6 Scope of the Study
M/S Mahalakshmi Profiles Pvt. Ltd. received the terms of reference issued by the
“Reconstitute Expert Appraisal Committee (Industry-I)” on 3rd May 2019.
For undertaking detailed EIA and EMP study the committee issued Specific ToR in
addition to the generic ToR enclosed as Annexure I read with additional ToRs at
Annexure-2 the same is attached in the report. The committee also desired that public
consultation should be done by the SPCB and final outcome of the same be incorporated
at the time of final EIA report. Accordingly this final EIA report has been prepared by
incorporating Public Hearing outcomes.
Accordingly the scope of the work includes detailed characterization of various
environmental components such as micro-meteorology, air, noise, water, land and socio-
economy within 10 km radius from the proposed plant. The main objectives of the study
are:-
To identify and quantify significant impacts due to various operations of the
proposed steel unit on various environmental components through prediction of
impacts.
To assess the existing baseline status of air, water, noise, land and socio-
economic environment
To evaluate and implement the Environmental Management Plan (EMP)
detailing control measures and its efficiency to minimize the pollution levels
within the permissible norms. To evaluate the beneficial and adverse impacts of
the proposed plant.
To design an occupational health & safety plan for the employees.
To design post project monitoring plan for regulating the environmental quality
within the limits and help in sustainable development of the area.
To assess the probable risks, likely to occur in unit and suggest appropriate
measures to avoid the same.
1.7 Structure of EIA Document
The objective of the EIA study is to prepare Environment impact assessment report
based on the guidelines of the Ministry of Environment and forests (MoEF) and CPCB.
In terms of the EIA notification of the MOE&F dated 14th September 2006 and
subsequent amendments on 01.12.09 and 04.04.2011, the generic structure of EIA
documents is as follows.
Executive Summary
Introduction
13
Project Description
Description of the Environment
Anticipated Environmental Impact & mitigation Measures
Analysis of Alternatives (Technology & Site)
Environmental Monitoring Program
Additional studies
Project benefits
Environmental Cost Benefits Analysis
EMP
Disclosure of Consultant Engaged
1.8 Post Environmental Clearance Monitoring
Half yearly compliance reports will be provided on 1st June and 1st December of each
calendar year.
14
2 PROJECT DESCRIPTION
2.1 Identification of the Project
M/S Mahalakshmi Profiles Pvt. Ltd., is already manufacturing Steel Billets. Presently it
has two induction furnaces (one stand by) with 12 tons per hour (TPH) capacity, with
total production of 90 tons per day (TPD). It also has a Strip mill and Tube mill of
165tonnes per day capacity each.
Now the company have proposed to expand the existing plant by installing 12TPH x 6
more (total 8 No. 12TPH) Induction Furnaces along with CCM for making 621 TPD
(2,04,930 TPA) of MS Billets and New roughing stand/Modernization activities for
making 534 TPD (1,76,220 TPA) of MS Skelp and installation of 3 new ERW Tube
mills for production of 835 TPD (2,75,550 TPA) of MS Pipes and installation of
scaffolding workshop for production of 50 TPD (16,500 TPA) of Scaffolding. It will also
Install continuous coil Galvanizing unit for manufacturing of 300 TPD (99,000 TPA) of
Galvanized Strips /Coils and installation of Hot Dip Galvanizing unit for manufacturing
of 300 TPD (99000 TPA) of Hot Dip Galvanizing of MS ERW Tubes.
M/S Mahalakshmi Profiles Pvt. Ltd.is situated at village Kallakal village, Manoharabad
Mandal, Medak District in Telangana state , Latitude 17° 41' 54.3408"N and Longitude
78°29'4.8192"E. The project falls under the Manoharabad Mandal.
The land area of the plant is 19 Acres and 17 Guntas (78,610.256 sq m) out of which
13.675 acres is being used for the Industrial processes and 5.75(33.0% )Acres has been
allocated for green belt.
The total project cost is Rs 150.00 Crores (after addition of proposed
machinery).Proposed Employment Generation from proposed project will be around 600
persons out of which 500 persons will be having direct employment and 100 persons
will have indirect employment.
The electricity load of 15500 KVA will be procured from Telangana Electricity supply
board. Fresh water consumption for the proposed project will be 75 KLD and recycle
water 115 KLD; proposed project is based on zero discharge, 15 KLD of waste water
will be generated and treated in septic tank.
The unit obtained CFO for Furnace on 16-08-2017 (valid up to 31-01- 2022) from State
Pollution Control Board to manufacture 90 T/Day of MS Ingots ,60TPD MS Pipes and
70TPD hot Rolling strips . The unit obtained the respective Consent Orders accordingly
and started its operations
15
Salient features of the project are given in Table2-1.
Table 2.1-1: Salient Features of the Site
Name of Project Mahalakshmi Profiles Pvt. Ltd.
Proponent( Director) Mr. Ramniranjan Agarwaland Mr. Vinod Kumar
Agarwal.
Nature of the Project Secondary Metallurgical Process based industry
Latitude and Longitude S.
NO.
LATITUDE LONGITUDE S.
NO.
LATITUDE LONGITUDE
1 17°42'3.22"N 78°29'1.19"E 14 17°41'56.60"N 78°28'47.00"E
2 17°41'57.66"N 78°29'0.91"E 15 17°41'56.50"N 78°28'47.00"E
3 17°41'57.60"N 78°28'55.80"E 16 17°41'55.90"N 78°28'42.00"E
4 17°41'52.50"N 78°28'55.60"E 17 17°41'56.20"N 78°28'41.90"E
5 17°41'52.50"N 78°28'55.40"E 18 17°41'56.80"N 78°28'46.70"E
6 17°41'54.20"N 78°28'50.00"E 19 17°41'57.60"N 78°28'46.70"E
7 17°41'54.20"N 78°28'49.60"E 20 17°41'57.50"N 78°28'48.20"
8 17°41'54.10"N 78°28'49.10"E 21 17°42'0.80"N 78°28'48.50"E
9 17°41'55.30"N 78°28'48.80"E 22 17°42'0.70"N 78°28'50.60"E
10 17°41'55.40"N 78°28'49.40"E 23 17°42'2.00"N 78°28'50.90"E
11 17°41'56.60"N 78°28'49.40"E 24 17°42'2.30"N 78°28'56.20"E
12 17°41'56.70"N 78°28'49.60"E 25 17°42'2.20"N 78°28'56.20"E
13 17°41'56.90"N 78°28'49.70"E 26 17°42'2.79"N 78°29'0.25"E
Site Location Survey. No. 287, 288 & 289 in Kallakal village,
Manoharabad Mandal, Medak District in Telangana state
Total land area 78,610.255 sq. m
Total area of green belt developed 2,594.22 sq. m (33.0%)
Nearest High way The plant site approached by small road which connect
NH-7 and Industry
Nearest Rly Stn Dabilpur Rail Way Station is 2.8 Km from the site
Nearest Air Port Rajiv Gandhi International Airport, Shamshabad,
Hyderabad is 70 km from the site
Nearest fire station Narsapur 21 km (North –West)
Nearest village Kallakal Village North 1km
Nearest surface water bodies Pond near Gomaram 9.0 km (West-North West)
Water body near Meenjipeta 5.5 km(North East)
Water body near Tunki Makta 8.0 km (NE)
16
Name of Project Mahalakshmi Profiles Pvt. Ltd.
Medchal Lake 8.63 km (South)
Nearest Reserve Forest Ellampet Reserve Forest 2.0 km South –South West
Any ecologically sensitive areas None
Fresh Water Requirement Industrial: 16 KLD; Domestic: 3.6 KLD (Existing)
Industrial: 57KLD; Domestic: 16 KLD (Proposed)
Source of Water Telangana: Gram Panchayat and tanker supply
Man Power 500 Members to be employed directly and around 100
people may be employed indirectly
Power Demand 15500 KVA and is supplied by Telangana Electricity
supply board
DG Set Existing one DG set of 380 kVA
Project Cost The cost of the project is Rs 150 crores (15000 lakhs)
along with all the accessories
2.2 Products and Capacities
The existing project was small scale and did not required prior Environmental Clearances
but complied fully to all the legislations required in case of Air, Water (Acts), hazardous
waste handling rules and regulations. The land area of the plant is 19 Acres and 17 Guntas
(78,610.256 sq m) out of which 13.675 acres is being used for the Industrial processes and
5.75(33.0% )Acres has been allocated for green belt.
Six Induction furnaces having capacity 12 TPH has been proposed. The existing capacity
of the unit is 90 TPD of Billets .The capacity of the unit after expansion is given in Table
2-2 .
Table 2-2: Existing and Proposed Capacities
S. No. Product Capacity
Existing Expansion After Expansion
1 MS Billets though Induction Furnace
90 TPD 621 TPD 711TPD
2 MS Skelp through Strip mill
165 TPD 534 TPD 699 TPD
3 Pipes through Tube Mill 165 TPD 835 TPD 1000 TPD
4 Scaffolding -- 50 TPD 50 TPD
5 Galvanized Strips/Coils -- 300 TPD 300 TPD
6 Hot Dip galvanizing of -- 300 TPD 300 TPD
17
MS ERW Tubes
2.3 Cost of the Project and Time of Completion
The total project cost is Rs 150.0 Crores (after addition of proposed machinery). The time
schedule required for the expansion will be within 5-6 months after getting necessary
statutory approval.
2.4 Infrastructure Facilities in Project District
Site is well connected to the Kallakal village road. Medchal is the Nearest Town to
Kallakal village. Medchal is 8 km from Veerlapally. Road connectivity is there from
Medchal to Kallakal. Dabilpur Rail Way Station is 2.8 Km from the site. However
Hyderabad Deccan Railway Station is major railway station 80 km.
2.5 Raw Materials
The steel manufacturing industry requires variety of raw material which is presently being
supplied locally /foreign market/both. The existing unit is using the MS Scrap; Sponge Iron
and Alloying metals for the MS Ingots and Billets. It is proposed to increase the production
capacity of MS Ingots/Billets from 27,000 TPA to 213,300 TPA, thus the raw material
requirement will also increase which is mentioned below in Table 2-3.
Table 2-3: Raw Materials Requirement for Existing Unit
S.N
o
Raw
Material
Source Transportation Quantity
TPD TPA
For Existing (90 TPD)
1 Sponge Iron Local/adjacent States By Road 63.54 19,062
2 Iron Scrape Local/Imported By Road 9.9 2,970
3 Pig Iron Local/adjacent States By Road 18.63 5,589
4 Ferro Alloys Local/adjacent States By Road 0.81 243
Strip mill
1 Billets In plant generation and
purchased from Market
Conveyors and
By Road
(Covered trucks)
165TPD
2 High grade
coal thermal
Imported/Purchased from
Traders
By Road
(Covered trucks) 9 TPD
Tube Mill
1 MS Skelp In plant generation By Road
(Covered trucks) 166 TPD
Material Balance for Existing
Billets 90 27,000
Slag 2 600
Cutting& Scaling 1.5 450
18
Table 2-4: Raw Materials Requirement for Existing Unit
S.No. Raw Material Consumption Source of Raw
Materials
Method of Transport
Induction Furnaces with concast
1 Sponge Iron 551 TPD From Sponge iron
plants By Road (covered trucks)
2 Scrap 164 TPD Local By Road (covered trucks)
3 Ferro Alloys 6 TPD Local By Road (covered trucks)
Strip mill
1 Billets 587 TPD In plant generation Conveyors
2 High grade coal
thermal 32 TPD
Imported/Purchased
from Traders By Road (Covered trucks)
Tube Mill
1 MS Skelp 699 TPD In plant generation By Road (Covered trucks)
2 HR Coil 354 TPD
Purchased from
SAIL/TATA/JSW/
Other Manufacturers
By Road (Covered trucks)
Scaffolding
1 MS Tubes 47 TPD In plant generation By Road (Covered trucks)
2 Accessories/
Components 3 TPD
Purchased from local
Manufacturers By Road (Covered trucks)
Continuous Coil Galvanizing
1 MS Skelp 150 TPD In plant generation By Road (Covered trucks)
2 HR Coils 150 TPD Purchased from
SAIL/TATA/JSW By Road (Covered trucks)
3 Zinc Hindustan Zinc/ Other
reputed Manufacturers By Road (Covered trucks)
Hot Dip Galvanizing
1 MS ERW Tubes 300 TPD In plant generation By Road (Covered trucks)
19
2 Zinc Hindustan Zinc/ Other
reputed Manufacturers By Road (Covered trucks)
2.6 Material Balance
Figure 2.6-1: Material Balances for (Existing) M.S. Billets to the tune of 27,000TPA
20
Figure 2.6-2: Material Balances for (Proposed) M.S. Ingots and Billets to the tune of
213,300 TPA
2.7 Total Efficiency of Induction Furnace
Efficiency of induction furnace is estimated after deducting electrical and heat transfer
losses. Electrical losses consist in transformer, frequency converter, condenser, wiring,
cable, coil, etc. Loss in coil is essential factor, on which the furnace capacity depends. Heat
losses in induction furnace consist of conduction loss of heat escaping from furnace wall to
coil side, radiation loss of heat released from melt surface, absorption loss in ring hood,
slag melting loss, etc.
Heat efficiency of high-frequency furnace (60- 78%) is slightly larger than that of low-
frequency furnace (58 - 71%). Low-frequency furnace is larger in heat loss, while high-
frequency furnace is larger in electrical loss. This is explicable from the fact that low-
frequency furnace has lower power density at melting and larger heat loss due to long
melting time, while high-frequency furnace has higher power density, heat loss is small due
to short melting time and primary electrical loss is large due to frequency conversion.
Table 2-5:Total Power Consumption in Induction Furnace per Hour
Heat Item
PERCENTAGE MWH
Heat
Input
Transformer Primary I/P Power
100
5.4
Heat Content of
Heat
Output
Metal 39.6 2.6136
Slag 8.5 0.561
Heat Content of
Walls
Waste Gases
Water Cooling
Electrical Losses
Miscellaneous Heat Losses
9.72
10.5
9.2
10.9
11.58
0.64152
0.693
0.6072
0.7194
0.76428
Total
100.00 6.6
Note: Energy balance is done considering 600 kWh/t – steel
Source: Specific Energy Consumption of Induction Crucible Furnace/ Intensive Programme “Renewable Energy Sources”,
May 2011, UWB, CZ
2.8 Source of Raw Material
The raw material required for the unit is M.S. Scrap; Sponge Iron & alloying materials
(Silico-Mn, Ferro-Silicon etc.) will be purchased from domestic market. The raw material
is sufficiently available in the domestic as well as in international market. The raw material
supply to the site will be carried out by trucks.
21
2.9 Water Requirement
The existing daily fresh water demand of the unit is 15 KLD out of which 11.4 KLD is
required for industrial purpose and 3.6 KLD for domestic purpose. The waste water
generated from the industrial process like blow down and quenching water is being treated
in settling tank baffle type and the treated water is being recycled in the process (23 KLD)
and reused for plantation (4KLD). Similarly, the domestic waste water is being routed to
septic tank followed by soak pit. Thus, the unit is maintaining zero discharge. After
expansion additional water will be required as new units will be installed. After expansion
the daily fresh water demand will be 75 KLD out of which the 60 KLD will be required for
industrial purpose and 15 KLD for the domestic purpose. The total recycle water will be 45
KLD and 10 KLD will be reused for plantation. The water is being met from Rural water
supply Scheme and same will be maintained after expansion. The detailed existing water
balance along with after expansion water balance is given below in figure 2-3 and 2-4:
The details of total water consumption, it's breakup is shown in Table below.
Table 2-6: Water Requirement
SOURCE Existing
in KLD
Expansion
in KLD
After expansion
in KLD
Cooling water make up for SMS 3 20 23
Cooling water make up for Strip mill 4 13 17
Cooling water make up for Pipe mill 4 13 17
Continuous Coil Galvanizing
Hot Dip Galvanizing
Domestic consumption 3.6 12.5 16.1
Total 14.6 say 15 59.5 say 60 74.1say 75
22
Figure 2.9-1: Existing Water Balance
Figure 2.9-2: Water Balance after Expansion
23
2.10 Manufacturing Process
INDUCTION FURANCE [STEEL MELTING SHOP]
In Steel Melt Shop (SMS) Sponge Iron will be melted along with melting scrap and fluxes
to make pure liquid steel and then to mould it in required size billets. The shop consists of
following equipment and subassemblies:
Induction Furnaces: Induction Furnace is a device to melt the charge material using
electrical power. It consists of Crucible lined with water cooled induction coils, Electrical
system to give controlled power to induction coil, Hydraulic tilting system, Heat exchanger
to cool the circulating water, water softener for generating soft water, furnace transformer,
Power Factor improvement system and surge suppressor.
Ladles: Ladles are pots with refractory lining inside to withstand 1600 deg C temperature.
It has side arms so that it can be lifted with the help of crane. Ladles are used to stores the
liquid steel from Induction Furnace and take it for further processing. Ladles are with
bottom nozzle and pneumatically operated gate for discharge of liquid.
Cranes: Electric Over-head (EOT) cranes of various capacities are used to carry the
ladles/materials at different places. Cranes are used in Melting hall to charge melting scrap,
remove the ladles to the LRF, further to place it over the Tundish of the Continuous Caster,
to remove billets from the cooling bed and store at designated places, and also for other
petty use. Accordingly the sizes, capacity and number of cranes are decided.
Continuous Casting Machine (CCM): CCM is used to continuously cast the liquid steel
in required cross section and in length. It consists of Tundish, Mould, Bow with
Withdrawal mechanism, straightening mechanism and cooling bed, hydraulic system for
withdrawal mechanism, water sumps and cooling towers for water spray on the withdrawn
section as well as on the cooling bed. Dummy bar is provided to start the casting. Tundish
is a rectangular vessel, lined with refractory and having discharge nozzle with
pneumatically operated gate. A stand is erected over it where the ladle is stationed for
discharging the liquid in it. Mould is of copper with water cooled jacked. Its cross-section
in the bottom is of the size of which billet is to be drawn. Initially the dummy for of the
same size is kept inserted. When the liquid steel is poured in the mould the dummy bar is
drawn slowly, so that the liquid steel in partially frozen state comes out of the mould.
Water spray nozzles are installed to spray water over the just drawn billet to cool it further
and to harden the skin of the drawn billet.
B) STRIP MILL
The primary function of the Hot Strip Mill is to reheat semi-finished steel slabs of steel
nearly to their melting point, then roll them thinner and longer through 8 successive rolling
mill stands driven by motors totalling 10,000 HP and finally coiling up the lengthened steel
strip for transport to the next process. The Hot Mill rolls billet pieces weighing up to 600
24
kg between 100*100 and 160*160mm. Steel billet of up to 160mm thickness is rolled into
strip as thin as 1.2mm up to 400 feet in length.
Raw Material Handling:
The raw material for making strip is MS square billets/MS Slabs. The billets are then cut
using liquid oxygen and LPG into smaller lengths as per the desired dimension of strip to
be produced. The cut-to-length billets are placed on a charging grate. With the help of a
hydraulic arrangement the billets are fed onto the conveyor and in turn conveyed to the
pusher top.
Reheating Furnace:
Critical to the Hot Strip Mill is its pusher-type reheat furnace nominally rated to produce
30 tons-per-hour. Heating this much steel from room temperature to 1150-1200°C
consumes around 32 MT of coal each day. The cut length billets are placed on a roll line.
When space is available in the furnace, large hydraulic ‘pusher arms’ are engaged to move
the billets into the furnace. Much of the preheating of the steel is achieved by the hot
exhaust gases rushing past the billets on the way to the ‘recuperates’ above the charge door.
Whatever heat is left in the exhaust gases preheats the incoming combustion air to over
450°C in these massive heat-exchangers. Conversely, in the heating zone the steel is
primarily heated by the glowing-hot furnace walls. In the soak zone, numerous smaller
burners seek to maintain a uniform temperature within the zones to equilibrate any cold
spots in the billets. Refractory dividers help to physically distinguish the zones, and
thermocouple temperature sensors throughout the furnace. When the billet reaches the
‘discharge door’ at the exit end of the furnace, the billet has been sufficiently heated, the
door opens and the ejector billet pushes the hot piece out of the furnace. The intensely hot
billet is placed on a roller table which carries it into the roughing mill.
Direct feeding of HOT Billets /slabs from CCM
Descaling:
After exiting the reheat furnace, the Billets/slabs passes through a descaling unit, an
enclosure employing two pairs of spray headers that blast the intensely hot billet with
pressurized water to remove the scale of oxidized iron that forms at the surface of the slab
in the oxygen-rich atmosphere of the reheat furnace. Shortly after descaling, a (relatively)
small 2-hi rolling mill called a scale breaker breaks up any scale that remains.
Roughing:
The roughing mill is made up of 5 rolling mill stands, two of which incorporate small
vertical rolling mills called edgers. Billets are heated in the furnace until they glow bright
orange-yellow are rolled through one stand at a time to produce so-called transfer bars
suitable for finish rolling. High-pressure water-jet nozzles clean the oxidized iron, or scale,
from the surface along the way. The two vertical stands, each incorporate edgers for width
25
control and roll the bar from five to six inches thick incrementally down to around an inch
and a quarter, depending on the customer’s ordered width, gauge, and steel grade.
Edging:
At the very high temperatures at which the steel is rolled in the roughing mill, it is very
plastic and ‘flows’ easily like cookie dough beneath a rolling pin. Consequently, as the
Billets/slab is reduced from five to six inches thick to the final bar thickness of few
millimetres; bars tend to spread width-wise by a few inches at their extremities, and by as
much as an inch through the body. The edgers serve to hold a uniform width through the
bar’s length, and are powerful enough to squeeze the bar as much as an inch narrower than
the slab’s original dimension.
Finishing:
The Hot Strip Mill includes three finishing stands, which reduce the thickness of the
transfer bar down to the gauge required by the customer or the next process. The rolling
speed is set to allow the last stand to perform the final reduction at the finishing
temperature, between 850° to 1000°C, specified to reach certain mechanical properties. By
now, the steel has been rolled into a flat strip as long as 200 feet. In contrast to the
roughing mills, the finishing mills roll the transfer bar in tandem, meaning each bar will be
rolled through all three stands at once. The hot steel is quite fragile as it is rolled and
tension between the finishing mill stands must be closely controlled at very low levels in
order to avoid stretching or tearing the strip.
Coiling
The strip is passed through a pinch roll and the head end is mounted on a horizontal coiler.
The coil build up takes place until the desired weight of the coil is achieved. The coil is
conveyed on conveyors to the point of storage or use for the next process.
C) TUBE MILL
The coil as per desired width and thickness is received from the stock yard and loaded onto
decoiler. The end of the strips are sheared and butt-welded and fed into a storage cage. The
strip is passed through the forming section of the pipe mill and then into the Fin-pass
section. In this process, it gradually takes the shape of a round tube. Using the process of
High Frequency Induction Welding, the edges of the strip are heated and welded. The extra
metal on the weld seam is removed using a scarfing tool. The tube which becomes hot in
the process is cooled in the cooling chamber. The sizing section adjusts any deviation in the
shape and size of the tube as per desired levels. The tube is then cut to suitable lengths
using a circular flying saw driven by rack & pinion system. The cut-length tubes are then
conveyed to a rack where they are bundled and stored in the stock yard for dispatch.
26
D) CONTINOUS COIL GALVANIZING
Coils to be processed on either galvanizing line are charged, or loaded, onto one of two
Pay-Off Reels. The head of the coil being charged is welded to the tail of the coil being
processed by a lap seam welder. Between 1/32” and 1/4” of the two coils are over-lapped
onto one another, and a pair of high-voltage copper wheels, one above and one below, roll
from one edge to the other, melting the laps and pressing them into one another. The
resulting weld is nearly flattened to the gauge of each coil, but with a slight bulge in the
center of the seam. The voltage applied between the two dies and the speed at which they
roll across the width of the strip are pre-programmed in a computer as various recipes that
are called up according to the gauges and grades being processed.
After welding, the strip travels into the ‘Entry Loop Car’, or accumulator section, where
enough material is stored to allow the entry section to shut down for at least a minute and a
half while another coil is charged without slowing the process (annealing and zinc pot)
section. The Loop Cars for the #1 CGL travel horizontally, while the newer line employs
multi-strand, vertical accumulators.
Cleaning & Preheating
Before heat treating, the strip is cleaned of rolling oils and iron fines with rotating brushes
and diluted sodium hydroxide (caustic soap). The steel is preheated in the process section
to a relatively low temperature to further clean the strip surface and minimize the time
needed for the reducing zones to bring the steel up to its annealing temperature.
Burners in the Preheat section combust natural gas in open air to maintain zone
temperatures as high as 2250° Fahrenheit. Under normal operating conditions, the steel is
in this section for only a few seconds and never actually reaches this furnace temperature.
Producing ‘full hard’ galvanized steel requires striking a delicate balance between cleaning
the surface adequately for good zinc adherence and not sacrificing the strength desired by
the customer by allowing the steel grains to recrystallize. Costly low-carbon steel grades
with small additions of titanium are sometimes used because they anneal at relatively high
temperatures and can be thoroughly cleaned prior to coating.
Heat Treatment
Because most of feed-stock for the galvanizing lines is Full Hard from the 5-Stand, both
units incorporate processing steps to remove rolling oils, iron fines and surface oxides from
the strip to ensure good zinc adherence, and to anneal the material to achieve the
combination of formability and strength sought by the customer.
Immediately after the preheat section, the strip enters the ‘reducing zone’ where it is
annealed to achieve the customer’s physical requirements for formability in a heated
atmosphere of 1 part hydrogen, 3 parts nitrogen. The atmosphere prevents the growth of
scale during heat-treatment, actually ‘reducing’ light surface oxide back to iron. Heat is
supplied by burning natural gas inside sealed tubes above and below the strip, with the heat
produced radiating from the walls of the tubes out into the reducing zones. These zones are
27
held at temperatures up to 1650° Fahrenheit, and, under normal operating conditions, the
product is annealed for less than a minute. Thin strip at the #2 CGL may spend only 10
seconds in the reducing zones, while heavier gauges at the #1 CGL may take a couple of
minutes to reach the necessary temperature. The steel is heated to temperatures typically in
the range of 1300° to 1500° Fahrenheit.
Because the furnace is cannot achieve abrupt changes in temperature, specific limits are
placed on the scheduling of coils to ensure smooth transitions between products with
different annealing requirements. Since the annealing process depends on both time and
temperature, operators can ease the transitions by adjusting the speed of the line.
Immediately after annealing, the strip travels through cooling zones incorporating air jets
and recirculating fans before being directed down the ‘snout’ to the zinc pot. The objective
is to cool the steel to a temperature that roughly matches that of the molten zinc; too warm
and the coating’s adherence will be compromised by an overly thick zinc-iron transition
layer; too cool and the aluminum can begin to precipitate (freeze) out of the molten zinc
and get picked up by the pot roll, marking the steel.
Galvanizing
The facilities for coating steel are of the ‘hot-dip’ type, as opposed to electro-galvanizing,
which is a plating process comparable to chroming. After the steel has been thoroughly
cleaned, annealed, and cooled to a temperature that roughly matches that of the molten zinc
bath, the strip enters the zinc pot and travels around a ‘pot roll’ which redirects it up
through an ‘air knife’ system. Coating thickness is controlled by blowing off excess molten
zinc; the air pressure applied to a tapered gap in the knife lips, as well as the distance
between the knives and the strip, regulate how much zinc is carried out of the pot on the
steel’s surface. The height of the air knives above the zinc pot is adjusted according to strip
speed. Additional blow-offs called edge baffles serve to prevent the excess zinc coating
inherent to the edges from resulting in a condition called ‘edge build-up’ that causes the
coil to flare up at the sides, stretching the material to the point that it will not lay flat during
further processing.
