Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Examples of the technical update newsletter which detailed SCIRT innovations.
Lessons learned from one of New Zealand’s most challenging civil engineering projects:
rebuilding the earthquake damaged pipes, roads, bridges and retaining walls in the city of
Christchurch 2011 - 2016.
This document has been provided as an example of a tool that might be useful for other organisations undertaking complex disaster recovery or infrastructure rebuild programmes.
For more information about this document, visit www.scirtlearninglegacy.org.nz
TechTimes Newsletters
Story: Technical Groups and Technical Newsletters
Theme: Design
Technical Group Updates
Wastewater – Jeanette White
Innovations:
An innovations prioritisation matrix has been established and used
successfully to asses and prioritise innovations based on a number of
different criteria including cost, speed of implementation and frequen-
cy of use.
There are a number of innovations which have been assessed using
the matrix and have been moved forward to the research stage of the
innovation process including the following:
Vented manhole lids
Micro-tunnelling
Manhole cones
Vertical lateral risers
Restriction of long socket connections to specific design areas
Standard drawings, SS paper , guidelines and specifications:
Innovations which have been approved through Scope and Standards
include:
Pipe embedment options -SS 211
Plastic manhole chambers-SS 206
Changes to the pre-cast Circular manhole-SS 163
Refer the Scope and Standards folder on the general drive for more
information on these papers.
Specifications have been updated for CIPP lining and a pre-approval
process for Delivery Team lining sub-contractors is currently being de-
veloped .
Standard repair drawing formats and tables have been developed to-
gether with the Land Drainage technical group and 12 D/ CAD repre-
sentatives. These are currently being trailed within the Blue Team be-
fore a final version is disseminated SCIRT wide. Representatives form
the technical group visited Citycare last week to inspect standard re-
pair methods in order to produce a standard repair detail sheet.
Technical group representatives are currently working with Pump Sta-
tion representatives to complete at trafficable pump and vacuum
chamber lid detail .
Geotechnical- Louise Kendal Riches
Lessons Learnt:
Visit site frequently, especially if site supervisors change.
Look beyond our asset sites, especially for drainage issues.
Discussions on site may lead to confusion, follow up with an email
or sketch.
Standard drawings, SS papers, guidelines and specifications:
Scope and Standards paper SS217 which presented a decision mak-
ing tool to allow designers to adopt a design life of less than 100 years
for retaining walls in certain circumstances has been approved. De-
signer Guideline 51 relating to the design life of retaining wall also has
been approved and available on the Project Centre library
A Soil Nail Installation specification has been drafted and is
currently under review.
TechTimes Innovations and Technical groups
this issue
Updates from Technical groups
Innovation of the month-DD Drainage
Callaghan Innovations
Howard Simpson
Citycare site visit to inspect repair methods
Soil Nail wall installation
London Street Lyttelton
Testing accessibility of plastic manhole
chambers for CCTV cameras with Citycare
(Scope and Standards Paper 206)
Pump Stations-Patrick Marshall
Lessons Learnt:
PS Control Cabinet Issues-There have been a number of issues identi-
fied with the current design including :
Insufficient space around Radio unit to allow for connection to ra-
dio setup port etc.
Issues with the current aerial mounting bracket arrangement due
to pole diameter size, and corrosion of bolts when needing to un-
do. Suggested solution was to use a standard Hi-Tec aerial mount-
ing bracket
Hoon Hay pressure 01-
Delivery team failed to confer with SCIRT Designers and Pressure
Sewer supplier on the detail and understood the minimum cover
requirement in the berm to be more important than installing the
boundary kit boxes at an accessible depth. This resulted in the
majority of the 85 boundary boxes installed at 650mm depth with
the base of the EOne boundary kit box cut off, and a piece of 225
PVC used to extend the pit down to the lower depth. Lesson
learned was no to assume the Delivery Team Project Manager
will know to raise/query modifications with the Designers. Remind
the delivery teams that if they propose a detail, they need to run it
passed us first, to avoid rework
Innovations:
Currently investigating six different innovations which have been as-
signed to different members of the Technical Group
Standard drawings, SS papers, guidelines and specifications:
Six Standard Details have been completed and uploaded tot eh project
centre library. The Pressure Sewer Design Guide and Specification
have been updated and uploaded to Project Centre
Lift Station Design Guide is being undertaken by three members of the
group.
Land Drainage –Amber Murphy
Standard drawings, SS papers, guidelines and specifications;
Stormwater repairs and lining: Should be detailed using the same
standard plan and table as wastewater (see F:AutoCAD_Shared/
Prepared Details/Patch and Repair).
