7/31/2013 - 2/7/2014Scheduled Vendor SAT Test
Developed from FAT Test
6/22/2012 4/11/2014
7/1/2012 8/1/2012 9/1/2012 10/1/2012 11/1/2012 12/1/2012 1/1/2013 2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013 8/1/2013 9/1/2013 10/1/2013 11/1/2013 12/1/2013 1/1/2014 2/1/2014 3/1/2014 4/1/2014
2/25/2013 - 7/31/2013IPT Commissioning Program
7/18/2012 - 8/17/2012 Vendor
Package Plan
6/22/2012 - 9/9/2012IPT Commissioning
Program Development
6/22/2012 - 7/18/2012WFS Quality PlanImplementation
9/9/2012 - 10/6/2012IPT Mechanical Completion
Program 10/6/2012 - 2/25/2013IPT Pre-Com Program
6/22/2012 - 4/11/2014
SAP Program
12/31/2013 - 3/7/2014IPT SubSea
4/12/2013 - 4/11/2014 Intergraph Operations and Maintenance Program
11/18/2013 - 12/31/2013IPT OnShore Commissioning
7/18/2012 - 10/6/2012WFS ProjecTools Program
7/31/2013 - 12/30/2013IPT Onshore Pre-Commissioning
12/30/2013 - 1/30/2014IPT Hook Up
12/30/2013IPT Commissioning 100%
7/11/2012Hess review & comment
8/10/2012Hess review & comment
10/6/2012 - 7/31/2013Scheduled Vendor FAT Test
VFT Punch List Development
9/8/2012 - 4/11/2014IPT Commissioning Program
IPT Commissioning TimelineTubular Bells Gulfstar 1 FPS
12/30/1899XXX FAT Test
12/30/1899XXX FAT Test
12/30/1899XXX FAT Test
12/30/1899XXX FAT Test
12/30/1899XXX FAT Test
3/22/2014 - 4/11/2014Hess Operations
Pre-Startup& Startup
1/30/2014 - 3/22/2014IPT Offshore Pre-Commissioning
3/1/2014 - 3/30/2014IPT Post Mech Comp
& Commissioning
3/30/2014IPT Post MC & Com 100%
12/30/1899XXX FAT Test
10/1/2012 - 8/17/2013
10/1/2012 - 8/17/2013
10/1/2012 - 8/17/2013
8/17/2013IPT Com Check Sheets 100%
10/6/2012IPT Commissioning Program Finish
8/17/2012 - 10/1/2012 Construction Package Plan
9/21/2012Hess review & comment
4/11/2014
FIRST OIL
7/13/2013Critical Path scheduling
change’s over to Systems Priorities upon 70% completion in construction
3/15/2013IPT Pre-Com Check Sheets 100%
10/31/2012IPT MC Check Sheets 100%
7/13/2012IPT Protocol Design
3/7/2014SubSea 100%
1/30/2014Hook Up 100%
3/22/2014Pre-Com 100%
MC, PC & Com TimelineTubular Bells FPS, HullP1, P2 and P3 Priorities
2/1/2013 3/1/2013 4/1/2013 5/1/2013 6/1/2013 7/1/2013
1/21/2013P1 Priorities, startMooring SystemsOil ProductionPressure Relief VentsMaterial HandlingUtilities
3/10/2013P3 Priorities, startElectricalUtilitiesPipelines & FlowlinesWater SeparationGas Separation
2/14/2013P2 Priorities, start Motor Control CenterHVACUtilities
5/24/2013P1, P2 & P3 Priorities, finishElectricalUtilitiesPipelines & FlowlinesWater SeparationGas Separation
6/1/2013WFS Schedule
Ready for Sailaway
7/15/2013Ready for Sailaway (Hess Forcast)
4/30/2013P2 Priorities, finish Motor Control CenterHVACUtilities
4/1/2013P1 Priorities, finishMooring SystemsOil ProductionPressure Relief VentsMaterial HandlingUtilities
Commissioning TimelineTubular Bells FPS,
Temporary Work Deck
6/1/2013 7/1/20135/6/2013
Phase 0 Start
5/6/2013 - 5/20/2013Phase 0 Equipment Set Up & Pre-ComGeneratorGenerator (back up)Crew Tool BoxWelder Machine (5 Set), 2 eachChange Room Building, 2 eachFuel Tank (2300 gal), 3 eachAir Compressor (375 CFM), 2 eachAir Volume TankFresh Water Tank (4200 gal)Oxygen Bottle RackPropylene Bottle RackPort O Let, 6 eachWork Tool Box, 2 eachHydraulic Oil Tote Tank, 3 eachPedestal CraneLife Jacket Box, 2 eachLife Raft, 4 eachNavigational Assembly, 4 eachSafety Locker