The thickness of the zinc applied to the steel is specified by CSI’s customers as a coating
weight, in the unit of hundredths of ounces per square foot. An order for ‘G-60’ seeks 0.60
ounces of zinc on every square foot of steel, which, when evenly distributed, equates to a
coating thickness of about one-half of one thousandth of an inch (0.0005”) per surface.
Since the heavier coating weights add as much as 0.004” (for G-235) to the overall
thickness of the coated steel, aim gauges at the rolling mills provide for this so the finished
product will meet the customer’s gauge requirements. The thickness of the zinc coating is
measured with a Gamma-ray and fed back into the computer which in turn adjusts the air
knives to optimize the coating weight. Changes in required coating weight, steel thickness,
and even line speed are rapidly compensated for automatically.
28
The ‘pot’ is replenished periodically with 1-ton ingots of 99.9% pure zinc. Massive
induction heaters in the basement maintain the pot at temperatures about 50 above the 800-
degree Fahrenheit melt point of the zinc. Small additions of aluminum improve the
adherence of the zinc to the base metal by inhibiting the growth of the brittle zinc-iron
transition layer.
The strip travels more than ten stories straight up into the air out of the pot to allow time
for the zinc to solidify against the steel. Large fans in the cooling tower air-cool the freshly
coated steel before it is sent through a water-quench ‘shock roll’ tank.
Galvannealing
Products designated by an ‘A’ in their coating weight (for instance A-40) are
‘Galvannealed’, a process wherein the just-coated steel’s surfaces are immediately reheated
by open-air burners. The zinc is baked into the steel until the two are alloyed, or
metallurgically blended, with one another at the surfaces of the strip. The finished product
has a dull gray appearance due to the large proportion of iron that has diffused to the
surface.
Galvannealed product corrodes more readily than galvanized steel and is intended for end-
uses that will be painted, such as computer brackets and appliance panels. While hot-dip
galvanize must be chemically treated before painting, galvanneal does not. The alloyed
layer is relatively brittle and will tend to fracture and flake off (‘powdering’) if flexed
significantly by a paint line or roll-former.
Reheating is accomplished for this operation with a short, vertical, natural-gas furnace that
is positioned above each line’s zinc pot. Because of the limitations of these furnaces, line
speeds are slowed considerably when producing galvannealed steel and available coating
weights are normally limited to A-60 or lighter to ensure that ‘free zinc’ does not remain at
the steel’s surface.
Flatness Correction
Situated after each pay-off reel is a small uncoilerLeveler that flattens the head-end of the
steel by removing its coil-set, or memory of having been coiled up.
After the steel has been through the cooling tower and is roughly room temperature again,
it passes through a Tension Leveler much like that at the Pickle Line where the strip is
tightly worked up and down by a series of roll cassettes. Shape defects are removed from
the strip as its thickness is reduced by around one-half of one percent.
The #2 Galvanizing line includes a 4-hi skin-pass mill stand situated just in front of the
tension leveler to reduce strain marks and impart a uniform surface texture on the coated
product, subject to the customer’s specifications.
29
Final Processing
When required by the customer, a thin coat of rust inhibitor is applied to the strip as it
travels through the chem treat section after the tension leveller. A solution is squeegeed
onto both surfaces and then air-dried, inhibiting the formation of ‘white rust’ (water-stained
zinc) for six months or longer.
Just before final inspection, the product passes into the stamping area where, when
indicated on the schedule, the strip is printed periodically with the product’s specifications.
The older line uses four 16” diameter ink drums, while the #2 CGL incorporates an ink-jet
printer for improved print quality and greater flexibility.
When indicated by the customer, the strip is oiled after inspection. A spreader roll at the #1
CGL squeegees oil evenly across the top surface of the steel shortly before it is recoiled,
while the newer line uses an electrostatic oiler. Oil is less expensive than Chem Treat, but it
is not as durable and is more difficult for the customer to clean from the strip. Typically,
galvanize products that will be painted are oiled, while end-uses calling for exposed zinc
receive Chem Treat.
Inspection
Before recoiling, the strip is inspected to ensure it is dimensionally sound, and that any
surface or shape defects are acceptable, based on customer- and end-use-specific criteria.
Each line has a small laboratory used to monitor the process on an ongoing basis. Rockwell
Hardness tests are performed on each parent coil to evaluate the annealing heat treatment
and feedback is normally given to the operator in time to adjust for the next coil.
Additional tests are performed to evaluate the coating quality; weighing a sample,
chemically removing the zinc, then reweighing the coupon confirms the coating weight;
creasing a sample with a tight bend tests the adherence of the zinc to the base metal.
Periodic checks are performed to monitor the cleaner’s detergent levels, the molten zinc
bath’s aluminum and lead content, and the chem treat solution’s make-up. Tensile test
coupons to qualify Physical Quality steel are sent to the main lab for evaluation.
The finished strip is recoiled and cut to the weight required by the customer.
E) HOT DIP GALVANIZING
Hot dip galvanizing is the process of coating pipe and fitting with a layer of zinc alloy in a
bath of molten zinc at temperature around 450 °C.
As ISO 1461, ASTM A123, and EN10240, the galvanizing process has its own built-in
means of quality control because zinc does not react with an unclean steel surface. So
Surface Preparation is a critical step.
Degreasing
A hot alkali solution, mild acidic bath removes organic contaminants such as dirt, paint
markings, grease, and oil from the metal surface.
Pickling
30
A dilute solution by heated sulfuric acid or ambient hydrochloric acid, removes mill scale
and iron oxides (rust) from the steel surface.
Figure 2.10-1 : Galvanized Sheets
Fluxing
A zinc ammonium chloride solution, removes any remaining oxides and deposits a
protective layer prior to dip steel in bath.
According to ISO 1461, zinc coating thickness follows below form:
Steel
thickness
mm
Local coating
thickness
(minimum)
μm
Average coating
thickness
(minimum)
μm
Average coating
mass
(minimum)
g/m²
steel >6 70 85 610
3< steel ≤6 55 70 505
1.5≤ steel ≤3 45 55 395
steel <1.5 35 45 325
31
3 SITE DETAILS
3.1 General
The anthropogenic activities specifically related to industrial sector are expected to cause
impacts on environmental quality in and around the project location. However, the intensity
of environmental impacts from a specific project depends on several factors such as type of
process physical, chemical, fuel combustion etc. involved in the project, processing
capacity (scale/size of the project), type and extent of pollution control measures, project
location surrounding geomorphology etc. To assess environmental impacts from proposed
expansion project at a specific location, it is essential to monitor the environmental quality
prevailing in the surrounding area prior to implementation of the proposed expansion. The
environmental status within the study zone is used for identification of significant
environmental issues to be addressed in the impact assessment study. The impacts from an
existing industrial project on its surrounding environment are mainly regulated by the
nature of pollutants, their quantities discharged to the environment, existing environmental
quality, assimilative capacity of the surrounding environment and topography and terrain of
the project site (its location) as well as the surrounding area.
3.2 Location of the project
M/S Mahalakshmi Profiles Pvt. Ltd.is situated on Latitude 17° 8' 53.48"N and Longitude
78°13'38.28"E. Location map is given in Fig 3-1. The existing land area of the unit is
29338.28 Sq. m.
The expansion will take place in the existing unit by installing six more additional
induction furnace of capacity 12 T capacity. The proposed installation will take place in the
existing shed area. Thus, the land use of the site will not change after expansion.
Project site is near to Kallakal village. It is located 49 KM towards East from District
headquarters Sangareddi. 14 KM from Tupran. Jeedipalle ( 5 KM ) , Kothur ( 6 KM ) ,
Muppireddipally ( 6 KM ) , Rangaipalle ( 6 KM ) , Sikindlapur ( 7 KM ) are the nearby
Villages to Kallakal. Kallakal is surrounded by Tupran Mandal towards North, Shivampet
Mandal towards North , Wargal Mandal towards East , Mulug Mandal towards East .
Hyderabad , Sangareddy , Medak , Singapur are the near by Cities to Kallakal.
Hyderabad is the Nearest Town to Kallakal. Hyderabad is 38 km from Kallakal. Road
connectivity is there from Hyderabad to Kallakal. Kuchavaram Rail Way Station , Dabilpur
Rail Way Station are the very nearby railway stations to Kallakal.
3.3 Site Selection
The Proposed project is expansion project so no alternative sites are considered.
3.4 Topography
The topography of the area is plain. Study area has been taken as 10 km radius around the
project site. Map showing study area of the project on 1:50,000 scale of Topo Sheet No 56
32
K /5, 6,9, 10 of the survey of India map is given in Fig 3-2. No National Parks/ Wildlife
Sanctuaries/ Biosphere Reserves exist within 10 km radius of project site.
3.5 Coordinates of the land plot
The 26 corners of Mahalakshmi Profiles Pvt. Ltd. are shown in Fig 3-3 on Google
Imagery. Figure 3-4 shows the layout of the plant site.
Figure 3.5-1: Location Map
33
Figure 3.5-2: Topography Map of the Project Site
Figure 3.5-3: Google Imagery with Latitude and Longitude of the Corners
34
Table 3.5-1: Coordinates of Mahalakshmi Profiles Pvt. Ltd.
S. NO. LATITUDE LONGITUDE
1. 17°42'3.22"N 78°29'1.19"E
2. 17°41'57.66"N 78°29'0.91"E
3. 17°41'57.60"N 78°28'55.80"E
4. 17°41'52.50"N 78°28'55.60"E
5. 17°41'52.50"N 78°28'55.40"E
6. 17°41'54.20"N 78°28'50.00"E
7. 17°41'54.20"N 78°28'49.60"E
8. 17°41'54.10"N 78°28'49.10"E
9. 17°41'55.30"N 78°28'48.80"E
10. 17°41'55.40"N 78°28'49.40"E
11. 17°41'56.60"N 78°28'49.40"E
12. 17°41'56.70"N 78°28'49.60"E
13. 17°41'56.90"N 78°28'49.70"E
14. 17°41'56.60"N 78°28'47.00"E
15. 17°41'56.50"N 78°28'47.00"E
16. 17°41'55.90"N 78°28'42.00"E
17. 17°41'56.20"N 78°28'41.90"E
18. 17°41'56.80"N 78°28'46.70"E
19. 17°41'57.60"N 78°28'46.70"E
20. 17°41'57.50"N 78°28'48.20"
21. 17°42'0.80"N 78°28'48.50"E
22. 17°42'0.70"N 78°28'50.60"E
23. 17°42'2.00"N 78°28'50.90"E
24. 17°42'2.30"N 78°28'56.20"E
25. 17°42'2.20"N 78°28'56.20"E
26. 17°42'2.79"N 78°29'0.25"E
35
Figure 3.5-4: Plant Layout after Expansion
36
3.6 Industries within 10 km Radius of Plant
Figure 58-5: Location Water Industries in 10 km Range of the Project Site
3.7 Geo-Hydrological Status
In Medak district there are two major hill ranges-one extending from Ramayampet in the
North to Tupran in the south, other from Narayankhed in the northwest to the Gajwel in the
east in the district. Precambrian rocks, such as, granite adamellite, tonalite, amphibolites,
hornblende biotite schist occupy a major part of the district. These formations were
subjected to tectonism and greenschist facies metamorphism. Except for a portion in the
western part of the district, most of the area is occupied by granites. Based on mineral
composition they were further classified as alkali feldspar granite, migmatite granite
gneiss, adamellite, granodiorite, tonalite and trondjhemite. A few patches of amphibolites
and pyroxene granulites are seen around Siddipet.
All these rock formations are traversed by NE-SW and N-S trending dolerite dukes and
vein quartz. The area experienced volcanism at the time of eruption of the Deccan Traps.
The Deccan Traps and intertrappeans are seen north and west of Jogipet, extending upto
the northern and western border of the district. A small portion of Deccan Traps is seen
37
south of Sangareddy. The laterite cappings are seen extensively around Zahirabad. Two
major lineaments trending E-W and N-S appear to cross each other between Medak and
Narsapur; the N-S lineament is also in part occupied by dyke rocks. There are two major
dykes one in central part, trending in N-S direction, the other one encountered at
Kowdipally trending in a NE-SW direction.
The Medak district is covered by hard rock except for 0.2% of the alluvium area. Ground
water occurs under unconfined to confined conditions in hard rock (Archaean and Deccan
traps ages) and recent alluvial formations. The common ground water abstraction structures
are dug wells, dug-cum-bore wells and bore wells and their yields mainly depending on the
recharge conditions in the area. Yield potential of the aquifers in the consolidated rocks
varies widely from 3 to 7 lps. Due to indiscriminate drilling of bore wells, the yields have
fallen drastically, lack of recharge to fracture confined aquifer and existing bore wells
becoming to defunct and even leading to failure. Ground water is one of the important
sources both for domestic and irrigation purposes in the District and is being exploited
through large diameter dug wells, dug-cum bore wells and bore wells. In the Archaeans,
ground water occurs under phreatic conditions, but it is desaturated and under semi-
confined conditions in the fractured zones. Figure 3-6 shows the drainage pattern around 10
km zone of the site.
Figure 3-6: Direction of Drainage in the Project area
38
3.8 Land Use
Land use in the 10 km radius around the project is studied from the proposed land use
zoning of Hyderabad for the year 2031 as in Figure 3-7. The project site falls within the
Metropolitan and various Land uses are mentioned. The plot falls under category of Pre
Urban Land use. The land was purchased by the project proponent and was converted by
the Revenue Divisional Officer Medak District for non-Agricultural use as in Annexure
3.1. The land use pattern within plant area is shown in Figure 3-8.
Figure 3-7: Land Use Zoning of Metropolitan Hyderabad -2031
Figure 3-8: Land Use Pattern within plant area
39
4 BASELINE ENVIRONMENT STATUS
4.1 General
This section describes the existing environmental baseline of the study area around the
project. It includes relevant components of physical, biological and socio- economic
environment.
The purposes of describing the environmental settings of the study area are:
• To understand the project needs and environmental characteristics of the area; and
• To assess the quality of the existing environment, as well as the
environmental impacts of the future developments being studied.
The baseline environment for the EIA was studied through primary survey, information
collected from secondary sources and discussion with local stakeholders.
The baseline environmental scenario of the study area was monitored during October to
December season 2018 and is carried out for 10 km radius from the plant site.
4.2 Methodology
4.3 Study Area
Project Influence Area (PIA): In accordance with MoEF&CC’s EIA Guidelines Manual
for industry and as per guidelines of EIA Notification-2006, the Project Influence Area has
been defined as 10 km Arial radius from boundary of Plant. Collection of secondary
data, including likely i m p ac t s due to other activities like, material storage, disposal
areas, etc. are done within this influence area.
4.4 Environmental Surveys and Studies
The baseline information on physical, chemical, biological, social and economic aspects
of the project area is the most important reference for conducting environmental impact
assessment studies. Thus, for conducting EIA, existing environmental conditions around
the project have been obtained by primary data collection, monitoring, sampling and
secondary data collection from published source and various government agencies. The
primary studies focused on the Project Influence Area but the sensitivities in the project
influence area have been collected through secondary literature.
To assess the baseline environmental status of the Project Influence Area, monitoring of
40
various environmental attributes were conducted by the consultants during February to
April 2019. Primary data for ambient air quality, ambient noise status, water quality
(Ground and surface) and soil quality was generated through NABL approved laboratory.
4.5 Physical Environment
4.6 Geomorphology
The present day landforms in the district are the products of different geomorphic
processes such as erosion, deposition, crustal movements coupled with climatic changes
operating on the surface. The specific geomorphic groups are (i) Residual hills (ii) Plateau
(Deccan traps) (iii) Pediment Inselberg complex (iv) Pediplain and (v) Flood plain.
i) Residual Hills: These geomorphic forms occur as massive hills comprising of
forest areas in Kulakacherla, Manchal and in Yacharam mandals with a maximum
elevation of 691 m amsl. The residual hills occurring around Ghatkesar,
Shamirpet and Rajendernagar mandals , the soil cover is thin and devoid of
vegetation except with low trees, thorny bushes and shrubs. Other forms in the
area include Mesa/Butt, having flat topped hills comprising of laterite and basalts.
ii) Plateau (Deccan traps): This geomorphic unit is characterized by elevated uplands
with steep slope and dissected by deep and narrow valleys occupied by different
flows.
iii) Pediment Inselberg Complex: Pediment inselberg complex is a gently undulating
plain abounding with a number of small hills, mounds, tors etc.
iv) Pediplain: Pediplains are characterized by flat or gentle sloping surface which is
the end product of coalescence of several pediments at the foot of hill slopes.
Pediplains are characterized by the vast area of low lying flat terrain with gentle
slopes covered by red brown and black clayey soils ranging in thickness from 20
cm to 60 cm.
v) Flood plain: Alluvial deposits occur along major river courses mostly derived
from catchments, transported and deposited.
4.7 Drainage
Manjira, a tributary of River Godavari is an important drainage flowing in the district. The
important Nizam Sagar dam is constructed on this river. The other important streams are
Haldi and Kudalair flow in the Eastern half of the district.
4.8 Irrigation
The chief sources of irrigation in the district are tanks, wells and canals. The major
irrigation projects are shown in Table below:
41
Table 4.8-1: Irrigation Projects in the District
4.9 Geology
The rock formation in the district is of the oldest type (Archaen gneisses) and consists
principally of Peninsular granite complex i.e. pink and grey granites and their metamorphic
variations. Minor inliers of Dharwar rocks occur as narrow bands in the granite and
consists of horn blend schists, chlorite schists and banded or massive ferruginous
quartzites. A few such exposures are seen due North and North-East of Siddipet. A part of
the Sangareddy taluk in the South-West of the district is covered by the Deccan traps
(Basalt flows) formation.
4.10 Climate & Meteorology
Climate: Medak district is situated at a considerable distance from the sea-coast, the
climate is tropical and is characterized by hot summer and dry except during the South-
west monsoon season. As per the climate conditions of the district, the year may be divided
into four seasons. The hot (summer) season is from March to May. From March onwards
the temperature continues to rise and May is generally the hottest month in the year. The
period from June to September constitute the South-west monsoon (SW rainy) season,
while October and November form the post monsoon (NE rainy) season. The cold (winter)
season is from December to February.
Winds: Winds are generally light to moderate with some increase in force during May and
South-west monsoon season. During the post-monsoon season winds are very light and
variable in direction in the mornings and mostly North-eastern in the afternoons. During
the latter half of the cold season and in March and April morning, winds continue to be
light and variable in direction, while the afternoon winds are being mostly Eastern to
South-western. Winds from Western direction begin to blow from May and in the South-
west monsoon season; winds are mainly from Western to North-western direction.
42
Temperature: The days are intensively very hot and on individual days the temperature
may go up to about 46°C. The maximum temperature of 45.3°C during the decade is
recorded during the year 2001 in the hottest month of May. With advance of South-west
monsoon by about middle of June there is an appreciable drop in temperature. By October
the day temperature begins to increase slightly, but the night temperature steadily
decreases. After November, both day and night temperature decreases rapidly.
Rainfall: Most of the rainfall is by the South-west monsoon with a normal rainfall of 680
mm; followed by the North-east monsoon with a normal rainfall of 133 mm. Rainiest
month is July. The least normal rainfall of 10 mm is from the winter season; followed by
50 mm of normal rainfall from hot weather season. During the later part of summer and
post monsoon season, the rainfall is sometimes in the form of thunder showers. The
maximum of 896 mm rainfall is recorded during the year 2005-2006 as against the normal
rainfall of 873 mm with a rainfall variation of 2.63 % on the positive side (an increase of
23 mm of rainfall). However, the total rainfall recorded during the decade is 7,160 mm as
against the normal rainfall of 8,730 mm; giving rise to a rainfall variation of -17.98 % on
the negative side (a reduction of 1570 mm of rainfall).
Figure 4-1: Wind Rose at the Project Site
The predominant wind directions are mainly from Western to North-western direction.
sector accounting to about 7.45 % of the total time with calm winds of less than 1.0 kmph
for about 5.80 % Wind speeds during this period were varying between 2.5-12 kmph and
during some of the times the wind speed was recorded more than 12 kmph. The summary
of the wind pattern is given below:
Table 4.10-2: Wind Speed and Direction
43
4.11 Test Methodology for Environmental Monitoring & Testing
Table 4.11-3: Sampling Methodology
S.NO Parameter Methodology Equipment used
1. Particulate Matter
( PM2.5 and PM10)
Collection of Particulate
Matters on Filter Papers
Fine Particulate Matter
Sampler and Respirable
Dust Sampler
2. Sulphur Dioxide
(SO2)
Absorption of Gases in
Liquid Absorbent
RDS with Gaseous
Sampling Attachment
3. Oxides of Nitrogen
(NOX)
Absorption of Gases in
Liquid Absorbent
RDS with Gaseous
Sampling Attachment
4. Carbon Monoxide
(CO) Detection Method CO Meter
5. Noise Instrumental Method Noise Meter with Data
Logger
Analysis
S. NO Parameter Methodology Equipment used
1. Particulate Matter
( PM2.5 and PM10) Gravimetric Method Analytical Balance
2. Sulphur Dioxide
(SO2)
Improved West and
Gaeke Method
UV/VIS
Spectrophotometer
3. Oxides of Nitrogen
(NOX)
Modified Jacob &
Hochheiser (Na-
arsenite) Method
UV/VIS
Spectrophotometer
4.12 Ambient Air Quality
4.12.1 Monitoring Location
Eight locations were selected for ambient air quality monitoring in and around
Mahalakshmi Profiles Pvt. Ltd.as in Figure 4.5 and Table 4.3. Monitoring was done for 24
hours twice a week for ambient air and noise quality at each location. The baseline status of
44
the air quality in the study area was assessed though a scientifically designed ambient air
quality monitoring network. The selection of monitoring network was based on the
following aspects:
Topography / terrain of the study are,
Populated area within the study area,
Residential and sensitive areas within the study area,
Magnitude of the surrounding industries,
Representation of regional background levels,
Representation of cross sectional distribution in downward direction.
Table 4.12-4: Sampling Locations
Station
Code
Name of the
Station
Latitude Longitude Distance
w.r.t.
