160
Downtown Expressway Parking Garage - Elevator Replacement Table of Contents Richmond, VA TC - i TABLE OF CONTENTS TECHNICAL SPECIFICATIONS CITY OF RICHMOND DOWNTOWN EXPRESSWAY PARKING GARAGE ELEVATOR REPLACEMENT DIVISION 1 – GENERAL REQUIREMENTS Section 01000 General Standards 01010 Summary of Work 01092 Reference Standards 01106 Construction Scheduling, Coordination and Sequencing 01130 Measurement and Payment 01152 Applications for Payment 01153 Change Order and Field Order Procedures 01200 Project Meeting 01300 Submittals 01310 Progress Schedule 01380 Construction Photographs 01400 Quality Control 01500 Construction Facilities and Temporary Controls 01510 Temporary Facilities 01600 Product Requirements 01700 Contract Closeout 01710 Cleaning Up 01720 Project Record Documents 01732 Selective Demolition DIVISION 14 – CONVEYING EQUIPMENT Section 142211 Modernization of Existing Traction Elevators DIVISION 21 – FIRE SUPPRESSION Section 210000 Sprinkler Systems Modifications DIVISION 28 – ELECTRONIC SAFETY AND SECURITY Section 283100 Conventional Fire Detection and Alarm System

TABLE OF CONTENTS TECHNICAL SPECIFICATIONS CITY OF ... Expressway Parking Garage - Elevator Replacement Table of Contents Richmond, VA TC - i ... AAMA American Architectural Manufacturers

  • Upload
    others

  • View
    9

  • Download
    0

Embed Size (px)

Citation preview

Downtown Expressway Parking Garage - Elevator Replacement Table of Contents Richmond, VA

TC - i

TABLE OF CONTENTS TECHNICAL SPECIFICATIONS

CITY OF RICHMOND DOWNTOWN EXPRESSWAY PARKING GARAGE

ELEVATOR REPLACEMENT

DIVISION 1 – GENERAL REQUIREMENTS

Section 01000 General Standards 01010 Summary of Work 01092 Reference Standards 01106 Construction Scheduling, Coordination and Sequencing 01130 Measurement and Payment 01152 Applications for Payment 01153 Change Order and Field Order Procedures 01200 Project Meeting 01300 Submittals 01310 Progress Schedule 01380 Construction Photographs 01400 Quality Control 01500 Construction Facilities and Temporary Controls 01510 Temporary Facilities 01600 Product Requirements 01700 Contract Closeout 01710 Cleaning Up 01720 Project Record Documents 01732 Selective Demolition

DIVISION 14 – CONVEYING EQUIPMENT

Section 142211 Modernization of Existing Traction Elevators

DIVISION 21 – FIRE SUPPRESSION

Section 210000 Sprinkler Systems Modifications

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

Section 283100 Conventional Fire Detection and Alarm System

Downtown Expressway Parking Garage - Elevator Replacement Table of Contents Richmond, VA

TC - ii

APPENDICES

A. City of Richmond - Health, Safety, and Environment Management Plan B. Sample NOI

Downtown Expressway Parking Garage - Elevator Replacement General Standards Richmond, VA

01000 - 1

SECTION 01000

GENERAL STANDARDS

PART 1 - GENERAL

1.01 SECTION INCLUDES

A. This section contains requirements and conditions governing the project in addition to those shown in Division 1 of the base project specifications.

B. Work under this contract shall be done in accordance to Section 01010 - Summary of Work.

1.02 MOBILIZATION/DEMOBILIZATION

A. The CONTRACTOR shall provide the facilities and equipment necessary to move personnel and equipment to and from the Work site, to set up temporary offices, to install any temporary utilities, to prepare the site for the Work, to demobilize, and to clean up the site upon completion of the work.

B. The CONTRACTOR’s price shall include the cost to mobilize at the beginning of project and demobilize at project closeout.

1.03 FIRE PROTECTION

A. The CONTRACTOR shall furnish and maintain on the site adequate firefighting equipment capable of extinguishing incipient fires. The CONTRACTOR shall comply with applicable parts of the National Fire Prevention Standard for Safeguarding Building Construction Operations (NFPA No. 241).