Stormwater pipe renewals/ new pipes: A shared roading and storm-
water plan and longsection sample drawing has been created (see
F:AutoCAD_Shared/Prepared Details/Roads). Where possible this
example should be followed. Some cases will require a separate
stormwater longsection (without plan, it will refer to the roading plan).
This may be relevant where there is not a singular underchannel pipe
only. If this is the case the stormwater longsection must match the
scale and direction of the roading plan. Obviously where stormwater
works are proposed on roads with no roading works, or through private
property, a separate stormwater plan and longsection will still be re-
quired.
Pipe Repair Toolbox:
A toolbox of pipe repair solutions is being developed. The additional
options (to a CIPP patch or partial renewal) may well be a more appro-
priate and cost effective solution in some situations (especially for the
stormwater pipes where exfiltration/infiltration is not of great concern).
It is envisioned that the toolbox will detail other options, and provide
guidance on where they will be appropriate.If you have seen/know of a
different repair method you think is of value, please contact Amber.
Innovations and Technical groups
Pump station control cabinet
Delivery Teams Innovations DD Drainage (sub-contractor to Downer) Dewatering Bins DD Drainage is installing LPS Tanks in New Brighton as a subcontrac-
tor to the SCIRT Downer DT. To treat sediments from dewatering, the
team designed a "multi bin treatment system" which consists in bins
connected to each other by recycled PVC fittings.
The system is cheap to build and maintain, efficient in treating sandy
soils and very mobile. If needed, further bins can be added in series to
improve discharge quality. Cost to build is less than $300.
Callaghan Innovation is a government organisation that works closely
with industry to provide knowledge and resources to promote innova-
tion. They have identified the Christchurch rebuild as one of the key
projects in New Zealand to be actively involved in and support. More
information about Callaghan can be found here:
http://www.callaghaninnovation.govt.nz/about-us and an insightful
presentation by Sir Paul Callaghan and his vision for New Zealand
here: http://www.youtube.com/watch?v=OhCAyIllnXY.
Ivo Gorny has been working alongside Annalise and Jeanette to un-
derstand the innovations process, identifying areas of improvement
and establishing an innovations business process to give direction and
support to the technical groups. We will be sharing and asking for your
feedback on this process in the next few weeks. Ivo brings many years
of experience with project management and business processes to
SCIRT and has been a great help acting an independent advisor to
innovations management.
Technical groups include representatives from all Deign teams and
also include Delivery team representatives.
If you would like an innovation, standard detail or common design is-
sue discussed please lodge and innovation on the Project Centre form
or talk to your technical representative.
Technical groups meet monthly or weekly. All meeting minutes can be
found in Project Centre Library, Innovations/technical group.
Callaghan Innovation
DD Drainage Dewatering Bins
operating onsite
Technical Groups
Wastewater –Jeanette White
Water reticulation -
Pump Stations-Patrick
Geotechnical—Louise Kendal Riches
Land Drainage– Amber Murphy
Structures-
Technical Group Updates
• Wastewater – Jeanette White The new Asset Assessment Spreadsheet has been released for use by
all design teams (H:\General\Asset Assessment Spreadsheet\Asset As-
sessment Spreadsheet v3.1).This update has improved the process of
summarising pipe repair decisions and importing repairs into the 12d
drainage model. Standard repair tables are able to be produced from
the spreadsheet and AutoCAD script files allow repairs to be directly im-
ported into drawings. This automated process significantly reduces the
number of drawings required and time spent preparing them at the De-
tailed Design stage of each project. Additionally, direct links to CCTV
footage are provided to enable quick viewing and assessment of faults on
each pipe asset.
The finalised Version 3.2 and updated Design Guideline 046 will be
released this month after testing has been completed. Please refer to the
draft guideline in the same location as the spreadsheet for guidance on
how to use the new design tool. Alternatively, please consult with
Rosman Abdullah or Tessa Flaws for spreadsheet based queries or Neil
Locke and Brent Stewart for AutoCAD based queries.
A draft of the SCIRT standard pipe repair methods has been reviewed
by the Wastewater Technical group and is expected to be released
shortly.
A new trial automatic flush tank has been installed in Marley View
Street as part of SCIRT project 10398. This new tank replaced
an existing flush tank where the downstream pipe sections were not able
to be relayed to tractive force grades. Modelling and preliminary
field testing indicted a peak flushing flow produces a shear stress greater
than 1 Pa (tractive force shear stress) for 100m downstream of the tank.
Scope and Standards paper 234 (SS 234) was submitted and approved
for installation of three similar flush tanks in SCIRT project
11066.Modelling of theoretical hydrographs in Infoworks enabled the
shear stress values to be determined for the pipes downstream of the
proposed flush tanks.