site (km)
Direction Environmental
Setting
AAQ1 Project Area 170 41' 54.34" 780 29 '4.82" - - Mixed Area AAQ2 Banda Mailaram 170 41' 53.43" 780 30 '21.00" 1.3 S-SW Cross wind AAQ3 Baswapur 170 42' 20.36" 780 32 '31.57" 6.4 E Cross wind AAQ4 Rawalkole 170 39' 29.53" 78 0 30' 26.20" 4.22 SE Down wind AAQ5 Medchal 170 37' 15.77" 78 0 28' 54.6" 1.8 SW-W Down wind AAQ6 Nuthankal 170 41' 21.95" 780 26' 56.56" 5.7 S-SW Cross wind AAQ7 Sikindlapur 170 44' 6.62" 780 25' 31.62" 5.8 NE-E Cross wind AAQ8 Koochavaram 17 0 43 '47.69" 780 28' 12.52" 9.3 S Cross wind
Source: Primary Surveys
Figure 4.12-2: Ambient Air Monitoring Locations
45
Table 4.12-5: Air Quality Monitoring Data
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name :Project Site (AAQ1) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February-2019
04.02.2019 88 36 25 21.0 0.81 1.49 0.72
07.02.2019 65 30 11 19.5 0.92 1.46 0.76
11.02.2019 83 38 14 20.7 0.85 1.49 0.74
14.02.2019 73 33 12 18.5 0.96 1.51 0.78
18.02.2019 69 32 12 23.1 0.82 1.54 0.76
21.02.2019 77 35 13 21.4 0.80 1.48 0.72
25.02.2019 57 26 10 18.6 0.83 1.44 0.73
28.02.2019 61 28 10 20.4 0.90 1.42 0.79
March-2019
04.03.2019 88 36 25 10 0.92 1.53 0.78
07.03.2019 67 27 14 8 0.96 1.59 0.80
11.03.2019 85 40 21 12 0.82 1.55 0.75
14.03.2019 75 30 15 9 0.85 1.59 0.78
18.03.2019 71 28 15 8 0.90 1.60 0.76
21.03.2019 79 32 16 9 0.98 1.66 0.80
25.03.2019 58 23 12 7 0.86 1.63 0.79
28.03.2019 62 25 13 7 0.80 1.61 0.71
April-2019
01.04.2019 90 36 18 10 0.90 1.70 0.79
04.04.2019 72 29 15 8 0.98 1.78 0.82
08.04.2019 92 37 19 11 0.92 1.65 0.80
11.04.2019 81 32 17 9 0.84 1.80 0.76
15.04.2019 76 31 16 9 0.99 1.72 0.82
18.04.2019 85 34 18 10 0.90 1.85 0.81
22.04.2019 63 25 13 7 0.85 1.76 0.80
25.04.2019 67 27 14 8 0.83 1.70 0.78
Mean 74 31 15 8 0.99 1.85 0.82
Minimum 57 23 10 5 0.80 1.42 0.70
Maximum 92 40 25 12 0.81 1.61 0.77
98th percentile 91 39 25 11 0.81 1.47 0.72
46
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Banda Mailaram ( AAQ2 ) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February -2019
04.02.2019 64 26 12 9 0.85 1.52 0.70
07.02.2019 98 29 22 8 0.79 1.46 0.65
11.02.2019 72 29 14 11 0.92 1.63 0.80
14.02.2019 68 27 13 10 0.86 1.40 0.72
18.02.2019 76 31 15 11 0.90 1.58 0.78
21.02.2019 56 23 11 8 0.87 1.42 0.62
25.02.2019 60 24 11 9 0.76 1.65 0.66
28.02.2019 87 35 17 13 0.80 1.43 0.60
March-2019
04.03.2019 69 28 13 10 0.90 1.80 0.72
07.03.2019 97 32 23 11 0.81 1.62 0.68
11.03.2019 78 31 15 11 0.98 1.78 0.76
14.03.2019 74 30 14 11 0.85 1.69 0.70
18.03.2019 83 33 16 12 0.80 1.53 0.65
21.03.2019 61 24 12 9 0.81 1.62 0.62
25.03.2019 65 26 12 10 0.92 1.69 0.73
28.03.2019 86 34 19 13 0.96 1.71 0.78
April-2019
01.04.2019 69 27 16 10 0.98 1.71 0.80
04.04.2019 93 41 23 15 0.92 1.68 0.76
08.04.2019 77 31 17 11 0.78 1.86 0.69
11.04.2019 73 29 17 11 0.89 1.79 0.70
15.04.2019 81 33 18 12 0.82 1.92 0.66
18.04.2019 60 24 14 9 0.93 1.86 0.75
22.04.2019 64 26 15 10 0.86 1.69 0.72
25.04.2019 98 42 20 13 0.99 1.85 0.85
Mean 75 29 16 11 0.99 1.92 0.85
Minimum 56 21 11 8 0.76 1.40 0.60
Maximum 98 36 23 15 0.81 1.66 0.71
98th percentile 98 35 23 14 0.79 1.44 0.62
47
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Baswapur ( AAQ3) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February -2019
04.02.2019 96 37 18 13 0.86 1.58 0.70
07.02.2019 85 28 20 17 0.79 1.52 0.68
11.02.2019 94 37 16 12 0.93 1.66 0.73
14.02.2019 80 30 14 11 0.78 1.50 0.62
18.02.2019 91 35 19 8 0.94 1.69 0.71
21.02.2019 95 38 18 12 0.87 1.59 0.68
25.02.2019 92 32 19 9 0.75 1.49 0.60
28.02.2019 83 29 13 8 0.81 1.51 0.65
March-2019
04.03.2019 90 28 11 10 0.90 1.75 0.74
07.03.2019 85 29 22 8 0.99 1.64 0.81
11.03.2019 98 37 19 10 0.85 1.90 0.72
14.03.2019 89 30 15 11 0.78 1.79 0.65
18.03.2019 75 20 16 9 0.82 1.68 0.68
21.03.2019 89 38 13 8 0.95 1.86 0.76
25.03.2019 91 32 17 12 0.79 1.78 0.65
28.03.2019 83 22 16 13 0.91 1.84 0.78
April-2019
01.04.2019 93 37 21 14 0.98 1.84 0.95
04.04.2019 74 30 17 11 0.96 1.97 0.73
08.04.2019 95 38 21 14 0.85 1.86 0.61
11.04.2019 83 33 19 12 1.05 1.90 0.82
15.04.2019 79 31 18 12 0.89 1.78 0.70
18.04.2019 88 35 20 13 0.96 1.86 0.69
22.04.2019 65 26 15 10 1.10 1.99 0.81
25.04.2019 69 28 16 10 0.98 1.81 0.72
Mean 86 32 17 11 1.10 1.99 0.95
Minimum 65 20 11 8 0.75 1.49 0.60
Maximum 98 38 22 17 0.90 1.74 0.72
98th percentile 97 38 22 16 0.78 1.51 0.63
48
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Ravalkole (AAQ 4) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February-2019
04.02.2019 81 33 16 11 0.83 1.42 0.68
07.02.2019 65 26 13 9 0.85 1.36 0.72
11.02.2019 98 39 19 13 0.98 1.56 0.80
14.02.2019 73 29 15 10 0.90 1.48 0.78
18.02.2019 69 28 14 9 0.82 1.55 0.70
21.02.2019 77 31 15 10 0.80 1.46 0.68
25.02.2019 57 23 11 8 0.86 1.58 0.71
28.02.2019 61 24 12 8 0.81 1.54 0.74
March-2019
04.03.2019 88 35 17 12 0.96 1.65 0.79
07.03.2019 99 41 27 9 0.89 1.48 0.70
11.03.2019 90 36 18 12 0.99 1.62 0.78
14.03.2019 79 32 16 11 0.86 1.56 0.72
18.03.2019 75 30 15 10 1.01 1.60 0.82
21.03.2019 83 33 17 11 0.98 1.44 0.80
25.03.2019 61 25 12 8 0.96 1.59 0.77
28.03.2019 66 26 13 9 0.81 1.48 0.69
April-2019
01.04.2019 75 34 13 6 0.99 1.80 0.74
04.04.2019 60 28 10 5 1.02 1.64 0.80
08.04.2019 90 41 15 8 0.94 1.73 0.72
11.04.2019 67 31 12 6 0.85 1.82 0.68
15.04.2019 64 29 11 5 0.90 1.68 0.75
18.04.2019 71 33 12 6 0.82 1.76 0.70
22.04.2019 52 24 9 4 0.96 1.69 0.80
25.04.2019 56 26 10 5 1.02 1.80 0.82
Mean 73 30 14 8 1.02 1.82 0.82
Minimum 52 23 9 4 0.80 1.36 0.68
Maximum 99 37 19 13 0.92 1.59 0.75
98th percentile 98 36 19 13 0.82 1.45 0.68
49
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Medchal (AAQ 5) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February-2019
04.02.2019 97 35 17 8 0.98 1.68 0.75
07.02.2019 84 26 18 10 1.05 1.80 0.82
11.02.2019 88 29 15 4 0.89 1.58 0.70
14.02.2019 81 34 20 7 0.96 1.60 0.76
18.02.2019 95 35 18 8 1.10 1.86 0.86
21.02.2019 73 22 16 5 0.99 1.69 0.80
25.02.2019 90 38 20 8 1.08 1.80 0.92
28.02.2019 88 28 14 8 0.96 1.62 0.85
March-2019
04.03.2019 85 30 16 6 1.08 1.71 0.99
07.03.2019 92 32 18 7 0.98 1.58 0.82
11.03.2019 87 21 11 9 1.12 1.78 0.70
14.03.2019 91 37 15 9 1.06 1.72 0.87
18.03.2019 84 23 7 9 0.99 1.58 0.77
21.03.2019 81 26 19 9 0.90 1.46 0.72
25.03.2019 78 22 15 11 0.92 1.49 0.77
28.03.2019 89 31 11 6 1.01 1.71 0.86
April-2019
01.04.2019 85 33 15 11 1.05 1.66 0.90
04.04.2019 75 25 17 8 1.13 1.80 0.95
08.04.2019 90 35 16 7 0.99 1.65 0.78
11.04.2019 80 24 18 12 1.02 1.78 0.82
15.04.2019 84 26 19 9 0.96 1.60 0.74
18.04.2019 93 28 16 9 1.06 1.86 0.86
22.04.2019 76 20 19 5 0.94 1.69 0.70
25.04.2019 89 32 15 7 1.00 1.83 0.80
Mean 86 29 16 8 1.13 1.86 0.99
Minimum 73 20 7 4 0.89 1.46 0.70
Maximum 97 38 20 12 1.01 1.69 0.79
98th percentile 96 37 20 11 0.91 1.58 0.68
50
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Nuthankal(AAQ 6) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February-2019
04.02.2019 77 24 20 7 0.86 1.68 0.65
07.02.2019 97 37 16 11 0.79 1.56 0.60
11.02.2019 84 24 18 10 0.93 1.73 0.72
14.02.2019 80 20 16 6 0.78 1.52 0.61
18.02.2019 90 30 13 11 0.94 1.72 0.75
21.02.2019 94 38 15 9 0.87 1.68 0.68
25.02.2019 99 33 13 8 0.75 1.59 0.60
28.02.2019 89 26 11 5 0.81 1.67 0.62
March-2019
04.03.2019 96 38 18 12 0.82 1.70 0.63
07.03.2019 93 29 19 11 0.80 1.62 0.60
11.03.2019 82 37 16 10 0.91 1.78 0.72
14.03.2019 72 23 13 8 0.85 1.66 0.68
18.03.2019 98 33 12 11 0.96 1.78 0.77
21.03.2019 89 29 20 7 0.81 1.66 0.72
25.03.2019 84 22 14 8 0.80 1.65 0.64
28.03.2019 86 21 16 11 0.93 1.79 0.76
April-2019
01.04.2019 78 24 18 6 0.99 1.70 0.78
04.04.2019 84 28 20 10 0.86 1.65 0.62
08.04.2019 90 34 15 7 0.92 1.69 0.72
11.04.2019 91 37 20 10 0.89 1.66 0.70
15.04.2019 79 27 11 4 1.04 1.75 0.80
18.04.2019 89 33 12 7 1.15 1.90 0.86
22.04.2019 78 36 14 10 1.06 1.86 0.82
25.04.2019 81 27 16 9 1.02 1.79 0.79
Mean 87 30 16 9 1.15 1.90 0.86
Minimum 72 20 11 4 0.75 1.52 0.60
Maximum 99 38 20 12 0.91 1.70 0.70
98th percentile 98 38 20 12 0.79 1.60 0.60
51
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Sikindlapur(AAQ 7) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February-2019
04.02.2019 66 36 20 7 0.86 1.66 0.72
07.02.2019 98 37 19 9 0.83 1.58 0.69
11.02.2019 88 32 22 4 0.92 1.76 0.79
14.02.2019 78 35 18 8 0.79 1.54 0.68
18.02.2019 75 31 16 8 0.90 1.72 0.75
21.02.2019 90 38 19 5 0.87 1.58 0.70
25.02.2019 97 30 12 8 0.83 1.60 0.66
28.02.2019 94 34 20 8 0.90 1.75 0.74
March-2019
04.03.2019 77 22 15 6 0.92 1.68 0.76
07.03.2019 98 29 17 11 0.98 1.79 0.80
11.03.2019 82 24 12 8 0.86 1.58 0.72
14.03.2019 68 20 18 10 0.92 1.72 0.74
18.03.2019 85 32 9 9 0.81 1.58 0.70
21.03.2019 80 28 20 9 0.86 1.50 0.65
25.03.2019 87 30 18 7 0.78 1.49 0.60
28.03.2019 91 33 13 10 0.81 1.56 0.72
April-2019
01.04.2019 86 24 17 10 0.98 1.65 0.79
04.04.2019 77 21 14 4 0.86 1.53 0.68
08.04.2019 97 36 19 7 1.04 1.79 0.89
11.04.2019 91 31 22 12 0.95 1.68 0.76
15.04.2019 78 27 21 11 0.89 1.60 0.65
18.04.2019 67 34 16 9 0.96 1.68 0.78
22.04.2019 90 33 22 10 1.10 1.85 0.92
25.04.2019 84 28 16 7 1.00 1.72 0.81
Mean 84 30 17 8 1.10 1.85 0.92
Minimum 66 20 9 4 0.78 1.49 0.60
Maximum 98 38 22 12 0.90 1.65 0.73
98th percentile 98 38 22 11 0.80 1.53 0.65
52
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
Location Name : Koochavaram(AAQ 8) Sampling Duration 24 hrs period
Date PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
µg/m3
I II III
Standards 100.0 60.0 80.0 80.0
February-2019
04.02.2019 92 38 18 7 0.82 1.42 0.68
07. 02.2019 94 36 16 11 0.81 1.58 0.72
11. 02.2019 85 31 13 10 0.90 1.52 0.78
14. 02.2019 62 23 15 6 0.92 1.40 0.76
18. 02.2019 87 26 15 12 0.80 1.42 0.72
21. 02.2019 98 38 18 10 0.86 1.50 0.70
25. 02.2019 86 28 20 10 0.78 1.62 0.68
28. 02.2019 80 36 24 13 0.81 1.43 0.74
March-2019
04.03.2019 90 39 10 8 0.86 1.64 0.74
07.03.2019 91 29 14 10 0.94 1.70 0.80
11.03.2019 96 34 18 13 0.98 1.62 0.79
14.03.2019 73 25 13 8 0.92 1.69 0.70
18.03.2019 95 30 15 11 0.90 1.72 0.68
21.03.2019 78 23 13 7 0.99 1.80 0.80
25.03.2019 90 25 18 9 0.96 1.64 0.79
28.03.2019 95 22 17 12 0.93 1.68 0.78
April-2019
01.04.2019 89 20 15 6 0.96 1.78 0.82
04.04.2019 97 34 21 11 0.98 1.86 0.84
08.04.2019 90 31 14 7 0.89 1.79 0.78
11.04.2019 98 28 21 10 0.94 1.82 0.80
15.04.2019 85 30 13 4 0.92 1.72 0.79
18.04.2019 99 35 24 7 0.97 1.86 0.86
22.04.2019 88 26 24 12 0.98 1.90 0.82
25.04.2019 91 34 22 14 0.94 1.85 0.89
Mean 89 30 17 10 0.99 1.90 0.89
Minimum 62 20 10 4 0.78 1.40 0.68
Maximum 99 39 24 14 0.91 1.66 0.77
98th percentile 99 39 24 14 0.84 1.42 0.69
Table 4.12-6: Results of Ambient Air Quality Monitoring (Maximum)
Name of the
Station PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
Project Area 92 40 25 12 1.61
Banda Mailaram 98 36 23 15 1.66
Baswapur 98 38 22 17 1.74
Rawalkole 99 37 19 13 1.59
Medchal 97 38 20 12 1.69
Nuthankal 99 38 20 12 1.70
Sikindlapur 98 38 22 12 1.65
53
Koochavaram 99 39 24 14 1.66
The results indicate that the results are within the standards specified in the NAAQS.
4.13 Ambient Noise Quality
The physical description of sound concerns its loudness as a function of frequency. Noise
in general is sound, which is composed of many frequency components of various types of
loudness distributed over the audible frequency range. The most common and universally
accepted scale is the A weighted scale, which is measured as dB (A). This is more suitable
for audible range of 20 to 20,000 Hz. The scale has been designed to weigh various
components of noise according to the response of human ear. The environmental impact of
noise can have several effects varying from Noise Induced Hearing Loss (NIHL) to
annoyance depending on loudness of noise.
4.13.1.1 Instrument Used for Sampling and Monitoring
The main objective of noise monitoring in the study area is to establish the baseline noise
levels, which was used to assess the impact of the total noise generated by the proposed
project activities. Noise level monitoring was carried out continuously for 24 - hours with
one-hour interval at each location using Sound level meter (HTC made in Taiwan Model
No. SL-1350) capable of measuring the Sound Pressure Level (SPL) in dB (A). Hourly Leq
values were computed by the noise integrating sound level meter and statistical analysis
was done for measured noise levels at 8 locations in the study area. The Leq day, and Leq
night calculated for various locations in the area are presented below which are compared
with the standards prescribed by CPCB for various zones.
4.13.1.2 Monitoring Locations
Noise at different generating sources has been identified based on the residential, industrial
and commercial activities in the area. The noise monitoring has been conducted for
determination of noise levels at eight locations in the study area. The noise levels at each
location were recorded for 24-hr.
Table 4.13-7: Sampling Locations
Station
Code
Name of the
Station
Latitude Longitude Distance
w.r.t.
site (km)
Direction Environmental
Setting
N1 Project Area 170 41' 54.34" 780 29 '4.82" - - Mixed Area N2 Banda
Mailaram
170 41' 53.43" 780 30 '21.00" 1.3 S-SW Cross wind
N3 Baswapur 170 42' 20.36" 780 32 '31.57" 6.4 E Cross wind N4 Rawalkole 170 39'
29.53"
78 0 30' 26.20" 4.22 SE Down wind
N5 Medchal 170 37'
15.77"
78 0 28' 54.6" 1.8 SW-W Downwind
N6 Nuthankal 170 41'
21.95"
780 26' 56.56" 5.7 S-SW Cross wind
N7 Sikindlapur 170 44' 6.62" 780 25' 31.62" 5.8 NE-E Cross wind
N8 Koochavaram 17 0 43
'47.69"
780 28' 12.52" 9.3 S Cross wind
54
Figure 4.13-3: Noise Monitoring Locations
Table 4.13-8: Monitoring Results
Project Name : Mahalakshmi Profiles Pvt. Ltd. Date: 04.04.2019
Time
Project Site N-1
Banda
Mailaram
N-2
Baswapur
N-3
Ravalkole
N-4
Medchal
N-5
Nuthankal
N-6
Skindlapur
N-7
Koochavara
m
N-8
6 AM 67.6 54.5 51.2 46.8 52.2 50.1 48.3 48.1
7 AM 69.7 57.5 52.6 49.3 54.1 49.3 51.9 48.9
8 AM 56.3 56.1 53.4 52.2 56.2 51.6 52.3 49.4
9 AM 57.8 58.2 56.7 54.3 57.6 53.1 53.3 50.4
10 AM 58.4 59.1 57.5 53.3 56.3 52.8 56.3 52.1
11 AM 59.2 60.5 59.1 55.3 57.8 53.7 57.2 52.8
12 Noon 58.1 58.6 59.4 54.3 58.4 54.2 58.3 53.2
13 PM 57.7 57.5 58.2 46.3 59.2 54.9 57.3 53.9
14 PM 58.9 59.8 59.8 54.2 58.1 55.1 56.8 54.1
15 PM 56.4 58.7 58.7 55.2 57.7 55.5 58.6 54.9
16 PM 58.4 57.7 57.6 56.6 58.9 56.2 57.8 55.5
17 PM 56.3 57.7 57.9 55.3 56.4 56.7 56.9 56.3
18 PM 57.8 58.9 58.4 53.5 58.4 54.1 57.8 56.7
55
Project Name : Mahalakshmi Profiles Pvt. Ltd. Date: 04.04.2019
Time
Project Site N-1
Banda
Mailaram
N-2
Baswapur
N-3
Ravalkole
N-4
Medchal
N-5
Nuthankal
N-6
Skindlapur
N-7
Koochavara
m
N-8
19 PM 58.4 57.5 59.2 52.1 55.1 55.2 56.6 55.2
20 PM 69.8 55.9 56.4 49.2 54.3 49.5 54.6 52.3
21 PM 68.8 53.1 54.6 47.9 52.9 48.2 53.6 50.1
22 PM 68.0 54.5 54.1 45.3 51.4 46.7 53.6 48.3
23 PM 66.2 53.4 52.4 44.3 48.6 45.4 51.3 47.2
24 MN 65.1 52.5 51.1 43.6 46.2 45.1 49.2 43.1
1 AM 63.2 53.6 52.7 42.6 45.1 44.3 48.1 42.5
2 AM 62.1 52.9 52.1 44.6 44.8 44.1 46.8 42.3
3 AM 63.8 51.1 52.6 42.3 43.2 42.2 44.3 41.0
4 AM 64.7 52.1 53.4 43.3 45.6 43.5 43.3 44.5
5 AM 66.4 53 53.1 44.3 46.4 46.4 44.8 45.2 Maximu
m 69.8 60.5 59.8 56.6 59.2 56.7 58.6 56.7
Minimum 56.3 51.1 51.1 42.3 43.2 42.2 43.3 41.0
Leq Day
dB(A)
66.3 58.1 57.7 53.4 57.1 54.0 56.3 53.6
Leq
Night
dB(A)
55.9 53.0 53.0 44.6 48.3 45.4 49.8 45.9
Leq Day
&Night
62.5 57.0 56.6 51.7 55.7 52.6 55.0 52.2
As per the standard of CPCB the noise level should be 75 dB (A) at day time and 70 dB
(A) at night time in industrial area. All the results found within the permissible limit.
However noise level in rural & residential is slightly above the standard limit.
4.14 Water Environment
Assessment of baseline data on Water environment includes
a) Identification of surface water sources
b) Identification of ground water sources
c) Collection of water samples
d) Analyzing water samples collected for physico-chemical and biological parameters
Ground water is another major water source in the study area and the water table lies at
about 50-80 m below 550 msl.
4.14.1.1 Monitoring Locations
Assessment of water quality and Soil Quality in the study area includes the quality
assessment of parameters as per the Indian standard IS 10500 (drinking water standard).
Eight Ground Water and Eight Surface Water samples have been collected from various
locations of the study area. The location of water and Soil sampling stations is shown in
Table-4.8 and the results are shown in Table 4.9, 4.10 and 4.11.
56
Figure 4.14-4: Surface and Ground water Monitoring Locations
Table 4.14-9: Water and Soil Sampling Locations
Station
Code for
Soil
Station
Code for
Ground
Water(GW)
and Surface
(SW)
Name of the
Station
Latitude Longitude Distance
w.r.t.
site (km)
Direction Environme
ntal Setting
S1 GW1/SW1 Project
Area
170 41' 54.34" 780 29 '4.82" - - Mixed
Area
S2 GW2/SW2 Banda
Mailaram
170 41' 53.43" 780 30 '21.00" 1.3 S-SW Cross wind
S3 GW3/SW3 Baswapur 170 42' 20.36" 780 32 '31.57" 6.4 E Cross wind
S4 GW4/SW4 Rawalkole 170 39' 29.53" 78 0 30' 26.20" 4.22 SE Down wind
S5 GW5/SW5 Medchal 170 37' 15.77" 78 0 28' 54.6" 1.8 SW-W Down wind
S6 GW6/SW6 Nuthankal 170 41' 21.95" 780 26' 56.56" 5.7 S-SW Cross wind
S7 GW7/SW7 Sikindlapur 170 44' 6.62" 780 25' 31.62" 5.8 NE-E Cross wind
S8 GW8/SW8 Koochavara
m
17 0 43 '47.69" 780 28' 12.52" 9.3 S Cross wind
Ground Water sample collected showed compliance of all parameters with the drinking
water standard of IS 10500 and surface water as IS 2296 Standards.
The study area is covered with alluvial read soil and in some parts with small patches of
clay with low thickness. Eight soil samples were collected within 10 km radial distance of
the study area and one sample from plant area were analyzed to study the soil quality.
4.15 Soil Environment
Medak district exhibits a variety of soils. Black cotton soil ranging in thickness from 0.3 to
0.75 m occurs in basaltic regions of Narayankhed, Nayalkel and Andole mandals. Red soil
57
ranges in thickness from 0.75 to 2.00 m. It possesses high water retention capacity.
Alluvium comprises 20 Sq.Km. area. Major part of the district is arable un-irrigated land
with patch of irrigated land around Medak. Areas of forest cover are seen in the central part
of the district with grass and scrubland in the western part. A few scrubland areas also exist
in the northeastern part around Siddipet.
Summary of Soil Quality in Plant Area
pH of the all soil sample was 7.21
Texture of soil sample is found to be clay with sand 36%, silt 16% and Clay
48%.
Phosphorus values in the soil sample collected was found to be 28 kg/ha.
Nitrate of the soil sample collected was found to be 186 kg/ ha.
Summary of Soil Quality in Study Area
pH of the all soil samples was found to be 7.16-7.86.
Texture of soil samples is found to be Clay and sandy Clay with sand % in
the range between 16-36%, silt between 16-48 % and Clay 34-54%.
Phosphorus values in the soil samples collected were in the range of 28-64
kg/ha
Nitrate of the soil samples collected were in the range of 186-282 kg/ha.