1.04 TEMPORARY UTILITIES

A. The CONTRACTOR shall provide temporary utilities as needed at no cost to the OWNER. The CONTRACTOR shall be responsible for installing the temporary utilities from the point of connection to the point of use and shall be responsible for all utility requirements. The location of all temporary utilities shall be approved by the OWNER prior to installation.

1.05 SITE CONDITIONS

A. Access and work space at the site is limited. The CONTRACTOR shall schedule and coordinate his Work as needed to minimize interference with the OWNER’s operation of the garage.

Downtown Expressway Parking Garage - Elevator Replacement General Standards Richmond, VA

01000 - 2

B. The work area contains equipment, piping, and electrical components. It is the CONTRACTOR’s responsibility to protect the equipment, piping, electrical components, and associated utilities during the CONTRACTOR’s operation. Any damage to the equipment, piping, or electrical system caused by the CONTRACTOR’s operations shall be repaired at no additional cost to the OWNER.

1.06 PROTECTION OF THE ENVIRONMENT

A. The CONTRACTOR’s operations shall in no way contribute to air, water, or land pollution. This includes such nuisances as odors, insects, noise, surface or groundwater contamination, or any other condition that would have detrimental effect on the environment and shall meet all local, state, and federal regulations for handling and disposal/beneficial reuse of the sediment.

B. The CONTRACTOR shall not store any hazardous materials, including fuel oil, at the project site or property of the City.

1.07 LIMITED AND RESTRICTED ACCESS

A. All areas which the CONTRACTOR uses for access shall be maintained and any damage due to his operations shall be repaired to leave these areas in a condition equal to that which existed at the start of the work.

B. The CONTRACTOR will not be entitled to any additional costs or time due to the limited and restricted access to the site.

1.08 WORKING LIMITS

A. The CONTRACTOR shall confine his operations within the areas of new work and to any other limited areas designated by the OWNER for storage of material, access and field office. Since working space is limited, the CONTRACTOR is responsible for securing any off-site space or any additional area required for performing the work.

B. If available, any on-site storage area shall be coordinated with the OWNER. The CONTRACTOR is responsible for securing any on-site storage. The City of Richmond shall not be responsible for any items stored on site.

C. Access to the garage must be maintained at all times.

PART 2 - PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Summary of Work Richmond, VA

01010 - 1

SECTION 01010

SUMMARY OF WORK

PART 1 - GENERAL

1.01 WORK COVERED BY THE CONTRACT DOCUMENTS

A. This Summary of Work is a general description of the extent of the work. This Summary of Work only highlights the general responsibilities of the Contractor to the City and does not supersede the specific requirements of the Contract Documents. Conditions of the Contract addenda, this section and other sections of Division 1 – General Requirements, apply to the entire work of the contract.

B. Work under this contract includes furnishing and installing all appurtenant and incidental materials and equipment, complete and in-place, fully operational and in accordance with the Contract Documents. The Work generally includes, but is not limited to the following:

1. Modernization of elevators #1 and #2 as specified in section 142211

2. Installation of sprinkler systems for elevator pits #1 and #2 and themachine room for elevator #1 as specified in section 21000

3. Installation of smoke detectors in elevator #1 machine room as specifiedin section 283100

4. Installation of heat detectors within 24" of sprinklers in elevator #1 and #2pits as specified in section 283100Concrete surface repairs

At least one elevator must be operable and useable at all times.

C. Work consists of providing labor, materials, equipment, training, services and administration required in conjunction with or properly incidental to construction of the project. All work shall be performed in accordance with Federal, State and Local regulations and OSHA requirements.

D. Consideration will not be given for misunderstanding the amount of work to be performed. Work includes all items and conditions specified, indicated in the specifications or required by nature of the building or site. Any questions arising during Bidding shall be submitted to the City of Richmond Procurement Services as specified in Section III of the General Condition. Questions that arise during the Construction Phase should be submitted in writing to the Owner for resolution.

PART 2 - PRODUCTS (NOT USED)

Downtown Expressway Parking Garage - Elevator Replacement Summary of Work Richmond, VA

01010 - 2

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Reference Standards Richmond, VA

01092-1

SECTION 01092

REFERENCE STANDARDS

PART 1 - GENERAL

1.01 REFERENCE TO STANDARDS AND SPECIFICATIONS OF TECHNICAL SOCIETIES

A. The provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity or discrepancy between the provisions of the Contract Documents and the provisions of any standard, specification, manual, code or instruction, or the provisions of any such Laws or Regulations applicable to the performance of the Work (unless such an interpretation of the provisions of the Contract Documents would result in violation of such Law or Regulation).

