Upload
others
View
6
Download
2
Embed Size (px)
Citation preview
TECHNICAL PAPER
Offshore Wind Energy for
Australia, A Case Study with a
Floating 15MW Turbine
Nitin Repalle, Yusuf Arikan and Mike Campbell
AOG March 2021
AOG Energy | Offshore Wind Energy for Australia - A Case Study with a Floating 15MW Turbine
2021
Nitin Repalle, Yusuf Arikan and Mike Campbell2H Offshore Engineering
Learn more at www.2hoffshore.com
• Introduction to NREL 15MW Wind Turbine
• Numerical Modelling and Validation
• Floating Foundation - Stinger Keel Concept
• Floater Mooring Configuration Optimisation
• Fully Coupled Analysis Results
• Pilot Site In Australia
• Wind Profile
• Energy output
• Levelized Cost of Energy (LCOE)
• Summary and Conclusions
Agenda
Learn more at www.2hoffshore.com
NREL 15MW Reference Wind Turbine Generator – Released March, 2020
240m15 000kW
Height 270m
NREL 15MW WTG
12MW GE Haliade-X220m Rotor DiameterPrototype - 2019Certification - 2020Serial Production - 2021
Wind Turbine Generator Capacity and Blade Sizes
Show Increasing Trend into the Future Learn more at www.2hoffshore.com
NREL 15MW Reference Wind Turbine Generator
342 km/h
Learn more at www.2hoffshore.com
-5.00
0.00
5.00
10.00
15.00
20.00
25.00
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
wind speed (m/s)
15MW Published (Monopile) vs OrcaFlex (Fixed)
Blade Pitch (deg) Rotor RPM Torque (MN.m) TSR
PITCH RPM TORQUE TSR
NREL-15MW Turbine – Model Validation
Reference
Model
0
0.5
1
1.5
2
2.5
3
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Pow
er M
W
Wind Speed (m/s)
NREL 15MW Reference WTG
POWER THRUST
Thru
st M
N
• Power is produced with wind speeds 3m/s to 25m/s
• After rated wind speed of 10.6m/s blades start to pitch to keep power production at rated 15MW. Turbine is parked for wind speeds over 25m/s
Numerical Model show excellent correlation (<2% difference) to the reference model Learn more at www.2hoffshore.com
Floating Foundation - Stinger Keel Concept
• Developed by Floating Energy Systems (FESL), UK (https://floatingenergysystems.com/)
• A hybrid system between spar and semi-submersible.
• Deployable ballast keel frame (stinger) stays in horizontal during transit, and deployed to vertical for operation.
• Stability is provided by ballast weight like spars, turbine tower and turbine are installed at quayside like semi-submersible (no need for heavy lift vessel)
• 1/50 scale model wave tank tested in September 2020
Learn more at www.2hoffshore.com
15MW Stinger Keel Foundation
15MW NREL Stinger Keel Foundation Data
Total height 132m
15m water level to turbine tower base
Minimum operating water depth 130m
COG 77.5m below MWL
~4400 Te Steel weight
~2500 concrete weight
~7500Te Ballast weight
Total ~14,500Te without turbine
Turbine tower base
Learn more at www.2hoffshore.com
CAD Model Panel Model
15MW Stinger Keel Hydrodynamics
Learn more at www.2hoffshore.com
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
0 5 10 15 20 25 30 35 40 45 50
m/
m
Period s
Heave
0 deg 30 45 90
0.00
0.10
0.20
0.30
0.40
0.50
0 5 10 15 20 25 30 35 40 45 50
de
g/
m
Period s
Roll
0 deg 30 45 90
0.00
0.10
0.20
0.30
0.40
0.50
0 5 10 15 20 25 30 35 40 45 50
de
g/
m
Period s
Pitch
0 deg 30 45 90
Used in Coupled Analysis (Load RAOs)
Hull Only
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
0 5 10 15 20 25 30 35 40 45 50
m/
m
Period s
Heave
0 deg 30 45 90
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
0 5 10 15 20 25 30 35 40 45 50
de
g/m
Period s
Roll
0 deg 30 45 90
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
0 5 10 15 20 25 30 35 40 45 50
de
g/
m
Period s
Pitch
0 deg 30 45 90
Used in Free Decay Tests
Hull & Turbine/Tower
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
0 5 10 15 20 25 30 35 40 45 50
m/
m
Period s
Heave
0 deg 30 45 90
0.00
5.00
10.00
15.00
20.00
0 5 10 15 20 25 30 35 40 45 50
de
g/
m
Period s
Roll
0 deg 30 45 90
0.00
2.00
4.00
6.00
8.00
10.00
12.00
14.00
0 5 10 15 20 25 30 35 40 45 50
de
g/
m
Period s
Pitch
0 deg 30 45 90
Used in Wave Tank Tests
Hull & Turbine/Tower
& Mooring
15MW Stinger Keel Hydrodynamics
Calculated RAO’s show good match with the scaled prototype Learn more at www.2hoffshore.com
Mooring Configuration Optimisation
• 4 Mooring Configurations Considered
• Semi-Taut with Polyester
• Catenary with All Chain
• Taut with Polyester
• Taut with Nylon
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
Su
rge
(m
)
Foundation Offset
Semi-Taut All Chain Taut-Polyester Taut-Nylon
0
100
200
300
400
500
600
700
800
An
ch
or
Ra
diu
s (
m)
Mooring Footprint
Semi-Taut All Chain Taut-Polyester Taut-Nylon