58
Figure 4.15-5: Soil Monitoring Locations
59
Table 4.15-10: Ground Water Sampling Results
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
S.No Parameter Requirement
(Desirable
Limits)
Permissible Limits
in the Absence of
Alternate Source
Units
Method of Analysis Instrument Used Project site
GW1
Banda
Mailaram
GW-2
Baswapur
GW-3
Ravalkole
GW-4
1 Ph 6.5 – 8.5 NR - IS:3025(Part 11) pH meter 6.68 7.84 7.18 7.14
2 Color (Hazen units) 5 25 Hazen IS:3025(Part 4) 02 02 01 02
3 Taste Agreeable - - IS:3025(Part 8) Agreeable Agreeable Agreeable Agreeable
4 Odor Unobjectionable
- - IS:3025(Part 5) Unobjec-tionable
Unobjec-tionable
Unobjec-tionable
Unobjec-tionable
5 Conductivity µS/cm IS:3025(Part 4) 3614 1036 1366 922
6 Turbidity (NTU) 5 10 NTU IS:3025(Part 10) Turbidity meter 1.80 1.60 1.40 1.80
7 Total Dissolve solids 500 2000 mg/l IS:3025(Part 16) Gravimetric method 2448 664 886 588
8 Total Hardness asCaCO3 300 600 mg/l IS:3025(Part 21) Titrimetric method 1628 416 472 400
9 Total Alkalinity 200 600 mg/l IS:3025(Part 23) Titrimetric method 240 300 480 360
10 Calcium as Ca 75 200 mg/l IS:3025(Part 40) Titrimetric method 477 125 109 152
11 Magnesium as Mg 30 100 mg/l IS:3025(Part 46) Titrimetric method 104 25 48 26
12 Residual Chlorine 0.2 min - mg/l IS:3025(Part 26) Titrimetric method Nil Nil Nil Nil
13 Boron 1 5 mg/l IS:3025(Part 57) AAS 0.04 <0.02 0.03 <0.02
14 Chloride as Cl 250 1000 mg/l IS:3025(Part 32) Titrimetric method 1079 116 86 35
15 Sulphate as SO4 200 400 mg/l IS:3025(Part 24) Spectrophotometer 69 66 68 42
16 Fluorides as F- 1.0 1.5 mg/l IS:3025(Part 60) Spectrophotometer 1.80 0.90 1.00 0.60
17 Nitrates as NO3 45 100 mg/l IS:3025(Part 34) Spectrophotometer 11 06 08 04
18 Sodium as Na $ $ mg/l IS:3025(Part 45) Flame photometer 76 43 93 26
19 Potassium as K $ $ mg/l IS:3025(Part 45) Flame photometer 06 03 04 02
20 Phenolic Compounds 0.001 0.002 mg/l IS:3025(Part 43) Spectrophotometer 0.006 <0.001 0.003 <0.001
21 Cyanides 0.02 NR mg/l IS:3025(Part 27) Spectrophotometer <0.02 <0.02 <0.02 <0.02
22 Anionic Detergents 0.2 1.0 mg/l APHA 5540-C MBAS Kit 0.3 <0.01 <0.01 <0.01
23 Mineral Oil 0.01 0.03 mg/l IS:3025(Part 39) Gravimetric method 0.004 <0.001 <0.001 <0.001
24 Cadmium as Cd 0.01 NR mg/l IS:3025(Part 41) AAS 0.002 <0.001 <0.001 <0.001
25 Arsenic as As 0.01 NR mg/l IS:3025(Part 37) AAS <0.001 <0.001 <0.001 <0.001
26 Copper as Cu 0.02 1.5 mg/l IS:3025(Part 42) AAS <0.01 <0.01 <0.01 <0.01
27 Lead as Pb 0.02 NR mg/l IS:3025(Part 47) AAS <0.04 <0.04 <0.04 <0.04
28 Manganese as Mn 0.1 0.3 mg/l IS:3025(Part 59) AAS <0.001 <0.001 <0.001 <0.001
29 Iron as Fe 0.3 1.0 mg/l IS:3025(Part 53) AAS 0.16 0.14 0.12 0.12
30 Chromium as Cr6+ 0.02 NR mg/l IS:3025(Part 53) AAS <0.001 <0.001 <0.001 <0.001
31 Zinc as Zn 5 15 mg/l IS:3025(Part 49) AAS 03 02 02 01
32 Aluminum as Al 0.03 0.2 mg/l IS:3025(Part 55) AAS <0.005 <0.005 <0.005 <0.005
33 Mercury as Hg 0.001 NR mg/l IS:3025(Part 48) Mercury ion analyzer <0.001 <0.001 <0.001 <0.001
34 Pesticides Absent 0.001 mg/l APHA 8081 B Gas chromatography Absent Absent Absent Absent
35 E-coli(Nos/100 ml) Absent IS 13428: 2005 Microbial count Nil Nil Nil Nil
36 Coliform Organisms MPN/100 ml IS 14543: 2004 Microbial count Absent Absent Absent Absent
60
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
S.No. Parameter Requirement
(Desirable Limits)
Permissible Limits
in the Absence of Alternate Source
Units METHOD OF
ANALYSIS
Instrument Used Medchal
GW-5
Nuthankal
GW-6
Skindlapur
GW-7
Koochavar
am
GW-8
1 pH 6.5 – 8.5 NR - IS:3025(Part 11) pH meter 6.84 7.36 7.36 7.72
2 Color (Hazen units) 5 25 Hazen IS:3025(Part 4) 02 02 02 02
3 Taste Agreeable - - IS:3025(Part 8) Agreeable Agreeable Agreeable Agreeable
4 Odor Unobjectionable
- - IS:3025(Part 5) Unobjec-tionable
Unobjec-tionable
Unobjec-tionable
Unobjec-tionable
5 Conductivity $ $ uS/cm IS:3025(Part 4) 2786 968 748 1026
6 Turbidity (NTU) 5 10 NTU IS:3025(Part 10) Turbidity meter 1.80 1.60 1.80 1.60
7 Total Dissolve solids 500 2000 mg/l IS:3025(Part 16) Gravimetric method 1784 602 478 652
8 Total Hardness as CaCO3 300 600 mg/l IS:3025(Part 21) Titrimetric method 1208 416 264 240
9 Total Alkalinity 200 600 mg/l IS:3025(Part 23) Titrimetric method 380 280 240 220
10 Calcium as Ca 75 200 mg/l IS:3025(Part 40) Titrimetric method 400 166 64 70
11 Magnesium as Mg 30 100 mg/l IS:3025(Part 46) Titrimetric method 135 31 25 14
12 Residual Chlorine 0.2 min - mg/l IS:3025(Part 26) Titrimetric method Nil Nil Nil Nil
13 Boron 1 5 mg/l IS:3025(Part 57) AAS <0.02 <0.02 <0.02 <0.02
14 Chloride as Cl 250 1000 mg/l IS:3025(Part 32) Titrimetric method 504 93 36 185
15 Sulphate as SO4 200 400 mg/l IS:3025(Part 24) Spectrophotometer 278 64 72 24
16 Fluorides as F- 1.0 1.5 mg/l IS:3025(Part 60) Spectrophotometer 1.80 0.80 0.60 0.80
17 Nitrates as NO3 45 100 mg/l IS:3025(Part 34) Spectrophotometer 09 04 06 05
18 Sodium as Na $ $ mg/l IS:3025(Part 45) Flame photometer 84 29 47 123
19 Potassium as K $ $ mg/l IS:3025(Part 45) Flame photometer 03 02 02 02
20 Phenolic Compounds 0.001 0.002 mg/l IS:3025(Part 43) Spectrophotometer <0.001 <0.001 <0.001 <0.001
21 Cyanides 0.02 NR mg/l IS:3025(Part 27) Spectrophotometer <0.02 <0.02 <0.02 <0.02
22 Anionic Detergents 0.2 1.0 mg/l APHA 5540-C MBAS Kit <0.01 <0.01 <0.01 <0.01
23 Mineral Oil 0.01 0.03 mg/l IS:3025(Part 39) Gravimetric method <0.001 <0.001 <0.001 <0.001
24 Cadmium as Cd 0.01 NR mg/l IS:3025(Part 41) AAS <0.001 <0.001 <0.001 <0.001
25 Arsenic as As 0.01 NR mg/l IS:3025(Part 37) AAS <0.001 <0.001 <0.001 <0.001
26 Copper as Cu 0.02 1.5 mg/l IS:3025(Part 42) AAS <0.01 <0.01 <0.01 <0.01
27 Lead as Pb 0.02 NR mg/l IS:3025(Part 47) AAS <0.04 <0.04 <0.04 <0.04
28 Manganese as Mn 0.1 0.3 mg/l IS:3025(Part 59) AAS <0.001 <0.001 <0.001 <0.001
29 Iron as Fe 0.3 1.0 mg/l IS:3025(Part 53) AAS 0.16 0.10 0.03 0.03
30 Chromium as Cr6+ 0.02 NR mg/l IS:3025(Part 53) AAS <0.001 <0.001 <0.001 <0.001
31 Zinc as Zn 5 15 mg/l IS:3025(Part 49) AAS 04 02 01 03
32 Aluminum as Al 0.03 0.2 mg/l IS:3025(Part 55) AAS <0.005 <0.005 <0.005 <0.005
33 Mercury as Hg 0.001 NR mg/l IS:3025(Part 48) Mercury ion analyzer <0.001 <0.001 <0.001 <0.001
34 Pesticides Absent 0.001 mg/l APHA 8081 B Gas chromatography Absent Absent Absent Absent
35 E-coli(Nos/100 ml) Absent NR IS 13428: 2005 Microbial count Nil Nil Nil Nil
36 Coli form Organisms Absent NR MPN/ 100 ml
IS 14543: 2004 Microbial count Absent Absent Absent Absent
61
Table 4.15-11: Surface Water Sampling Results
Project Name: Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
S.No Parameter Units IS:2296
Class C Limits
METHOD OF
ANALYSIS
Instrument Used Project site
SW1
Banda
Mailaram
SW-2
Baswapur
SW-3
Ravalkole
SW-4
1 Ph - 6.5 – 8.5 IS:3025(Part 11) pH meter 7.96 7.46 7.68 7.26
2 Color Hazen units 300 IS:3025(Part 4) 04 06 04 02
3 Conductivity S/cm $ IS:3025(Part 4) 326 216 462 408
4 Dissolved Oxygen mg/l 4 min IS:3025(Part 38) Titrimetric method 3.80 3.60 3.10 3.10
5 BOD ( 3 days at 27oC) mg/l 3 IS:3025(Part 44) BOD Incubator,
Titrimetric method
02 02 01 02
6 Total Dissolved Solids mg/l 1500 IS:3025(Part 16) Gravimetric method 208 134 292 256
7 Total Hardness mg/l $ IS:3025(Part 21) Titrimetric method 104 88 168 160
8 Chloride as Cl mg/l 600 IS:3025(Part 32 ) Titrimetric method 21 146 43 21
9 Fluorides as F- mg/l 1.5 IS:3025(Part 60) Spectrophotometer 0.3 0.2 0.30 0.30
10 Sulphate as SO4 mg/l 400 IS:3025(Part 24 ) Spectrophotometer 27 22 26 64
11 Alkalinity mg/l $ IS:3025(Part 23) Titrimetric method 140 60 140 100
12 Nitrates as NO3 mg/l $ IS:3025(Part 34 ) Spectrophotometer 03 03 02 04
13 Cyanide as CN mg/l 0.05 IS:3025(Part 27) Spectrophotometer <0.02 <0.02 <0.02 <0.02
14 Calcium as Ca mg/l $ IS:3025(Part 40) Titrimetric method 26 19 42 51
15 Magnesium as Mg mg/l $ IS:3025(Part 46) Titrimetric method 09 10 15 07
16 Sodium as Na mg/l $ IS:3025(Part 45) Flame photometer 25 06 27 18
17 Potassium as K mg/l $ IS:3025(Part 45) Flame photometer 01 02 01 02
18 Iron as Fe mg/l 50 IS:3025(Part 53) AAS 0.24 0.26 0.24 0.0.12
19 Chromium as Cr mg/l 0.05 IS:3025(Part 41) AAS < 0.001 < 0.001 < 0.001 < 0.001
20 Cadmium as Cd mg/l 0.01 IS:3025(Part 47) AAS < 0.001 < 0.001 < 0.001 < 0.001
21 Lead as Pb mg/l 0.1 IS:3025(Part 47) AAS < 0.04 < 0.04 < 0.04 < 0.04
22 Copper as Cu mg/l 1.5 IS:3025(Part 42) AAS < 0.01 < 0.01 < 0.01 < 0.01
23 Arsenic as as AS mg/l 0.2 IS:3025(Part 37) AAS < 0.001 < 0.001 < 0.001 < 0.001
24 Selenium as Se mg/l 0.05 IS:3025(Part 56) AAS < 0.01 < 0.01 < 0.01 < 0.01
25 Phenolics as C6H5Oh mg/l 0.005 IS:3025(Part 43) Spectrophotometer < 0.001 < 0.001 < 0.001 < 0.001
26 Zinc as Zn mg/l 15 IS:3025(Part 49) AAS 02 01 02 02
27 Mercury as Hg mg/l $ IS:3025(Part 48) Mercury ion
analyzer
<0.001 <0.001 <0.001 <0.001
28 Aluminum as Al mg/l $ IS:3025(Part 55) AAS <0.005 <0.005 <0.005 <0.005
29 Anionic detergents as mbas mg/l 1 APHA 5540-C MBAS Kit <0.1 <0.1 <0.1 <0.1
30 Oil and grease mg/l 0.1 IS:3025(Part 39) Gravimetric < 1.0 < 1.0 < 1.0 < 1.0
31 Sodium Absorption Ratio - - APHA 3000 ICP AAS 1.30 0.39 0.86 0.22
32 Insecticides mg/l Absent Gas
chromatography
Absent Absent Absent Absent
33 Coli form Organisms MPN/
100 ml
Should not exceed
5000
IS 14543: 2004 Microbial count
method
308 248 228 212
62
Project Name: Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
S.No Parameter Units IS:2296
Class C Limits
METHOD OF
ANALYSIS
Instrument Used Medchal
SW-5
Nuthankal
SW-6
Skindlapur
SW-7
Koochavaram
SW-8
1 Ph - 6.5 – 8.5 IS:3025(Part 11) pH meter 7.98 7.18 7.86 6.68
2 Color Hazen units 300 IS:3025(Part 4) 02 02 03 02
3 Conductivity S/cm $ IS:3025(Part 4) 362 264 288 228
4 Dissolved Oxygen mg/l 4 min IS:3025(Part 38) Titrimetric method 3.20 3.20 3.70 3.00
5 BOD ( 3 days at 27oC) mg/l 3 IS:3025(Part 44) BOD Incubator,
Titrimetric method
02 02 02 02
6 Total Dissolved Solids mg/l 1500 IS:3025(Part 16) Gravimetric method 228 168 178 146
7 Total Hardness mg/l $ IS:3025(Part 21) Titrimetric method 128 80 96 88
8 Chloride as Cl mg/l 600 IS:3025(Part 32 ) Titrimetric method 29 35 14 21
9 Fluorides as F- mg/l 1.5 IS:3025(Part 60) Spectrophotometer 0.3 0.30 0.20 0.20
10 Sulphate as SO4 mg/l 400 IS:3025(Part 24 ) Spectrophotometer 15 16 28 18
11 Alkalinity mg/l $ IS:3025(Part 23) Titrimetric method 120 60 80 80
12 Nitrates as NO3 mg/l $ IS:3025(Part 34 ) Spectrophotometer 03 03 03 03
13 Cyanides as CN mg/l 0.05 IS:3025(Part 27) Spectrophotometer <0.02 <0.02 <0.02 <0.02
14 Calcium as Ca mg/l $ IS:3025(Part 40) Titrimetric method 35 22 29 22
15 Magnesium as Mg mg/l $ IS:3025(Part 46) Titrimetric method 10 06 06 07
16 Sodium as Na mg/l $ IS:3025(Part 45) Flame photometer 22 22 20 10
17 Potassium as K mg/l $ IS:3025(Part 45) Flame photometer 01 01 01 01
18 Iron as Fe mg/l 50 IS:3025(Part 53) AAS 0.24 0.10 0.20 0.22
19 Chromium as Cr mg/l 0.05 IS:3025(Part 41) AAS < 0.001 < 0.001 < 0.001 < 0.001
20 Cadmium as Cd mg/l 0.01 IS:3025(Part 47) AAS < 0.001 < 0.001 < 0.001 < 0.001
21 Lead as Pb mg/l 0.1 IS:3025(Part 47) AAS < 0.04 < 0.04 < 0.04 < 0.04
22 Copper as Cu mg/l 1.5 IS:3025(Part 42) AAS < 0.01 < 0.01 < 0.01 < 0.01
23 Arsenic as as AS mg/l 0.2 IS:3025(Part 37) AAS < 0.001 < 0.001 < 0.001 < 0.001
24 Selenium as Se mg/l 0.05 IS:3025(Part 56) AAS < 0.01 < 0.01 < 0.01 < 0.01
25 Phenolics as C6H5Oh mg/l 0.005 IS:3025(Part 43) Spectrophotometer < 0.001 < 0.001 < 0.001 < 0.001
26 Zinc as Zn mg/l 15 IS:3025(Part 49) AAS 02 01 01 03
27 Mercury as Hg mg/l $ IS:3025(Part 48) Mercury ion analyzer <0.001 <0.001 <0.001 <0.001
28 Aluminum as Al mg/l $ IS:3025(Part 55) AAS <0.005 <0.005 <0.005 <0.005
29 Anionic detergents as mbas mg/l 1 APHA 5540-C MBAS Kit <0.1 <0.1 <0.1 <0.1
30 Oil and grease mg/l 0.1 IS:3025(Part 39) Gravimetric < 1.0 < 1.0 < 1.0 < 1.0
31 Sodium Absorption Ratio - - APHA 3000 ICP AAS 0.86 1.36 0.96 0.61
32 Insecticides mg/l Absent Gas chromatography Absent Absent 148 Absent
33 Coli form Organisms MPN/100 ml >5000 IS 14543: 2004 Microbial count method 214 224 212 248
63
Table 4.15-12: Soil Analysis
Project Name: Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
S.
No.
Parameter Instrument Analysis Method of Analysis Project site
S-1
Banda
Mailaram
S-2
Baswapur
S-3
Ravalkole
S-4
1 Texture - Texture Analysis Chart Sandy
Clay
Sandy Clay Clay Silty
Clay
Sand (%) - 36 32 26 18
Silt (%) - 16 18 22 48
Clay (%) - 48 50 54 34
2 pH Ph meter - 7.21 7.45 7.41 7.63
3 EC (us/cm) Conductivity Meter - 216 252 198 212
4 Bulk Density (g/cc) Colorimeter - 1.06 1.12 1.24 1.40
5 Available Nitrogen
(kg/ha)
Colorimeter - 186 212 246 282
6 Available P as PO4
(kg/ha)
Titrimetric method Sodium bicarbonate
method
28 34 48 64
7 Available K (kg/ha) Flame photometer method - 104 108 134 128
8 Exchangeable Ca
(meq/100gr)
Flame photometer method - 3.00 2.90 3.60 3.20
9 Exchangeable Mg
(meq/100gr)
Flame photometer method - 1.00 1.20 1.30 1.00
10 Exchangeable Na
(meq/100gr)
Flame photometer method - 3.60 3.40 3.60 3.20
11 Organic Carbon (%) Titrimetric method Walkley-Black method 0.24 0.30 0.40 0.40
12 Manganese (meq/100gr) Flame photometer method - 0.05 0.03 0.06 0.03
13 Zinc (meq/100gr) AAS - 2.90 3.40 4.10 4.40
14 Boron (meq/100gr) AAS - 0.04 0.03 0.04 0.02
64
Project Name : Mahalakshmi Profiles Pvt. Ltd. Season : Winter - 2019
S. No. Parameter Instrument
Analysis
Method of Analysis Medchal
S-5
Nuthankal
S-6
Skindlapur
S-7
Koochavara
m
S-8
1 Texture - Texture Analysis
Chart
Silty Clay Clay Sandy Clay Silty
Clay
Sand (%) - 16 18 32 16
Silt (%) - 34 28 24 38
Clay (%) - 50 54 44 46
2 pH Ph meter 7.72 7.19 7.86 7.16
3 EC (us/cm) Conductivity Meter 257 218 242 198
4 Bulk Density (g/cc) colorimeter 1.32 1.40 1.09 1.50
5 Available Nitrogen (kg/ha) colorimeter 256 268 192 274
6 Available P as PO4 (kg/ha) Titrimetric method Sodium bicarbonate
method
58 54 32 52
7 Available K (kg/ha) Flame photometer
method
- 156 132 124 136
8 Exchangeable Ca
(meq/100gr)
Flame photometer
method
- 3.60 3.20 3.40 3.20
9 Exchangeable Mg
(meq/100gr)
Flame photometer
method
- 1.30 1.40 1.38 0.90
10 Exchangeable Na
(meq/100gr)
Flame photometer
method
- 3.90 4.20 3.00 3.60
11 Organic Carbon (%) Titrimetric method Walkley-Black
method
0.30 0.30 0.30 0.60
12 Manganese (meq/100gr) Flame photometer
method
0.03 0.02 0.04 0.01
13 Zinc (meq/100gr) AAS 4.60 4.40 4.10 4.00
14 Boron (meq/100gr) AAS 0.03 0.02 0.03 0.04
65
4.16 Flora and Fauna
4.16.1 Forest
The period of monsoon is very short lived in this area, which has a significant bearing apart from
other biotic pressures, on the floristic composition of the forests. These are open forests in which
thorny and usually hard wood species predominate.
It is been found that the field area is inhabited by various types of plants belonging to families
like Leguminosae (104), Poaceae (83), Cyperaceae (49), Asteraceae (37), Euphorbiaceae (31),
Acanthaceae (22), Rubiaceae (20), Lamiaceae (18), Convolvulaceae (17) and Amaranthaceae
(15).
4.16.1.1 Flora
The study area does not habitat any thick vegetal cover. There is usually a thin grass growth
which December appear during the short rainy season in most of the study area, but more or less
the soil is barren and devoid of any grass growth.
Table 4.16.1-13: List of Flora
Name Family Common Name
Acacia Auriculiformis Mimoseae Cutch Tree
Carissa Spinarum Apocynaceae Karaunda
Cassia Pumila Caesal pinaceae Yellow Cassia
Cassia Renigera Caesal pinaceae Pink Cassia
Dendrocalamus Strictus Poaceae Solid Bamboo
Emblica Officinalis Euphorbiaceae Gooseberry
Ficus Gibbosa Moraceae Tella Barinika
Ficus Hispida Moraceae Kala Umbar
Heterophragma Roxburghii Bignoniaceae Barukoligottu
Mangifera Indica Anacardiaceae Mango Tree
Pinus Roxburghii Pinaceae Chilgoza
Prosopis Cineraria Mimos Eae Khejri
Psidium Guayava Myrtaceae Guava Tree
4.16.1.2 Fauna
Some of the animals which you would find here are Tigers, Panthers, Jackals, Indian Giant
Squirrel, Mouse Deer, Spotted Deer, Sambhar Deer, Black Bucks, Wild Boar, Tree Shrew,
Mugger Crocodiles, Wolves, Wild dogs, Foxes, and Sloth Bear. No endangered fauna species are
found in the area.
66
Table 4.16.1-14: List of Fauna
Scientific Name Common Name
Ananthana ellioti Tree shrew
Ratufa indica Indian Giant Squirrel
Mus dunni Mouse
Sus scrofa cristatus Indian Wild Boar
Axis axis Spotted Deer/ Chital
Cervus unicolor Samber
Pavo cristatus Peacock
Panthera pardus fusca Leopard
Ursus thibetanus Bears
Canis aureus Golden Jackal
Vulpus vulpus Fox
Columba livia wild pigeons
Corvus splendens Kaola
Anas crecca Teal
Gallinago gallinago snipe
Antilope cervicapra Blackbuck
Crocodylus palustris Mugger Crocodiles
4.17 Socio Economic Environment
Socio-economic environment includes description of demography, available basic amenities like
housing, health care services, transportation, education and cultural activities. Information on the
above said factor has been collected to define the socio-economic profile of the study area (10
km radius), which is also a part of Environmental Impact Assessment study for the proposed
project.
A detailed socio-economic survey was conducted covering all tehsils in the 10 km radius from
the center. The information on socio-economic aspects has been compiled from various
secondary sources including various government and semi-government offices.
Basic Socio-economic conditions are as follows:
There are 55 villages and many hamlets in the study area.
As per the 2011 census data, the population in the study area is 58,498.
Density of population is 164.12 persons per Sq km.
Literacy status of the area is found to be moderate with a total of 62 % of the
population. Male and Female literacy is about 72 % and 52% respectively.
67
Occupational status in the study area is in agriculture. 50 % of total population of
the study area falls under main workers category.
Agricultural activities are mainly in monsoon season. Major crops in the area are
Jowar, Maize, groundnut, Ragi, Onion, Vegetables etc
Medical facilities are inadequate, only few villages have the primary health care
centers. For any major health care, the populace of the area has to go to
Shadnagar, which is a major town located at a distance of about 13.0 Km from
the proposed site.
Educational facilities are adequate. Higher educational center is Shadnagar at a
distance of 13.0 km.
This region is well connected by road.
Many villages are adequately provided with protected water supply
68
5 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION
MEASURES
5.1 Introduction
Impact prediction is a very important phenomenon in evaluating the environmentally potential
adverse impacts for any proposed industrial project. The impact prediction is always carried out
under worst possible conditions so as to mitigate or to eliminate the environmental hazards.
These predictions thus calculated are superimposed over the baseline data to calculate the net
impact on the environment after the proposed project comes into production.
5.2 Air Environment
It is possible that increase in the background concentration of even a minor constituent of the
atmosphere may lead to significant changes in the atmospheric properties. So these changes are
essential in understanding potential climatic changes due to air pollutants. For example under
strongly stable condition, disturbances are highly damped and mixing of pollutants is strongly
suppressed. It is under such conditions that the worst air pollution episodes have occurred.
Prediction of impacts is the most important component in the environmental impact assessment
studies. Several scientific techniques and methodologies are available to predict impacts of
developmental activities on physico, ecological and socioeconomic environments. Such
predictions are superimposed over the baseline (pre project) status of environmental quality to
derive the ultimate (post project) scenario of environmental conditions. The prediction of
impacts helps to identify the environmental management plan required to be executed during and
after commissioning the proposed project to minimize the adverse impacts on environmental
quality.
The mathematical models are the best tools to quantitatively describe cause-effect relationships
between sources of pollution and different components of environment. In case, mathematical
models are not available or it is not possible to identify / validate through models for particular
situation, prediction could be arrived at through available scientific knowledge and judgments.
5.3 Impact on Topography and Climate
5.4 Impact on Topography
The major envisaged topographical changes would be limited to the immediate vicinity of the
plant. The change in topography will be only due to manmade structures like industrial complex
and administrative building. Similarly, it will invite positive benefits in the form of land leveling
and green belt development in the plant vicinity.
69
5.5 Impacts on Climate
As the temperature of effluent gases will not be high, generally this will not cause any thermal
imbalance as extensive greenbelt will be developed within the plant premises. However, there
will be natural dispersion of heat due to unstable conditions during day and as such there would
be no significant micro / macro climatological changes of any consequence.
5.6 Air Quality Impact Prediction
Different types of mathematical models are available for short term prediction of Ground Level
Concentrations (GLC's) of air pollutants. These models deal with different types of atmospheric
dispersion computations, air pollution sources, topographic features and comprehend to different
types of atmospheric conditions. The available mathematical models require the input of stack
characteristics such as diameter, height, source strength, meteorological data and computer
resources to handle the available inputs. Keeping the mentioned facts in view, one has to identify
a proper and suitable model applicable to the characteristics of source and prevailing topographic
conditions to enable GLC to be known at any location under a variety of factoral changes. The
area around the plant is generally flat.
The stacks will be situated very near to each other. Therefore, these stacks are identified as
elevated continuous point sources. The modeling is based on hourly meteorological data
collected at the plant site. Twenty hour average incremental GLCs have been predicted for the
proposed plant for multi stack dispersion modeling using double Gaussian diffusion equation.
Prediction of impacts on air environment has been carried out employing mathematical model
based on a steady state Gaussian plume dispersion model designed for multiple point sources for
short term. In the present case, Industrial Source Complex [ISCST-3] dispersion model based on
steady state Gaussian plume dispersion, designed for multiple point sources for short term and
developed by United States Environmental Protection Agency [USEPA] has been used for
simulations from point sources.
AERMOD is a regulatory steady-state plume modeling system with three separate components:
AERMOD (AERMIC Dispersion Model), AERMAP (AERMOD Terrain Preprocessor), and
AERMET (AERMOD Meteorological Preprocessor). The AERMOD model includes a wide
range of options for modeling air quality impacts of pollution sources, making it a popular choice
among the modeling community for a variety of applications. AERMOD contains basically the
same options as the ISCST3 model.
70
5.7 Model Input Data
For the modeling purpose, all pollutants as described above are considered. The details of stack
emissions envisaged from the project are given in Table 5-1.
Table 5-1: Details of Emissions
Proposed
Parameters 2*12 TPH 320 KVA
Emissions
PM2.5 µg/m3 0.01 0.0086
PM10 µg/m3 0.021 0.0144
SO2 µg/m3 0.1 0.0062
NO2 µg/m3 0.3 0.132
CO µg/m3 0.0009 0.0000561
Stack Particulars
Exit Temp (K) 376 383
Exit vel- m/s 15 15
Dia (m) 1.5 0.2
Stack height (m) 30 9
Major pollutant of the source would be PM10, PM2.5, SO2 and NOx. For the transportation to and
from the plant, Fugitive Dust Model (FDM) has been used, which is a computerized air quality
model specifically designed for computing concentration and deposition impacts from fugitive
dust sources. The sources may be point, line or area sources. The model has not been designed to
compute the impacts of buoyant point sources, thus it contains no plume rise algorithm. The
model is generally based on the well-known Gaussian Plume formulation for computing
concentrations, but the model had been specifically adapted to incorporate an improved gradient
transfer deposition algorithm. Emissions for each source are apportioned by the user into a series
of particle size classes. A gravitational settling velocity and a deposition velocity are calculated
by FDM for each class. Concentration and deposition are computed at all user selectable receptor
location.
24 hours average incremental GLCs are summarized in Table 5.2 .The dispersion modeling is
carried out for the existing and expansion of the plant.
Meteorological Data
The hourly meteorological data recorded at site is converted to the mean hourly meteorological
data as specified by CPCB and the same has been used in the model. The meteorological data of
summer season is used for modelling.
71
5.8 Ground Level Concentration
In the present case, model simulations have been carried out for the study period. The Ground
level concentrations are computed for 24-hr average. Maximum Incremental Ground level
concentrations of PM10 is 0.8 μg/m3, PM2.5 is 0.1 μg/m3, SO2 is 0.6 μg/m3, NOx is 8.00 μg/m3
and CO is ).005 μg/m3 were falling within a distance of 200 m from the point source. The
obtained GLC’s are well within the stipulated CPCB standards. Figure 5.1 to 5.9 shows the
isopleths of different pollutants
The maximum GLCs for PM10, PM2.5, SO2 NOx and CO after the Installation of the proposed
project are well within the prescribed limit of 60g/m3 ,100 g/m3 , 80 g/m3 and 80 g/m3 and
4000g/m3 respectively for residential and rural zone. Based on the predicted concentrations it can
be inferred that area is unlikely to be significantly affected due to the proposed project.
Table 5-1: Isopleths of Maximum Total Concentration
Pollutant Maximum AAQ
Concentrations
Recorded During the
Study (g/m3)
Incremental
Concentration due to
proposed expansion
(g/m3)
Resultant
Concentration
(g/m3)
PM10 38.2 0.8 39.0
PM2.5 18.49 0.1 18.5
SO2 17.17 0.6 17.77
NOx 21.38 8.0 29.38
CO BDL 0.005 0.005
5-1: Isopleths of PM 2.5 Incremental Values
72
5-2: Isopleths of PM 2.5 Ambient Value
5-3: Isopleths of PM 10 Incremental Values
73
5-4: Isopleths of PM 10 Ambient Value
5-5: Isopleths of SO2 Incremental Values
74
5-6: Isopleths of SO2 Ambient Value
5-7: Isopleths of NOx Incremental Values
75
5-8: Isopleths of NOx Ambient Value
5-9: Isopleths of CO Incremental Value
76
5-10: Isopleths of CO Ambient Value
77
6 ANALYSIS OF ALTERNATIVES (SITE AND TECHNOLOGY)
6.1 General
This chapter summarizes the alternatives that were explored during development of the Project.
The range of alternatives considered included those that would reasonably accomplish the basic
Project objectives while avoiding or lessening any potentially significant, negative impacts of the
proposed Project. These include considerations of the project location, overall size, and choice of
machinery, access road locations, and use of alternative generating technologies.
It is very important to select technology and site for project setup because the /technology and
site selection factors play very decisive role for the industry future.
The Proposed project is an expansion of existing M.S. Ingots and Billets manufacturing unit
situated on Survey. No. 287, 288 & 289 in Kallakal village, Manoharabad Mandal, Medak
District in Telangana state. Thus, alternative of site is not applicable on this project as the
expansion is coming up on existing plant area. No additional land is required for expansion. The
unit is proposing additional induction furnaces for the proposed expansion capacity.