B. No provision of any standard, specification, manual, code or instruction shall be effective to change the duties and responsibilities of OWNER, CONTRACTOR or ENGINEER, or any of their subcontractors, consultants, agents or employees from those set forth in the Contract Documents.

C. Work specified by reference to the published standard or specification of a government agency, technical association, trade association, professional society or institute, testing agency, or other organization shall meet the requirements or surpass the minimum standards of quality for materials and workmanship established by the designated standard or specification.

D. Where so specified, products or workmanship shall also meet or exceed the additional prescriptive or performance requirements included within the Contract Documents to establish a higher or more stringent standard of quality than that required by the referenced standard.

E. Where two or more standards are specified to establish quality, the product and workmanship shall meet or exceed the requirements of the most stringent.

F. Where both a standard and a brand name are specified for a product in the Contract Documents, the proprietary product named shall meet or exceed the requirements of the specified reference standard.

G. Copies of standards and specifications of technical societies:

1. Copies of applicable referenced standards have not been bound in theseContract Documents.

Downtown Expressway Parking Garage - Elevator Replacement Reference Standards Richmond, VA

01092-2

2. Where copies of standards are needed by the CONTRACTOR, obtain acopy or copies directly from the publication source and maintain in anorderly manner at the site as Work site records, available to theCONTRACTOR's personnel, Subcontractors, OWNER, and ENGINEER.

H. Any reference to standards in the Contract Documents shall always imply the latest issue in effect including all amendments and errata at the time bids are taken, of said standards unless otherwise stated.

1.02 ABBREVIATIONS

A. Abbreviations for trade organizations, units of measure and government agencies: Following is a list of construction industry organizations and government agencies to which references may be made in the Contract Documents, with abbreviations used.

1. AA Aluminum Association 2. AABC Associated Air Balance Council 3. AAMA American Architectural Manufacturers Association 4. AASHTO American Association of State Highway and

Transportation Officials 5. AASHO The American Association of State Highway Officials 6. ACI American Concrete Institute 7. ACS American Chemical Society 8. AFBMA Anti-Friction Bearing Manufacturers' Association 9. AGA American Gas Association 10. AGMA American Gear Manufacturers’ Association 11. AI Asphalt Institute 12. AICHE American Institute of Chemical Engineers 13. AIEE American Institute of Electrical Engineers (now IEEE) 14. AIMA Acoustical and Insulating Materials Association 15. AISC American Institute of Steel Construction 16. AISI American Iron and Steel Institute 17. AITC American Institute of Timber Construction 18. ALS American Lumber Standards 19. AMA Acoustical Materials Association 20. AMCA Air Movement and Control Association 21. ANSI American National Standards Institute 22. APA American Plywood Association 23. API American Petroleum Institute 24. APWA American Public Works Association 25. AREA American Railway Engineering Association 26. ARI Air Conditioning and Refrigeration Institute 27. ASA American Standards Association (now ANSI) 28. ASAE American Society of Agricultural Engineers 29. ASCE American Society of Civil Engineers

Downtown Expressway Parking Garage - Elevator Replacement Reference Standards Richmond, VA

