TARGET2 presentation
• London, 3 January 2008
• Bernard de Groes
• Bas Dekker
Agenda NL
• TARGET2 update Bernard de Groes
• Migration issues Bas Dekker
TARGET2 update
Bernard de Groes
NL
Public project plan NL
GFS, UDFS
T2 user guide
Testing NL
Internal tests
(3CB)
Acceptance (CBs)
2007 2008
User testing activities(group 1)
User testing activities(group 2)
User testing activities(group 3)
Group 2 testingESCB planning
NL
User testing activitiesConnectivity tests
Interoperability tests (certification)
Free testing
Country testing Business day testing
at institution level at country level at European level
19/0
6
17/0
9
05/1
0
09/1
1
01/0
2
Group 2 testingdocumentation
NL
• USER TESTING GUIDE FOR MIGRATION
•Connectivity and interoperability test scenarios
•Test tool (T2TRIS)
•Operating hours test environment
•Responsibilities Credit Institutions and NCB
•Country and business day test scenarios:
•Migration weekend test
•Contingency procedures
•Connection with TARGET1
•Ancillary system schedules
Group 2 testingdocumentation and registration
NL
Other Testing related documents:
•ICM User Handbook
•T2TRIS user guide
•Nat. Migration Profiles
•Ancillary System Profiles
Registration TEST:
•SSP registration forms
•e-mssf SWIFT registration
Group 2 testingDNB planning
NL
User testing activitiesconnect
Interoper tests
(certification)Free testing
Country testing Business day testing
at institution level
at country level at European level
15/0
5 st
atic
dat
aen
try
19/0
606
/07
conn
ecti
vity
test
fin
ishe
d
17/0
9
05/1
0
09/1
1
01/0
2
15/0
8 in
tero
per.
test
fin
ishe
d
NLtest
01/0
1 st
atic
dat
aE
ntry
in P
RO
D
01/09-28/09 NL test scenarios
07/0
2 G
O/N
O G
O18
/02
T2
LIV
E
Group 2 Migration to PROD NL
Registration:
•15/10/07 legal documents finalized
e-mssf SWIFT registration submitted
•01/01/08 SSP registration forms PROD submitted
(no copy of data from TEST)
Migration:
•07/02/08 GO / NO-GO
•15/02/08 18:00 TOP close of day, no night-settlement
•16/02/08 migration of dynamic data
•17/02/08 verification of data in SSP
•18/02/08 07:00 opening TARGET2
NO FALL-BACK!
Planning
• 19 Nov 2007 Group 1 live• 18 Febr 2008 Group 2 live• 19 May 2008 Group 3 live, start T2 pricing
Public project plan NL
GFS, UDFS
T2 user guide
Other Documentation NL
• SSP specifications– ICM User Handbook version 2.3– GFS version 2.1– UDFS version 2.4
• Operational procedures– T2 user guide– T2 user guide for migration– T2 Guideline
Questions?
Migration issues
Bas Dekker
NL
Migration
• TARGET2 is one of the most demanding changes in the European financial sector
=> A lot of projects must be synchronised
• Individual migration - CB, CI, AS• National migration - CB• SSP - 3CB• ESCB wide migration - ESCB+3CB
Migration scenario
No European wide Big Bang …
Not all participating countries and their banking communities should change together in one single day!
Conclusion:• Interlinking for migration purposes only• Pilot group• Country windows
Migration scenario
… but a Country Big Bang
Not feasible to connect one country with two RTGS components
One major possible exception to Country Big Bang:• Settlement of ancillary systems might be transferred
to the SSP at a later stage• This implies the use of the local system (home
accounting) for this transition period
TARGET2 Migration
• Smooth transition from the current TARGET to the new TARGET2 system for all involved players (CBs, CIs, ASs)
• Co-ordination of all implementation activities after the development of the system, meaning testing plus changeover until all participating CBs have moved to the SSP
• Steering and monitoring the implementation process
TARGET2 migration
• To ensure a smooth migration from TARGET1 to TARGET2 for all involved players
How• Migration strategy following a phased approach• Central banks migrating together with their banking
community• Four migration groups (one reserved for contingency)
– 19 November 2007– 18 February 2008– 19 May 2008– 15 September 2008
Group composition aimed at minimising project risk, reducing effect on level playing field and limiting the costs for central banks and users
Group 1 Group 2 Group 3 Group 4 Austria Belgium Denmark
Germany Finland Estonia
Lithuania
France ECB Reserved
Luxembourg
Ireland Greece for
Slovenia
Netherlands Italy contingency Portugal Poland Spain
Cyprus
Malta
Latvia
Migration group allocation
National Migration Profile
• Objectives:– Information to users– Basis to monitor and steer the migration
• Content– Country migration model
• National Big Bang• No compulsion, no prohibition
– Usage of optional modules selected by a CB– Migration group
Available for all countries.