The Wastewater Technical group will be monitoring the performance of
the installed flush tank in addition to investigating further potential use of
this innovation in other locations.
this issue Updates from Technical groups
Delivery Team smart innovations
Testing an automatic flush tank
installed in Marley View Street
Section detail of the
Automatic Flush Tank
TechTimes Innovations and Technical groups
• Geotechnical- Louise Kendal Riches
The site investigations team have recently carried out some investigations
using ground penetrating radar (GPR). However, it was discovered that
this method does not perform well in Loess soils. Loess absorbs the sig-
nals and therefore penetration to only 2m or less is typical.
The Orange team is preparing a document regarding wall aesthetics and
the desired finishes. This is as a result of a recent disappointment over
the final appearance of a gabion wall with a concrete capping beam. The
final wall has the top row of gabions covered by a partial and broken con-
crete face. As well as the poor appearance, this section is now less flexi-
ble and therefore attracts more load than the design anticipated. The pic-
ture (top right) is of a similar wall, also designed by SCIRT, with the finish
the designers were hoping for.
• Pump Stations-Patrick Marshall
The Lift Station Design Guideline draft is complete and
is being reviewed by members of the Pump Station technical group.
Four innovations are also being currently investigated.
A standard drawing for an access ladder to the valve chamber and the
wet well draft is complete and is being currently reviewed by Technical
Group members.
Pump Station Electrical Design
The electrical design for pump stations is currently being updated.
The Lead Designer for any station which is at the Detailed Design stage
should consult with their Pump Station Technical group representative or
Technical Lead before issuing drawings.
Innovations and Technical groups
Pump station 105 Concept
Drawings
Gabion wall with concrete capping beam
Horotane Overpass Bridge
(temporary works) SCIRT project
Innovations and Technical groups
• Land Drainage-Amber Murphy A pipe repair toolbox of alternative repairs for stormwater has been
created and these are currently being priced by the SCIRT estimation
team. These repairs include epoxy crack repair, installation of concrete
saddles and steel plates, a concrete surround of the existing pipe, con-
crete point joint ties, and relaying the existing pipe.
A standard detail for Rodding Inspection Chambers and Subsoil drains
is currently being developed within the Land Drainage technical group.
Standard rates for Concept and Detailed Design stormwater items has
been uploaded to Project Centre as part of a SCIRT Designer Guideline
055 (https://projectcentre.net/CHCH).
The “ Interpretation of SW requirements of the IRTSG” Designer Guide-
line 054 is also available in Project Centre.
• Structural-Campbell Apthorp
The introduction of the Structural Standards Notes (SC6201 Sheets 1-
5) has been introduced and needs to be specified with any structural
drawings. The new edition of the NZTA Bridge Manual was released in
May.
All Detailed Design after the 1st June 2013 should be abiding by the new
edition. There is also the push for more innovations to be logged and
progressed within the Structural technical group.
• Water reticulation-Sebastian Ichim
In the last couple of meetings the water group has developed a SCIRT
Guideline for water supply drawings which includes updating
the symbology for water supply components which has been released to
CAD users . There has also been some preliminary discussion regarding
as-built survey information collection and an as-built information survey
guideline.
Delivery Teams Smart Innovations
Safety and Environmental inspections and audit by tablet Fletcher’s safety and environmental team are trialling electronic tablets to
carry out their safety /environmental audits. It has already proved to very
effective in saving time and improved the accuracy of information. The
users have particularly found that the ability to take photos on site that
are instantly attached to the audit to be very efficient.
iAudit
Fulton Hogan (FH) EQ Rebuild since June has been conducting and pi-
loting Environmental Audits using the iAuditor tool. The rebuild team is
the first project to utilise this software in FH, and its success and support
by management has already shown great interest by other regions within
FH and also other members of the SCIRT alliance.
The tool is versatile, with the ability to create audit templates, checklists
and forms to suit individual needs. FH has loaded up resource consents
on the share file so that all users have easy and quick access to
the consent conditions. Emailing audits and performing them on tablets
has also meant that there is reduced paper work
and administrative burden on FH staff.
For the full Delivery Team innovations report for August please see
G:\Value\Innovations\Delivery Team Innovation Reports or Annalise
Johns.
Technical groups include representatives from all Deign teams and
also include Delivery team representatives.
If you would like an innovation, standard detail or common design issue
discussed please lodge and innovation on the Project Centre form or talk
to your technical representative.
Technical groups meet monthly or weekly. All meeting minutes can be
found in Project Centre Library, Innovations/technical group.