01092-3

30. ASHRAE American Society of Heating, Refrigeration and Air-Conditioning Engineers, Inc.

31. ASNT American Society for Nondestructive Testing 32. ASME American Society of Mechanical Engineers 33. ASSCBC American Standard Safety Code for Building Construction 34. ASTM American Society for Testing and Materials 35. AWI Architectural Wood Work Institute 36. AWPA American Wood Preservers' Association 37. AWPB American Wood Preservers Bureau 38. AWPI American Wood Preservers' Institute 39. AWS American Welding Society 40. AWWA American Water Works Association 41. BHMA Builders Hardware Manufacturers' Association 42. BIA Brick Institute of America 43. CBRA Copper and Brass Research Association 44. CBMA Certified Ballast Manufacturers' Association 45. CDA Copper Development Association 46. CGA Compressed Gas Association 47. CIPRA Cast Iron Pipe Research Association 48. CIPRI Cast Iron Pipe Research Institute 49. CISPI Cast Iron Soil Pipe Institute 50. CMAA Crane Manufacturers' Association of America 51. CRSI Concrete Reinforcing Steel Institute 52. CS Commercial Standard (US Dept of Commerce) 53. CSA Canadian Standards Association 54. CSI Construction Specifications Institute 55. CTSS Caltrans Standard Specification 56. E/A Engineer and/or Architect 57. EEI Edison Electric Institute 58. EJCDC Engineers Joint Contract Documents' Committee 59. EPA U.S. Environmental Protection Agency 60. ETL Engineering Test Laboratories 61. FCC Federal Communications Commission 62. FEMA Federal Emergency Management Agency 63. FGMA Flat Glass Marketing Association 64. FM Factory Mutual 65. Fed. Spec. Federal Specifications66. FS Federal Specification 67. FTI Facing Tile Institute 68. GA Gypsum Association 69. GPM Gallons per Minutes 70. HI Hydraulic Institute 71. HMI Hoist Manufacturers' Institute 72. HP Horsepower 73. ICBO International Conference of Building Officials 74. ICEA Insulated Cable Engineers' Association

Downtown Expressway Parking Garage - Elevator Replacement Reference Standards Richmond, VA

01092-4

75. ID Inside Diameter 76. IEEE Institute of Electrical and Electronics Engineers, Inc. 77. IES Illuminating Engineering Society 78. IFI Industrial Fasteners Institute 79. IPCEA Insulated Power Cable Engineers Association 80. ISA Instrument Society of America 81. ISO Insurance Service Office 82. JIC Joint Industry Conferences of Hydraulic Manufacturers 83. MBE Minority Business Enterprise 84. MBMA Metal Building Manufacturers Association 85. MIA Marble Institute of America 86. Mil. Sp. Military Specification (or MIL) 87. MS Military Specifications 88. MSS Manufactures Standardization Society of the Valve

and Fittings Industry 89. MMA Monorail Manufacturers' Association 90. NAAMM National Association of Architectural Metal Manufacturers 91. NACE National Association of Corrosion Engineers 92. NBHA National Builders' Hardware Association 93. NBFU National Bureau of Fire Underwriters 94. NBS National Bureau of Standards 95. NCPI Nation Clay Pipe Institute 96. NCMA Nation Concrete Masonry Association 97. NEC National Electrical Code 98. NECA National Electrical Contractor's Association 99. NEMA National Electrical Manufacturers' Association 100. NESC National Electric Safety Code 101. NFPA National Fire Protection Association 102. NHLA National Hardwood Lumber Association 103. NHPMA Northern Hardwood and Pine Manufacturer's Association 104. NLMA National Lumber Manufacturers' Association 105. NPT National Pipe Threads 106. NRCA National Roofing Contractors Association 107. NSF National Sanitation Foundation Testing Lab. 108. NSPE National Society of Professional Engineers 109. NTMA National Terrazzo and Mosaic Association 110. NWWDA National Wood Window and Door Association 111. OD Outside Diameter 112. OECI Overhead Electrical Crane Institute 113. OFCCP Office of Federal Contracts Compliance Programs 114. OSHA Occupational Safety and Health Act (both Federal and

State) 115. PCA Portland Cement Association 116. PCI Prestressed Concrete Institute 117. PEI Porcelain Enamel Institute 118. PPI Plastic Pipe Institute

Downtown Expressway Parking Garage - Elevator Replacement Reference Standards Richmond, VA

01092-5

119. PS Product Standards Section-U.S. Department of Commerce 120. PSIG Pounds Per Square Inch Gauge 121. RMA Rubber Manufacturers' Association 122. RPM Revolutions per Minutes 123. SAE Society of Automotive Engineers 124. SCPI Structural Clay Products Institute 125. SCPRF Structural Clay Products Research Foundation 126. SDI Steel Deck Institute 127. SDI Steel Door Institute 128. SIGMA Sealed Insulating Glass Manufacturing Association 129. SJI Steel Joists Institute 130. SMACNA Sheet Metal and Air-Conditioning Contractors