5/17/2013 - 5/24/2013Phase 1 Equipment Set Up & Pre-ComPull-In Winch (linear)Take Up Wire Rope Spooling WinchWinch Cooling UnitJob Box, 2 eachWinch Hydraulic Power Unit (HPU)HUC Box Job Box, 2 eachMessenger Wire Storage Bin, 3 eachLight StandBoarding Valve AssembliesCentral Fairleader
5/24/2013Phase 1 Finish
5/17/2013Phase 1 Start
5/20/2013Phase 0 Finish
5/23/2013Phase 2A/2B Start
5/23/2013 - 5/31/2013Phase 2A Prelim Riser Pull-In & Hang OffSet Up & Pre-ComVB200 Riser Pull-In Steering Winch, 3 eachSheave Skid, 3 eachVB200 HPU, 3 eachContingencies
Chain Jack HPUControl CabinChain JackTooling/SparesChain Locker
Phase 2B Contingency Lucker Winch OptionSet Up & Pre-ComLucker Winch75 KIP SpoolerLucker Winch HPU
5/31/2013Phase 2A/2B Finish
5/27/2013 - 6/3/2013Phase 3A Prelim Riser Pull-In & Hang Off ComPhase 3B Contingency Lucker Winch Option Com
5/27/2013Phase 3A/3B Start
6/4/2013 - 6/14/2013Phases 4. 5 & 9
Permanent TWD Equipment Com
6/3/2013Phase 3A/3B Finish
6/4/2013Phases 4, 5 & 9 Start
6/14/2013Phase 4, 5 & 9 Finish
6/14/2013 - 6/21/2013Phase 6 Umbilical Pull-In Set Up & Pre-Com/ComVB75 HPUVB75 WinchSheave Skid
6/14/2013Phase 6 Start
6/21/2013Phase 6 Finish
6/22/2013 - 6/29/2013Phase 7 Export Pipelines Pre-CommissioningInstrument CabinGenerator (Not Req if 220v available)Hose/Fitting BasketHydro-Test Pumps (Split Sys), 2 eachFlushing Pumps, 2 eachPig BasketTemporary Launcher/ReceiverSeawater Lift Pumps
6/22/2013Phase 7 Start
6/29/2013Phase 7 Finish
6/30/2013 - 7/28/2013Phase 8 Production & Water Injection F/L
Pre-Commissioning
6/30/2013Phase 8 Start
7/28/2013Phase 8 Finish
Pre-Commissioning
Commissioning TimelineTubular Bells FPS, TWD/SURF
9/1/2013 10/1/2013 11/1/2013 12/1/2013
8/28/2013Temp Work Deck
Mobilization/Installation
8/29/2013 - 9/11/2013SCR Transfer Vessel - Mobilization
8/29/2013 - 9/4/2013Equipment Change-Out
9/12/2013 - 9/30/2013SCR Transfer (x5) Export & SURF
9/4/2013Equip Change-Out Finish
9/30/2013SCR Transfer Finish
10/1/2013 - 10/10/2013Hurricane Allowance
10/13/2013 - 11/11/2013Hull & Mooring Installation
10/16/2013 - 10/19/2013Install Flying Leads/Jumpers - Well B (DC1)
10/12/2013 - 10/15/2013Install Flying Leads/Jumpers - Well D (DC2)
10/18/2013 - 10/31/2013Diving Operations (Export & SURF)
10/11/2013 - 10/17/2013Diving Operations - Mobilization
10/15/2013Well D (DC2) Finish
11/1/2013 - 11/2/2013Umbilical Pull-In for TWD
11/3/2013 - 11/5/2013Set-Up Pig & Hydro Test Equip
11/6/2013 - 11/18/2013Pig & Hydro Export P/L's
11/19/2013 - 11/30/2013DeWater & Dry Gas Export P/L
10/19/2013Well B (DC1) Finish
11/18/2013Export P/L's Finish
11/30/2013DeWater/Dry Gas Export Finish
12/14/2013SURF F/L's Finish
12/1/2013 - 12/14/2013Pig & Hydro Test SURF F/L's
12/22/2013 - 1/1/2014Topsides Transport & Installation
12/25/2013Temp Work DeckDemobilization
1/1/2014Topside Install Finish
11/3/2013CSU Mobilization
11/24/2013 12/1/2013 12/8/2013 12/15/2013 12/22/2013 12/29/2013
MC, PC & Com TimelineTubular Bells FPS, Topside
P1, P2 & P3 Priorities
11/18/2013P1 Priorities, startElectricalUtilitiesArch/Civil/StructuralComm/Cnrls/Safety
11/27/2013P2 Priorities, start ElectricalUtilitiesPressure Relief Vents
12/4/2013P3 Priorities, startElectricalUtilitiesWater SeparationGas Separation
12/8/2013P1 Priorities, finishElectricalUtilitiesArch/Civil/StructuralComm/Cnrls/Safety
12/15/2013P2 Priorities, finish ElectricalUtilitiesPressure Relief Vents
12/22/2013P1, P2 & P3 Priorities, finishElectricalUtilitiesWater SeparationGas Separation