Onsite auditing by Fulton Hogan
Wastewater—Jeanette White
Water reticulation—Sebastian Ichim
Pump Stations— Patrick Marshall
Geotechnical—Louise Kendal Riches
Land Drainage– Amber Murphy
Structures– Campbell Apthorp
Technical Groups
Fulton Hogan iAudit tool format
1
NOVEMBER 2013
TECHNICAL AND INNOVATIONS UPDATE
Inside this addition:
Technical group updates
Wastewater 2
Geotechnical 3
Water Reticulation 3
Land Drainage 4
Pump Stations 4
Roading 5
Explosive Induced Liquefaction Trials 5
2
Wastewater – Jeanette White
Standard Drawings and Specifications
A SCIRT standard drawing for pipe repair methods (SC6312) and a SCIRT standard detail for a vertical risers for lateral connections from mains (SC6314) has been completed and uploaded to Project Centre. Further investigations by the Wastewater (WW) Technical group will be done into improving repair methods and alternative couplings which
could be potentially used in sections replacements.
A l l w a s t e w a t e r p r o j e c t s w i t h r e p a i r / r e l i n e /section replacements strategies are required to note the pipe diameter of each pipe on the plan. This is to help communicate the existing and new network more effectively and emphasise
the location of trunk mains.
Innovations
Couplings
A meeting with Rehau (German based company) took place last month at which a number of Rehau products were presented. Included was a stepped coupling (right) which has great potential for achieving a higher ring seal pressure around the existing and new section replacements than existing shear bands currently available in the New Zealand market. The coupling is lightweight, features a hydrophilic seal and is able to be used on a range of pipes with different outer diameters. Rehau are currently in the process o f app ly ing fo r inc lus ion in the CCC Approved Materials list and the WW Technical group will be
updated on the progress of this process at a later date.
Manhole Venting
A Short Form Report is currently under review by the WW Technical group which summarises the venting of the Christchurch wastewater network and the potential to accommodate venting within a 600mm manhole cover. The report investigates the origins of the existing Christchurch venting systems, capacity and an alternative
venting detail.
Traffic Loading
The current traffic loading criteria for buried structures is currently under review.If approved, this assessment will assist in the design and specification of trafficable chambers and other buried
structures.
Pipe Lining
An additional SCIRT lining specification for larger diameter pipes (over DN 375) has been completed and will be uploaded shortly
to Project Centre.
November 2013
Updates from Technical groups
Liquefaction Trials
Rehau Stepped Coupler
Innovations and Technical groups
Technical and Innovations Update November 2013
3
Geotechnical - Louise Kendal Riches
Innovations
Glass fibre Reinforced Plastic (GRP) Anchors
The Geotechnical Technical group recently had a presentation from the suppliers of GRP Anchors, Bluey. Following this Design teams are considering using these GRP anchors in their designs. These are likely to be for either low height walls or for flexible walls where
the additional flexibility of the GRP may be an advantage.
Impact Barriers
In a change to the previous procedure, it is now required that every retaining wall where an upgraded or new impact barrier is
recommended has a Scope and Standards Paper prepared.
Soil Nails through Crib Wall
In the past it has been challenging for Designers and Delivery Teams to anchor through an existing crib wall. However, the Blue team have successfully designed a crib wall with anchors and a shotcrete facing. The construction involved drilling anchors within a PVC casing through the crib fill and then drilling through the rear of the crib unit because the angle of the anchors could not match the
crib. Following this a shotcrete brushed face was applied.
Water Reticulation-Sebastian Ichim
Standard Drawings and Specifications
Thrust Block
An in-line thrust block standard detail is currently being revised by the Water Reticulation Technical group. It is anticipated that short presentation will be given at a Designer’s meeting in the near future about the in-l ine thrust block detai l and
what reference documents are available.
Drawing Legend
A new legend is available for water supply drawings and a
short guideline has been uploaded to Project Centre.
Shared Trenches
The Utilities Design Approval (UDA) form on Project Centre has been amended to include a section for proposing shared trenches where utility companies would like the opportunity to install their services in a
shared trench with new watermains or submains.
Impact Barrier: Cunningham Terrace
SCIRT project 10427
New structures: Rangatira Terrace SCIRT
project 10462
Innovations and Technical groups
Technical and Innovations Update November 2013
4
Land Drainage-Amber Murphy
CCTV Training
A CCTV Request training workshop was held for Designers to inform them on processes, systems, and tools available for requesting asset assessment. For more information refer
G:\General\CCTV or talk to Mike Tate.
GIS
A new layer, Integrated Planning and Design of Private Property and Roading Related Stormwater Drainage, has been included on GIS. Please refer see the associated guideline within the GIS
Map Metadata for information on this layer.
