Dixons McMillan AcademyT D S M I D L A N D S - C A S E S T U D Y
Bradford, West Yorkshire
Education
Steelwork
S I T E :
T Y P E :
S E R V I C E S :
T D S M I D L A N D S
Watson BattyI M A G E :
T D S M I D L A N D S
The Dixons Academies Trust chose the former
Bradford College site to be the location for their
4th Free School, the Dixons McMillan Academy.
It was a building very much in need of conversion in
order to provide a modern, fit-for-purpose learning
environment for 11-18 year olds. In addition to the
conversion a double-height, multi-use entrance
hall was added to the existing structure and a
freestanding, new build sports hall was added to
the site.
TDS were asked to design the additional steelwork
required to strengthen the existing building
throughout the extensive renovation and remodel.
We were also commissioned to provide a new access/
escape staircase for the double-height entrance area
as well as plant access stairs to the roof.
The Project
Objective
DN
BML 1
45.19
BML 1
45.19
BML 1
45.20
BML 1
45.19
SLOPING CEILING
3801113
GUTTER FORMED IN INSULATION RWP
1:40 F
all
RWP
1450
RWP
EXISTING STRUCTURESTO BE DEMOLISHEDSHOWN DASHED.
HATCHED AREA DENOTESEXTENT OF NEW ROOFCONSTRUCTION OVER.
ColCol
UP
EXISTING STRUCTURESTO BE DEMOLISHEDSHOWN DASHED.
EXISTING STRUCTURESTO BE RETAINED SHOWNSHADED.
900
AREA OF NEW FLATROOF CONSTRUCTION
DENOTES SPAN OF50x225 C16 JOISTS
PLAN AT TOP OF ROOF LEVEL1:50
ROOF OPENINGFOR LADDERACCESS TOARCHITECTSSPECIFICATION
EXISTING RWPTO REMAIN ANDROOF TRIMMEDAND SEALEDAROUND
PLAN AT U/S OF ROOF LEVEL1:50
150x90
PFC
150x90
PFC
150x90
PFC
150x90
PFC
100x10
0x5 SHS
178x102x19 UB 178x102x19 UB 178x102x19 UB
178x
102x
19 U
B17
8x10
2x19
UB
150x90
PFC
150x90
PFC
PFC / SHS COLUMNS TO BEFIXED TO EXISTING CONCRETECOLUMNS USING 16mmØ RESINANCHOR THROUGH BOLTS @450 v ctrs
178x102x19 UB
DETAIL 1
DETAIL 3DETAIL 2
BEAM TO BE POSITIONED TOUNDERSIDE OF EXISTINGCONCRETE SOFFIT.
CONTRACTOR TO ENSUREFIXING INTO CONCRETE /STEEL COLUMN.
STAIR DETAIL TBC BY ARCHITECTAND SPECIALIST SUPPLIER
INSULATED UPSTAND. MINIMUM 150MM.MEMBRANE TO BE DRESSED INTO BRICKWORKJOINT TO ROOFING MANUFACTURER'S DETAIL. OPENING FOR ROOF ACCESS
HATCH. TRIM OUT WITH DOUBLEDUP 50x225 C16 JOISTS
FFL
INSULATION TOARCHITECTSSPECIFICATION
50x225 C16 TIMBER JOISTS@ 400 MAX cts DOUBLED UPAROUND OPENING,PROVIDE FULL DEPTHNOGGINS AT THIRD POINTS
NOMINAL 10mm GAP BETWEENWALL AND FIRST JOIST
SECTION A-A1:25
178x102x19 UB FITTED INTO LINEOF EXTERNAL BRICK LEAF
DENOTES WALL TO BEREMOVED UNDER
EXISTING CONCRETEDOWNSTAND BEAM
NOMINAL 10mm GAP BETWEENWALL AND FIRST JOIST
Existing structure to bedemolished shown dashed.
