22
TEL382 Greene Chapter 11

TEL382 Greene Chapter 11. 10/27/09 2 Outline What is a Disaster? Disaster Strikes Without Warning Understanding Roles and Responsibilities Preparing For

  • View
    216

  • Download
    2

Embed Size (px)

Citation preview

TEL382

Greene Chapter 11

10/27/09 2

Outline• What is a Disaster?

• Disaster Strikes Without Warning

• Understanding Roles and Responsibilities

• Preparing For Disaster

• Responding to a Disaster

• Planning For Contingencies

• Recovering From Disaster

• Testing and Maintaining the Plan

10/27/09 3

What is a Disaster?• A disruption of normal business functions where

the expected time for returning to normalcy would impact the organization’s ability to maintain operations, including customer commitments and regulatory compliance

• Steps:– Determine Threats, Perform Business Impact Analysis

(BIA), Determine Safeguards

• BIA provides direction and guidance to those who plan the response, recovery and continuity efforts

10/27/09 4

Disaster Strikes Without Warning

• Must have a written plan!

• Business Continuity Plan (BCP) should have:– Disaster Preparation : to be done in anticipation – Disaster Response: to be done immediately following

incident– Business Contingency: alternate business processes

prior to full recovery – Business Recovery: recovering information systems

to their original state

10/27/09 5

Understanding Roles and Responsibilities

• Senior Management Leadership• BCP Team• Operational Management defines needs of department • IT Department • HR Department• Internal Audit Department• BCP Team Responsibilities:

– Assessing damage, declaring a disaster, managing response, providing leadership, provide post-disaster assessment, plan impact analysis when changes made, testing plan, reviewing plan with management

10/27/09 6

Preparing For Disaster• Predefined key elements:

– Establish organizational structure to respond: chain of command and succession

– Designate Emergency Command Center: Location where BCP Team meets and directs operations

– Prepare Notification Procedures: Call trees, cell phones

– Design Alternate Operations Sites: Delivery (product to customer) and Operational (HR, accounting, security, etc.) functions

– Invest in redundant infrastructure: Hot Sites, Warm Sites, Cold Sites, Mobile Sites

– Develop and implement procedures to support response, recovery and continuity activities

10/27/09 7

Responding to a Disaster• Four Stages of Disaster Notification

– Detection: Whoever first discovers it– Notification: Notify BCP Team– Declaration: BCP Team evaluates the situation and activates

the plan– Activation: BCP Team Leader (or alternate)

• Non-operational Business Concerns to be addressed before disaster:– Public Safety: Who, how, when, etc– Employee Relations: Show up to work, where, when, how, etc.– Media Relations: Single media focal point– Customer Relations: Who, how, what, etc.– Crime:

10/27/09 8

Planning For Contingencies• Contingency Operations Established at Main Site

or Alternate Location

• Develop Business Contingency Operating Procedures (BCOP)

10/27/09 9

Recovering From Disaster• Break Down into categories:

– Mainframe, Network, Communications

• Detailed Procedures Need to be Developed and Documented Before Needed– What needs to be done, where it needs to be done,

how it needs to be done

• Recovery Manuals on specific systems and/or devices

10/27/09 10

Testing and Maintaining the Plan• Plans and Procedures are only theoretical until tested• Must be accurate, relevant and operable under adverse

conditions• 5 Standard Testing Techniques:

– Preliminary Review, Structured Walkthrough, Tabletop Simulation, Parallel Testing, Full-Scale Testing

• Must revisit plan frequently to take into account changes • Should have SLAs with Major Vendors• Some Regulated Industries MUST Audit Plan

TEL382

Wallace Chapter 1

10/27/09 12

Outline• Introduction

• Initiating the Project

• Contingency Planning Coordinator

• Scope of the Project

• Adequate Funding

• Selecting a Team

• Planning the Project

• Executing and Controlling

• Closing the Project

10/27/09 13

Introduction• Building a BCP is like any other business project• In developing a BCP, the early stages must be done

sequentially. After a certain point, then many tasks can be done in parallel

• Typical Steps:– Management Decision

– Contingency Plan Coordinator (CPC) is selected

– Sponsor and CPC define effort Scope

– CPC selects Team

– CPC and Team develop Project Plan

– Project Plan is Executed

– Reports Produced and CPC closes Project

10/27/09 14

Initiating the Project• Sponsor from Senior Management

• Selection of CPC

10/27/09 15

Contingency Planning Coordinator• Public announcement

• May begin by using an Outside Consultant

• Tasking begins as plan developer, evolves to plan implementer, then plan maintainer

10/27/09 16

Scope of the Project• Defines boundaries of what will be accomplished

• A guideline:– Any event that would cost >5% of quarterly revenues

merits its own plan

• Build slowly and systematically

• Written Scope Statement

• Focus on Critical Business Functions and the Processes that Support Them

• Most Plans can be developed within 6 Months

10/27/09 17

Adequate Funding• Indicates Management Commitment

• Project Budget Items:– BCP Training for CPC and some Team Members– Consultant– Overtime Expenses– Temporary Administrative Help– Food/Beverages– Bonuses/Trinkets, etc.

10/27/09 18

Selecting a Team• Identify Stakeholders• Core Team (CPC, Assistant, Administrative Assistant)• Other Team Members:

– Building Maintenance or Facilities Manager– Facility Safety and Security– Labor Union Representative– HR– Line Management – Community Relations– Public Information Officer– Sales and Marketing– Finance and Purchasing– Legal

• Use Standard Tools• Initial Training• Knowledge of Department Processes• Team Meetings

10/27/09 19

Planning the Project• Identify Activities

– Write Paragraph on Each Task, Document Assumptions and Constraints

• Estimate How Long Each Will Take

• Decide Who Should Do What

• Sequence the Tasks Into a Logical Work Flow– Assign Start Dates

• Look for Problems in Plan– Resource Overobligation, Availability, etc.

10/27/09 20

Planning the Project• Common Problems

– CPC lacks experience– Lack of Management Support– Inadequate Funding– Too Many Locations– Too Many Departments– Business Interruptions– Not Enough Time

10/27/09 21

Executing and Controlling• Scope Verification• Communications Plan

– Mandatory, Informational, Marketing

• Controlling– Change– Scope– Cost– Quality– Performance Reporting– Risk Response

• Plan Testing

10/27/09 22

Closing the Project• Turn Files over to Administrator

• Report Results to Management

• Identify Known Exposures

• Thank the Team