Non-Critical Defects
Approximately 42 Scope and Standards papers have been prepared for No Action of Non-Critical Defects in stormwater pipes. This amounts to over $50 million that has been saved than can be spent on critical faults. Please consult with the Stormwater Technical group representative or Stormwater Designer in your Design team for further
information.
Pump Stations-Patrick Marshall
Control Cabinet CI Card Update
John McKirdy will be producing a design for Pump Station 105. A Notice of Requirement has been issued to Delivery Teams noting that no control interface (CI) cards are to be installed. If a Pump Station cabinet is constructed with a CI card then CCC are staff to make the adjustment in the field. Andrew Whittle of the CCC. Instrumentation and Control Team will be co-ordinating within Council and Mark Slater will finalise a list of Pump Stations that require
an electrical update.
Panel Level - Lift Station/Pump Stations
Designers are required to consult CCC on the location of each cabinet to check the 50year design flood level (not including climate change, increased rainfall intensity and sea level rise). The cabinet will be initially designed to the standard 1.4 m in height. If the 50year event plus 300 mm freeboard is greater than the base of the cabinet, Don Gracia and Mark Johnson (CCC) should be consulted regarding the height of the cabinet in relation to the heights
of surrounding dwellings
Lift Station Review Process
Designers are required to consult Don Gracia regarding the location of the wet well and the cabinet. Don will be responsible for forwarding to
CCC Roading Asset Representatives for further comment.
Pump Station 107 In Construction
New GIS Land Drainage Layer
Innovations and Technical groups
Technical and Innovations Update November 2013
5
Roading-Richard Bailey
Coal Tar
A standard detail which addresses the treatment of coal-tar in trenches and roading has been completed and uploaded to Project
Centre (SD6606).
Bill of Quantities
The standardised Bill of Quantities for Roading and Stormwater has
now been uploaded into the Project Centre library.
Stockpiling of Contaminated Material
T h e R o a d i n g T e c h n i c a l g r o u p h a s s u p p o r t e d the centra l ised stockpi l ing and re -use of coal -tar contaminated material, however approval from ECan and CCC will
be required.
Recycled Grout
It was also agreed that recycled grouting material from re-levelling of the Art Gallery would be a good, flow-able fill material as it has the same strength as low-strength concrete back fill. It is anticipated the
material will be suitable for use around structures in roads.
EQC, MBIE and NZTA have undertaken trials within the CERA Resi-dential Red Zone to assess seismic performance of various ground improvement techniques. EQC utilised both a T-Rex machine and explosives to induce liquefaction of the soil and had agreed to include a plot of land within the Residential Red Zone for SCIRT infrastructure trials. Explosives were used within the SCIRT trail to initiate liquefaction and allow the assessment of
post liquefaction performance and effects.
Duncan Gibb noted that SCIRT had taken the opportunity to develop a
trial that would:
Confirm changes made with CCC to design details and specifications to make the underground infrastructure more
resilient
Test innovative concepts to further improve materials
and methods for the horizontal infrastructure rebuild
The purpose of the liquefaction field trials was to assess the effects of liquefaction on various elements of below-ground infrastructure in a controlled and closely monitored field situation. The results will provide information to SCIRT designers in reviewing the appropriateness of current CCC standard details
and proposed alternatives.
Explosive Induced Liquefaction Trials
Land Trials: Controlled Blasting
Previous Trial Example
(source: hhttp://ww.eqc.govt.nz/
canterbury/earthquakes/land/-claims/
landtrials)
Innovations and Technical groups
Technical and Innovations Update November 2013
6
Wastewater- Jeanette White
Water reticulation- Sebastian Ichim
Pump Stations- Patrick Marshall
Geotechnical- Louise Kendal Riches
Land Drainage- Amber Murphy
Structures- Campbell Apthorp
Roading- Richard Bailey
Technical Groups
A number of different infrastructure tests were completed including :
DN 150 PVC-U SN16 with easily compacted granular haunching
within the trench
DN150 PVC-U SN16 pipe with NZTA AP20 haunching within
trench
Pressure Sewer Chamber (PE) – Granular backfill relieving pore
water pressures
P r e s s u r e S e w e r C h a m b e r ( P E ) – B a c k f i l l with excavated materials (pre-SCIRT). In accordance with suppli-
er installation details.
Pressure Sewer Chamber (PE) – Backfill with excavat-ed materials (pre-SCIRT). In accordance with supplier installation
details.
