TEEGA TOWNHALL SESSION 25 th November 2018

TEEGA TOWNHALL SESSION - my-community.com · PUTERI HARBOUR OVERVIEW Development info : • Total Development area : 1082 acres (Puteri Harbour & Estuari) • 1st layout approved

  • Upload
    lamque

  • View
    218

  • Download
    1

Embed Size (px)

Citation preview

TEEGA TOWNHALL SESSION25th November 2018

PUTERI HARBOUR

PUTERI HARBOUR OVERVIEWDevelopment info :

• Total Development area : 1082 acres (Puteri Harbour & Estuari)

• 1st layout approved on 2008

Photo as of 12 Oct 2018

REJUVENATING PUTERI HARBOUR AS PART OF COOL IP INITIATIVE

Iskandar Puteri (IP) as the preferred location for retailers, F&B, and entertainment

Estuari 1C : One˚15 Estuari Sport Center

Completion : Q4 2019

Water Garden & Sandy Beach

Completion : Q2 2019

Tanjung Point Park

Completion : Q4 2020

TM1 : One˚15 Marina Puteri Harbour

Grand Opening : Q1 2021

TH1-1 @ Puteri Harbour

Target to commence : Q2 2021

Tanjung Marina Promenade

Completion : Q4 2019

REJUVENATING PUTERI HARBOUR : INFRASTRUCTURE

Architecture Prospective

Architecture Perspective

One˚15 Marina Puteri Harbour

Water Garden & Sandy Beach Tanjung Point Park Tanjung Marina Promenade

Puteri Harbour Marina Promenade

Architecture Perspective

One˚15 Estuari Sport Center

FUTURE INFRASTRUCTURE

Puteri Harbour Linear Park

Size 2.80 acre

Februa February 2019

Target Completion

August 2019

▪ Pond view

▪ Garden Facilities

▪ Viewing Deck

FUTURE INFRASTRUCTURE

Size 3.45 km of roads

Start Date June 2016

Completion Oct 2018

Key Features

▪ 1-way street for main road

▪ Dedicated bus & bicycle lane

▪ Braille tile

Current Status ▪ Laksamana 2 (Access to Almas Phase 1). Others road already complete.

Puteri Harbour Road Upgrading (Southern Area)

Teega

YSL Freshmart

My News.com

Arashi

Tribus

BUILDING COMMUNITIES: F&B, RETAIL AND PLACEMAKING

Imperia

Yum Shabu

Kinsahi

UEMS Southern Sales Gallery Puteri

Harbour

Ferry to Batam & TgBalai

Shuttle Bus IP to JB

All Year Round Celebrations

‘Makan’ Spot

BUILDING COMMUNITIES : PLACEMAKING EVENTS

DINASOUR KINGDOM

20 Nov –

1 Jan 2019

MOSCOW

CIRCUS

20 Nov –

31 Dec 2018

ISKARNIVAL ‘MAIN-MAIN’

8 - 9

Dec 2018

ISKANDAR PUTERI CONNECTIVITYConnectivity – Current transport available in Puteri Harbour, Iskandar Puteri

• Complimentary shuttle service brought to you by UEM Sunrise & Medini Iskandar Malaysia

• Current Status : 3 number of buses operational since 1 September 2018.

• Pending 1 more bus – pending insurance clearance by Finance. Target operating date is on 1st December2018.

• PHIFT ←→ Puteri Cove ←→ Imperia ←→ Teega ←→ Kota Iskandar ←→ Sunway Iskandar ←→ SunwayInternational School ←→ Medini 6 & 7 ←→ Gleneagles Medini ←→ Mall of Medini ←→ Afiniti Medini←→ Somerset Medini ←→ Legoland ←→ 1 Medini ←→ Educity ←→ East Ledang ←→ Anjung ←→Larkin Sentral

FREE SHUTTLE SERVICE

ISKANDAR PUTERI CONNECTIVITY• Proposed Route - Phase 2 Community Shuttle

M6/M7

Rumah Iskandar

Malaysia (RIM) –

Gelang Patah

Bukit Indah

Taman

Nusa Perdana - Afiniti Medini

- Somerset Medini

- 1 Medini

- Sunway Iskandar

- Sunway

International

School

- Imperia

- Teega

- Puteri Cove

- Ledang

Clubhouse

- Ujana

- Nusajaya Center

- Tesco

Iskandar Puteri Community Shuttle

Service

Route

Route 1 (Morning & Evening only)

RIM - PHIFT

Route 2 Edu City - PHIFT

Route 3(existing)

Terminal Larkin -PHIFT

Route 4 Bukit Indah

Note:-

• Awaiting permit approval from Land Public Transport Commission (SPAD) on the proposed route

Note:Route 1-3 are in operation.Route 4 – Target to commence by 1st December 2018

ISKANDAR PUTERI BUS SCHEDULE

Note:-

• Timing for the public bus are base on the operator schedule (available in mobile apps HUGO)• There will be changes in the schedule once 4th bus is in operation.

ISKANDAR PUTERI CONNECTIVITY

TEEGA RETAIL LOTS

STATUS UPDATE

NO UPGRADING ITEM STATUS DATELINE

Other upgrading;

Badminton/Basketball court

3. Ventilation – Installation of Exhaust Fan Completed -

4. Benches Completed -

Signages

5. Tower A exit to Jalan Laksamana Boulevard- To add exit signage

Completed -

6. Installation of 2nos of Electric Charging Point for hybrid car

Completed -

NO UPGRADING ITEM STATUS DATELINE

Suites

1. Propose Suites Upgrading – Installation of Big 10 ft fan

Completed

2. Propose Suites Upgrading - Loading/unloading bay path way

Awarded. Included in signages contract.

