Project
TAKING OFF ALLOCATION AND PROGRESS GFA
Item Descriptions Sub-Element Taker PROGRESS
Off
BUILDING WORKS
A Piling 1 Elevated Water Tank
2 Suction Tank
3 Pump House
B Work Below Lowest 1 Pile Caps/Footings
Floor Level 2 Column Stumps
3 Grd Floor Slab
4 Apron Slab
5 Ramp
C Steel Structure 1 Steel Column/Stanchion
2 Steel Roof Structure
D Frame 1 Columns / Stiffeners
2 Floor Beams
3 Roof Beams
E Roof & Accessories 1 Roof Slabs
2 Waterproofing
3 Roof Gutters
F Roof Finishes 1 Metal Roof Deck and Sheet
2 Flat roof finishes
3 Canopies
4 Skylight
5 Sun Louvres
6 Expended Metal Screen
G Staircases, Finishes, 1 Structure
Railing and Balustrading 2 Finishes
3 Railings & balustradings
H External Wall & Wall 1 115mm brickwalls
Cladding 2 230mm brickwalls
3 Metal Wall Cladding
4 Glaze Panel
I Internal Wall and Partition 1 115mm brickwalls
2 230mm brickwalls
3 Gypsum board partition
4 Railings etc
J Windows and Doors 1 Doors
2 Windows
3 Lintol
K Wall Finishes 1 Internal Walls Finishes
2 External Walls Finishes
: 0 M: 0 Ft
Water Tank
Project
TAKING OFF ALLOCATION AND PROGRESS GFA
Item Descriptions Sub-Element Taker PROGRESS
Off
: 0 M: 0 Ft
Water Tank
L Floor Finishes 1 Internal Floor Finishes
M Ceiling Finishes 1 Internal Ceiling Finishes
2 External Ceiling Finishes
N Sanitary Fittings
O Signages
EXTERNAL WORKS
A Earthworks
B Roads and Carparks 1 Road Work
2 Road Accessories
C Drainage
D Water reticulation
Systems
E Sewerage System
F Fencing
G Retaining Walls (if any)
H Ancillaries Buildings Guard House
Refuse Bin Centre
J Landscaping Works
OTHERS
A GFA
B BQ Format
C Bulk Check
NOTES :