6.2 Analysis of Alternative Site
As mentioned above the proposed expansion is coming up in existing plot area and no additional
land is required for expansion thus, analysis of alternative site is not required for this particular
project. The existing plant is located in notified industrial area, Manoharabad Mandal. Thus, all
the basic amenities are within the reach of the unit.
6.3 Analysis of Alternate Technology
The unit is proposing to install one additional induction furnace of 12T capacity and wet
scrubber and bag filters as pollution control equipment. The proposed induction furnace is a core
less induction furnace which is one of the best available technologies.
6.4 Induction Furnace
The advantages of induction furnace are given below:
Optimized Consistency
78
Induction heating eliminates the inconsistencies and quality issues associated with open
flame, torch heating and other methods.
The heating pattern is repeatable and consistent
With modern solid state systems, precise temperature control provides uniform results; power
can be instantly turned on or shut off
With closed loop temperature control, advanced induction heating systems have the
capability to measure the temperature of each individual part
Specific ramp up, hold and ramp down rates can be established & data can be recorded for
each part that is run
Maximized Productivity
Heat is developed directly and instantly (>2000º F. in < 1 second) inside the part
No warm up or cool down cycle is required
Extended Fixture Life
Induction heating rapidly delivers site-specific heat to very small areas of part, without
heating any surrounding parts. This extends the life of the fixtures and mechanical setup
Environment Friendly
Induction is a clean, non-polluting process which will help to protect the environment. It
doesn’t require any fossil fuel
An induction system improves working conditions for employees by eliminating smoke,
waste heat, noxious emissions and loud noise
Heating is safe and efficient with no open flame to endanger the operator or obscure the
process
Non-conductive materials are not affected and can be located in close proximity to the
heating zone without damage
Reduced Energy Consumption
This uniquely energy-efficient process converts up to 90% of the energy expended energy
into useful heat; batch furnaces are generally only 45% energy-efficient.
And since induction requires no warm-up or cool-down cycle, stand-by heat losses are
reduced to a bare minimum.
The repeatability and consistency of the induction process make it highly compatible with
energy-efficient automated systems.
79
6.5 Reheating Furnace
No reheating furnace is being used in the system as the Ingot received from the CCM is directly
taken for rolling mill. The system is saving the energy without using the reheating furnace.
Figure 6-1: Venturi Scrubber
80
Figure 6-2: Layout of Pollution Control Equipment for Induction furnace and Rolling mill
7 ENVIRONMENTAL MONITORING PROGRAM
7.0 General
Monitoring is one of the most important components of a management system. The regular
monitoring of environmental parameters is of immense importance to assess the status of
environment during project operations. With the knowledge of baseline conditions, the monitoring
program will serve as an indicator for any deterioration in environmental conditions due to
operation of the project, to enable taking up suitable mitigation steps in time to safeguard the
environment. Monitoring is as important as that of control of pollution since the efficiency of
control measures can only be determined by monitoring.
7.1 Objectives of Monitoring
The objectives of the monitoring plan are as follows:
Verify effectiveness of planning decisions
To check and assess the efficacy of pollution control equipment
Measure effectiveness of operational procedures
Confirm statutory and corporate compliance
Identify unexpected changes
7.2 Environmental Monitoring
Environmental monitoring during operational phase will be carried out through outsource laboratory
(NABL/MOEF/TSPCB approved). Environmental monitoring schedules are prepared covering
various phases of project advancement, such as regular operational phase.
81
7.1 Monitoring Schedule during Operational Phase
During operational stage, following activities will be undertaken:
Ambient air quality
Ground water quality
Water and wastewater quality
Soil quality
Noise quality
The following routine monitoring program as detailed will be implemented at site. Besides to
this monitoring, the compliances to all environmental clearance conditions and regular permits
from TSPCB/MoEF&CC will be monitored and reported periodically.
Table 7-1: Environmental Monitoring during Operational Phase
S.
No
Potential
impact
Action to be
followed
Parameters for
monitoring
Frequency of
monitoring Location
1 Air emissions
Ambient air quality
within the premises of
the proposed unit and
nearby habitations to
be monitored
PM10, PM 2.5,
SO2, NOx and
CO
As per CPCB/
TSPCB
requirement or
on weekly basis
whichever is
earlier
At least two
locations
inside
premises, three
locations
outside.
Exhaust from vehicles
to be minimized by use
of fuel efficient
vehicles and well
maintained vehicles
having PUC certificate.
Vehicle logs to be
maintained -
-
Measuring onsite data
of Meteorology
Wind speed,
direction,
temperature,
relative humidity
and rainfall
Continuous
monitoring
using on-line
weather station
during
operation phase
Onsite at one
location
Vehicle trips to be
minimized to the
extent possible
Vehicle logs Daily records Main gate
2 Noise
Noise generated from
various plant
operations, vehicles to
be optimized and
monitored
Spot Noise Level
recording
Leq (night)
Leq (day)
Periodic
during
operation phase
Noise
measurement
at four
locations
Generation of Maintain records Periodic during
82
S.
No
Potential
impact
Action to be
followed
Parameters for
monitoring
Frequency of
monitoring Location
vehicular noise of vehicles operation phase
3 Waste water
discharge
No untreated discharge
to be made to surface
water, ground water or
soil.
No discharge
hoses in vicinity
of watercourses
Periodic during
operation phase
Take care in disposal
of wastewater
generated such that soil
and groundwater
resources are protected
Discharge norms
for effluents will
be maintained
Periodic during
operation phase
Compliance of treated
waste water usage/
discharge to standards
pH, TSS, TDS,
BOD, COD &
temperature
Periodic during
operation phase
One location
(treated waste
water)
4 Drainage and
effluent
management
Ensure drainage
system and specific
design measures are
working effectively.
Design to incorporate
existing drainage
pattern and avoid
disturbing the same
Visual inspection
of drainage and
records thereof
Periodic during
operation phase -
5 Water quality
and water levels
Monitoring used water
quality & ground water
quality and levels
Comprehensive
monitoring as per
IS:10500
Groundwater
level bgl
Periodic during
operation phase
Three
locations
surrounding
industry site
6 Energy usage
Energy usage for air
conditioning and other
activities to be
minimized.
Conduct annual
energy audit for the
buildings
Energy audit
report
Annual audits
and periodic
checks during
operational
phase
-
7
Emergency
preparedness,
such as fire
fighting
Fire protection and
safety measures to take
care of fire and
explosion hazards, to
be assessed and steps
taken for their
prevention
Mock drill
records, on site
emergency plan
evacuation plan
Periodic during
operation phase -
8 Maintenance of
flora and fauna
Vegetation, greenbelt/
green cover
development
No plants, species Periodic during
operation phase -
9 Waste
Management
Implement waste
management plan that
identified and
characterizes every
waste arising
associated with
Records of solid
waste generation,
treatment and
disposal
Periodic during
operation phase -
83
S.
No
Potential
impact
Action to be
followed
Parameters for
monitoring
Frequency of
monitoring Location
proposed activities and
which identifies the
procedures for
collection, handling &
disposal of each waste
arising
10 Soil quality Maintenance of good
soil quality
Physico-
chemical
parameters and
metals
Periodical
Monitoring
Plantation
areas
11 Health
Employees and
migrant labour health
checkups
All relevant
parameters
including HIV
Regular
checkups
7.3 Generation of Baseline Data
The detailed study carried out for ascertaining the baseline scenario within the project area for
different environmental components as follows:
Micro Meteorology: Weather monitoring station was used to monitor wind speed, wind
direction, temperature and relative humidity on hourly basis.
Ambient Air Quality: For assessing ambient air quality, monitoring was done within the
project site.
Water Analysis: Water sample from site was collected and analyzed as per drinking water
standards for different parameters to ascertain water quality.
Soil Analysis: Sample was collected and analyzed from the project area to estimate the soil
quality and its nature.
Noise: An integrated sound level meter was used to monitor noise levels on basis within the
project area.
Biological: The detailed flora and fauna study has been conducted to ascertain the different
species available within the study area.
Demography: Status of demography and socio-economic features within 10 km radius of
project site has been collected from the secondary sources.
7.4 Proposed Schedule of Environmental Monitoring
84
Monitoring is one of the most important components of a management system. Continuous
monitoring needs to be carried out for regulatory requirements, environmental effects and
performance of EMP implementation. Environmental monitoring program is a vital process of
any management plan of the development project. This helps in assessing the potential problems
that resulting from the proposed project, changes in environmental conditions and effectiveness
of implemented mitigation measures.
Table 7-2: Time Schedule for Post Project Environment Monitoring
S.
No
Area of
Monitoring
Sampling
Locations
Parameters to be
Analyzed
Frequency
of sampling
Air pollution monitoring
1 Stack Emission Each utility stack As per consent of
TPCB/CPCB Once in six month
2 Ambient Air Quality As per consent of
TPCB/CPCB Once in six month
3 Work zone
Environment All plant PM, SO2, NOx, CO. Once in six month
Water Pollution Monitoring
4 Ground and surface
water
Two sampling
locations
pH, TSS, COD, BOD,
TDS, Chloride, Sulphate
etc.
Once in Six month
Soil Pollution Monitoring
5 Soil Four sampling
locations of
Impact Area
As per consent of RPCB Once in Six month
Noise Pollution Monitoring
6 Noise
Noise generating
units
Sound Pressure Levels
(Leq) Once in Six month
Five sampling
locations
within Plant
Sound Pressure Levels
(Leq) Once in Six month
7.5 Proposed Investment for the Environment Control Measure
Total capital cost/annum for environmental pollution control measures for proposed expansion
would be Rs 75.00 Lac.
Budget for Implementation of Environmental Management Plan
S. No Component Capital cost for the
proposed expansion in
Lakhs
1 Pollution equipment for Induction Furnace 75
2 Greenbelt development 5
3 Environmental management cell 25
4 CER 112
85
Total 217 Lakhs
7.6 Staff Requirements for Post-Project Monitoring
An environment protection cell will be created at Mahalakshmi Profiles Pvt. Ltd. directly under
General Manager / Production Manager. This cell will consist of the following persons and have
the responsibility of air, water and land environmental monitoring:
Environmental Engineer: One
Chemist: One
Technician: One
86
8 ADDITIONAL STUDIES
8.1 Public Hearing
This Draft report is being submitted for conducting Public Hearing.
8.2 Risk
Managing these accidental risks in today’s environment is the concern of every industry
including steel, because either real or perceived incidents can quickly jeopardize the financial
viability of a business. Many facilities involve various manufacturing processes that have the
potential for accidents which may be catastrophic to the plant, work force, environment, or
public. Risk analysis involves the identification and assessment of risks; the neighboring
populations are exposed to as a result of hazards present in the plant operation. This requires a
thorough knowledge of failure probability, credible accident scenario, vulnerability of
populations etc. The risk analysis is often confined to maximum credible accident studies.
The main objectives of the Risk Assessment Studies are as given below:
To identify the source of hazards in the unit.
Assessment of risk on basis of different tools available.
To safeguard employees and people in vicinity.
To minimize damage to property and environment.
To inform the employees, the general public and the authority about the hazards / risk
assessed, safeguards provided, residual risk if any and the role to be played in them in
the event of emergency.
To inform authorities and mutual aid centers to come for help.
To affect rescue and treatment of casualties.
To secure the safe rehabilitation of affected areas and to restore normalcy.
8.3 Risk Assessment & an Approach to Emergency Preparedness Plan
Risk assessment study includes study of nature of hazards due to the proposed expansion of the
M.S. Ingots/Billets manufacturing unit including operations activities and machinery handling.
The study includes:
Preliminary identification of hazardous area.
Identification of cause of accident.
Analysis of maximum accidental scenarios.
87
Study of characteristics of risk levels.
Evaluation of damage criteria.
Hazard identification provides information on hazardous substances, their nature, quantities and
details of storage.
Preliminary hazard identification is used to identify typical and often relatively apparent risk
sources and damage events in a system.
8.4 Identification of Hazards
8.5 Major Hazards
Hazard is the associated term with material, which is a measure or the likely hood of the damage
to human working with, or studying the material in question.
All the probable potential hazardous is classified under different heads.
Fire Hazards: Since the Stone Age term 'fire' is associated with fear. It is very dangerous if
occurs in uncontrolled manner. When a liquid is used having flash point below the normal
ambient temperature, it could, in suitable circumstances, liberate a sufficient quantity of
vapour to give rise to flammable mixtures with air.
Toxic Gas Release Hazards: Toxic substances affect in three ways by ingestion, absorption
& inhalation
Explosion Hazards: Release of energy in a rapid and uncontrolled manner gives rise to
explosion
Corrosion Hazards: Corrosion is a chemical reaction-taking place at the surface of metal
M/s Mahalakshmi Profiles Pvt. Ltd. is M.S. Ingot/Billet manufacturing unit. Thus, it possess
fire, explosive hazards because it deal with molten metal of high temperature.
The lists of source of fire and explosive hazards are given below:
Induction furnace with CCM
Ladle furnace
Rolling mill.
88
In all the above furnaces the temperature is too high and continuous cooling is required but if the
cooling fails there are chances of explosion. The molten metal taken through ladle furnace to
CCM and spillage during the travel can cause burn and fire. In rolling mill the molten metal
travel through series of mills and there are chances of burn while handling the bars. Along with
this the induction furnace is electric fired thus, higher amount of power load is required which
may sometime causes risk of fire in electric wiring.
Following are the measures to prevent the hazards:
Cooling of induction furnace should be continuous and back up cooling system should
be installed in case one of the systems fails to cool.
Overhead water tank should be placed for continuous water supply.
D.G. set should be installed for power back up and prevent sudden shut of furnaces.
The worker should be provided with gloves and shoes to prevent any burn incidences.
The wiring in the industry should be fire insulated to prevent any fire incidences
Organization of an investigative team to study the accident and to record the same to
avoid repetition of such an accident in future.
Provide training to specific company personnel in first aid as well as preliminary
rescue operations.
Arrangement for medical aid centers being informed immediately in case of such an
event.
8.6 Accidents
Process Operations
The process operation may lead to serious injuries at the site.
Power failures.
Failure of utility services.
System failure
Defective communication system
Types of Accidents
In steel industries accidents may occur due to the mishandling of the materials.
In steel making process burns may occur due to the heat generation in furnace.
Improper handling of mechanical transportations within the work areas.
89
8.7 Risk Assessment
Risk will be assessed by:
To identify potential hazard areas.
To identify the chances of explosion.
Recommendations to minimize accidental possibilities.
Preparation of Disaster Management Plan (DMP)
Identifying the emergency plan.
8.8 Risk Prevention Methods
Safety And Health Measures (Safety Organization)
Safety organization is of prime importance in the steel industry, involving all persons in site
hazard assessments, behavior observation and feedback exercises can promote positive safety
attitude and focus work groups to prevent injuries and illnesses.
Accident statistics identifies danger areas and require additional protection as well as greater
stress on housekeeping. The value of different types of protective clothing will be evaluated
and the advantages can be communicated to the workers concerned.
Training
Training will include information about hazards, safe methods of work, avoidance of risks and
the use of PPE. Training and refresher courses for all levels of personnel are particularly
valuable. They will be familiarized personnel with safe working methods, unsafe acts to be
prescribed, safety rules and the chief legal provisions associated with accident prevention.
Training will be conducted by experts and will make use of effective audio-visual aids. Safety
meetings or contacts will be held regularly for all persons to reinforce safety training and
awareness.
Engineering and Administrative Measures
All dangerous parts of machinery and equipment, including lifts, conveyors, long
travel shafts and gearing on overhead cranes, will be securely guarded. Preventive
maintenance plan should be adopted.
Proper housekeeping should be followed.
90
Industrial Hygiene
Good ventilation system with proper air circulation and maintaining the cleanliness
and housekeeping.
To improve work environment, induced ventilation will be installed to supply cool air.
Pedestal fans/ blowers are provided to give the comfort of working. Heat protection
can be provided by installing heat shields between workers and radiant heat sources,
such as furnaces or hot metal, by installing water screens or air curtains in front of
furnaces or by installing heat-proof wire screens.
Acclimatization to the work environment.
Wherever possible, sources of noise will be isolated.
Personal Protective Equipment
All parts of the body are at risk in steel industries. Type of protective wear required will vary
according to the activities & location. Those working at furnaces need clothing that protects
against burns-overall of fire-resisting material, spats, boots, gloves, helmets with face
shields/goggles. Safety glasses and helmets are imperative in almost all occupations and gloves
are widely necessary.
Medical Supervision
Medical examinations are of great importance in selecting persons suitable for the iron
and steel making industries.
Medical supervision required for those exposed to heat stress; periodic chest
examinations will be provided for those exposed to dust, and audiometric
examinations for those exposed to noise; mobile equipment operators will also receive
periodic medical examinations to ensure their continued fitness for the job.
8.9 Disaster Management Plan Including Risk Assessment and Damage Control
Rapid development has proposed wide-ranging hazards threatening safety and health of people.
Accidents may adversely affect the environment and the people living in the vicinity. These
accidents can be minimized to a great extent by proper procedures, handling and training.
8.10 On-Site Emergency Plan
The emergency is caused by an accident that takes place in a hazardous installation and the
effects are confined to the factory premises involving the people working in the factory. On-site
91
emergency plan is dealing with eventualities and it is the responsibility of the occupier, to
prepare/ implement necessary measures to contain the severity of cause of disaster to the bare
minimum. Furnishing of relevant information to the district administration authority for the
preparation of the off-site emergency plan is statutory responsibilities of the occupier of every
industry and other units.
8.11 Objectives
Maximize the resource utilization and combined efforts towards emergency operations. It
broadly covers the following:
Safety of the personal located in the premises.
To minimize the effects of accidents on people, property and environment.
To take remedial measures within time.
To utilize the internal resources in the most effective way.
To minimize the damage.
To keep the required emergency equipment at designated places.
To keep the concerned personnel fully trained for the use of emergency equipment.
To mobilize effected persons.
8.12 Basic Contents of Disaster Management Plan (DMP)
An emergency is said to have arisen when operators in the plant are not able to cope up with a
potential hazardous situation i.e. loss of control of an incident causes the plant to go beyond its
normal operating conditions, thus creating danger. When such an emergency evolves, chain of
events affect the normal working within the factory area and / or which may cause injuries, loss
of life, substantial damage to property and environment both inside and outside the factory and a
DISASTER is said to have occurred.
The various steps involved in the process of Disaster Management can be summarized as:
Minimize Risk Occurrence (Prevention)
Rapid Control (Emergency Response)
Effectively Rehabilitate Damaged Areas (Restoration)
Basically, the Disaster Management Plan (DMP) contains the following aspects:
Location of the site.
Brief Description of Unit.
Details of major potential hazards.
92
Identification of specific type of disasters.
Action plan – specific responsibilities.
Declaration of emergency with emergency action plan.
Evacuation and assembly points.
Evaluation of implementation system.
8.13 Purpose & Scope
The principal aim of DMP of steel unit is prevention of identified major hazards. It is totally
committed to “Total Quality Assurance” from conception stage to enable its objective of
prevention. The control strategy adopted could be reducing potential by way of minimizing the
handling of such materials manually by individuals both in process and storage within the
purview of continuous operation.
The adopted control measure could be well structured and well-rehearsed. On site plan which
could intercept any such occurrence with speed and rectify by ensuring safety of worker,
equipment, public and ultimately the environment as a matter of priority. General details like
location, project layout, neighboring entities and the assistance they can render etc are as
follows.
The important elements considered in this plan are:
Statutory requirements.
Roles and Responsibilities.
Communications during emergency.
Emergency shutdown & control of situation.
Rescue & rehabilitation.
Emergency facilities.
Important information.
The primary purpose of the on-site emergency plan or DMP is to control and contain the incident
and to prevent it from spreading. It is not possible to cover every eventuality in the plan and the
successful handling of the emergency will depend on appropriate action and decisions being
taken on spot.
8.14 Preventive Measures & Plans
DMP specifies the actions to be taken in case of such incident, including its prevention,
corrective action so as to mitigate such occurrence by the proponent. Practice and procedure with
respect to the operational hazards, equipment failure, human safety, malfunctioning of safety
interlocks. Natural disasters relevant to unit and its different section of operation will be
93
formulated and a detailed disaster management action plan will be prepared and made available
to all concerned persons to take care of the following aspects.
To install emergency alarm for immediate information.
A suitable location inside the unit will be demarcated for assembly point.
Intercom will be provided to all departments for easy and immediate means of
communication.
At sensitive fire prone areas fire alarm and fire hydrant lines will be provided.
Workers will be trained regularly to use personal protective equipment.
Mock drill will be conducted at regular interval to evaluate the effectiveness of the
emergency preparedness plan.
First aid boxes will be made available at various sensitive points to meet the
requirement.
Personnel will be appointed and responsibilities will be assigned.
Color-coding will be followed as per the statutory requirements.
All heavy moving machines will be properly maintained and protected and valid
license will be obtained before their usage.
All applicable Indian laws, rules and regulations for which company subscribes shall
be strictly followed under a senior qualified environment and safety personal.
8.15 Emergency Management
The emergency control center will be located in an area of minimum risk. Suitable location from
where clear view of the unit is possible.
8.16 Infrastructure at Emergency Control Centre
Emergency control center contains the following:
An adequate number of external telephones.
An adequate number of internal telephones.
Areas where there are large inventories of hazardous materials.
Sources of safety and first aid equipment.
The fire-fighting system and additional sources of water.
Site entrance and roadways, including up-to-date information on road traffic.
Assembly points.
Vehicle parking.
Additional work and lay out plans detailing alternate routes and affected areas during
an emergency.
A list of key personnel, with addresses, telephone numbers, etc.
94
The emergency control center will be located in an area of minimum risk. Suitable location from
where clear view of the unit is possible.
8.17 Health and Safety Measures For The Workers
Belts etc: The fitness of the belts should be regularly checked.
Helmets: To avoid any head injury helmets to be provide.
Machinery: All machines should be operated as per operation manual.
Methods of work: Work instructions should be followed.
Electricity: Electric installation should be carried during the idle hours of working.
Medical Check-up: Regular medical Checkups shall be carried as per the annual plan.
8.18 Safety of Personnel
Adequate personal safety equipment as applicable to the work i.e, industrial safety shoes, hand
gloves, ear muffs, welder’s screen, aprons, gas masks, respirators, safety belts, goggles, etc. are
to be provided to the workers.
8.19 Emergency Action Plan for Fire
The fire proximity suits be made available at the site to fight with the fire & Adequate personal
safety equipment as possible to the work i.e. industrial safety shoes, hand gloves, ear muffs,
welder’s screen, aprons, gas masks, respirators, safety belts, goggles etc. are to be provided to
the workers.
8.20 Emergency Action Plan For Electric Shock Casualties
Rescue And First Aid
Provide first aid without delay.
Switch off the supply immediately.
Use of non-conducting material to separate the victim.
The rescuer should use the gloves or using a jacket to pull the victim.
8.21 First Information
The first person who observes/ identifies the emergencies will inform by shouting and by
telephone to the Shift- in-charge and fire station about the hazard. The shift-in-charge will
inform to the incident controller.
95
8.21.1.1 Declaration of Emergency
The Chief Incident Controller taking into account of the severity of the situation will declare
emergency.
Emergency Alarm: Emergency will be declared by Emergency alarm, which will be sounded by
fire station on receipt of orders from Shift in-charge/ Works Incident Controller.
Evacuation: In an emergency it is necessary to evacuate personnel from affected areas and as
precautionary measure to evacuate non-essential workers. In the first instance from areas likely
to be affected will be evacuated immediately. The evacuation will follow at Assembly points.
Mock Drills: It is imperative that the procedures laid in this plan are put to the test by
conduction Mock Drills. The mock drills will be carried out by the step as stated below.
First Step: Test the effectiveness of communication system.
Second Step: Test the speed of mobilization of the unit emergency teams.
Third Step: Test the effectiveness of search, rescue and treatment of casualties.
Fourth Step: Test emergency isolation and shut down and remedial measures taken on
the system.
Fifth Step: Conduct a full rehearsal of all the actions to be taken during an emergency.
The Disaster Management Plan will be periodically revised based on experience gained from
mock drills. There are two types of mock drills recommended in Disaster Management Plan –
Full Mock Drill (to be conducted at least once in 6 months) and Disaster Management Efficacy
Drill (to be conducted at least once in 3 months.)
Full Mock Drill: This will be conducted with Unit Head, Head of O & M as General Manager;
Heads of Operation, Maintenance, Medical, Personnel, Security, Auto Base and Materials as
Members and Head of Safety as Convener and it shall test the following:
Properly functioning of Emergency Control Centre.
To evaluate communication of the Disaster Plan to all segments of employees.
To ensure that all facilities as required under the plan are available.
To ensure that the necessities under material assistance scheme is properly documented
and the concerned employees are fully aware in this regard.
To ensure that the employees are fully aware to fight any emergency.
8.21.1.2 Objectives of Onsite Emergency Plan
96
A quick and effective response at that time can have tremendous significance on whether the
situation is controlled with little loss or it turns into a major emergency. Therefore, the purpose
of this Onsite Emergency Plan (OSEP) is to provide basic guidance to the personnel for
effectively combating in case of an emergency.
To maximise the resource utilisation & combined efforts towards emergency operations as
follows:
During an Emergency
To increase thinking accuracy and to reduce thinking time.
To localise the emergency and if possible eliminate it.
To minimise the effects of accident on people and property.
To take correct remedial measures in the quickest time possible to contain the incident
and control it with minimum damage.
To prevent spreading of the emergency situation to other sections.
To mobilize the internal resources and utilize them in the most effective way.
To arrange rescue and treatment of causalities.
8.21.1.3 Elements of Onsite Emergency Plan
The important elements considered in this plan are:
Emergency Organisation
Emergency Procedures
Emergency Facilities
Roles and Responsibilities
Emergency Communications
Emergency Shutdown
Emergency Action for Control of situation and Mitigation
Important Information
8.21.1.4 Methodology
The consideration in this emergency planning includes the following:
Identification and assessment of hazards and risks
Identifying, appointment of personnel & Assignment of Responsibilities
Identification and equipping Emergency Control Centre
Identifying Assembly, Rescue points, Medical Facilities
Formulation of plan and of emergency sources
Action on site Training, Mock Drill & Evaluation
An emergency organisation is constituted towards achieving objectives of this plan.
97
General Manager is designated as site controller and over all in charge of onsite
emergency management. Head- Production is designated as an alternate to general
manager. Head- Laboratory is second alternate.
Mechanical, Head - Laboratory, Security In-charge are designated as Emergency
Coordinators.
Shift In-charge of Production is designated as Incident Controller. This being a process
industry, round the clock, Shift In-charge would be available.
All the above are Key Persons in Onsite Emergency Management.
All Engineers / Supervisors, Chemists in the shift, Assistants in the Shift, Operators in the
shift, Technicians in the Shift, Trained First Aiders, Trained Fire Fighters, Security
Guards, Drivers of the Transport Vehicles are designated as Essential Employees.
Figure 8-1: Elements of Onsite Emergency Plan
98
Figure 8-2: Emergency Organisation in Shift
Onsite Controller
In the absence of Site Controller, assumes the role of Site Controller in addition to his
role as Incident Controller. On arrival of Site Controller, hands over the charge of Site
Controller by word and continues to act at Incident Controller.