18mm PLYWOODDECK FIXED DOWNTO JOISTS
SECTION B-B1:25
178x102x19 UB FITTED INTO LINEOF EXTERNAL BRICK LEAF
EXISTING RCCONCRETECOLUMN
150x90 PFC COLUMN DOWN TOGROUND LEVEL FIXED TOEXISTING CONCRETE COLUMNUSING M16 RESIN ANCHORS @450 v ctrs
450
450
50x225 C16 TIMBER JOISTS @ 400 MAXcts DOUBLED UP AROUND OPENING,PROVIDE FULL DEPTH NOGGINS ATTHIRD POINTS, JOISTS SUPPORTEDAT EACH END ON JOIST HANGERSFIXED TO WALL PLATE
TIMBER WALL PLATE FIXEDTO EXISTING MASONRYWITH M12 RESIN ANCHORS@ 300 ctrs
TIMBER WALL PLATE FIXEDTO EXISTING MASONRYWITH M12 RESIN ANCHORS@ 300 ctrs
INSULATION TOARCHITECTSSPECIFICATION
18mm PLYWOODDECK FIXED DOWNTO JOISTS
FACE OF EXISTING COLUMN
100x
100x
5 SHS
COL
UMN
450
450
450
100
ELEVATION ON DETAIL 11:10
350x75x8THK PLATES FIXEDWITH M16 RESIN ANCHORTHROUGH BOLTS, PLATESTO BE STAGGERED AT450mm ctrs
100
100100
100100TOP OF COLUMN
FIXINGS IN BOTHDIRECTIONS AT TOP OFCOLUMN
6 No. M16SLOTTED BOLT2 No. M16 BOLTS
150x90 PFC
EXISTING COLUMNSHOWN INDICATIVELY
16mmØ RESIN ANCHORTHROUGH BOLTS AT450mm VERTICALCENTRES
178x102x19 UB
4 No. M16 BOLTS 178x102x19 UB
6 No. M16SLOTTED BOLT
150x90 PFC
16mmØ RESIN ANCHORTHROUGH BOLTS AT450mm VERTICALCENTRES
10mm PLATE
10mm PLATE
PACKER TO BE USEDIF REQUIRED10mm PLATES
PLAN SECTION
PFC TO BEAM CONNECTION -DETAIL 2SCALE 1:10
10mm PLATE
100x100x5 SHS
100x100x10EQUAL ANGLE
2 No. M16BOLTS
100x100x10EQUAL ANGLE
2 No. M16 BOLTS
178x102x19 UB
178x102x19 UB
2 No. M16 BOLTS
178x102x19 UB
10mm PLATE
100x100x10 SHS
6mm FILLET WELD
6mm FILLET WELD
10mm PLATE
PLAN SECTION
SHS TO BEAM CONNECTION -DETAIL 1SCALE 1:10
16mmØ RESIN ANCHORTHROUGH BOLTS
16mmØ RESIN ANCHOR THROUGHBOLTS UNDER PERPENDICULARBOLTS
CAPTIVE NUTSTO INTERNALFACE
PLANSECTION
PFC TO BEAM CONNECTION -DETAIL 3SCALE 1:10
178x102x19 UB
150x90 PFC
10mm PLATE
178x102x19 UB
150x90 PFC
10mm PLATE
10mm STIFFENERPLATE
16mmØ RESIN ANCHORTHROUGH BOLTS AT 450mmVERTICAL CENTRES
4 No. M16 BOLTS
4 No. M16 BOLTS
16mmØ RESIN ANCHORTHROUGH BOLTS AT 450mmVERTICAL CENTRES
A01. THESE NOTES ARE INTENDED TO AUGMENT DRAWINGS ANDSPECIFICATIONS. WHERE CONFLICT OF REQUIREMENTS EXISTS THEORDER OF PRECEDENCE SHALL BE AS SHOWN IN THE SPECIFICATION.OTHERWISE THE STRICTEST PROVISION SHALL GOVERN.
A02. THIS DRAWING TO BE READ IN CONJUNCTION WITH ALL OTHERRELEVANT ENGINEERS AND ARCHITECTS DRAWINGS.
A03. DRAWINGS NOT TO BE SCALED. ALL DIMENSIONS TO BE CHECKEDON SITE BY THE CONTRACTOR. ANY DISCREPANCIES TO BE NOTIFIEDTO THE ENGINEER AND FURTHER INSTRUCTIONS OBTAINED BEFOREWORK IS COMMENCED.
