5
7/31/2013 - 2/7/2014 Scheduled Vendor SAT Test Developed from FAT Test 6/22/2012 4/11/2014 7/1/2012 8/1/2012 9/1/2012 10/1/2012 11/1/2012 12/1/2012 1/1/2013 2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013 8/1/2013 9/1/2013 10/1/2013 11/1/2013 12/1/2013 1/1/2014 2/1/2014 3/1/2014 4/1/2014 2/25/2013 - 7/31/2013 IPT Commissioning Program 7/18/2012 - 8/17/2012 Vendor Package Plan 6/22/2012 - 9/9/2012 IPT Commissioning Program Development 6/22/2012 - 7/18/2012 WFS Quality Plan Implementation 9/9/2012 - 10/6/2012 IPT Mechanical Completion Program 10/6/2012 - 2/25/2013 IPT Pre-Com Program 6/22/2012 - 4/11/2014 SAP Program 12/31/2013 - 3/7/2014 IPT SubSea 4/12/2013 - 4/11/2014 Intergraph Operations and Maintenance Program 11/18/2013 - 12/31/2013 IPT OnShore Commissioning 7/18/2012 - 10/6/2012 WFS ProjecTools Program 7/31/2013 - 12/30/2013 IPT Onshore Pre-Commissioning 12/30/2013 - 1/30/2014 IPT Hook Up 12/30/2013 IPT Commissioning 100% 7/11/2012 Hess review & comment 8/10/2012 Hess review & comment 10/6/2012 - 7/31/2013 Scheduled Vendor FAT Test VFT Punch List Development 9/8/2012 - 4/11/2014 IPT Commissioning Program IPT Commissioning Timeline Tubular Bells Gulfstar 1 FPS 12/30/1899 XXX FAT Test 12/30/1899 XXX FAT Test 12/30/1899 XXX FAT Test 12/30/1899 XXX FAT Test 12/30/1899 XXX FAT Test 3/22/2014 - 4/11/2014 Hess Operations Pre-Startup & Startup 1/30/2014 - 3/22/2014 IPT Offshore Pre-Commissioning 3/1/2014 - 3/30/2014 IPT Post Mech Comp & Commissioning 3/30/2014 IPT Post MC & Com 100% 12/30/1899 XXX FAT Test 10/1/2012 - 8/17/2013 10/1/2012 - 8/17/2013 10/1/2012 - 8/17/2013 8/17/2013 IPT Com Check Sheets 100% 10/6/2012 IPT Commissioning Program Finish 8/17/2012 - 10/1/2012 Construction Package Plan 9/21/2012 Hess review & comment 4/11/2014 FIRST OIL 7/13/2013 Critical Path scheduling change’s over to Systems Priorities upon 70% completion in construction 3/15/2013 IPT Pre-Com Check Sheets 100% 10/31/2012 IPT MC Check Sheets 100% 7/13/2012 IPT Protocol Design 3/7/2014 SubSea 100% 1/30/2014 Hook Up 100% 3/22/2014 Pre-Com 100%

TBells IPT Com Master Timeline

Embed Size (px)

Citation preview

Page 1: TBells IPT Com Master Timeline

7/31/2013 - 2/7/2014Scheduled Vendor SAT Test

Developed from FAT Test

6/22/2012 4/11/2014

7/1/2012 8/1/2012 9/1/2012 10/1/2012 11/1/2012 12/1/2012 1/1/2013 2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013 8/1/2013 9/1/2013 10/1/2013 11/1/2013 12/1/2013 1/1/2014 2/1/2014 3/1/2014 4/1/2014