1050mm dia concrete manhole with connecting PVC-U SN16 pipe, backfilled with AP65. With Long Socket Connection to Test 1 pipe and an Iplex Manhole Connector to a 150mm PVC-U
SN16 dia lateral
DN600 PE manhole with connecting PVC-U SN16 pipe, backfilled
with AP65
Pressure Sewer Chamber (PE) – Low strength concrete backfill
DN150 Restrain PVC-U SN16 pipe installed by directional drilling
Chambers were installed within the zone anticipated to liquefy, while the pipes were installed though both ground which remained non liquefied, liquefied ground and connection with the concrete precast standard manhole. Peizometers were used to monitor the increase in pore water pressure and liquefaction
was induced when the pore water pressure equalled the total stress.
SCIRT will be responsible for exhumation of the site and detailed interpretation of the data. It is anticipated that once the information has been processed a SCIRT presentation will be given to those interested in results of the trials. For more information on
SCIRT’s involvement please contact Marcus Gibson.
For more information on the EQC trials and links to footage
of previous trials refer to the EQC website.
http://www.eqc.govt.nz/canterbury-earthquakes/land-claims/land-trials
Technical groups include representatives from all Design teams and
also Delivery team representatives.
If you would like an innovation, standard detail or common design issue discussed please lodge an innovation on Project Centre form or
talk to your technical representative.
Technical groups meet monthly, weekly or as required. All meeting minutes can be found in Project Centre Library, Innovations/technical group.
6
Site Plan For SCIRT Infrastructure With-
in EQC Explosive
Induced Liquefaction Trial
Technical and Innovations Update November 2013
1
APRIL 2014
TECHNICAL AND INNOVATIONS UPDATE
Inside this edition:
Technical group updates
Wastewater 2
Wastewater 3
Geotechnical 4
Land Drainage 4
Roading 6
Delivery Team Innovations 6
Delivery Team Innovations 7
2
Wastewater – Jeanette White
Standard Drawings and Specifications
The SCIRT Standard Project Specification has been modified to exclude the generic sections. The generic sections will now stand a-lone on Project Centre and include revision numbers which should be referenced in the appropriate areas within the Specification. These specifications are available to the Delivery Teams directly through Project Centre. The new format wi l l s treamline the project documentation and also clarify which revision the TOC
estimate was based on prior to construction.
The generic specifications include:
Pressure Sewer
Trenchless Pipe Installation
Pump Station Electrical
Technical Road Maintenance
Lining (to be updated shortly)
The generic specifications can be viewed at:
Project Centre/ Register / 005 Generic Specifications / 006 SCIRT
Standard Specifications.
Modifications have also been completed to part of the Project Specification for sections relating to flexible pipe embedment material and compaction and a new SCIRT standard detail (SC6315) “Pipe embedment for flexible pipes” has also been
uploaded to the SCIRT library.
The results from trench field trials investigations as well as recommendations from Delivery Team representatives and University of Canterbury academic staff, was incorporated into
the update of sections 2.8.1 and 2.8.3 of the Project Specification [3].
The main changes to part of the Project Specification relate to :
Minimum trench widths (refer to SCIRT standard detail SC6315)
PVC-U minimum pipe class
A new embedment material option
Embedment compaction requirements to replace previous re-quirements for clause 8.5.1 of CSS Part 3-Ultilty Drainage includ-
ing alternative embedment types
Acceptance Criteria for the surface restoration over excavations
The SCIRT Project Specification can be viewed at:
Project Centre/ FileCentre / Library / Specifications./Project Specifica-
tion
Alternatively please contact Tony Gordon (Orange Team 3 Waters Design Lead) for more information or queries regarding
these amendments.
April 2014
Updates from Technical groups
Delivery Team Innovations
Innovations and Technical groups
Technical and Innovations Update April 2014
SCIRT standard detail : SC6315
Pipe embedment for flexible pipes
3
Wastewater – Jeanette White (continued)
Innovations
Manhole Venting
The Short Form report which investigated the origins of the existing Christchurch venting systems and the potential of accommodating a DN600 manhole cover, was expanded to a Scope and Standards pa-per (SS176). This paper was submitted to the Scope and Standards
Committee last month.
CCC Approved Materials Committee have now approved the use of both vented and non-vented Ductile Iron DN600 manhole covers for
wastewater and stormwater.
Plastic manhole chambers and Rehau couplings
Rehau are also in the process of applying for third party accreditation for their DN600 plastic manhole chambers to be included on the CCC Approved Materials list. The use of DN600 plastic man-hole chambers has been previously approved for use through Scope
and Standards paper 206 (SS206).
