Technical Trans La Ton BG - En

  • Upload
    si-mona

  • View
    216

  • Download
    0

Embed Size (px)

Citation preview

  • 8/8/2019 Technical Trans La Ton BG - En

    1/3

    . 1 3

    TENDERER: "TERA GRUP" OOD PLOVDIV: " "

    EMPLOYER: "SIEMENS":"SIEMENS"

    TENDER BILL OF QUANTITY

    ITEM Description of Work . Unit

    Anti static rubber flooring

    2 m2

    1 120 3 kg

    2

    3

    4

    5 20 .

    6 20 Concrete 20 for beams

    7 20 Concrete 20 reinforced concrete girdles

    8 20 Concrete 20 in columns with concrete pump

    9 20 Concrete 20 in walls with concrete pump

    10 20 Concrete 20 in floor slabs with concrete pump

    11

    12

    13

    14

    15

    16 Concrete for foundations and shafts

    17 Concrete for foundation slabs

    18 18/35 Kerbs 18/35 m

    19

    20 Fans pcs

    21 100/18/35 Visible concrete kerbs 100/18/35 m

    22 18/35 Visisble concrete kerbs 18/35 m

    23 18/35 Visible concrete kerbs 18/35 m

    24 PVC flooring 2 m2

    25 Roof drainage pipes m

    26 Dewatering of excavations by pumping

    27

    28 10 24 Dewatering 10 x 24 hours pcs

    29 Roof collecting drainage wells 2 m2

    30 100/210 Door 100/210 pcs

    31 100/210 PVC door 100/210cm pcs

    32 100/210 PVC door 100/210cm 2 m2

    33 70/200 PVC door 70/200cm 2 m2

    Reinforcement - 120m3 tank

    25 - 20 , 6

    Concrete pavement B25, 20 cm thick,reinforced, designated for roads , joints atintervals of 6m

    3 m3

    25- 20 , 6/6

    Concrete pavement B25 -reinforced, 20 cmthick, jointed 6/6m, designated for road

    3 m3

    25- 20 , 6/6

    Concrete pavement B25, 20 cm thick,reinforced, designated for roads , joints atintervals of 6m/6m

    3 m3

    Concrete 20 in staircases and and slopingsurfaces

    3

    m3

    3 m3

    3 m3

    3 m3

    3 m3

    3 m3

    25 -

    Concrete 25 in machine foundations with withconcrete pump-gas generator

    3 m3

    25 -

    Concrete 25 in machine foundations withconcrete pump-steam generator

    3 m3

    25 25 , - 60 KN

    Concrete B25 for pavement reinforced and 25cm thick for bearing of concentrated load

    60kN

    2 m2

    25 600 .

    Concrete 25 for foundation reinforcementbelow 600t boiler

    3 m3

    - 1203

    Concrete for foundation of 120m3 tank for softwater

    3 m3

    3 m3

    3 m3

    Rolling of crushed stone for making of base forconcrete pavement designated for roads

    3 m3

    machineshift

    Dewatering with submerged pump for mudwaters

    machineshift

  • 8/8/2019 Technical Trans La Ton BG - En

    2/3

    . 2 3

    ITEM Description of Work . Unit

    Anti static rubber flooring

    2 m2

    34 Steel Door pcs

    35 120/210 Steel door 120/210 pcs

    36 120/220 Steel doors 120/220 cm pcs

    37

    38 pcs

    39 - Temporary traffic sign - barrier pcs

    40 Temporary circle traffic sign pcs

    41 pcs

    42 55/55 Temporary traffic sign - ordinary 55/55 pcs

    43 Temporary triangle traffic sign - ordinary pcs

    44 pcs

    45 pcs

    46 Temporary guide sign board pcs

    47 pcs

    48 pcs

    49 pcs

    50 . VIII. TOTAL under item VIII.

    51 Entrance box 2 m2

    52 Restoration of crushed stone pavement

    53

    54 m

    55 2

    56 2

    57 2 m2

    58 5 External termal insolation 5 cm on walls 2 m2

    59 Lime-cement plaster on internal brick walls 2 m2

    60 Gypsum stopping on walls 2 m2

    61 50/20/8 Garden concrete kerbs 50/20/8 cm m

    62 Granitogress 2 m2

    63 kg

    64 Removal of visible concrete kerbs m

    65 m

    66 Demolition of sidewalk made of basalt tiles

    67

    68

    69 pcs

    60 210/260

    Steel doors - fire resistant 60 minutes 210/260cm

    60 100/210

    Steel doors - fire resistant 60 minutes 100/210cm

    Temporary circle ordinary traffic sign forregulation of the internal transport in the plant

    Temporary triangle ordinary traffic sign forregulation of the internal transport in the plant

    Temporary triangle ordinary traffic sign forregulation of the internal transport in the plant

    Temporary guide sign board for regulation of

    the internal transport in the plant

    Temporary barrier for regulation of the internaltransport in the plant

    Temporary barrier for regulation of the internaltransport in the plant

    2 m2

    Restoration of ballast prism from crushedstone of railway road section

    3 m3

    ..

    Restoration of railway section from railwayroad

    External waterproofing on external walls forfoundation of Steam Generator

    External mineral plaster on walls and footingswith installed waterdropping shaped profile

    External mineral plaster on walls and footingswith installed waterdropping shaped profile

    St A I &St A III

    Delivery and installation of reinforcement St A I& St A III

    ..

    Disassemblage of railway road on reiforcedconcrete sleepers

    2 m2

    -

    Forming and leveling of excavation bed -manually

    3 m3

    500

    Delivery and installation of troughshapedelements for heating main 500

    3 m3

    Delvery and installation of steel shed for gasstation

  • 8/8/2019 Technical Trans La Ton BG - En

    3/3