2/25/2013 - 7/31/2013IPT Commissioning Program

7/18/2012 - 8/17/2012 Vendor

Package Plan

6/22/2012 - 9/9/2012IPT Commissioning

Program Development

6/22/2012 - 7/18/2012WFS Quality PlanImplementation

9/9/2012 - 10/6/2012IPT Mechanical Completion

Program 10/6/2012 - 2/25/2013IPT Pre-Com Program

6/22/2012 - 4/11/2014

SAP Program

12/31/2013 - 3/7/2014IPT SubSea

4/12/2013 - 4/11/2014 Intergraph Operations and Maintenance Program

11/18/2013 - 12/31/2013IPT OnShore Commissioning

7/18/2012 - 10/6/2012WFS ProjecTools Program

7/31/2013 - 12/30/2013IPT Onshore Pre-Commissioning

12/30/2013 - 1/30/2014IPT Hook Up

12/30/2013IPT Commissioning 100%

7/11/2012Hess review & comment

8/10/2012Hess review & comment

10/6/2012 - 7/31/2013Scheduled Vendor FAT Test

VFT Punch List Development

9/8/2012 - 4/11/2014IPT Commissioning Program

IPT Commissioning TimelineTubular Bells Gulfstar 1 FPS

12/30/1899XXX FAT Test

12/30/1899XXX FAT Test

12/30/1899XXX FAT Test

12/30/1899XXX FAT Test

12/30/1899XXX FAT Test

3/22/2014 - 4/11/2014Hess Operations

Pre-Startup& Startup

1/30/2014 - 3/22/2014IPT Offshore Pre-Commissioning

3/1/2014 - 3/30/2014IPT Post Mech Comp

& Commissioning

3/30/2014IPT Post MC & Com 100%

12/30/1899XXX FAT Test

10/1/2012 - 8/17/2013

10/1/2012 - 8/17/2013

10/1/2012 - 8/17/2013

8/17/2013IPT Com Check Sheets 100%

10/6/2012IPT Commissioning Program Finish

8/17/2012 - 10/1/2012 Construction Package Plan

9/21/2012Hess review & comment

4/11/2014

FIRST OIL

7/13/2013Critical Path scheduling

change’s over to Systems Priorities upon 70% completion in construction

3/15/2013IPT Pre-Com Check Sheets 100%

10/31/2012IPT MC Check Sheets 100%

7/13/2012IPT Protocol Design

3/7/2014SubSea 100%

1/30/2014Hook Up 100%

3/22/2014Pre-Com 100%

Page 2: TBells IPT Com Master Timeline

MC, PC & Com TimelineTubular Bells FPS, HullP1, P2 and P3 Priorities

2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013

1/21/2013P1 Priorities, startMooring SystemsOil ProductionPressure Relief VentsMaterial HandlingUtilities

3/10/2013P3 Priorities, startElectricalUtilitiesPipelines & FlowlinesWater SeparationGas Separation

2/14/2013P2 Priorities, start Motor Control CenterHVACUtilities

5/24/2013P1, P2 & P3 Priorities, finishElectricalUtilitiesPipelines & FlowlinesWater SeparationGas Separation

6/1/2013WFS Schedule

Ready for Sailaway

7/15/2013Ready for Sailaway (Hess Forcast)

4/30/2013P2 Priorities, finish Motor Control CenterHVACUtilities

4/1/2013P1 Priorities, finishMooring SystemsOil ProductionPressure Relief VentsMaterial HandlingUtilities

Page 3: TBells IPT Com Master Timeline

Commissioning TimelineTubular Bells FPS,

Temporary Work Deck

6/1/2013 7/1/20135/6/2013

Phase 0 Start

5/6/2013 - 5/20/2013Phase 0 Equipment Set Up & Pre-ComGeneratorGenerator (back up)Crew Tool BoxWelder Machine (5 Set), 2 eachChange Room Building, 2 eachFuel Tank (2300 gal), 3 eachAir Compressor (375 CFM), 2 eachAir Volume TankFresh Water Tank (4200 gal)Oxygen Bottle RackPropylene Bottle RackPort O Let, 6 eachWork Tool Box, 2 eachHydraulic Oil Tote Tank, 3 eachPedestal CraneLife Jacket Box, 2 eachLife Raft, 4 eachNavigational Assembly, 4 eachSafety Locker

5/17/2013 - 5/24/2013Phase 1 Equipment Set Up & Pre-ComPull-In Winch (linear)Take Up Wire Rope Spooling WinchWinch Cooling UnitJob Box, 2 eachWinch Hydraulic Power Unit (HPU)HUC Box Job Box, 2 eachMessenger Wire Storage Bin, 3 eachLight StandBoarding Valve AssembliesCentral Fairleader

5/24/2013Phase 1 Finish

5/17/2013Phase 1 Start

5/20/2013Phase 0 Finish

5/23/2013Phase 2A/2B Start

5/23/2013 - 5/31/2013Phase 2A Prelim Riser Pull-In & Hang OffSet Up & Pre-ComVB200 Riser Pull-In Steering Winch, 3 eachSheave Skid, 3 eachVB200 HPU, 3 eachContingencies