Contact information and general presentation of the Central Bank’s project.
Settlement modes for ancillary systems.
Requirements for settling specific operations (reserve holding, standing facilities, cash operations…).
National specificities.
National Migration Profile
• Final Migration strategy will be developed following a top-down approach
• Strategy documents will cover:– Testing– Roles & Responsibilities– Communication– Organisation of changeover– Operational framework
Migration Strategy
Tasks Responsibilities
Coordination of T2 Migration Level 2
(TF on Migration Issues)
SSP migration Support to Level 2
3CB
Coordination of national banking community migration
Own migration CBs
Own migration CIs & ASs
Tasks & Responsibilities
Dutch implementation strategy
• National Big Bang– Conversion on Saturday– Ascertain successful migration all accountholders
• Decision to migrate some weeks in advance
Preparation
Before 7 December 2007:• SSP forms with activation date 18 February• E-Ordering CUG with implementation date 2
February 2008
Between 18 January and 1 February 2008:• BKE with :
– TRGTXEPM (for direct participants) or
– TRGTXEHM (for co-managers or HAM accountholders)
Migration weekend February 18, 2008 &
Test weekend Migration December 8, 2007
NL
PURPOSE
• One central communication plan for February 18, 2008. Each participant should provide their milestones (based on their migration plan) to DNB.
• Agreement on the way of communication between participants and DNB.
• To provide a short plan for the test weekend of December 8 and to complete the final version of February 18 with the experiences of testing
NL
CURRENT AGREEMENTS
• Per participant one main contact person and one back up (December 8 and February 18)
• DNB will send out her current generic milestones• All participants can send their milestones to DNB • DNB will create one overall plan
NL
CLARIFICATION OF DECEMBER 8
• Testing is December 8 from 08.00 – 16.00• Participants have to communicate contact persons,
phone numbers and e-mail addresses• TOP will be closed and balances of participants will
be transferred to SSP • Credit facility will be available• Check(s) if all amounts are correct
NL
ADDITIONAL ITEMS• Communication from DNB to participants via e-mail• Feedback of checks by participants by phone• At the end of migration one email will be send to DNB
to confirm everything went well• A short version of the plan will be written for testing as
well• After testing a meeting will be organized to discuss the
experiences
NL
Milestones (1)
04-02-08 / 15-02-08:• Connect to ICM and check Static Data
08-02-08:• Interim version of T2 directory available
11-02-08 / 15-02-08:• Participant send a live payment to themselves (this one will be
rejected since account is not active)• Enter standing order bilateral/multilateral limits• Enter standing order highly urgent/urgent reservations
Milestones (2)
13-02-08:
• Deadline for corrections in T2 directory
15-02-08:
• Final version T2 directory available
• Standing order liquidity transfers between RTGS and sub/mirror account (if applicable)
Milestones (3)16-02-08:• Migration TOP to TARGET2
17-02-08:• Extended Migration possibility
18-02-08:• From 05:00 - 06:00 exchange of one euro payments between Direct
Participants• Before 06:15 Direct Particpants inform DNB about the results of the one
euro payment.• 07:00 TARGET2 (migration group 2) going live.
18-02-08 – 22-02-08:• TOPView available for inquiry
Be prepared NL
It is your responsibility to be ready in time!
Questions?
Lunch! NL
Customer Information about TARGET2
General Functional Specifications
Only fo
r centra
l banks
•General concept of the Single Shared Platform
•„Order book“ for the three central banks developing the Single Shared Platform
Current version 2.1, published July 2007
For Centra
l banks o
nly
Customer Information about TARGET2
User Detailed Functional Specifications
Detailed description ofthe Single Shared Platform's features
OperationalTechnical
Basis for preparing participation in theSingle Shared Platform
Current version 2.4, published November 2007
Customer Information about TARGET2
User Detailed Functional Specifications
• Book 1 - Core Services
• Book 2 - Optional Services
• Book 3 - For Central Banks only
• Book 4 - XML-specifications
• ICM Book 1 - User guide ICM
• ICM Book 2 - For Central Banks only
Communication DNB
• Information sessions• TARGET2 newsletters• TARGET2 websites• Email address ([email protected])• Bilateral meetings• TARGET2 Bank Co-ordination Group (T2-
BCG)• TARGET User Group
NL
TARGET2 websites
ECB-website• Address: https://target2.ecb.int/• User: t2user• Password: VBjmspRR7
DNB-website• Address: http://www.dnb.nl
Payments / Non cash-payments / TARGET2
NL
DNB website
• ESCB documents– General Functional Specifications– User Detailed Functional Specifications– ICM User Handbook– Schema Files for XML-messages– National Migration Profiles– Ancillary Systems Profiles– Progress Reports
• DNB documents– Analysis of the consequences of the migration– Presentations– TARGET2 Newsletters– Frequently Asked Questions