National Association 131. SMSA Standard Metropolitan Statistical Area 132. SPI Society of the Plastics Industry 133. SPIB Southern Pine Inspection Board 134. SSPC Steel Structures Painting Council 135. STA Station (100 feet) 136. SWI Steel Window Institute 137. TDH Total Dynamic Head 138. TEMA Tubular Exchanger Manufacturers' Association 139. TCA Tile Council of America 140. UBC Uniform Building Code 141. UFC Uniform Fire Code 142. UL Underwriters Laboratories Inc. 143. UMC Uniform Mechanical Code 144. US U.S. Bureau of Standards 145. USASI United States of America Standards Institute 146. USBR U.S. Bureau of Reclamation 147. USC&GS United States Coast and Geodetic Survey 148. USGS United States Geological Survey 149. WCLIB West Coast Lumber Inspection Bureau 150. WWPA Western Wood Products Association

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED) END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Reference Standards Richmond, VA

01092-6

PAGE LEFT INTENTIONALLY BLANK

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 1

SECTION 01106

CONSTRUCTION SCHEDULING, COORDINATION AND SEQUENCING

PART 1 - GENERAL

1.01 GENERAL REQUIREMENTS

A. Construction work under this contract shall have the least amount of interferences with the operations of existing facilities. Existing facilities must be maintained in continuous operation at all times during the course of the work under this contract.

B. To achieve reliable, continuous operation, new equipment and facilities shall be tested and in operating condition before final tie-ins are made which connect new equipment and facilities to the existing system.

C. The CONTRACTOR shall submit to the OWNER, drawings showing details of all temporary connections or facilities as required.

D. No extra payment shall be made for any labor, materials, tools, equipment or temporary facilities required during the construction of facilities. All costs therefore shall be considered to have been included in the price bid of the Proposal.

1.02 SEQUENCE OF CONSTRUCTION

A. A plan for the sequence of construction and delivery dates is necessary to keep shutdowns and the construction to a minimum. The CONTRACTOR shall develop a sequence of construction and submit it to the OWNER for review and approval. The plan shall include all work to be performed and shall be broken down to allow coordination with “Requests for Payment”. The sequence of construction shall be such that all work under this contract shall be completed within the construction time stated in these specifications.

1.03 OPERATIONS OF EXISTING FACILITIES

A. The CONTRACTOR shall coordinate all sequence of the work, operation of existing facilities, shutdowns, etc. with the OWNER. All N.O.I.’s and shutdown requests shall be made, in writing, for approval by the OWNER. No work shall proceed until approval has been received from the OWNER.

B. The CONTRACTOR shall schedule his work in such a manner as to perform the work under this contract with the least possible interference to normal operation. If it is necessary to interrupt the normal operation of portions of the existing facilities brought about by the need to disconnect and reconnect or to add to or modify certain

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 2

items of equipment, piping, and other existing facilities, such interruptions shall require that the CONTRACTOR submit a Notice of Operation Impact (N.O.I.) request form and arrangements shall be made with the OWNER. The NOI shall be submitted a minimum of three (3) days in advance of such activities requiring the interruption of services by the CONTRACTOR to the OWNER.

C. The N.O.I. forms shall be initiated by the CONTRACTOR and submitted to the OWNER for review and release prior to any work being done that might, in any way, have an effect on the operations of the facility. An example of an N.O.I. is located in Appendices.

D. It is the CONTRACTOR’s responsibility to coordinate work with the OWNER to be sure that N.O.I.s are submitted in a timely fashion.

1.04 FACILITY SHUTDOWNS

A. The CONTRACTOR shall carefully coordinate all work and schedules and shall provide the OWNER with written notice prior to each shutdown period unless otherwise approved by the OWNER.

B. Prior to a shutdown, the CONTRACTOR shall submit to the OWNER in writing, detailed descriptions and schedules of the proposed construction procedures during the shutdown period. Information submitted to the OWNER shall include a complete inventory of materials and equipment needed to perform the work. No shutdown of a facility or operation will be permitted until the OWNER has reviewed and approved, in writing, the proposed construction plans and procedures.

C. If, during any temporary shutdown periods, the work performed is not satisfactory, as planned, or not completed with the maximum time allocated, the OWNER may order the CONTRACTOR to place the facility back in service and reschedule the work, or he may order the work required to place the facility or operation back in service to be performed with other forces.

D. During scheduled shut downs the CONTRACTOR shall be responsible for all damages and costs thereof due to negligence.

E. Under no circumstances cease Work at the end of a normal working day if such actions may inadvertently cause a cessation of any facility operating process, in which case, remain onsite until necessary repairs are complete.