The Rehau FLEXCONNECT mechanical coupler has been approved for use by the CCC and is now listed on the CCC Approved Materials list. Rehau are now working towards confirming a New Zealand suppli-
er. For more updates to the approved materials list refer to:
ht tp: / /www.ccc.govt .nz/business/construct iondevelopment /
approvedmaterials.aspx#jumplink4
Flushing Siphons
A workshop was held this month to collate the knowledge from the different design teams involved in design of Flushing Siphons for
SCIRT projects.
Currently Flushing Siphons have been proposed and approved for are-as where the renewal of pipes with flat grades has not been the recommended option in order to achieve the best value for the project based on a Level of Service design approach. Various common issues were discussed and resolved at the work-shop including standard terminology for the different configurations,
cover/access details and design steps.
Minutes for the meeting are available in Project Centre:
Project Centre/ Register / Library / Innovations/ Wastewater / Minutes /
Flush
Scope and Standards papers have been approved for four SCIRT projects in the Halswell and Hoon Hay/ Westmorland areas. Currently one Flushing Siphon has been installed and is operating in the Somerfield area at the top of Marley View Street. The system oper-ates automatically and is connected to a restricted mains water supply. As the water level in he Flushing Siphon Chamber reaches a designat-ed point a siphon is used to flush the downstream pipes
to prevent sediment accumulation.
Innovations and Technical groups
Technical and Innovations Update April 2014
Vented DN600 Manhole: Example of a Ductile
Iron DN600 vented manhole with
dust collector before installation
Flushing siphon :Steinhardt Hyrdoflush
unit before installation
4
Geotechnical - Louise Kendal Riches
Innovations
Planning guidance for Retaining Walls Guidance has been developed for SCIRT designers dealing with retaining walls which may be significant with regard to their appearance or age. This is in addition to the existing guidance for walls which are heritage listed in the City Plan and Lyttelton retaining walls which are marked on the Significant Walls List. It specifically addresses walls which are not heritage walls but support a heritage listed property, and walls which are Port Hills rock, or early boxed concrete, but not listed heritage or pre-1900. The photo above right shows a retaining wall which is not a heritage listed structure, but was built as part of the Cashmere Sanatorium in the early 1900s. Guidance for this wall is provided in this document. Specific data is available on request.
The photo below right shows a Port Hills rock wall. This is not a heritage structure, but the walls in this area add character and contribute to it being a special amenity area. Guidance for this wall is also provided in this document. Refurbishing Gabion Walls Anchoring through gabion baskets has been proposed as a method for the repair of two existing walls. It is anticipated that drilling through the baskets may be difficult and therefore a test anchor is due to be installed by Rock Control this month to assess the feasibility of this solution. Groundwater Monitoring SCIRT has recently received extensive groundwater monitoring data from locations across the city. Webmaps contains a layer which shows the piezometer locations and IDs which can be cross-
referenced with the data. Specific data is available on request.
Innovations and Technical groups
Technical and Innovations Update April 2014
Retaining Wall: Non-heritage structure in
the Port hills
Retaining Wall: Built early 1900’s
5
Land Drainage-Amber Murphy
Innovations
Lightweight Localised Pump Stations SCIRT project NE3 New Brighton Repairs #11110 (currently at the TOC stage) utilises a new innovative design philosophy which focuses on the use of horizontal axial flow pumps which enable shallow and lightweight structures to be used. A Scope and Standards paper (SS269) was submitted and approved for this project which proposed the use of a light-weight localised pump station with horizontal axial flow pumps. This option has a number of advantages from design through the lifecycle of the asset, including Design templates are able to be transferred to other projects
with minor amendments Construction duration and temporary work costs are able to be
greatly reduced as deep excavation in poor ground with a high water table is not required
Stations can be located to serve existing infrastructure or low points, minimising the amount of reticulation required to convey flows to a centralised point
In the case of earthquake damage, repair costs, duration and complexity of repairs are reduced as the structure is relatively small and lightweight allowing the structure to rotate and/or differentially settle and remain operational with minor damage
The relative small size of the structures allows for significant cost saving relating to land acquisition and legal costs as the structures are able to be located within the road reserve
Significant cost savings were identified within SS269 associated with a shorter and safer construction programme in addition to potential cost savings associated with future repairs of
the shallower structures .
Innovations and Technical groups
Technical and Innovations Update April 2014
Lightweight pump: Light-
weight stormwater pump
with horizontal axial flow pumps
6
Roading-Richard Bailey
Standard Drawings and Specifications
The Maintenance Specification has now been uploaded to Project Centre as part of the generic specifications and is not required to
be included in the Project Specification.