-

STATUS UPDATE

13. WIFI Service in Common Area and Lifts Others are completed.Pending installation in Cabana Lift only.

June 2018

10. WIFI Service in Common Area and Lifts Completed. Aug 2018

11. Water dispenser Delivered. -

12. Mosquito repellant bulb Delivered. July 2018

13. Missing Links Roof at E-deck Awarded. Work in progress.

Feb 2019

14. Child care and multipurpose room furnishings Awarded. Jan 2019

15. Upgrading of fencing Awarded. 90% completed, pending fencing at LG only.

Jan 2019

16. Signages Upgrading Awarded – 50 % completed

Jan 2019

17. Security Upgrading Awarded. Jan 2019

NO UPGRADING ITEM STATUS DATELINE

Changing Room

7. Installation of Changing Room Fittings(hanger, towel racks and locker)

Completed. July 2018

9. Benches Completed. -

FIT-OUT WORKS• Project duration : 12th November 2018 – 21st January 2019 (10 weeks)• Items included under this project are as follows;

No. Location Item

1. Fit-out for childcare centre • Indoor Play area• Reading nook(Please refer to Perspective)

2. Cabana Lobby • Arm chair and coffee table

3. Games Room • Storage Cabinet to be fixed

4. Multipurpose Room / Function Room (E-deck Tower A & B)

• Foldable rectangular table• Block Curtain• Additional Banquet Chair

5. Pantry at Multipurpose / Function Room (Sky-lounge Tower A, B & Suites)

• Cabinet and wash basin

6. Mailroom at Suites • To provide metal strips at corner to avoid crack/damages to the glass.

FIT-OUT FOR CHILDCARE CENTRE Proposal for Childcare Fit-out concept

TEEGA RETAIL LOTS

GROUND LEVEL

LOWER GROUND

Teega Handover Office

Tribus Café SUTL Sales Gallery

Note: 1. Occupied unit delineated in green2. Units in negotiation delineated in yellow3. Vacant unit delineated in red

SUTL-One Degree 15 Marina Puteri HarbourTarget to open: 1 October 2018

YSL FreshmartTarget to open: 1 December 2018The Tribus

Target to open: 1

December 2018

COMMON AREA DEFECTS UPDATE

Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.

OVERALL PROGRESS

CLOSED/ COMPLETED

1671(78.2%)

WIP/ NEW

466(21.8%)

PREVIOUS DEFFECT RECTIFICATION WORK PROGRESS

1 SEPTEMBER 2018 - 30 SEPTEMBER 2018

CLOSED/ COMPLETED

1831(84.2%)

WIP/ NEW

343(15.8%)

CURRENT DEFECTS RECTIFICATION WORK PROGRESS

1 OCTOBER 2018 - 31 OCTOBER 2018

DEFECTS RECTIFICATION WORK RECORD

DESCRIPTION

TEEGA TOWER

(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK

CONDOMINIUM

E-DECKRETAIL

SERVICE

APARTMENT

E-DECK

TOTAL

DEFECTS

PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT

Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18

CLOSED/

COMPLETED 220 250 560 602 145 183 227 247 14 21 427 437 20 20 39 46 19 25 1671 1831

WIP/ NEW 20 9 51 12 117 91 183 164 7 0 35 25 21 23 18 11 14 8 466 343

LODGED 240 259 611 614 262 274 410 411 21 21 462 462 41 43 57 57 33 33 2137 2174

Variance, σClosed : 160

WIP : -123

COMMON AREA DEFECTS UPDATE

423

678

868

1000

1208

1454

1671

1831

1163

1045

901

810742

641

466

343

0

200

400

600

800

1000

1200

1400

1600

1800

2000

Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18

NU

MB

ER

OF

DE

FE

CT

S

MONTH

COMMON AREA DEFECTS RECTIFICATION WORK PROGRESSMARCH 2018 - SEPTEMBER 2018

Completed/Closed Work In progress (WIP)

Variance, σClosed : 217

WIP : -175

Variance, σClosed : 246

WIP : -101Variance, σClosed : 208

WIP : -68Variance, σClosed : 132

WIP : -91

Variance, σClosed : 190

WIP : -144

Variance, σClosed : 225

WIP : -118

Variance, σClosed : 160

WIP : -123

Defects / Month Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18

Completed/Closed 423 678 868 1000 1208 1454 1671 1831

Work In progress (WIP) 1163 1045 901 810 742 641 466 343

Closed/Completed Variance, s - 255 190 132 208 246 217 160

Work in Progress (WIP), s - -118 -144 -91 -68 -101 -175 -123

Thank you

COMMON AREA DEFECTS UPDATE

Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.

WORK IN PROGRESS BY AGING

DEFECTS < 30 DAYS

109(23.4%)

DEFECTS > 30 DAYS

356(76.6%)

PREVIOUS WORK IN PROGRESS (WIP) BY AGING

01 SEPTEMBER 2018 - 30 SEPTEMBER 2018

DEFECTS < 30 DAYS

18(5.2%)

DEFECTS > 30 DAYS

325(94.8%)

CURRENT WORK IN PROGRESS (WIP) BY AGING

1 OCTOBER 2018 - 31 OCTOBER 2018

WORK IN PROGRESS (WIP) DEFECTS CATEGORY BY AGING

DEFECTS

AGING

TEEGA TOWER

(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK

CONDOMINIUM

E-DECKRETAIL

SERVICE

APARTMENT

E-DECK

TOTAL

DEFECTS

PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT

Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18 Sep-18 Oct-18

DEFECTS < 30

DAYS 11 1 9 0 29 10 21 2 0 0 11 2 8 2 16 1 4 0 109 18

DEFECTS > 30

DAYS 9 8 42 12 88 81 161 161 7 0 24 23 13 21 2 11 10 8 356 325