F. Electrical Work

1. Power outages will require a N.O.I. submitted to the OWNER. Describe thereason, anticipated length of time, and areas affected by the outage in its

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 3

written request. Provide temporary provisions for continuous power supply to critical existing facility components if requested by OWNER.

2. Other miscellaneous partial electrical shutdowns and tie-ins will be fieldidentified during progress of the various parts of the work.

G. Sequence of Construction

1. The Contractor shall develop a sequence of construction and submit it to theOWNER for review and approval.

2. In general, the CONTRACTOR shall perform the various items of workunder the contract in a sequence but in keeping with the above requirements.The work shall be performed in the general sequence to meet the proposedprogress schedule, but in keeping with the requirements of the paragraph1.03, Operation of Existing Facilities.

3. The plan shall include all work to be performed and shall be broken down toallow coordination with “Requests for Payment”. The Sequence ofConstruction shall be such that all work under this contract shall becompleted within the construction time stated in these specifications.

4. The sequence of construction shall show items of work on the critical pathand other major items that have the potential to lie on the critical path. Allitems shall be tested and be complete for operation before beginning on thenext item of work unless otherwise noted.

5. The constraints specified above regarding outages of the existing facilitiesinclude certain scheduling requirements. Those requirements shall beconsidered together with the provisions of this paragraph when planning thework.

6. The Contractor shall schedule all required tests, approvals and inspections ofthe Work or portions thereof at appropriate times so as not to delay theprogress of the Work or other work related to the Project.

1.05 COORDINATION

A. Contractor, Subcontractors and Owner Personnel

1. The CONTRACTOR’s staging areas shall be limited to a 20 feet by 40 feetarea designated by the OWNER. Any additional areas may be coordinatedwith the OWNER but additional space is not guaranteed.

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 4

2. The CONTRACTOR is responsible for the proper coordination of his workand his subcontractor's work, to prevent interference with the operation of thefacility and to assure that the OWNER is made aware in advance of proposedconstruction activities.

3. There will be no basis for claim for extra compensation or contract timeextension due to delay caused by the CONTRACTOR's failure to give propernotice for requested shutdowns or to advise the OWNER of proposedconstruction activities that in the judgement of the OWNER will interferewith operation of the facility.

4. Should an emergency condition arise, the OWNER has the authority torequire the CONTRACTOR and his subcontractors to suspend theiroperations temporarily until conditions return to normal, without claim forextra cost or contract time extension by the CONTRACTOR and hisSUBCONTRACTORS.

5. CONTRACTOR agrees to indemnify the OWNER and to hold the OWNERharmless for any injury or malady suffered by any agent, employee, orservant of CONTRACTOR including any subcontractor or independentCONTRACTOR of CONTRACTOR (collectively hereinafter "agent").Furthermore, CONTRACTOR agrees to adhere to all applicable andpertinent OSHA and Commonwealth of Virginia rules, regulations, andguidelines; to adhere to all OWNER ordinances, laws, rules, and regulations;and to follow and apply safe construction practices in order to promote andprovide a safe working environment for agents. CONTRACTOR agrees toindemnify and pay the OWNER for any attorneys fees incurred by theOWNER in the defense of any claim against the OWNER for an injuryresulting from CONTRACTOR negligent failure: (1) to provide a safeworking environment; (2) to follow safe construction practices; (3) toinspect, supervise or review the job site or any plan or specification preparedby CONTRACTOR or his agents; and (4) to comply with any OSHA orCommonwealth of Virginia rules, regulation or guideline or any Cityordinance, law, rule and regulation. CONTRACTOR agrees to pay all courtcosts and any settlement or judgement incurred by the OWNER as a result ofany such action or claim.

1.06 RELATIONS WITH OTHER CONTRACTORS

A. The CONTRACTOR shall conduct his operations so as not to interfere with or injure the work of other contractors or workmen doing work for the City. The CONTRACTOR shall promptly make good, at his own expense, any injury or damage which may be done to such work by him or his employees, agents or subcontractors.

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 5

B. The CONTRACTOR shall suspend such part of his work, or shall carry on the same in such manner as may be ordered by the OWNER when necessary to facilitate the work of such other contractors or workmen.