Proceed to site quickly
Assess the magnitude of the incident
Arrange to inform the Occupier
Protects him and initiates the emergency procedure to secure the safety of workers and
minimize damage to installation and property.
Direct, rescue and firefighting operations until (if necessary) the fire brigade arrives
Ensure that adequate Personal Protective Equipment is available for Emergency Team
Arrange for search of causalities
Arrange evacuation of non-essential workers to assemble at designated assembly point.
Emergency Coordinator (Departmental Heads)
On hearing about an Emergency, reach ECC and assist Site Controller in all respects
Seek information and instruction whenever necessary
Ensure special equipment like compressed air, power supply
During normal times, take stock of emergency needs including special equipment, blinds,
sealing material, available.
Seek information and instruction whenever necessary
Organize emergency illumination including cutting of power supply to affected areas
Emergency Coordinators (Personnel Manager)
On hearing about an Emergency, reach ECC and assist Site Controller in all respects
Seek information and instruction whenever necessary
External Mutual Aid Site Controller Emergency Coordinators
Incident Controller
Essential Employees
in Shifts
99
Send Information to Emergency Services like Fire / Ambulance
Organize Emergency Transport for shifting injured / affected
Organize Emergency and First Aid for injured / affected
Organize head-count for rescue / evacuation / and organize rehabilitation and other
humanitarian needs of those who are evacuated and send proper intimation to their kith
and kin.
Maintain sufficient stock of first aid material, stretchers and other emergency equipment
for rescue.
Organize liaison with neighboring industries regarding mutual aid
Keep informed Statutory Authorities and Management, on the instructions of Site
Controller.
Direct Security In-charge regarding control at gate and for law and order coordinate with
Police Authorities and appraise Site Controller on a continuous basis .
Coordinate with other Emergency Coordinators for effective control of situation
He is responsible for maintenance of Emergency Control Centre and Assembly Points
Emergency Coordinators (Security In-Charge)
On hearing about an Emergency, reach ECC and assist Site Controller in all respects
Seek information and instruction whenever necessary
Ensure availability of firefighting equipment in order
Train regular and new Security Guards regarding plant hazards and demonstrate
emergency actions and firefighting, rescue and evacuation.
Organize control measures at gate to prevent unauthorized persons entering the plant
during emergency and liaise with police officials in maintaining law and order.
Direct unconnected truck drivers and vehicles etc. to move away from plant to a safe
location
Security guards posted in night are to be fully informed of emergency telephones and
how to communicate emergencies if required.
Arrange Emergency Telephone numbers displayed in security and are to be updated as
and when there is a change.
8.21.1.5 Risk Assessment Matrix
Likelihood
Almost Certain
Probable
Possible
Possible (under unfortunate circumstances)
Rare
100
Severity
Fatality
Major Injury, resulting in disability
Injury Requires, Doctor's or Hospital attendance
Minor Injury, 1st Aid required
Minor Injury, 1st Aid not required
Risk Rating
Is calculated by multiplying the likelihood against the consequences, e.g. taking a likelihood of
4, which is classified as Probable, and multiplying this against a consequence of 2, which is
classified as a Minor Injury 1st aid required, would give you and overall risk rating of 8, which
would be risk rated as a low risk.
Table 8-1: Risk Assessment
High risk equals 16 to
25
High Risks activities should cease immediately until
further control measures to mitigate the risk are introduced.
Medium risk equals 9
to 15
Medium Risks should only be tolerated for the short-term
and then only whilst further control measures to mitigate
the risk are being planned and introduced, within a defined
time period.
Note: Medium risks can be an organizations greatest risk,
it's achilles heel, this due to the fact that they can be
tolerated in the short-term.
Low risk equals 1 to 8 Low Risks are largely acceptable, subject to reviews
periodically, or after significant change etc.
Table 8-2: General Risk Assessment
Flow of Communication during Emergency
Whoever
Notices,
Informs
incident
controller,
Site
controller
Site
controller
would cause
informed to
all
concerned in
the plant
If emergency
has a potential
of turning an
off-site
controller
would send
information to
all concerned
101
S.
NO.
Hazards
& details
Persons
at risk Control measures
Action plan in case of
emergency
Risk
Likeli
hood
Seve
rity
Risk
rating
L S Rr= l x
s
1
Induction
furnace-
fire
hazard
caused
by
fuels/igni
table
substanc
es.
Persons
working
in the
Furnace
area-
Burns
may be
possible
if
directly
coming
in
contact.
Emergency alarm
to be put on to
signal the
emergency.
Switch off the
system.
2 3 6
Firefighting
equipment
power/foam type
extinguishers on
vehicles and
mounted on walls
are kept readily
available
Water hose will be
operated to set out
the fire depending
on the situation.
Water hose is
provided.
Outside fire brigade
is to be called if the
fire cannot be
extinguished
immediately.
No smoking zone
declared.
Inform the
occupier/manager
and activate the
onsite emergency
plan.
Plant workers are
trained to fight
fire.
Immediate first aid
to the victim and
sent to hospital for
treatment.
2
In case of
furnace
crack,
molten
metal
may leak
causing
splash of
hot
metal.
Persons
working
in the
tapping
area.
Continuous
monitoring of
furnace shell is
done to maintain
and observe proper
temperature.
Immediately drain
out the furnace by
pouring or tapping
out. Molten splashed
metal is allowed to
cool down before
removing.
2 4 8
Movement of staff
and labor is not
permitted near the
Further process is
stopped till repairs
are conducted.
102
Table 8-2: General Risk Assessment
S.
NO.
Hazards
& details
Persons
at risk Control measures
Action plan in case of
emergency
Risk
Likeli
hood
Seve
rity
Risk
rating
L S Rr= l x
s
furnace.
Heat zone sign is
displayed near the
furnace.
In case of fire,
firefighting
equipment are used
to set out the fire.
Safety shoes,
safety goggles,
hand gloves, apron
and safety helmet
provided to
workers.
Plant workers are
trained to fight fire
3
Slag pot
leakage
due to
breakage.
Persons
working
in the
tapping
area.
Frequent checking
of slag pot to be
observed.
Further process
should be stopped
till slag cools down
and after cooling the
slag is removed
carefully.
3 4 12
4
Molten
hot metal
may fall
on
human
body.
Persons
working
in the
tapping
area.
Whole process is
done under
supervision of
qualified/ trained
persons
No entry zone
should be declared.
3 4 12
Only trained labors
are allowed with
proper heat proof
dress/gum, boots/
aprons
First aid should be
given to the victim
and send to hospital
for further treatment. Entry of other
workers /persons is
strictly prohibited.
5 Hoist
rope
Persons
standing
No movement of
strange people in
Crane movement is
carried out only after 1 5 5
103
Table 8-2: General Risk Assessment
S.
NO.
Hazards
& details
Persons
at risk Control measures
Action plan in case of
emergency
Risk
Likeli
hood
Seve
rity
Risk
rating
L S Rr= l x
s
breakage
in E.O.T.
crane
below
the
crane
bay and
in
nearby
areas.
crane bay is
permitted.
getting the signal of
line clearance.
Frequent checking
of rope and other
load bearing
material before
process is started.
Cranes are not
allowed to operate
without line clear
signal.
Weak rope is
immediately
replaced.
6
Electrical
Transfor
mer-
Electrical
shock
and fire
Persons
near the
transfor
mer
Shock proof
insulated PCC
Platform.
Cut off power
supply.
2 3 6
Treat the injured for
electrical shock.
If fire is caused,
immediately fight
fire with available
resources,
summoning outside
help if necessary.
7
Lab-
Chemical
s-in case
of bottle
breakage,
causes
burns
and
damage
to
Persons
working
in the
lab.
Proper care should
be taken while
handling the
chemicals.
Immediately treat
the persons as
guided in the MSDS.
3 2 6 First aid box
should be available
at the site with all
necessary and
required
medicines.
Hospitalize the
effected person if
deemed necessary.
104
Table 8-2: General Risk Assessment
S.
NO.
Hazards
& details
Persons
at risk Control measures
Action plan in case of
emergency
Risk
Likeli
hood
Seve
rity
Risk
rating
L S Rr= l x
s
respirator
y
systems
due to
inhalatio
n.
Firefighting
equipment like fire
extinguishers, sand
buckets should be
always available.
Instruction boards
to be displayed for
knowledge of
other workers to
care of the
situation in the
event of
occurrence.
8
Cooling
Tower-
Burns
from
returning
hot water
Persons
working
with the
cooling
tower.
All workers are
not permitted near
the tank and hot
water line. Railing
is provided all
around the tank.
Victims are first
aided by trained
person and then
referred to
Doctor/Hospital.
2 3 6
Always
precautionary
measures should
be taken and
adopted.
If any worker gets
hurt, then immediate
first aid should be
provided to him and
he should be referred
to the
Hospital/doctor for
further treatment.
9
Charging
of scrap
and other
material
in
furnace
Persons
working
in the
raw
material
handling
Workers are
provided with
gloves & proper
equipment to
handle and feed
the scrap.
Immediate first aid
should be given to
the victim by trained
person and refer to
the doctor/hospital
for further treatment.
3 3 9
105
Table 8-2: General Risk Assessment
S.
NO.
Hazards
& details
Persons
at risk Control measures
Action plan in case of
emergency
Risk
Likeli
hood
Seve
rity
Risk
rating
L S Rr= l x
s
and
moving
parts like
fly
wheel,
roller
stand and
other
accessori
es-
cut/burn
and fire
may be
possible.
yard and
in the
furnace
floor.
Workers charging
the materials in the
furnace are
equipped with fire
proof dress and
proper equipment
to handle the scrap
and material.
Fireproof system
made available and
firefighting
equipment like
extinguisher &
water with
sufficient number
of points easily
available.
Only trained &
qualified people
will operate the
furnace.
10
Furnace
transfor
mer-Fire
Hazard
Persons
working
in
Furnace
area and
in the
electrica
l
sections.
Furnace will be
operated with
prescribed load.
Power line should be
immediately put off.
2 3 6
Carefully changing
of tap on load.
Firefighting steps
should be taken to
stop fire.
Temperature of
furnace/
transformer should
be observed
continuously.
Further processing
must be stopped till
repairing is over. Furnace oil
level/quality
should be
106
Table 8-2: General Risk Assessment
S.
NO.
Hazards
& details
Persons
at risk Control measures
Action plan in case of
emergency
Risk
Likeli
hood
Seve
rity
Risk
rating
L S Rr= l x
s
mentioned.
Unauthorized
persons will be
restricted and no-
Entry Board will
be put up.
11
Water
tank-
drawing
of
personne
l
Persons
near the
water
tank
Water tank will be
fenced/ covered. Drowned person
should immediately
be given first aid.
2 2 4 The tank will not
be permitted for
general utility.
12
Control
Room
electrical
shock
Persons
working
in the
control
room
Earth leakage
circuit breaker
installed.
Main supply will be
immediately shut
off.
2 2 4
Responsibility;
Site Controller; head-production
Incident controller: Shift-in charge
Emergency Co-coordinators: Departmental Heads.
8.22 Heat Stress
Aim is to maintain body core temperature within +1°C of normal (37°C). This core body
temperature range can be exceeded under certain circumstances with selected populations,
environmental and physiologic monitoring, and other controls.
8.23 Source
High temperature and humidity; direct sun or heat; limited air movement; physical exertion; poor
physical condition; some medicines; inadequate tolerance for hot workplaces; and insufficient
water intake can all lead to heat stress
107
Table 8-3: Heat Stress
Signs &
symptoms Cause Symptoms Treatment Prevention
Heat Rash
Hot humid
environment;
plugged sweat
glands.
Red bumpy rash
with severe
itching.
Change into dry
clothes and avoid
hot environments.
Rinse skin with
cool water.
Wash regularly to
keep skin clean
and dry.
Sunburn
Too much
exposure to
Sun.
Red, painful, or
blistering and
peeling skin.
If the skin blisters,
seek medical aid.
Use skin lotions
and work in the
shade.
Work in shade;
cover skin with
clothing; use sun
protection lotions
with the factor 15.
Heat
Cramps
Heavy
sweating
Painful cramps in
arms, legs or
stomach which
occur suddenly at
work or later at
home.
Move to a cool
area and drink cool
salted water.
While working in
the heat, workers
should put salt on
their food and
avoid taking salt
tablets.
Fainting
Not enough
blood flowing
to the head,
causing loss
of
consciousness.
Sudden fainting
after two hours of
work; cool moist
skin; weak pulse.
Fainting may be
due to the heart
attack get the
medical aid
immediately and
move to the cool
place; loosen
clothing and make
the person lay
down. Offer sips of
cool water.
Reduce activity
levels and/or heat
exposure. Drink
fluids regularly.
Drink fluids
regularly.
Heat
exhaustion
Inadequate
salt and water
intake causes
a person’s
body’s
cooling
system to start
to break
down.
Heavy sweating;
moist skin; body
temperature over
38 deg.
Centigrade; weak
pulse; normal or
low blood
pressure; person
is tired, weak
clumsy, upset or
confused; is very
thirsty.
Arrange medical
aid
Reduce activity
levels and/or heat
exposure.
Regularly. Drink
fluids regularly.
Heat Stroke
The body used
all its water
and salt, it
High body
temperature(over
41 deg.
Call Ambulance.
Meanwhile remove
the excess
Reduce activity
levels and/or heat
exposure.
108
Table 8-3: Heat Stress
Signs &
symptoms Cause Symptoms Treatment Prevention
will stop
sweating and
will cause
body
temperature to
rise.
Centigrade) clothing; start fan
and spray with
cool water; offer
sips of cool water
if the person is
conscious.
Regularly. Drink
fluids.
Table 8-4: Permissible Heat Exposure Threshold Limit Value
WORK LIGHT MODERATE HEAVY
Continuous work 30.0˚C (86˚F) 26.7˚C (80˚F) 25.0˚C (77˚F)
75 % work, 25% rest,
each hour 30.6˚C (87˚F) 28.0˚C (82˚F) 25.9˚C (78˚F)
50 % work,50% rest,
each hour 31.4˚C (89˚F) 29.4˚C (85˚F) 27.9˚C (82˚F)
25 % work,75% rest,
each hour 32.2˚C (90˚F) 31.1˚C (88˚F) 30.0˚C (86˚F)
8.24 Occupational Health & Safety
In general occupational health and safety is an interdisciplinary area concerned with
safety, health and welfare of people engaged in industries.
The main concerns of occupational health are:
Promotion and maintenance of the highest degree of physical, mental and social well-
being of workers in all occupations
Prevention amongst workers of departures from health caused by their working
conditions
Protection of workers in their employment from risks resulting from factors adverse to
health.
Placing of worker in an occupational environment suitable to his physiological and
psychological capabilities.
Working conditions and the nature of employment tend to have major repercussions on the
health of a workman. The concept of ‘Occupational health’ has evolved from work-related
ailments. Occupational health broadly means any injury, impairment or disease affecting a
worker or employee during his course of employment. Further, it not only deals with work-
related disorders but also encompasses all factors that affect community health within it.
109
The occupational health and safety laws exist in all countries including India which makes the
employee of the worker responsible for any damages to its work force. The ignorance of law
cannot be an excuse under any circumstances. Hence, the owners and managers must have the
basic knowledge of the subject.
8.25 Legal Provisions
The Indian Constitution has shown notable concern to workmen in factories and industries as
envisaged in its preamble as Directive Principles of State Policy.
For securing the health and strength of workers, men and women
That the tender age of children is not abused
That citizens are not forced by economic necessity to enter avocations unsuited to their
age or strength
Just and humane conditions of work and maternity relief are provided and,
That the Government shall take steps, by suitable legislation or in any other way, to
secure the participation of workers in the management of undertakings, establishments or
other organizations engaged in any industry
The Factories Act, 1948, the Mines Act, 1952, the Dock Workers (Safety, Health & Welfare)
Act, 1986 are some of the laws, which contain provisions regulating the health of workers in an
establishment. Whereas the Employees State Insurance Act, 1948 and the Workmen’s
Compensation Act, 1923 are compensatory in nature. It may be sufficient to indicate at this stage
that metallurgical industries are classified as hazardous industry and legal provisions must be
adhered to avoid any harm to work force and local residents in the vicinity of the industry.
8.26 Role of Management
It is believed that “the safety begins at the top”. The ‘Safety Engineer’, ‘Foreman’ and
“Supervisor’ can never achieve good result if the top management does not take lead in the
promoting and maintaining a high standard of safety and health at work place. The cost towards
‘Health & Safety’ must be part of total production cost and should not be treated as extra.
The management concerned with safety has duties as below:
Have undeniable decision making authority
Lead in the establishment of rules and policies designed to promote safety and health,
accident prevention and hazard awareness
Be responsible for maintaining the safety policy, safety manual, the proper safety and
health training documentation and the necessary recordkeeping
Make all employees aware of the established safety and health rules of the safety policy
110
Hold each employee responsible and accountable
Monitor all aspects of the safety policy and safety manual
Promote and ensure proper safety training, worksite audits, accident investigations, and
hazard control
Manage the safety team (committee)
Conduct or coordinate all site safety inspections
Manage safety violation and award program
Provide and/or coordinate safety training for all new employees
Be notified immediately regarding accidents and/or injuries
Eliminate all hazardous practices performed by employees
Assign and train a replacement in the event he/she is unavailable for duty
In any industry, particularly hazardous industry like metallurgical plants, the incidences do
happen with many safety provisions. This needs investigation and modifications in the safety
system. This requires accident statistics.
8.27 Accident Record
India has had legislation on occupational safety and health for past 50 years. However, the nation
lacks strong system to monitor and regulate incidences though it employs around 26 million
industrial workers besides millions who work in the informal sector with absolutely no
safeguards. The work safety improvements are possible when the related data is available for
analysis.
Accident
The occupational (industrial) accident can be defined as an undesirable event that results in a
certain length of disability and stoppages of work and time loss due to the effect of production
related dangerous factor. The accident may cause personal injury, material damage and loss of
production time.
Injury
The injury is an external damage to the human body resulting from accident. It can be
mechanical (bruise, cut, tissue rupture, breakage etc.), chemical (burn, acute intoxication and
poisoning), radiated (tissue regeneration, changes in the hematopoietic system) or combined
effect of more than one cause. The result of accident may be (serious, minor or no injury) may
cause temporary or permanent disablement.
Occupational Disease
The unhealthy condition caused to the person by exposure to unsafe working conditions
111
Occupational Poisoning: It is occupational disease caused by long exposure of relatively
small amount of poisonous material.
Accidental Poisoning: Acute intoxication is caused by penetration of large amount of
noxious substance in a short exposure.
Accident Investigation Form: It is the principle document that provides information for
record and statistical analysis of the data. This form gives the detail of the accident, injuries
by cause and identification of cause. This may help in making policy to avoid its re-
occurrence. This form must be filled within 24 hours
Accidental Statistics
The statistical method is based on total number of accidents (serious and minor) compiled for a
certain period of time. The statistical method is helpful in showing the distribution of accidents
by occupation, length of service, age or sex, cause or type, nature of injury, equipment involved,
and by organizational and technical factors.
The various indices used to indicate safety performance are following:
Number & Type: The total number of incidences and its type record may help in planning
the mitigation of incidents by adopting appropriate means.
The Frequency Coefficient (F): It is defined as number of incidents per 1000 man hour
exposure. It is expressed as;
F = (1000 T) / P,
Where, T - number of injuries for a given period
P - Total man hours of exposure.
The Severity Coefficient (S): It is defined as the average time loss (length of disability) due
to incident per one incident for a given period. This is expressed as
S = D / T,
Where, D - Time loss in days due to all incidents that occurred for a given period
T - Number of incidents in a given period.
Accident Responsibility: In the event of an incident causing loss of production time,
damage to equipment, injury to worker (minor, major, fatal) or loss of life the records form
the basis of fixing the responsibility of the incidence. This could lead to different types of
liability depending upon the nature of incident.
112
Disciplinary Liability: This implies the punishment in the form of disciplinary action by the
management which could be in the form of warning, reprimand, transfer, term demotion or
dismissal.
Administrative Liability: This implies penalties imposed by state authority for violating the
safety regulations causing the incident.
Financial Liability: This is compensation by the violator for losses and rehabilitation of the
victim decided by court of law.
Criminal Liability: This is a sanction by law for violating safety laws and industrial
regulations causing accident and other serious consequences.
8.28 General Safety at Work
The safety at work begins at the planning stage. While planning various manufacturing units to
provide safety measures like guards, emergency switches, interlocking and signaling (operating,
warning, and indicating). In addition the training, good housekeeping, color labeling, display
signs, notices etc. can help in improving safety at work and reduce the chance of accidents.
8.28.1.1 Safe Guards, Signals, Signs
The working areas must have safe guards at all moving and hazardous points to prevent casual
access. The moving cranes and equipment must have sound and light signals to keep people at
safe distance. The various activities in the area must be indicated by sign boards in suitably big
size to warn people. This must be in local language of the area with mostly known language like
English. Some typical sign are illustrated in figures 8.3.
In addition to possible hazards the workers and visitors may be advised to use protection wears
while working or entering in the area. The signs displaying such warnings are illustrated in figure
8.4
113
Figure 8-3: Some Typical Warning Signs Figure 8-4: Signs for Putting Protection
Wears in Various Areas of The Plant
8.28.1.2 Safety Guards
The use of safety helmet and shoes are mandatory in the plant area while the use of glasses, face
shield, dust mask, ear muff are advisable in many parts of the plant depending on the hazard
nature. Some of the safety gears are shown in figure 7.5
Figure 8-5: Commonly Used Safety Gears
8.28.1.3 Electric Safety
Several accidents occur due to defective electrical systems. The machine frame, casings, motor
guards, control panel etc. get connected to main electrical supply due to poor insulation, heat,
moisture etc. Such incidents could be avoided by using good quality electrical fittings, providing
electrical earth to the equipment, rubber / wooded matting at control panel.
8.28.1.4 Hoisting, Loading & Handling
114
The material is handled using cranes of different types. The ropes and chains are essential parts
of the system. The strength of ropes and wires require high safety factor (k) which is expresses as
k = P / S
Where, P – Breaking load, N
S – Maximum anticipated stress, N
The safety factor (k) is generally kept 5-6 in most cases. It is kept as 9 when people are to be
hoisted.
The stress in the rope depends on number of strand and the angle formed by pulling rope as
shown in figure 7.6. The rope type and its quality selection must be made accordingly. The rope
gets worn with time and use. These ropes must be inspected time to time before use.
The hook of the crane is a very critical component and must be tested periodically for any stress
defect.
Figure 8-6: Changes in Rope Stress Due to Pulling Rope Angle Caused by Sling Position
8.28.1.5 Safety Training & Drills
Safety training plays significant role in minimizing incident rate and fatality. A trained worker
not only is able to help himself but he can also save others under given situation. This safety
training is normally imparted to freshly employed persons but it is necessary to conduct refresher
courses for trained persons also. The periodic mock drill is necessary to check the fitness and
alertness.
115
8.29 Occupational Health Monitoring & Record
The working conditions and the nature of employment are known to have major repercussions on
the health of a workman. The concept of ‘Occupational Health’ has evolved from work-related
ailments. Occupational health broadly means any injury, impairment or disease affecting a
worker or employee during his course of employment. Further, it not only deals with work-
related disorders but also encompasses all factors that affect community health within it.
Article 21 of the Indian Constitution guarantees the protection of life and personal liberty of a
person. Various Supreme Court judgments have, under this "right to life" upheld the ‘right to
employees’ health.
In view of this provision the employer is obliged to provide health care to its worker during
employment and retirement period.
Health Examination
The workers must be medically examined at the time of employment to observe the physical
fitness and to know any ailment which may need care while placing him in some hazardous area.
The medical examination must be done for every worker on annual basis to monitor the effect of
working atmosphere on his health.
Health Record And Analysis
The industry is supposed to keep health records of all its employees starting from employment
date till their retirement.
These medical records must be analyzed annually to know the trend of employee health. In case
some serious trend is noted then suitable action should be taken to address such health issues.
Some typical health record analysis are given here as illustration.
Chest X-Ray: The chest X-Ray is conducted to reveal the health problems associated with
dust. Silicosis (particularly the acute form) is characterized by shortness of breath, cough,
fever, and cyanosis (bluish skin). It may often be misdiagnosed as pulmonary edema (fluid in
the lungs), pneumonia, or tuberculosis.
Spirometry Test: Pulmonary function tests are a group of tests that measure how well the
lungs take in and release air and how well they move gases such as oxygen from the
atmosphere into the body's circulation. Spirometry (meaning the measuring of breath) is the
most common of the Pulmonary Function Tests (PFTs), measuring lung function, specifically
the measurement of the amount (volume) and/or speed (flow) of air that can be inhaled and
exhaled. Spirometry is an important tool used for generating pneumotachographs which are
116
helpful in assessing conditions such as asthma, pulmonary fibrosis, cystic fibrosis,
and Chronic obstructive pulmonary disease (COPD).
Pulmonary function tests are done to:
Diagnose certain types of lung disease (especially asthma, bronchitis, and emphysema)
Find the cause of shortness of breath
Measure whether exposure to contaminants at work affects lung function
Electrocardiogram (ECG) Test: The electrocardiogram (ECG) is a diagnostic tool that
measures and records the electrical activity of the heart in exquisite detail. A typical ECG
record is illustrated in figure 7.10 Interpretation of these details allows diagnosis of a wide
range of heart conditions. These conditions can vary from minor to life threatening.
Audiometry Test: Audiometry is the testing of hearing ability, involving thresh-holds and
differing frequencies. Typically, audiometric tests determine a subject's hearing levels with
the help of an audiometer, but may also measure ability to discriminate between different
sound intensities, recognize pitch, or distinguished speech from background noise. Acoustic
reflex and otoacoustic emissions may also be measured. Results of audiometric tests are used
to diagnose hearing loss or diseases of the ear, and often make use of an Audiogram.
Noise-induced hearing loss (NIHL) is an increasingly prevalent disorder that results from
exposure to high-intensity sound, especially over a long period of time. The ear can be
exposed to short periods in excess of 120 dB without permanent harm — albeit with
discomfort and possibly pain, but long term exposure to sound levels over 80 dB can cause
permanent hearing loss.
There are two basic types of NIHL:
NIHL Caused by Acoustic Trauma: refers to permanent cochlear damage from a one-
time exposure to excessive sound pressure. This form of NIHL commonly results from
exposure to high-intensity sounds such as explosions, gunfire, a large drum hit loudly
and firecrackers.
Gradually Developing NIHL: refers to permanent cochlear damage from repeated
exposure to loud sounds over a period of time. Unlike NIHL from acoustic trauma, this
form of NIHL does not occur from a single exposure to a high-intensity sound pressure
level.
Vision Test: An eye examination is a battery of tests performed by an ophthalmologist and
optometrist assessing vision and ability to focus on and discern objects, as well as other tests
and examinations pertaining to the eyes. Health care professionals often recommend that all
117
people should have periodic and thorough eye examinations as part of routine primary care,
especially since many eye diseases are asymptomatic.
Eye examinations may detect potentially treatable blinding eye diseases, ocular manifestations of
systemic disease, or signs of tumors or other anomalies of the brain.
A refractive error (RE): or refraction error is an error in the focusing of light by
the eye and a frequent reason for reduced visual acuity.
Colour blindness: or colour vision deficiency is the inability or decreased ability to
see colour, or perceive color differences, under lighting conditions when color vision is
not normally impaired. "Color blind" is a term which indicate a fault in the development
of either or both sets of retinal cones that perceive color in light and transmit that
information to the optic nerve.