Taut Mooring with Polyester and Chain provides a good balance for loads, motion and
footprint for the considered water depth of 130m Learn more at www.2hoffshore.com
Fully Coupled Analysis Results
▪ Coupled Model
▪ Turbine Model
▪ Foundation RAOs
▪ Mooring model
▪ Design Load Cases (IEC 61400-3-1)
DLC 1.6 Power Production
Wind speed= Vrated=10.6m/s
Wave=Severe Sea Sate
Hs=6m, Tp=11.2sAnimation Speed = 4X
0
5,000
10,000
15,000
20,000
25,000
0 1000 2000 3000 4000
Po
we
r k
W
Time (s)
Generated Power
0 degree 45 degree 90 degree 180 degree
Average Power = 13.3MW
Governing Operational Load case resulted in 13.3MW of Power over
one hour duration
Learn more at www.2hoffshore.com
Pilot site In Australia
Offshore Geraldton WA, 400km North of Perth
Learn more at www.2hoffshore.com
Pilot Site Wind Profile
• Wind Data obtained from Australian Government Bureau of Meteorology
http://www.bom.gov.au/climate/averages/tables/cw_008050_All.shtml
• Average monthly wind speed at 3m reference height
• Average monthly wind speed at 15MW WTG hub height (150m)
0.0
2.0
4.0
6.0
8.0
Win
d S
pe
ed
(m
/s)
Average Wind Speed
9am 3pm
0.0
5.0
10.0
15.0
Win
d S
pe
ed
(m
/s)
Average Wind Speed Hub Location (150m)
9am 3pm
α=0.14, IEC 61400-3-1 eq 6
Learn more at www.2hoffshore.com
Wind Speed Distribution
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0 4 8 12 16 20 24
Pro
ba
bil
ity D
en
sit
y
Wind Speed (m/s)
Wind Speed Distribution (Rayleigh)
January February March April May June
July August September October November December
• Wind Speed Distribution Based on Average Wind Speed
IEC 61400-1 eq 8
Learn more at www.2hoffshore.com
Power Production
0.0
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
Average Monthly Wind Speed and Power
Average Wind Speed (m/s) Average Power (MW)
Win
d S
pee
d (
m/s
) /
Po
wer
(M
W)
15MW Annual Power Production 58911 MW.hr
Gross Annual Production per MW 3927 MW.hr/MW
Uptime 85%
Net Annual Production per MW 3338 MW.hr/MW
Capacity Factor 38.1%Learn more at www.2hoffshore.com
LCOE for a Single 15MW Floating WTG
Component Unit Cost 15MW-Floating WTG PercentTurbine 1691$/kw $25.4M 16.7%Foundation 1873$/kw $28.1M 18.5%Assembly & Installation 567$/kw $8.5M 5.6%Electrical 1296$/kw $19.4M 12.8%PM, Development, Lease 507$/kw $7.6M 5.0%
Soft Cost (Finance, Insurance) 1023$/kw $15.3M 10.1%O/M (25 years) 178$/kw/yr $66.6M 31.3%Total $170.9 100.0%Based on NREL’s “2018 Cost of Wind Energy Review” Report for Floating WTG , ALL cost in AUD
Turbine Foundation Assembly &Installation
Electrical PM, Devp,Lease
Soft Cost(Finance,Insurance,Decom)
O/M (Annual)
15MW Floating Wind Cost Distribution
LCOE = AUD 170 / MW.hr
Design Life 25 years
FCR = 5.6%
USD to AUD = 1.30
Learn more at www.2hoffshore.com
$170
$230
$170
$160
$150
$170$165
$159
$120
$146
$100
$250
LCOE Sensitivity -1GW Floating Wind Farm
Learn more at www.2hoffshore.com
Source : RBA Bulletin March 2020
Floating Wind
Floating Wind - Future in Australia ?• Floating Wind is currently the most expensive option
However increasing WTG capacities and decreasing foundation costs is encouraging to keep the concept in the mix of considerations
• Potential Applications • Energy Storage : hydrogen storage technologies gaining
traction and being trialed• Offshore wind to power offshore field operations
• Inter- Continental Power transmission
Source : Equinor Website
Source : Suncable WebsiteLearn more at www.2hoffshore.com
Summary• Fully coupled global analysis of wind turbine, ‘Stinger Keel’ floating foundation,
and the mooring lines has been performed.
• Good accuracy of the model compared to NREL reference turbine and model testing. “Stinger Keel” offers a viable hybrid floating foundation solution for offshore wind
• Catenary, semi-taut and taut mooring configurations with various materials can be developed for floating foundations based local seabed and station keeping requirements
• It is estimated that LCOE will be approximately $170/MW.hr for a single 15MW WTG with floating foundation considering local wind conditions based on case study at the selected location with 25 years design life
• LCOE for a wind farm can be as low as $120/MW.hr considering 35 year design life and 20% savings on CapEx and OpEx costs
• Favourable trend of increasing WTG capacities and decreasing foundation costs is encouraging for uptake of floating wind concepts in Australia.
Authors gratefully acknowledge Gary Ross (FESL) for providing the details of the stinger keel foundation concept and prototype testing data for model validation Learn more at www.2hoffshore.com
Questions ?
Learn more at www.2hoffshore.com