23
Techno-Economic Assessment of Oxy-Combustion Turbine Power Plants with CO 2 Capture John Davison IEA Greenhouse Gas R&D Programme, Cheltenham, UK Paper by Luca Mancuso, Noemi Ferrari – Amec FosterWheeler, Milan, Italy Paolo Chiesa, Emanuele Martelli, Matteo Romano – Politecnico di Milano, Italy John Davison – IEAGHG, Cheltenham, UK 5 th Oxy-combustion Network Meeting Wuhan, China, 27 th -30 th October 2015

Techno-Economic Assessment of Oxy-Combustion Turbine …ieaghg.org/docs/General_Docs/5oxy presentations/Session 6B/6B-04...Techno-Economic Assessment of Oxy-Combustion Turbine Power

Embed Size (px)

Citation preview

Techno-Economic Assessment of Oxy-Combustion Turbine Power

Plants with CO2 CaptureJohn Davison

IEA Greenhouse Gas R&D Programme, Cheltenham, UK

Paper byLuca Mancuso, Noemi Ferrari – Amec FosterWheeler, Milan, Italy

Paolo Chiesa, Emanuele Martelli, Matteo Romano – Politecnico di Milano, Italy John Davison – IEAGHG, Cheltenham, UK

5th Oxy-combustion Network MeetingWuhan, China, 27th-30th October 2015

• Background and scope of the study• Cycle descriptions• Cycle performance• Costs• Conclusion

Outline of Presentation

• Oxy-combustion turbines are not a new concept

• Increasing interest in oxy-combustion turbines

• Competitive efficiencies and costs are claimed for some cycles

• An independent techno-economic assessment is needed

• IEAGHG commissioned Amec Foster Wheeler and Politecnico di Milano to carry out a study

• IEAGHG report 2015/5, August 2015• Available within IEAGHG’s member countries

Background to the Study

• Review literature on oxy-combustion power generation cycles and their development status

• Assess performance of selected natural gas-fired plants• Detailed modelling of the gas turbine• Flowsheet modelling of the overall cycle

• Estimate capital and operating costs• Sensitivity to technical and economic parameters

and potential for future improvements• Assess a coal gasification oxy-turbine power plant

• Study uses the assumptions in IEAGHG’s recent CCS plants studies

Study Scope

Selection criteriaExpected efficiency

State of development/technical challenges

Cycles Selected for Detailed Assessment

Cycles using recycled CO2• Semi-Closed Oxy-Combustion

Combined Cycle (SCOC-CC)• NET Power – Allam Cycle

Cycles using mainly H2O• S-Graz (2 versions)• CES (3 versions)

• CES has carried out Multi-MW component tests

Practical Activities

CES OFT-900 turbineCES 170MWth gas generator

• NET Power combustor tests• 50MWth integrated plant scheduled to start

commissioning in late 2016• Partnership with Toshiba, Exelon and Shaw Group

Conventional Combined Cycle Fuel

Flue gas

Combustor

17 bar1430C

1 bar

AirCondenser

Steam turbine

Gas turbine

HRSG

PumpSimplified flowsheet

FuelAir/oxygenHot combustion gasCool combustion gas / CO2Pure steam/water

630C

Turbine

Compressor

Cooling air

Semi-Closed Oxy-Combustion Combined Cycle (SCOC-CC)

Condenser

Fuel

Cooler

Combustor

Water

45 bar

CO2 to storage

Compressor

Oxygen

CO2

Steam turbine

1 bar620 C

HRSG

Simplified flowsheet

NET Power - Allam Cycle

Compressor

Fuel Combustor

Condenser

Water

300 bar1150C

Oxygen

34 bar740C

CO2

CO2

Heat input from ASU air compressor

Heat exchanger

720C

<400C

TurbineO2+ CO2

Cooler

Simplified flowsheet

Modified S-Graz Cycle

Fuel Condenser

CO2

Combustor

Compressor

Oxygen

LP Steam turbine40 bar

1 bar

Steam turbine

Water

Turbine

Compressor

90% steam 10% CO2

1423C

Simplified flowsheet

HRSG170 bar555C

Steam

Supercritical CES Cycle

300 bar

CO2 Water

HP Combustor

Fuel

Oxygen

59 bar

1150C

LP Combustor

HP turbine

LP turbine

0.2 bar

MP turbine

MP Combustor

Steam

Steam

7.6 bar

Simplified flowsheet

Thermal Efficiencies

9C ambient temperature, Natural draught cooling towers

Capital Costs

Total Plant Cost, excluding owner’s costs and interest during construction,2Q 2014, Netherlands location

Cost of Electricity

2Q 2014 costs, constant money values Netherlands locationGas cost €8/GJ (LHV), 90% capacity factor, 8% discount rate, 25 year life,

€10/t CO2 transport and storage cost

Sensitivity of LCOE to Novel Equipment Costs

Future Improvements

COT - Combustor outlet temperature: NET Power - 1150C base case, 1100/1200C low/high casesSCOC - 1533C base case, 1453/1613C low/high cases

Turbine blade metal temperature: 860C base case, 950C high case

Sensitivity to CO2 Capture Percentage and Purity

CO2Capture

%

CO2Purity

%

Efficiency

%

TPC

€/kW

LCOE

€/MWh

CAC

€/t

Base case 90 99.8 55.1 1320 83.6 68

Membrane separation

98 99.8 54.7 1340 84.8 65

No purification

100 97.9 55.3 1270 82.7 58

Total Plant Cost, excluding owner’s costs and interest during construction

2Q 2014 costs, constant money values Netherlands locationGas cost €8/GJ (LHV), 90% capacity factor, 8% discount rate, 25 year life,

€10/t CO2 transport and storage cost

Lower abatement cost at higher percent capture

• High CO2 natural gas (70%)• Quantity of CO2 captured over 3 times higher

• Natural gas with high N2 content (14%)• Oxygen purity• Higher ambient temperature (25C)• Alternative cooling system (mechanical draught tower)

Other Sensitivities

Economic Sensitivities

Gasification SCOC-CC Plant

CO2

Steam turbine

Acid Gas Removal

Water

Sulphur recovery

ASU

Gasifier (GE)

Radiant boiler

Water quench / coolers

HP steam

LP steam

Oxygen

Coal

SCOC-CC cycle

Coal Gasification + Oxy-turbines

SC-PC no capture

SC-PC post combustion capture

IGCC pre combustion capture

Gasification + SCOC-

CCEfficiency, % LHV 44.1 35.2 34.9 34.0

TPC, €/kWe 1450 2770 3070 3540

LCOE, €/MWh 52 95 114 127

CAC, €/t - 65 96 115

Total Plant Cost, excluding owner’s costs and interest during construction

Bituminous coal: 2.5 €/GJ (LHV), Discount rate: 8%, 25 year plant life, Constant €, CO2 transport and storage: €10/t,

Capacity factor: 90% SCPC, 85% IGCC and SCOC

SCOC-CC costs are not competitive

for coal

Need for Further Work• Continue component and cycle development • Operation of integrated large pilot plants

• Achieve target efficiency• Achieve reliable operation• Demonstrate operating flexibility

• Cost reductions through optimisation, learning-by-doing and technology development

• Commercial roll-out to meet timescales for emission reduction

Conclusions• Oxy-combustion turbines with CCS have the

potential to achieve competitive efficiencies• Up to 55% • Higher than NGCC with post combustion capture (52%)

• Broadly similar capital cost, LCOE and cost of CO2avoidance to post combustion capture

• Other advantages• Potential for near 100% capture• Low water use• Small area

• Need for demonstration in integrated plants