1.07 UTILITIES

A. Coordinate Work with various utilities within Project limits. Notify applicable utilities prior to commencing Work, if damage occurs, or if conflicts or emergencies arise during Work. Should any utility be damaged or if conflicts or emergencies arise, the OWNER shall be notified immediately.

1.08 INFORMATION NOT GUARANTEED

A. All information in the Contract Documents relating to existing construction and other conditions, natural phenomena and existing pipes is from the best sources at present available to the City. All such information is furnished only for the information and convenience of bidders and is not guaranteed.

B. It is agreed further and understood that no bidder or CONTRACTOR shall use or be entitled to use any of the information made available to him or obtained in any examination made by him in any manner as a basis of or ground for any claim or demand against the City, arising from or by reason of any variance which may exist between the information made available and the actual conditions, natural phenomena or existing pipes actually encountered during the construction work, except as may be otherwise expressly provided for in the Contract Documents.

1.09 OBSTRUCTIONS UNEXPECTEDLY ENCOUNTERED

A. In case any pipe, structure, or other obstruction, so located or placed as to interfere with the work, is unexpectedly encountered, the CONTRACTOR shall at once notify the Engineer by telephone and confirm in writing, of the locality and circumstances, and the work at this location shall be suspended until satisfactory arrangements are made, without any claim for damages or extra compensation arising from the delay, but the CONTRACTOR may be allowed an extension of time as hereinbefore provided.

1.10 COMPLETION OF WORK

A. In addition to the definition in the General Conditions, Substantial Completion is further defined as (i) that degree of completion sufficient to provide the OWNER the full time, uninterrupted, continuous beneficial operation of the Work; and (ii) all inspections required have been completed and identified conditions corrected. Specific items of Work which shall be completed prior to declaration of Substantial Completion date include, but are not limited to, the following:

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 6

1. Correction of all state, local, and other regulatory agencies defective Worklists.

2. Submittals have been received and approved by the ENGINEER.

3. All additional warranty or insurance coverage requirements have beenprovided.

4. The OWNER may request utilization of substantially completed parts of theproject prior to substantial completion of all work. These guidelines aredescribed in paragraph 1.13 in this section.

1.11 HOLIDAYS, WORKING HOURS, AND NOISE

A. The City observes a five-day work week and the following holidays: New Year's Day; Martin Luther King's Birthday; Washington's Birthday, Easter Monday; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; the Friday after Thanksgiving; Christmas Eve and Christmas Day. The CONTRACTOR will not be permitted to work on these holidays unless otherwise authorized from the OWNER.

B. The CONTRACTOR shall not work during City holidays, unless approved by the OWNER, with two (2) weeks prior request needed. CONTRACTOR shall reimburse OWNER for additional expenses incurred for working beyond operation times identified above or on a City holiday.

C. Contractor operations shall be limited to Monday through Friday, 7.00 a.m. to 5:30 p.m., local time, unless approved by the OWNER. The CONTRACTOR may beallowed to work outside of the specified hours or days. The CONTRACTOR shall request written authorization from the OWNER. Request must be submitted 48 hours prior to the work activity. For work outside the standard hours, the CONTRACTOR will be required to pay the whole cost for the City inspection.

D. No Work shall be scheduled without prior notification and authorization.

E. In case of an extreme emergency which may require that work be done on Saturdays, Sundays, holidays or longer than ten hours per day, the CONTRACTOR shall request permission of the OWNER to do so. If, in the opinion of the OWNER, the emergency is bona fide, he will grant permission to the CONTRACTOR to work such hours as may be necessary. Also if in the opinion of the OWNER, a bona fide emergency exists, he may direct the CONTRACTOR to work such hours as may be necessary whether the CONTRACTOR requests permission to do so or not.

F. No playing of portable or car radios at or adjacent to the project site will be permitted.

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 7

G. Noise Control Ordinance: City of Richmond. The maximum allowable noise level at the property line of neighborhood residences is 55 dBA for CONTRACTOR operations at all times.

1.12 ADJACENT FACILITIES AND PROPERTIES

A. Examination:

1. After Effective Date of the Agreement and before Work at site is startedOWNER, CONTRACTOR and utility owners shall make thoroughexamination of pre-existing conditions including existing buildings,structures, and other improvements in vicinity of Work, as applicable, whichmight be damaged by construction operations. Periodic re-examination shallbe jointly performed to include, but not limited to, cracks in structures,settlement, leakage, and similar conditions.