RAMM Repairs Rates have been revised and are now aligned with TOC, therefore reducing TOC time and giving more accurate Detailed Design Estimates. There has also been an extensive review of the Roading, Water Services and Stormwater Bill of Quantities. The new RAMM Calculation sheets and Roading, Stormwater and Water supply BOQ template havs been uploaded into the Project Centre library and can be viewed at:
Project Centre/ FileCentre / Library/Templates/BOQ
SCIRT standard drawing SC6601 with new Detail D has also been
uploaded to the Project Centre library.
An example standard CAD layout drawing for Roading projects has been uploaded into Project Centre which will help with standardisation
of SCIRT drawings across all design teams.
The Roading Technical group are also working towards new methodologies for treatment of Coal Tar including treatment of coal tar with cement which may negate the requirement to
wrap contaminated material with fabric .
Directional Drilling Head-Fulton Hogan and CDS
Brief Description: Fulton Hogan were the Delivery Team for the pressure main 128 SCIRT project #10926 and had engaged the drilling expertise of CDS NZ Ltd to complete the directional drilling components of the project . The ground conditions were highly unstable and there were unforeseen areas of organic matter within sandy soils discovered while horizontally drilling. The difficult ground conditions interfered with the drilling fluid and borehole stability which resulted in sink holes forming in the early stages of drilling. With drilling works moving into Bower Ave and passing under a number of major intersections the risk and poten-tial consequences of sink holes was significant and the drilling methodology was modified to mitigate this risk. The response from Fulton Hogan and CDS was to change the drilling approach from a full ream and closed pipe installation, to an open ended cut and pull operation. This eliminated having a large diameter borehole open underground and removed the reliance on the drill fluids to provide down hole stability, which had been compromised on earlier works by pit instability and unforeseen organic concentra-tions.
Delivery Team Innovations
Innovations and Technical groups
Technical and Innovations Update April 2014
SCIRT standard drawing SC6601-2
Cleaning head for
open ended horizontal drilling
7
The revised method saw the 800mm OD pipestring pulled into place as the borehole was opened up, lining and supporting the borehole immediately. This methodology mitigated the risk of ground deformation occurring while drilling under Bower Avenue which is a major traffic arterial route in North New Brighton. The change in methodology was successful in preventing sink holes however a method for removing the build-up of material deposited in the pipe during the drilling process was required. CDS developed and constructed a project specific clean out tool to run through the installed pipelines. Given lengths of over 500m, the long reach of CDS’s maxi rig enabled the cleaning tool to be run through the full length of the string and remove the bulk of the sand and fluid within the pipe. The remaining material was then able to be removed with hydrojetters and flushing volumes of clean water through the pipe-lines for final testing and manhole construction.
Coal Tar Encapsulation– Fletchers
Brief Description: Note: This proposal is not a current CCC practice at time of circulation. Encapsulated material must be deposited above the water table. The Fletchers Delivery team have proposed an alternative Coal Tar Encapsulation detail for one of the Coal Tar contaminated streets within the SCIRT project #11131. Fletcher were expecting to remove approximately 220m3 of coal tar impacted material from Averill Street in the Richmond area. The current detail for recycling this type of material into the road is to encapsulate it into a 100mm thick layer sand-wiched between geotextile and clean sub-base material. Fletchers proposed a detail which encapsulated the material into a slip trench located adjacent to the kerb line, approximately 500mm deep below road formation level and between 1000-2000mm wide. This detail had the following advantages: The trench could be excavated ahead of the removal of the road
surface therefore double handling was mitigated The coal tar could be mixed with cement using a rotary hoe
therefore removing the need for clean fill material to be added Locating the coal tar trench in a parking area of the
road minimised traffic loading Limiting encapsulation to the edge of the road will assist with
future maintenance issues This detail was environmentally friendly and cleaned up 85% of
the road The extent of area rehabilitated was easy to define and plot on
GIS
Technical and Innovations Update April 2014
Coal tar: Design sketch for coal tar
encapsulation in the road
Delivery Team Innovations
Fulton Hogan/CDS Innovation : Cleaning
Head for open ended horizontal drilling
8
Wastewater- Jeanette White
Water reticulation- Sebastian Ichim
Pump Stations- Patrick Marshall
Geotechnical- Louise Kendal Riches
Land Drainage- Amber Murphy
Structures- Campbell Apthorp
Roading- Richard Bailey
Technical Groups Technical groups include representatives from all Design teams and
also include Delivery Team representatives.
If you would like an innovation, standard detail or common design
issue discussed please lodge an innovation on the Project Centre
form or talk to your technical representative.
Technical groups meet regularly. All meeting minutes can be found in
Project Centre Library, Innovations/technical group.
Technical and Innovations Update April 2014