A04. THE STRUCTURE IS DESIGNED TO BE SELF-SUPPORTING ANDSTABLE AFTER THE BUILDING IS FULLY COMPLETED. IT IS THECONTRACTORS SOLE RESPONSIBILITY TO DETERMINE THE ERECTIONPROCEDURE AND SEQUENCE AND ENSURE THAT THE BUILDING AND ITSCOMPONENTS ARE SAFE DURING ERECTION. THIS INCLUDES THEADDITION OF WHATEVER TEMPORARY BRACING, GUYS OR TIE-DOWNSWHICH MAY BE NECESSARY, SUCH MATERIAL REMAINING THEPROPERTY OF THE CONTRACTOR ON COMPLETION, AND FORENSURING THAT THE WORKS AND ANY ADJACENT PROPERTIES ARESAFE IN THE TEMPORARY CONDITION.
NO PART OF THIS DRAWING MAY BE REPRODUCED, STORED IN ARETRIEVAL SYSTEM OR TRANSMITTED IN ANY FORM OR BY ANY MEANSWITHOUT PRIOR PERMISSION IN WRITING FROM ALAN WOOD &PARTNERS.
COURTYARD ROOF INFILLDETAILS
AS NOTED
SW
CONSTRUCTION
20.08.15
35968 518 B
MC
Notes
100mm at A1
Project:
Client:
Drawing:
Date: Scale@A1:
Drawn By:
Job. no. Dwg. no.
Approved By:
Drawing Status:
Rev.
Check By:
Consulting Civil& Structural EngineersProject ManagersBuilding Surveyors
Description Date Chk.Rev. Drn.
Hull Office341 Beverley RoadHullHU5 1LD
T. 01482 442138F. 01482 448086www.alanwood.co.uk
Also at:
YorkScarboroughLincoln Sheffield
T. 01904 611594T. 01723 865484T. 01522 300210T. 01142 440077
A CONSTRUCTION ISSUE 16.12.15 KR MC
B DETAILS ADDED & MINOR AMENDMENTS 23.03.16 SO MC
DIXONS McMILLANACADEMY
INTERSERVE
B
ALL DIMENSIONS BASED ON MET GEO ENVIRONMENTALBUILDING SURVEY DRAWINGS. TBC ON SITE BYCONTRACTOR
STEELWORK FABRICATOR TO UNDERTAKE MEASUREDSITE SURVEY TO CONFIRM ALL REQUIRED SETTING
COSMETIC CRACKING LIKELY TO OCCUR ANDALLOWANCE FOR REPOINTING TO BE MADE
STRUCTURAL STEELWORK
S01. All dimensions in millimetres U.N.O
S02. It is the responsibility of the steelwork fabricator to obtain any necessarysite dimensions required and to prepare connection design calculations forsubmission to the local authority for Building Regulation Approval.
S03. All steelwork to be grade S355
S04. Steelwork to be in accordance with BS 5950-1:2000, Table 4 and 5.
S05. Steelwork to be shot blasted to Sa2.5 and painted with a shop applied 75microns dry film thickness of quick drying zinc phosphate and epoxy primer.
S06. Steelwork built into cavities to be given additional 2no site coats ofbituminous paint.
S07. Steelwork connections and baseplates to be designed by the fabricator.
S08. After erection on site all damaged areas to be manually cleaned back to asound surface and repainted with a primer and other coats as noted above or anequivalent approved by the Engineer. In the case of galvanising the steel is to bepainted with an appropriate number of coats of zinc rich paint to give theequivalent specified thickness.
S09. Concrete encased steelwork to be left untreated.
S10. See steelwork fabricators drawings for details and positions of holdingdown bolts.
S11. All structural steelwork to be in accordance with the National StructuralSteelwork Specification for Building Construction 5th edition.
S12. Fabricator to provide GA's / detail drawings to Engineer prior to fabrication
B
B
T D S M I D L A N D S
We received, from our contractor client, all necessary
site surveys of the demolition works and designs for
the steelwork. From this, using Tekla Structures, we
produced a comprehensive set of steelwork details
for approval. After the sign-off, we issued the designs
to the fabricator complete with all information
to ensure they could be correctly and efficiently
assembled on site.
Outcome
Watson BattyI M A G E S :
Watson Batty
Alan Wood & Partners
A R C H I T E C T :
S T R U C T U R A L E N G I N E E R S :
Tel: 01952 225835
Email: [email protected]
TDS Midlands Limited, Telford Enterprise HubHadley Park East, Telford, TF1 6QJ