Chain Jack HPUControl CabinChain JackTooling/SparesChain Locker

Phase 2B Contingency Lucker Winch OptionSet Up & Pre-ComLucker Winch75 KIP SpoolerLucker Winch HPU

5/31/2013Phase 2A/2B Finish

5/27/2013 - 6/3/2013Phase 3A Prelim Riser Pull-In & Hang Off ComPhase 3B Contingency Lucker Winch Option Com

5/27/2013Phase 3A/3B Start

6/4/2013 - 6/14/2013Phases 4. 5 & 9

Permanent TWD Equipment Com

6/3/2013Phase 3A/3B Finish

6/4/2013Phases 4, 5 & 9 Start

6/14/2013Phase 4, 5 & 9 Finish

6/14/2013 - 6/21/2013Phase 6 Umbilical Pull-In Set Up & Pre-Com/ComVB75 HPUVB75 WinchSheave Skid

6/14/2013Phase 6 Start

6/21/2013Phase 6 Finish

6/22/2013 - 6/29/2013Phase 7 Export Pipelines Pre-CommissioningInstrument CabinGenerator (Not Req if 220v available)Hose/Fitting BasketHydro-Test Pumps (Split Sys), 2 eachFlushing Pumps, 2 eachPig BasketTemporary Launcher/ReceiverSeawater Lift Pumps

6/22/2013Phase 7 Start

6/29/2013Phase 7 Finish

6/30/2013 - 7/28/2013Phase 8 Production & Water Injection F/L

Pre-Commissioning

6/30/2013Phase 8 Start

7/28/2013Phase 8 Finish

Pre-Commissioning

Page 4: TBells IPT Com Master Timeline

Commissioning TimelineTubular Bells FPS, TWD/SURF

9/1/2013 10/1/2013 11/1/2013 12/1/2013

8/28/2013Temp Work Deck

Mobilization/Installation

8/29/2013 - 9/11/2013SCR Transfer Vessel - Mobilization

8/29/2013 - 9/4/2013Equipment Change-Out

9/12/2013 - 9/30/2013SCR Transfer (x5) Export & SURF

9/4/2013Equip Change-Out Finish

9/30/2013SCR Transfer Finish

10/1/2013 - 10/10/2013Hurricane Allowance

10/13/2013 - 11/11/2013Hull & Mooring Installation

10/16/2013 - 10/19/2013Install Flying Leads/Jumpers - Well B (DC1)

10/12/2013 - 10/15/2013Install Flying Leads/Jumpers - Well D (DC2)

10/18/2013 - 10/31/2013Diving Operations (Export & SURF)

10/11/2013 - 10/17/2013Diving Operations - Mobilization

10/15/2013Well D (DC2) Finish

11/1/2013 - 11/2/2013Umbilical Pull-In for TWD

11/3/2013 - 11/5/2013Set-Up Pig & Hydro Test Equip

11/6/2013 - 11/18/2013Pig & Hydro Export P/L's

11/19/2013 - 11/30/2013DeWater & Dry Gas Export P/L

10/19/2013Well B (DC1) Finish

11/18/2013Export P/L's Finish

11/30/2013DeWater/Dry Gas Export Finish

12/14/2013SURF F/L's Finish

12/1/2013 - 12/14/2013Pig & Hydro Test SURF F/L's

12/22/2013 - 1/1/2014Topsides Transport & Installation

12/25/2013Temp Work DeckDemobilization

1/1/2014Topside Install Finish

11/3/2013CSU Mobilization

Page 5: TBells IPT Com Master Timeline

11/24/2013 12/1/2013 12/8/2013 12/15/2013 12/22/2013 12/29/2013

MC, PC & Com TimelineTubular Bells FPS, Topside

P1, P2 & P3 Priorities

11/18/2013P1 Priorities, startElectricalUtilitiesArch/Civil/StructuralComm/Cnrls/Safety

11/27/2013P2 Priorities, start ElectricalUtilitiesPressure Relief Vents

12/4/2013P3 Priorities, startElectricalUtilitiesWater SeparationGas Separation

12/8/2013P1 Priorities, finishElectricalUtilitiesArch/Civil/StructuralComm/Cnrls/Safety

12/15/2013P2 Priorities, finish ElectricalUtilitiesPressure Relief Vents

12/22/2013P1, P2 & P3 Priorities, finishElectricalUtilitiesWater SeparationGas Separation