8.30 Disasters & its Types
A disaster is the impact of a natural or man-made hazard that negatively affects society or
environment
Natural Disasters
A natural disaster is the consequence of a natural hazard (e.g. earthquake, flood, tsunami,
hurricane etc.) which affects humans. The damage is caused by the lack of
appropriate emergency management leading to financial, environmental and human life loss.
Man – Made Disasters
The man-made disasters are caused by human action, negligence, error, or involving the failure
of a system, Human-made disasters are in turn categorized as technological disaster.
Technological disasters are the results of failure of technology involving material, design, system
or operational failures. The metallurgical plants like steel industry require very good hazard
management plan due to its hazardous nature and large scale of operation.
8.31 Hazards in Steel Industry & its Effects
Steel plants use and produce various chemicals in their day to day operation. Some of the
common chemicals used annually in a steel plant are illustrated below:
Sulphur,
Calcium Carbide
118
Hydrochloric Acid
Diesel
Furnace oil
Sulphuric Acid
The hazardous substances storage capacity of some substances can be listed as:
Coke Oven Gas Holder
Blast Furnace Gas Holder
LD (BOF) Gas Holder
Liquid Oxygen
Liquid NH3
Sulphuric Acid
Hot Metal (mixer vessel)
Liquid Steel in Ladles
Acetylene pipe
These chemicals always pose a risk of accident leading to a disaster. These can be largely
prevented by a good safety management system. Common causes of chemical accidents are
therefore deficiency of safety systems, human error or natural calamity.
Nature of possible hazards could be:
Toxic release of Blast Furnace Gas, BOF Gas, Coke Oven Gas
Fire and explosion of tank firm areas.
Hot metal spillage and overflows during handling.
Leakage of liquid Oxygen
Fire & explosion
8.32 Common Hazards in Industry
The various types of common hazards and their effect are described briefly in following sections.
Explosion
The word explosion is used to cover all processes characterized by a sudden flow of material
(usually hot gases) outward from one point. There are two types of explosions depending on the
cause of this outflow:
Explosion due to physical cause (eg. pressure vessels)
Explosion due to chemical reaction resulting release of heat. This is again of two types:
Deflagration occurs when the burning velocity is relatively slow (1 m/s).
119
Detonation occurs when the flame speed is very high (2000-3000 m/s).
The explosions are characterized by the production of a shock wave causing damage to building
and eject sharp pieces like missiles over long distances causing injury to the people.
Dust Explosion & Release
The dust explosion occur when a flammable solid material (eg pulverized coal) are extensively
mixed with air. Such explosions follow initially small fire or explosion which causes settled
powder airborne and cause second explosion. This chain of explosion continues.
This generally causes effect locally and people in the plant vicinity are not affected unless large
quantity of dust particles becomes airborne.
Fire
Fire is the release of energy during the oxidation of a fuel (burning substance) with most of
energy being in the form of heat. The fire can be in different forms such as:
Jet Fire: is a narrow flame. This is formed when a leaking gas from pipe line gets ignited
from some source.
Pool Fire: results from the ignition of pooled oil spilled from pipe line.
Flash Fire: occurs when the escaping fuel gas reaches an ignition source and rapidly
burns back to the point of gas release.
Fire Ball: (BLEVE - Boiling Liquid Expanding Vapor Explosion) is a combination of fire
and explosion. This type of fire occurs with tankers carrying liquefied petroleum gas
(LPG). The tank failure or tippling can cause the release of LPG which rapidly expands at
room temperature forming a rising cloud. When this gas cloud is ignited a fire ball
appears. Depending on the quantity of gas involved the heat intensity may be sufficient to
cause death and severe skin burns at several hundred meters away from the tank.
Toxic Release
A toxic release is the uncontrolled emission of a toxic material in the atmosphere/ water / soil
which is harmful to living objects. The impact on human body depends on the concentration of
the toxic material, age and health of the person exposed.
8.33 Disaster Management
120
Any type of disaster management needs its analysis and assessment to make preparations. As
human being we learn from our past experience and make efforts to avoid it in future. Analysis
of accidents has revealed that they are the result of chain of event often starting with relatively
trivial incident which is ignored many a times. Now there is a trend to have a predictive approach
towards risk assessment for determining the safety parameters.
8.34 Risk Assessment
Many different methods and systems have been devised with varying degree of complexity to
assess risk in different fields.
The figure 7.7 shows an example of risk matrix suitable for ranking risk as an aid to the decision
making. In another circumstances if it is needed to know whether the industrial process is in safe
limits then a more complex quantified risk analysis system may be needed. The figure 7.9 shows
an ALARP (As Low as Reasonably Practicable)
Figure 8-7: The Risk Matrix
Triangle is practiced in UK. This triangle shows “not to be exceeded limit” as upper part of the
triangle and “negligible risk limit” in the lower part. The area in between the two limits is
considered for risk reduction with cost benefits for plant operation.
In industry nothing can be said as “zero risk” or “100 percent safe”. One has to understand the
possible risk and adopt preventive means and keep preparedness to manage the hazard.
121
Figure 8-8: THE ALARP TRIANGLE
8.35 Disaster Management Steps
The disaster of any nature leads to an emergency situation and demands an effective and efficient
management system to minimize the loss. This emergency management has four components (4
R’s) shown in figure 7.9:
Figure 8-9: Four Steps for Hazard Management
Mitigation
122
The mitigation concerns knowing the possible hazards and avoiding unnecessary risks. This
includes an assessment of possible risks to health and property.
One example of mitigation would be to avoid industry in the area that is exposed to hazards like
flood, subsidence, landslide etc. The structural mitigation in earthquake prone areas includes
appropriate building layout and structures which can sustain earthquakes, installation of
a device to instantly shut off the some harmful systems.
Preparedness
The preparedness focuses on planning and having the required material and equipment with
well-planned procedures for their use during emergency period. This includes following:
Communication and Warning devices
Shelter area
Emergency Power system
Life Saving Material Storage (Water, Medicine, Food, warm cloths etc)
Evacuation plans.
The preparation of a survival kit such as a "12-hour kit” is often advocated. These kits may
include food, medicine, flashlights, candles etc.
Response
The response phase of an emergency may commence with search and rescue but in all cases the
focus will quickly turn to fulfilling the basic humanitarian needs of the affected area. This
requires following:
Local Emergency Management Agency (LEMA) for conducting the operation
Evacuation Plan and Shelter Place to accommodate the affected people temporarily till
they are shifted to hospital or other places.
Transportation facility for injured ( Ambulances) and supplies (Heavy Vehicles)
Fire Fighters with equipment to deal with fire caused by disaster.
Security to manage the law and order situation
The quick and efficient coordination of many agencies involved in the process would need a
good planning and mock drills.
Recovery
The recovery phase starts after the immediate threat to human life has subsided. This may
involve cleaning up the area and reconstruction of the damaged equipment and building etc.
123
This also involves reviewing the incident and analyzing for various aspects to know the
deficiency in mitigation, preparedness and response during hazard management.
8.36 Incident Control and Command
In the event of any incident a command structure is required to take necessary action. The
common weakness during such time is due to following reasons:
Lack of accountability, including unclear chains of command and supervision.
Poor communication due to both inefficient uses of available communications systems and
conflicting codes and terminology.
Lack of an orderly, systematic planning process.
No predefined methods to integrate inter-agency requirements into the management structure
and planning process effectively.
Freelancing by individuals with specialized skills during an incident without coordination
with other first responders
Lack of knowledge with common terminology during an incident.
Key Factors
The key to a good incident command structure (ICS) are:
Unity of Command: Each individual participating in the operation reports to only one
supervisor. This eliminates the potential for individuals to receive conflicting orders from a
variety of supervisors, thus increasing accountability, preventing freelancing, improving the
flow of information, helping with the coordination of operational efforts, and enhancing
operational safety. This concept is fundamental to the ICS chain of command structure.
Common Terminology: When different organizations are required to work together, the use
of common terminology is an essential element in team cohesion and communications, both
internally and with other organizations responding to the incident
8.37 Incident Action Plans (IAP)
Incident action plans ensure that everyone is working in concert toward the same goals set for
that operational period by providing all incident supervisory personnel with direction for actions
to be taken during the operational period identified in the plan. Incident Action Plans provide a
coherent means of communicating the overall incident objectives for both operational and
124
support activities. They include measurable strategic objectives to be achieved in a time frame
called an Operational Period.
Action Plans must have four elements:
What do we want to do?
Who is responsible for doing it?
How do we communicate with each other?
What is the procedure if someone is injured?
Resource Management During Incident
The resource management is a key management principle that implies that all assets and
personnel during an event need to be tracked and accounted for. It can also include processes for
reimbursement for resources, as appropriate. Resource management includes processes for:
Categorizing resources.
Ordering resources.
Dispatching resources.
Tracking resources.
Recovering resources.
Communication System
The use of a common communications plan is essential for ensuring that responders can
communicate with one another during an incident. Communication equipment, procedures, and
systems must operate across jurisdictions. Developing an integrated voice and data
communications system, including equipment, systems, and protocols, must occur prior to an
incident.
Effective ICS communications include three elements:
Modes: The "hardware" systems that transfer information.
Planning: Planning for the use of all available communications resources.
Networks: The procedures and processes for transferring information internally and
externally.
The plant must have an independent communication system like satellite phone, ham radio or
wacky-talkie system. In the event of earth quake and fire regular communication towers may not
be operational.
8.38 Incident Command Structures (ICS)
125
ICS is organized by levels holding supervising person's title as given below:
Incident Commander:
Single incident commander: Most incidents involve a single incident commander. In
these incidents, a single person commands the incident response and is the decision-
making final authority.
Unified command: A Unified Command is used on larger incidents usually when
multiple agencies are involved. A Unified Command typically includes a command
representative from major involved agencies and one from that group to act as the
spokesman, though not designated as an Incident Commander. A Unified Command acts
as a single entity.
Area command: During multiple-incident situations, an Area Command may be
established to provide for Incident Commanders at separate locations. Generally, an Area
Commander will be assigned - a single person - and the Area Command will operate as a
logistical and administrative support. Area Commands usually do not include an
Operations function.
Command Staff Member (Officer): Command Staff
Safety officer: The Safety Officer monitors safety conditions and develops measures
for assuring the safety of all assigned personnel.
Public information officer: The Public Information Officer (PIO or IO) serves as the
conduit for information to and from internal and external stakeholders, including the
media or other organizations seeking information directly from the incident or event.
While less often discussed, the Public Information Officer is also responsible for
ensuring that an incident's command staff is kept apprised as to what is being said or
reported about an incident. This allows public questions to be addressed, rumors to be
managed, and ensures that other such public relations issues are not overlooked.
Liaison Officer: A Liaison serves as the primary contact for supporting agencies
assisting at an incident
Section (Chief): General Staff
Branch (Director)
Division (Supervisor): A Division is a unit arranged by geography, along jurisdictional
lines if necessary, and not based on the makeup of the resources within the Division.
126
Group (Supervisor): A Group is a unit arranged for a purpose, along agency lines if
necessary, or based on the makeup of the resources within the Group.
Unit, Team, or Force (Leader): Such as "Communications Unit," "Medical Team," or a
"Reconnaissance Task Force." The Task Force is composed of different types of resources
(one ambulance, two fire trucks, and a police car, for instance).
Individual Resource: This is the smallest level within ICS and usually refers to a single
person or piece of equipment. It can refer to a piece of equipment and operator, and less
often to multiple people working together
127
9 PROJECT BENEFITS
9.0 General
The proposed expansion project M/S Mahalakshmi Profiles Pvt. Ltd. is proposing expansion of
its current M/S Billets, Skelp and Pipes manufacturing. The demand of the product has been
increasing swiftly which has resulted in the proposed expansion of the existing capacity. The
industry is expanding which predicts economic benefits on the regional basis
9.1 Tangible Benefits
The proposed expansion project offers many tangible benefits. It includes increase in production
capacity, increase in tax income to the government, employment generation etc.
The proponent will give employment to 600 people (Existing 250 No. & Proposed 350 No)
Localities will be preferred for the jobs as per their skill, experience and knowledge. Due to the
expansion nature of the project not many direct jobs will be created. However, there will be
increase in the income of the indirect employment as the returns will increase especially those
involved in the supply chains or direct selling, Government revenues, taxes, transportation will
also gain from the expansion project.
9.2 Intangible Benefits
The proposed expansion project will increase the intangible benefits. The expansion is of the
existing products which indicate the market potential of it. The creditability of the products is
excellent which is increasing the demand in the market. Increase in income will lead to more
saving as well as investment which will be satisfying for an individual.
9.3 Other Benefits
The expansion project will bring newer opportunities, increase in network work related influence
area, and increase in accomplishments
128
10 ENVIRONMENT COST BENEFITS ANALYSIS
Not applicable for this project
129
11 ENVIRONMENTAL MANAGEMENT PLAN
11.1 Environmental Management Cell
Apart from having an environmental management plan, it is also necessary to have a permanent
organizational set up charged with the task of ensuring effective implementation. In this effect,
M/s. Mahalakshmi Profiles Pvt. Ltd. will assign responsibilities to officers from various
disciplines to co-ordinate the activities concerned with management and implementation of
environment control measures. An organogram of Environment management is shown in figure-
11.1. Basically, this department undertakes the monitoring of environmental pollution level by
measuring stack emissions, ambient air quality, water and effluent quality, Noise level, etc.,
either departmentally or appointing external agency whenever required.
The industry will continue the regular
monitoring in future to ensure that pollution is
limited below prescribed limits and to take
corrective action by either providing new
equipment or improving the performance of
existing pollution control equipment. In case the
monitored results of environment pollution are
found to exceed the prescribed limits, remedial
actions are taken through the concerned plant
authorities. The actual operation and
maintenance of pollution control equipment of
each department is under respective department
heads. The Environmental, Occupational health
and Safety department is also looking after for
preparation of environment statement, carrying
out environment audit, preparation of Water
Cess Return and various consent applications
and renewal under water (Prevention and Control
of Pollution) Act, 1974 and Air (Prevention and
Control of Pollution) Act, 1981 as well as
application for authorization and its renewal
under Hazardous Waste (Management and
Handling) Amended Rules, 2003 under
Environment Protection Act, 1986.
Fig 11.1: Organogram for Environment
Management Cell
130
11.2 Environment Management Plan
Operation phase of any industry being longer in duration and because of its’ potential to create
continuous impacts, is much more important from the environmental impact point of view and a
comprehensive and effective EMP has to be prepared and implemented to safe-guard
environmental concerns during operation phase of any unit.
Detailed EMP is as under:
Table 11.1: Detailed EMP
PARTICULARS EMP
Air Pollution
Control
Raw material stockyard for Iron & steel billets/Ingots, Scrap, sponge
iron etc. Other raw materials are being stored under cover sheds.
Good housekeeping is essential for steel complex.
Height of all the stacks will be as per statutory requirement. All the
stacks will have stack monitoring facility (SMF) consisting of sampling
port-hole, platform and access ladder.
Transport vehicles will be properly maintained to reduce air emissions
(PUC).
Induction furnace will be operated by electricity; hence there will be no
pollution by combustion of the fuel.
The hoods with proper geometry will be designed.
Plantation of trees, herbs & shrubs will be developed to attenuate the
pollution. This not only providing aesthetic benefits to site, but such
vegetation is able to capture dust.
Measures will be taken to avoid fugitive dust emission.
Idle running of vehicles will be minimized during material loading /
unloading operations
Air Pollution
Minimization
During
Manufacturing
Process
Regular maintenance is being done for exhausters, chimney and
abatement equipment (Wet Scrubber).
To prevent the quench water becoming contaminated.
Quench towers are being cleaned out periodically.
Pipe joints are welded and pumps are gas tight.
In furnace the sequence in which vent and bleeder valves open is
important, opening the cleanest first.
The essential requirement of electric Induction furnace is for primary
fume control.
131
Table 11.1: Detailed EMP
PARTICULARS EMP
The primary fume is extracted from the electric Induction furnace
through a duct by the exhaust fan(s) of the abatement plant.
Dust and fume is being minimized by discharging slag from the electric
Induction furnace into slag pots.
Solid Waste
Management
The generation of solid wastes from process operation is minimal, and
may include contaminated redundant equipment, refractory linings and
cleaning debris.
The generation and use of furnace oil is controlled to avoid
contamination of land.
Waste oil from interceptors, sweeping is being recovered.
No hazardous waste will be generated from the project.
Green Belt
Development
Plan
Extensive green belt development has been done.
About 10233.238 sq m i.e. 35 % of total plant area shall be developed
as green belt at plant boundary, road side, around offices & buildings
and Stretch of open land. Total investment in green belt development
shall be Rs. 5.0 Lac. Apart from greenbelt, lawns, gardens and approach
road-side plantation also carried out at all vacant spaces inside the plant
premises. The main objective of the green belt is to provide a barrier
between the source of pollution and the surrounding areas. The green
belt helps to capture the fugitive emissions and to attenuate the noise
generated apart from improving the aesthetics.
Occupational
Health Plan
Exposure problems to noise, dust, heat and gases are the major
occupational hazards. The employees working in dusty environment will
be diagnosed for respiratory functions at periodic intervals and during
specific complaints for lung function test, sputum test, X-ray test, etc.
Plant personnel working in dust prone areas will wear personnel
protective equipment like air filters over their nose. Job rotation schemes
will be practiced for over-exposed persons.
In case a person inhales CO, he will be removed to fresh air and kept
calm. Thereafter, supportive treatment will be given in the hospital.
It will be ensured that workers are not exposed above the threshold
limits prescribed above through suitable administrative controls. PPE
like earplugs and muffs will be provided and administrative pressure
applied to the workers to using them despite uncomforted.
Auditory examination by qualified doctors upon the first employment
and thereafter periodic examination will be conducted.
132
Table 11.1: Detailed EMP
PARTICULARS EMP
Workers exposed to mechanical accident-prone areas will be given
personal protective equipment (PPE).
Safety data sheets of the hazardous chemicals will be displayed at
specific locations.
All safety and health codes prescribed by the Bureau of Indian Standards
will be implemented.
Fire hydrants will be located at all convenient and strategic points
along the major drains and checked for water availability on regular
basis. Fire extinguishing equipment, sand buckets, water sprinklers and
water hoses will be provided at all convenient point. Fire, heat and
smoke detection alarms will be installed.
Noise Pollution
Control
Noise generating sources and their platforms will be maintained properly
to minimize noise vibrations generated by them.
Personnel working near the noisy machines in different plant locations,
will be provided with well-designed ear muffs / plugs (effective noise
reduction 10-15 dB (A).
Green belt will be developed to act as a noise barrier.
Noise barriers/ shields in the form of walls, beams will be provided
around the units wherever found feasible
Training to personnel will be imparted to generate awareness about
effects of noise and importance of using PPEs.
Structure of
Environmental
Management
Department
Recommended functions of the Environment Management Department
are given below:
1. Develop and maintain Environmental Management System in
line with ISO 14001.
2. Regular monitoring of stack emissions and fugitive emissions
and report any abnormalities for immediate corrective measures.
3. Regular monitoring of ambient air quality around the plant and
work environment monitoring inside the plant.
4. Regular monitoring of re-circulating water quality, water quality
of the storage ponds, ground water quality and surface water
quality.
5. Regular noise monitoring of the work zone and surrounding area.
6. Green belt plantation, maintenance, development of other forms
of greenery like lawns, gardens, etc. in the plant boundary,
133
Table 11.1: Detailed EMP
PARTICULARS EMP
premise.
7. Regular monitoring of solid wastes quantity and developing
avenues for utilization of solid wastes.
In addition to above the EMD will estimate the following performance
indicators:
1. Annual mass emissions to air (SO2, NOx, PM2.5, PM10)
2. Energy use and efficiency;
3. Annual raw materials use;
4. Water use and efficiency; and
5. Annualized waste generation, minimization and recycling.
All the above observations will be compiled and documented to serve
the following purposes.
1. Identification of any environmental problems that are occurring
in the area.
2. Initiating or providing solutions to those problems through
designated channels and verification of the implementation
status.
3. Controlling activities inside the plant, until the environmental
problem has been corrected.
4. Suitably respond to emergency situation.
Safeguard
Mechanisms for
Pollution
Control and
Sustainable
Development
The safeguard mechanism for pollution control and sustainable
development is double sided mechanism comprising on one hand and
Regulatory Authorities on the other hand.
To submit the yearly progress report and compliance report to the
regulatory authorities.
To allow unrestricted entry inside its premises to the staff of the
regulatory authorities at any time for inspection and checking provided
the staff carries with him.
The functions of regulatory authorities are covered under Water
(Prevention & Control of Pollution) Act, Air (Prevention & Control of
Pollution) Act and Environment Protection Act. The environmental
compliance and performance of this project will be monitored and
checked by the State Level Authorities/Central Level Authorities.
134
11.3 Central Pollution Control Board {CPCB} Guide Lines for Steel Industry
CPCB in its publication “Probe/97/2002 - 03”- ‘Environmental Management in Selected
Industrial Sectors Status / Needs’, which also includes steel sector has brought out
suggestions/recommendations and norms for steel units. The suggestions/ recommendations and
norms as applicable to proposed expansion and their compliance status are detailed below:
135
Table 11.2: Action Points as per CPCB Guidelines for Steel Industry
S.
NO Action Point Action Implemented
1 Conservation of water Already under compliance with zero
liquid effluent discharge.
2 Fugitive Emissions Reduction Remedial measures will be adopted.
3 Solid Waste/hazardous waste management All the solid waste generated would be
recycled back.
4
Monitoring of Effluent, Emission and
Ambient air quality
A detailed environmental monitoring
plan has been proposed which would be
implemented with additions after
approval by the TPCB.
5 Emission Control
Emission control is met by installation
of:
High efficiency Wet
scrubbing system;
High Stack as per norms;
6 To Improve overall housekeeping. Agreed
7 To implement rainwater harvesting Rain water harvesting will be adopted.
8
To implement the recommendations of
Life Cycle Assessment (LCA) study
Sponsored by MoEF by December 2003.
The issue shall be examined & shall be
done as per the Government Directives.
9
The industry will initiate the steps to adopt
the following clean technologies/measures
to improve the performance of industry
towards production, energy and
environment.
Agreed
10 Environmental Management Cell EM cell will be there to execute the
tasks related to EHS.
136
12 DISCLOSURE OF CONSULTANTS ENGAGED
Name of the Project M/S Mahalakshmi Profiles Pvt. Ltd., established on Survey. No. 287, 288
& 289 in Kallakal village, Manoharabad Mandal, Medak District in
Telangana state
Nature of the
consultancy
Name of the
Consultant/expert
Address & E-
Approvals, if any from
(NABL/ DGMS/ IBM/
NRBPT/ MOEF/ CPCB/
others etc)*, give reference
EIA/EMP Organization Global Management And
Engineering Consultants
International
Saharan
Tower, 308,
Officers
Campus
Extension,
Sirsi Road,
Khatipura,
Jaipur-302012
E-mail:
info@gmecint
ernational.com
NABET Accredited EIA
Consultant Organization
An ISO 9001:2008
Certified company
Env.Coordinator Dr. Meena Bhaduri
FAE-LU
TM
Vikas Kumar Samaria
Omprakash Kumar
FAE- AP
TM
Omprakash Kumar
FAE-AQ
TM
Dr. Meena Bhaduri
Yogesh Poonia
FAE-WP
FAA
TMs
Omprakash Kumar
FAE-EB
FAA
TM
Dr. Alok Pandey
Sunil Lamba
Yogesh Poonia
FAE-NV
TM
Shishir Chandra Bhaduri
FAE-SE Dr. MeenaBhaduri
137
FAAs Raj Kumar Tailor
Brijesh Chaturvedi
Bhaskar Sinha
FAE-HG Dr. MeenaBhaduri
FAE-GEO Parmeshwar P Soni
FAE-RH
TM
Sunil Lamba
FAE-SC
TM
Dr. Sita Ram Bhakar
Dr. MeenaBhaduri
FAE-SHW
TM
Omprakash Kumar
Environmental Monitoring &
analysis
Nakshatra Enviro
Services
66/40, Heera
Path,
Mansarover,
Jaipur
NABL Accredited Laboratory
An ISO 9001:2008 Certified
Laboratory
Hydro - geological
study& Rain Water
Harvesting
Dr. MeenaBhaduri Saharan Tower,
308, Officers
Campus
Extension,
SirsiRoad,
Khatipura,
Jaipur-302012
--
138
139
140
Annexures 3.1
LAND CONVERSION LETTER BY RDO-1
141
142
143
144
145
146
147
148
149
Additional Information of Galvanizing
DATE :- 27/04/2019 SHEET :- 1 OF1
CONT. STRIP GALVANIZING LINE
LIST OF CONSUMABLES & CHEMICALS FOR 300 TONS PER DAY
S.No. DESCRIPTION SPECIFICATION INITIAL FILL
(QTY.) CONSUMPTION REMARKS
1 ELECTRIC POWER 415 V± 10 % 3 PHASE, AC 40 KWH / Ton 600 KVA
CONNECTED LOAD
2 WATER REQUIREMENT
INDUSTRIAL WATER TDS < 250 ppm.
30 KL 30 KL / DAY COOLING + PICKLING
3 AIR REQUIREMENT CLEAN LUBRICATED
AIR 50 CFM AT 7 BAR MISC. USE
4 LEAD HIGH GRADE 99.9 % 125 TON NEGLIGIBLE BOTTOM BUFFFER
5 ZINC HIGH GRADE 99.9 % 25 TON 10.5 Kg / Ton ZINC COATING
6 ALUMINIUM (Al ) HIGH GRADE 99.9 % 0.25% In Zinc MIXING WITH ZINC
7 WET FLUX
AMMONIUM CHLORIDE
ZINC CHLORIDE ( CHLORIDE BASE )
50 Kg 1.2 Kg / Ton SURFACEP
PREPRATION FOR ZINC COATING
8 DEGREASING AGENT
CAUSTIC BASE 150 Kg 2 Kg / Ton SURFACE CLEANING
9 CHROMIC ACID DICHROMATE FLAKES 2 - 2.5 % IN WATER 200 - 300 Gms /
Ton PASSIVATION
10 FUEL FURNACE OIL 12 Litre / Ton ZINC MELTING
FURNACE
11 FUEL ( OR ) H S DIESEL 12 Litre / Ton ZINC MELTING
FURNACE
12 FUEL ( OR) NATURAL GAS 11 Kg / Ton ZINC MELTING
FURNACE
150
13 DM WATER PH VALUE 6 - 7.5 & CONDUCTIVITY < 50
Microsiemens 10 KL 20 Litre / Ton
FOR QUENCHING + CHROMATING
14
HYDROCHLORIC ACID COMMERCIAL GRADE
STRENGTH 33% SPECIFIC GRAVITY
1.15 Gms/Cm³ 20 KL 25 Litre / Ton FOR PICKLING
15 NATURAL GAS STORAGE BULLET INDUSTRIAL LPG
CYLINDER - 2 NOS.
4 Kg / Ton PREHEATER PILOT
BURNER
EFFLUENTS GENERATION :-
1. SPENT HCL ACID OF APPROX. 6 - 8 % CONC. -
20 Litre / Ton
2.SPENT & BURNT FLUX (CHLORIDE BASE ) -
0.5 Kg / Ton
3. RINSING WATER WITH HCL ACID CONCENTRATION OF 1 - 2 % -
50 Litre / Ton
4. SPENT DEGREASING AGENT (SOAP CAUSTIC BASE) -
0.25 Kg / Ton
Additional Information of Galvanizing
DATE :- 27/04/2019 SHEET :- 1 OF1
HOT DIP PIPE GALVANIZING PLANT
LIST OF CONSUMABLES & CHEMICALS FOR 300 TONS PER DAY
S.No. DESCRIPTION SPECIFICATION INITIAL FILL
(QTY.) CONSUMPTION REMARKS
1 ELECTRIC POWER 415 V± 10 % 3 PHASE, AC 5 KWH / Ton 100 KVA
CONNECTED LOAD
2 WATER REQUIREMENT
INDUSTRIAL WATER TDS < 250 ppm.
15 KL 10 KL / DAY COOLING WATER
3 AIR REQUIREMENT CLEAN LUBRICATED
AIR
100 CFM AT 7 BAR
MISC. USE
151
4 LEAD HIGH GRADE 99.9 % 20 TON NEGLIGIBLE BOTTOM BUFFFER
5 ZINC HIGH GRADE 99.9 % 30 TON 25 - 30 Kg / Ton ZINC COATING
6 ALUMINIUM (Al ) HIGH GRADE 99.9 % 0.25% In Zinc
7 WET FLUX
AMMONIUM CHLORIDE
ZINC CHLORIDE ( CHLORIDE BASE )
100 Kg 800 Gms / Ton SURFACEP
PREPRATION FOR ZINC COATING
8 CHROMIC ACID DICHROMATE
FLAKES 2 - 2.5 % IN
WATER 200 - 300 Gms /
Ton PASSIVATION
9 FUEL FURNACE OIL 15 Litre / Ton ZINC MELTING
FURNACE
10 FUEL ( OR ) H S DIESEL 15 Litre / Ton ZINC MELTING
FURNACE
11 FUEL ( OR) NATURAL GAS 13 Kg / Ton ZINC MELTING
FURNACE
12 DM WATER PH VALUE 6 - 7.5 & CONDUCTIVITY < 50
Microsiemens 10 KL 20 Litre / Ton
FOR QUENCHING + CHROMATING
13
PICKLING AGENT HYDROCHLORIC ACID COMMERCIAL GRADE
STRENGTH 33% SPECIFIC GRAVITY
1.15 Gms/Cm³ 20 KL 25 Litre / Ton FOR PICKLING
EFFLUENTS GENERATION :-
1. SPENT HCL ACID OF APPROX. 6 - 8 % CONC. -
23 Litre / Ton
2.SPENT & BURNT FLUX (CHLORIDE BASE ) -
0.5 Kg / Ton
3. RINSING WATER WITH HCL ACID CONCENTRATION OF 1 - 2 % -
50 Litre / Ton
5. SPENT CHROMIC ACID WITH 2% CONCENTRATION -
50 Gm / Ton
a
EXECUTIVE SUMMARY
1.0 Introduction
M/S Mahalakshmi Profiles Pvt. Ltd., established on Survey. No. 287, 288 & 289 in Kallakal
village, Manoharabad Mandal, Medak District in Telangana state, is already manufacturing
Steel Billets. Presently it has two induction furnaces (one stand by) with 12 tons capacity, with
total production of 29,700 tons per Annum. It also has a Strip mill and Tube mill of 165tonnes
per day capacity each. The existing plant is having valid Consent for Operation from TS
Pollution control Board.
Now the company have proposed to expand the existing plant by installing 12TPH x 6 more
(total 8 No. 12TPH) Induction Furnaces along with CCM for making 621 TPD (2,04,930 TPA)
of MS Billets and New roughing stand/Modernization activities for making 534 TPD
(1,76,220 TPA) of MS Skelp and installation of 3 new ERW Tube mills for production of 835
TPD (2,75,550 TPA) of MS Pipes and installation of scaffolding workshop for production of
50 TPD (16,500 TPA) of Scaffolding. It will also Install continuous coil Galvanizing unit for
manufacturing of 300 TPD (99,000 TPA) of Galvanized Strips /Coils and installation of Hot
Dip Galvanizing unit for manufacturing of 300 TPD (99000 TPA) of Hot Dip Galvanizing of
MS ERW Tubes.
Project Proponent
M/S Mahalakshmi Profiles Pvt. Ltd. is a Private Limited Company. The Directors of the
company are as under:
Directors: The company is promoted by: Mr. Ramniranjan Agarwal and Mr. Vinod Kumar
Agarwal.
Address: Mahalakshmi Profiles Pvt. Ltd. Private Limited has its registered office at 1-9-8,
I.D.A, Azamabad, Hyderabad, Telangana.
1.1 Location
M/S Mahalakshmi Profiles Pvt. Ltd.is situated at village Kallakal village, Manoharabad
Mandal, Medak District in Telangana state , Latitude 17° 41' 54.3408"N and Longitude
78°29'4.8192"E. The project falls under the Manoharabad Mandal.
The land area of the plant is 19 Acres and 17 Guntas (78,610.256 sq m) out of which 13.675
acres is being used for the Industrial processes and 5.75(33.0% )Acres has been allocated for
green belt.
b
2.0 Product and Capacities
The project proposes to expand the production capacity by upgrading existing capacity as
given below:
S. No. Product Capacity
Existing Expansion After Expansion
1 MS Billets though Induction Furnace
90 TPD 621 TPD 711TPD
2 MS Skelp through Strip mill
165 TPD 534 TPD 699 TPD
3 Pipes through Tube Mill 165 TPD 835 TPD 1000 TPD
4 Scaffolding -- 50 TPD 50 TPD
5 Galvanized Strips/Coils -- 300 TPD 300 TPD
6 Hot Dip galvanizing of MS ERW Tubes
-- 300 TPD 300 TPD
The unit obtained CFO for Furnace on 16-08-2017 (valid up to 31-01- 2022) from State
Pollution Control Board to manufacture 90 T/Day of MS Ingots ,60TPD MS Pipes and 70TPD
hot Rolling strips . The unit obtained the respective Consent Orders accordingly and started its
operations.
Salient Features of the Project
Name of Project Mahalakshmi Profiles Pvt. Ltd.
Proponent( Director) Mr. Ramniranjan Agarwaland Mr. Vinod Kumar
Agarwal.
Nature of the Project Secondary Metallurgical Process based industry
Latitude and Longitude S.
NO.
LATITUDE LONGITUDE S.
NO.
LATITUDE LONGITUDE
1 17°42'3.22"N 78°29'1.19"E 14 17°41'56.60"N 78°28'47.00"E
2 17°41'57.66"N 78°29'0.91"E 15 17°41'56.50"N 78°28'47.00"E
3 17°41'57.60"N 78°28'55.80"E 16 17°41'55.90"N 78°28'42.00"E
4 17°41'52.50"N 78°28'55.60"E 17 17°41'56.20"N 78°28'41.90"E
5 17°41'52.50"N 78°28'55.40"E 18 17°41'56.80"N 78°28'46.70"E
6 17°41'54.20"N 78°28'50.00"E 19 17°41'57.60"N 78°28'46.70"E
7 17°41'54.20"N 78°28'49.60"E 20 17°41'57.50"N 78°28'48.20"
8 17°41'54.10"N 78°28'49.10"E 21 17°42'0.80"N 78°28'48.50"E
9 17°41'55.30"N 78°28'48.80"E 22 17°42'0.70"N 78°28'50.60"E
10 17°41'55.40"N 78°28'49.40"E 23 17°42'2.00"N 78°28'50.90"E
11 17°41'56.60"N 78°28'49.40"E 24 17°42'2.30"N 78°28'56.20"E
c
Name of Project Mahalakshmi Profiles Pvt. Ltd.
12 17°41'56.70"N 78°28'49.60"E 25 17°42'2.20"N 78°28'56.20"E
13 17°41'56.90"N 78°28'49.70"E 26 17°42'2.79"N 78°29'0.25"E
Site Location Survey. No. 287, 288 & 289 in Kallakal village,
Manoharabad Mandal, Medak District in Telangana state
Total land area 78,610.255 sq. m
Total area of green belt developed 2,594.22 sq. m (33.0%)
Nearest High way The plant site approached by small road which connect
NH-7 and Industry
Nearest Rly Stn Dabilpur Rail Way Station is 2.8 Km from the site
Nearest Air Port Rajiv Gandhi International Airport, Shamshabad,
Hyderabad is 70 km from the site
Nearest fire station Narsapur 21 km (North –West)
Nearest village Kallakal Village North 1km
Nearest surface water bodies Pond near Gomaram 9.0 km (West-North West)
Water body near Meenjipeta 5.5 km(North East)
Water body near Tunki Makta 8.0 km (NE)
Medchal Lake 8.63 km (South)
Nearest Reserve Forest Ellampet Reserve Forest 2.0 km South –South West
Any ecologically sensitive areas None
Fresh Water Requirement Industrial: 16 KLD; Domestic: 3.6 KLD (Existing)
Industrial: 57KLD; Domestic: 16 KLD (Proposed)
Source of Water Telangana: Gram Panchayat and tanker supply
Man Power 500 Members to be employed directly and around 100
people may be employed indirectly
Power Demand 15500 KVA and is supplied by Telangana Electricity
supply board
DG Set Existing one DG set of 380 kVA
Project Cost The cost of the project is Rs 150 crores (15000 lakhs)
along with all the accessories
3.0 Requirement of the Proposed Project
3.1 Raw Materials
d
The existing unit is using the MS Scrap; Sponge Iron and Alloying metals for the MS Billets.
It is proposed to increase the production capacity of MS Ingots/Billets from 27,000 TPA to
213,300 TPA, thus the raw material requirement will also increase which is mentioned below.
Raw Materials Requirement for Existing Unit
Raw Materials Requirement for Expansion of the Unit
S.No. Raw Material Consumption Source of Raw
Materials
Method of Transport
Induction Furnaces with concast
1 Sponge Iron 551 TPD From Sponge iron
plants By Road (covered trucks)
2 Scrap 164 TPD Local By Road (covered trucks)
3 Ferro Alloys 6 TPD Local By Road (covered trucks)
Strip mill
1 Billets 587 TPD In plant generation Conveyors
2 High grade coal
thermal 32 TPD
Imported/Purchased
from Traders By Road (Covered trucks)
Tube Mill
S.N
o
Raw
Material
Source Transportation Quantity
TPD TPA
For Existing (90 TPD)
1 Sponge Iron Local/adjacent States By Road 63.54 19,062
2 Iron Scrape Local/Imported By Road 9.9 2,970
3 Pig Iron Local/adjacent States By Road 18.63 5,589
4 Ferro Alloys Local/adjacent States By Road 0.81 243
Strip mill
1 Billets In plant generation and
purchased from Market
Conveyors and
By Road
(Covered trucks)
165TPD
2 High grade
coal thermal
Imported/Purchased from
Traders
By Road
(Covered trucks) 9 TPD
Tube Mill
1 MS Skelp In plant generation By Road
(Covered trucks) 166 TPD
Material Balance for Existing
Billets 90 27,000
Slag 2 600
Cutting& Scaling 1.5 450
e
1 MS Skelp 699 TPD In plant generation By Road (Covered trucks)
2 HR Coil 354 TPD
Purchased from
SAIL/TATA/JSW/
Other Manufacturers
By Road (Covered trucks)
Scaffolding
1 MS Tubes 47 TPD In plant generation By Road (Covered trucks)
2 Accessories/
Components 3 TPD
Purchased from local
Manufacturers By Road (Covered trucks)
Continuous Coil Galvanizing
1 MS Skelp 150 TPD In plant generation By Road (Covered trucks)
2 HR Coils 150 TPD Purchased from
SAIL/TATA/JSW By Road (Covered trucks)
3 Zinc Hindustan Zinc/ Other
reputed Manufacturers By Road (Covered trucks)
Hot Dip Galvanizing
1 MS ERW Tubes 300 TPD In plant generation By Road (Covered trucks)
2 Zinc Hindustan Zinc/ Other
reputed Manufacturers By Road (Covered trucks)
3.2 Water requirement
Fresh Water
Requirement
Industrial: 15KLD; Domestic: 3 KLD (Existing)
Industrial: 75KLD; Domestic: 15KLD (Proposed)
Source of Water Gram Panchayat and tanker supply
4.0 Manufacturing Process
Billets
Sponge iron, scrap and metal alloys are charged to furnace. Small quantity of silico-manganese
and flux chemicals will be added to molten metal. The advantage of the induction furnace is a
clean, energy-efficient and well-controllable melting process compared to most other means of
metal melting.
Raw materials for the process are scrap, fluxes and Ferro alloys. Sponge iron can substitute
f
scrap up to 50%. The 16”x16” size Scrap bundles will be Lifted and Transported by Overhead
cranes and fed to Induction Furnace. Scrap/ sponge iron, fluxes, Ferro alloys are melted in an
Induction furnace, wherein electric current is passed through it. In the Induction Melting
Furnace the scrap melts at temperature of about 1650C. When the total charge is melted into
hot liquid metal then the metallurgy of steel in terms of carbon, phosphorus content, alloy
elements etc., is controlled at this stage. Based upon the Composition of the molten steel,
additives will be added to get the requisite composition and grade of Steel.
The molten material is poured into mould to produce ingots. The ladle is placed over the
Continuous Casting machine to cast the molten steel into required size of billets. The Cut
Billets are transported by a Billet handling crane and stored in the Storage yard as per the
Grade and Quality for dispatch.
Strip Mill
Reheating of semi-finished steel slabs of steel nearly to their melting point, then roll them
thinner and longer through 8 successive rolling mill stands driven by motors totaling 10,000
HP and finally coiling up the lengthened steel strip for transport to the next process.
Tube Mill
The coil as per desired width and thickness is received from the stock yard and loaded onto
decoiler. The end of the strips are sheared and butt-welded and fed into a storage cage. The
strip is passed through the forming section of the pipe mill and then into the Fin-pass section,
it gradually takes the shape of a round tube.
Continues Coil Galvanizing
Coating gauge is designed for online measurement of metal coatings on both sides of metal
sheet in Continuous Galvanizing Lines (CGL). The deviations from preset target values are
instantly detected allowing immediate corrections to the production process to maintain
uniform coating. As the steel exits the furnace, it enters into a vacuum chamber, or snout,
before entering the molten zinc bath to prevent and air from re-oxidizing the heated steel
product. ERW Pipe are completely immersed in a bath of molten zinc. The bath chemistry is
specified by ASTM B6, and requires at least 98% pure zinc, to form series of bonded zinc-iron
alloy layers.
4.1 Material Balance and Emissions
g
Material Balances for (Existing )M.S. Billets to the tune
of 27,000 Material Balances for (Expansion) M.S. Billets to the
tune of 213,300 TPA
5.0 Measures for Mitigating the Impacts
The purpose of mitigation measures is to avoid, reduce or minimize unwanted impacts on the
environment. To minimize & control the Flue Gas emission from the stack attached to Boiler
& DG Set, M/S Mahalakshmi Profiles Pvt. Ltd. shall be installing Separate Bag filters with
Induction Furnaces & canopy with DG set. 51.76 TPD of Slag from furnaces is given to
cement plant for reuse for land filling. Solids from APCD are disposed off at designated TSDF
site. Used Oil from DG set is being sold to the authorized Recyclers. STP is provided for
treatment of domestic effluent. Treated effluent is used for plantation in the premises. The
industry is regularly operating and maintaining its APCD and ensuring that the emissions are
adequately collected and concentration of air pollutants in its emissions conforms to the
emission standards laid down by the board.
6.0 Cost of the Project
The total project cost is Rs 150.0 Crores (after addition of proposed machinery).Proposed
Employment Generation from proposed project will be around 600 persons out of which 500
persons will be having direct employment and 100 persons will have indirect employment.
7.0 Site Selection
M M/S Mahalakshmi Profiles Pvt. Ltd. is situated at village Kallakal village, Manoharabad
Mandal, Medak District in Telangana state , Latitude 17° 41' 54.3408"N and Longitude
h
78°29'4.8192"E. The project falls under the Manoharabad Mandal.
The land area of the plant is 19 Acres and 17 Guntas (78,610.256 sq m) out of which 13.675
acres is being used for the Industrial processes and 5.75(33.0% )Acres has been allocated for
green belt.
No National Parks/ Wildlife Sanctuaries/ Biosphere Reserves exist within 5 km radius of
project site. Nearby water body is at Meenjipeta 5.5 km(North East) from the unit.
7.1 Land ownership and Related Details
The project land is owned by the proponent Mahalakshmi Profiles Pvt. Ltd.
It is an Orange category industry that comes under the Industrial area of
Manoharabad, The project falls under the Manoharabad Mandal.
Non agriculture waste Land has been converted for industrial purpose. Land
conversion documents has been enclosed at the end of the report
The existing industry is with a Shed and two 12 tons per hour (TPH) Induction
furnace and a Re- rolling mill. To increase the production The industry is now
proposing addition of 6more 12 TPH additional induction furnace in the same
premises.
8.0 Baseline of the Environment
8.1 Regional Meteorology
The study area has a severe summer season during the month of May with temperature
shooting up to 47oC. The Normal means minimum temperature is 13.7
0C and means maximum
is 39.90C. The onsite of the monsoon in the area is from June and tapers off during October.
The average annual rainfall of the area is 644 mm. The area in general has dry climate with
low humidity.
The predominant wind direction during this period was from SE to NW sector accounting to
about 45.83 % of the total time with calm winds of less than 1.0 kmph. During some of the
times the wind speed was recorded more than 11 kmph. The monitoring period is from March
to May 2019.
8.2 Ambient air quality
Ambient air quality of the study area has been assessed in and around the project. PM10
monitored in the Plant area showed 98th
percentile value of 91.0 g/m3 with PM 2.5 of 39.0
µg/m3. 98
th percentile values of Sulphur dioxide and Oxides of Nitrogen in the Plant area from
the monitored data were 11.0 g/m3 and 25.0 µg/m
3 respectively. CO concentration at all the
locations was found to be 1.47 µg/m3 .
8.3 Air Quality in Buffer Zone
The maximum monitored value of Air pollutants at site and in the buffer zone at selected
i
location is given below:
Name of the
Station PM10
µg/m3
PM2.5
µg/m3
NOX
µg/m3
SO2
µg/m3
CO
Project Area 92 40 25 12 1.61
Banda Mailaram 98 36 23 15 1.66
Baswapur 98 38 22 17 1.74
Rawalkole 99 37 19 13 1.59
Medchal 97 38 20 12 1.69
Nuthankal 99 38 20 12 1.70
Sikindlapur 98 38 22 12 1.65
Koochavaram 99 39 24 14 1.66 Source : Primary monitoring
8.4 Water Quality
Assessment of water quality in the study area includes the quality assessment of parameters as
per the Indian standard IS 10500 for Ground Water. Water characteristics are as follows:
Parameters Results mg/l
TDS 478 - 2448
Hardness 240 - 1628 mg/l
Chlorides 35 - 1079 mg/l
Sulphates 24 - 278 mg/l
Calcium 64 - 477 mg/l
Magnesium 14 - 135 mg/l
Iron 0.03 - 0.16 mg/l
Heavy metals Zn, Pb, Cu and Al BDL Source :Primary monitoring
The analyzed values are found within the permissible/desirable limits of IS: 10500.
8.5 Nature of Soil
Soil samples were analyzed in and around the project site.
The following are the highlights of soil quality in the study area.
Summary of Soil Quality In plant Area
pH of the all soil sample was 7.21.
Texture of soil sample is found to be clay with sand 36%, silt 16% and Clay 48%.
Phosphorus values in the soil sample collected was found to be 28 kg/ha.
Nitrate of the soil sample collected was found to be 186 kg/ ha.
Summary of Soil Quality in Study Area
pH of the all soil samples were found to be 7.16-7.86.
j
Texture of soil samples is found to be Clay and sandy Clay with sand % in the
range between 16-36%, silt between 16-48 % and Clay 34-54%.
Phosphorus values in the soil samples collected were in the range of 28-64 kg/ha
Nitrate of the soil samples collected were in the range of 186-282 kg/ha.
8.6 Ambient Noise
Noise monitoring was conducted in and around the project site. The values were below the
respective statutory norms as applicable. 1st Feb to 30
th April
8.7 Forests
The period of monsoon is very short lived in this area, which has a significant bearing apart
from other biotic pressures, on the floristic composition of the forests. These are open forests
in which thorny and usually hard wood species predominate. Rangipalli ,Manoharabad,
Minajipet ,Kanukunta ,Munurabad and Dabilpur Reserve forest falls within 10 km radius
around the site, with forest wealth such as Teak wood, Bamboo, Tamarind, Rosa grass, Beedi
leaves, Neem seeds, medicinal plants etc., Bamboo fetches maximum revenue along with
Beedi leaves ranging from 50 lakh to one crore per annum.
8.8 Flora
The study area does not habitat any thick vegetal cover. There is usually a thin grass growth
which may appear during the short rainy season in most of the study area, but more or less the
soil is barren and devoid of any grass growth.
8.9 Fauna
Some of the animals which you would find here are Indian Giant Squirrel, Rhesus Monkey,
Jackal, Red vented bulbul, Indian cuckoo, Common House Rats, Indian Fox, Indian Palm
Squirrel, Wild Boar, House Sparrow, Common Myna, Common kingfisher, Common Peafowl,
Common Pigeon, Goose Greylag, Grey Heron, House Crow, Indian Courser and Indian Pond
Heron. No endangered fauna species are found in the area.
8.10 Socio-economic Status
Basic Socio-economic conditions are as follows:
There are 60 villages and many hamlets in the study area.
As per the 2011 census data, the population in the study area is 60,000.
Density of population is 313 persons per sq. km.
Literacy status of the area is found to be moderate with a total of 61.42 % of the
population. Male and Female literacy is about 71.43 % and 51.37% respectively.
Occupational status in the study area is in agriculture. 50 % of total population of the
study area falls under main workers category.
k
Agricultural activities are mainly in monsoon season. Major crops in the area are
Jowar, Maize, groundnut, Ragi, Onion, Vegetables etc
Medical facilities are inadequate, only few villages have the primary health care
centers. For any major health care, the populace of the area has to go to Medchal
/Manoharabad, which are major towns located at a distance of about 8.0 Km from the
proposed site.
Educational facilities are adequate. Higher educational center is Medchal at a distance
of 8.0 km.
This region is well connected by road.
Many villages are adequately provided with protected water supply.
9.0 Identification of Hazards & Risks
Based on the type of operations, the possible Hazards and Emergencies are identified
and appropriate mitigation measures are proposed. Safety hazards relating to Induction
Furnace and Rolling Mill can be classified into 3 categories:
Thermal hazards
Electrical hazards
Physical hazards
S.No. Plant
Area
Possible Deviation from
normal operation
Likely Causes Consequences
1 Furnace Re-circulating and cooling
water coming in contact with
the molten iron or slag
Leakage of water
from the walls
Spurting of metal/
slag
Explosion under
extreme cases
Presence of Oil & Grease and
other Impurities in raw
materials
Fire
Sudden catches
fire & flames
2 High
Power
Transforme
r
Oil temperature being very
high.
Varying room
Temperatures
Sudden flashing
of fire or
bursting.
3 High
Tension
Electrical
Installation
Heavy sparking at the pot
heads and the joints.
Loose joints, cable
cut, burning of
fuses, short
circuits etc.
Sparks in the
beginning,
devastating fire
if neglected.
10.0 Likely Impact on Environment
10.1 Air Environment
l
During construction water will be sprinkled on the soil to avoid dust generation if any. The
debris and unused construction material shall be removed immediately for recycling, if any, or
for land fill.
Bag filters & Cyclone shall be provided to arrest SPM from flue gases to keep it within
permissible limits. All vehicles for service activities at the project site shall be checked for
vehicular emission. The agencies will be asked to keep them within prescribed limits. They
will also be asked to maintain them properly.
A chimney of suitable height is already provided for the D.G. set to control the G.L.C. of
S.P.M., SO2, & NOx levels. Extensive tree plantation shall be resorted to for further improving
the air environment in general and minimize noise levels.
10.2 Water Environment
Water shall be drawn from a tube-well installed in the factory area and distributed through an
Over Head Service Reservoir. This will all be a closed system. During construction existing
toilet facilities shall be used by the labour. Finally waste water from the toilets shall be taken
to septic tank. It will not be thrown outside either on land or in any water body. Roof top Rain
Water shall be harvested and used for ground water recharge to minimize effect of withdrawal
of water from the underground.
10.3 Land Environment
No additional land will be required for expansion. The requirements of sand and aggregates for
the construction works like foundation etc. will be supplied by venders. The land use is thus so
planned that there is minimum adverse impacts.
10.4 Solid/Hazardous Waste
The other solid/Hazardous wastes from the bag filters shall be stored in a dumping pit of
R.C.C. Construction and sent for proper disposal. Slag from the manufacturing process shall
be used for making roads or sent to cement plant for further use.
10.5 Green Belt
The main objective of the green belt is to provide a barrier between the source of pollution and
the surrounding areas. The green belt helps to capture the fugitive emission and to attenuate
the noise generated, apart from improving the aesthetics. Development of green belt and other
forms of greenery shall also prevent soil erosion and washing away of topsoil besides helping
in stabilizing the functional ecosystem and further, to make the climate more conducive and to
m
restore water balance. It is planned that the selected plants will be grown as per normal
horticultural (or forestry) practice and authorities responsible for plantation will also make sure
that adequate provision for watering and protection of the saplings exists at site.
11.0 Emergency Preparedness Plan
Emergency planning is primary for the protection of plant personnel and people in nearby
areas and the environment that could be affected by unplanned hazardous events. Use of
proper personnel protective equipment, fire protection systems and continuous training of
people working in the shop floor are the only measures which helps industries to avoid
accidents.
12.0 Issues And Response During Public Hearing
It is a Draft report submitted to SPCB for grant of public hearing dates.
13.0 Corporate Environment Responsibility
Proposed project will result in growth of the surrounding areas by increased direct and indirect
employment opportunities in the region including ancillary development and supporting
infrastructure. Special emphasis on Financial and Social benefits will be given to the local
people. Development of social amenities will be in the form of medical facilities, education to
underprivileged and creation of self-help groups. The company has earmarked Rs 112 lakhs
towards the Corporate Social Responsibility (CSR) Activities.
14.0 Occupational Health Measures
Conceptually when the healthy employees are placed on the jobs, they produce much better
than what unhealthy employees produce. Larger the number of unhealthy employees, the
greater is the loss to the steel plant in terms of low productivity, increasing healthcare cost,
sickness absenteeism, and loss of production.
Project management is keenly protecting health of the employees by preventing and
controlling occupational diseases and by eliminating occupational factors and conditions
hazardous to the health of the employees at work place by promoting regular medical checkups
and by building safe protecting environment at work sites.
15.0 Post Project Environmental Monitoring Program
A number of environmental aspects will be regularly monitored so as to ensure the
implementation and effectiveness of various mitigative measures adopted. The implementation
and monitoring of effectiveness of the environmental mitigation measures will be assigned to
the Environmental Control Department. An Environmental Management Unit, comprising of
n
senior management level officers will periodically assess and monitor the implementation of
mitigation measures and environmental monitoring Program, and tackle the bottlenecks of the
implementation of mitigation measures.
Budget for Implementation of Environmental Management Plan
S. No Component Capital cost for the
proposed expansion in
Lakhs
1 Pollution equipment for Induction Furnace 75
2 Greenbelt development 5
3 Environmental management cell 25
4 CER 112
Total 217 Lakhs