2. Record observations for signature of OWNER and CONTRACTOR.

B. Documentation:

1. Submit two copies of photographs or other records documenting examinationfor OWNER’s signature. OWNER will review, sign, and return one recordcopy of every observation document and photograph to CONTRACTOR tobe kept on file in CONTRACTOR’s field office as site records.

2. These observations and photographs are intended for use as indisputableevidence in ascertaining whether and to what extent damage occurred as aresult of CONTRACTOR’s operations, and are for protection of adjacentproperty owners, CONTRACTOR, and OWNER.

1.13 PARTIAL UTILIZATION BY THE OWNER

A. Definition: Use by OWNER of a substantially completed part of the Work for the purpose for which it is intended (or a related purpose) prior to Substantial Completion of all the Work.

B. Unless agreed in writing prior to OWNER’s use, the following conditions shall apply:

1. CONTRACTOR’s Responsibilities:

a. Allow access for OWNER’s personnel.b. Allow operation of heating, ventilating, and electrical systems.c. Perform all required lubrication and maintenance of equipment

installed by him until final acceptance of the complete project.

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 8

2. OWNER’s Responsibilities:

a. Operate heating and ventilating systems and pay costs of same.b. Assume responsibility for security and fire protection in utilized

areas, but not extending to protection of CONTRACTOR’s materialsand equipment in utilized areas.

3. Other Conditions of OWNER’s Use: The correction period for the occupiedor separately operated portion of Work shall commence at the date ofSubstantial Completion for that separate part.

C. Property Insurance: OWNER may occupy or use a portion or portions of the Work prior to Substantial Completion of all the Work, provided that no such use or occupancy shall commence before the insurers providing the property insurance have acknowledged notice thereof and in writing effected any changes in coverage necessitated thereby. The insurers providing the property insurance shall consent by endorsement on the policy or policies, but the property insurance shall not be canceled or permitted to lapse on account of any such partial use or occupancy.

1.14 OWNER FACILITIES

A. Operation of Existing Facilities:

1. Continuous operation of OWNER’s facilities is of critical importance.Schedule and conduct activities to enable existing facilities to operatecontinuously, unless otherwise specified.

2. Conduct Work outside regular working hours on prior written consent ofOWNER to meet Project schedule and avoid undesirable conditions.

3. Do not proceed with Work affecting a facility’s operation without obtainingOWNER’s advance approval of the need for and duration of such Work.

4. Provide N.O.I. as required for approval to OWNER of need to shut down aprocess or facility.

1.15 SALVAGED MATERIALS

A. In the course of performing the work, it will be necessary for the CONTRACTOR to remove existing materials and equipment which will not be incorporated in the new work. Such materials and equipment which the OWNER determines to be salvageable shall remain his property and be turned over to him. All other removed items shall become the property of the CONTRACTOR.

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 9

B. Materials and equipment to be salvaged by the OWNER shall be removed with care by the CONTRACTOR so that they are not damaged. They shall be disassembled and stored in a neat and orderly manner at a location approved by the OWNER.

1.16 CONSTRUCTION PHOTOGRAPHS

A. Provide photographs showing the preconstruction site, construction progress, and the post-construction site. Photographs shall be taken and delivered in accordance with Section 01380 – Construction Photographs.

1.17 TESTS AND INSPECTIONS

A. Provide initial and subsequent inspections of Work to ensure that the Work conforms to the Contract Documents. Give OWNER timely notice of readiness of the Work for all non-CONTRACTOR required inspections, tests or approvals, and cooperate with inspection and testing personnel to facilitate required inspections or tests.

B. OWNER shall employ and pay for the services of an independent testing laboratory to perform all non-CONTRACTOR inspections, tests, or approvals required by the Contract Documents.

C. If Laws or Regulations of any public body having jurisdiction require any Work (or part thereof) specifically to be inspected, tested or approved by an employee or other representative of such public body, assume full responsibility for arranging and obtaining such inspections, tests or approvals, pay all costs in connection therewith. Furnish OWNER the required certificates of inspection, or approval. CONTRACTOR shall also be responsible for arranging and obtaining and shall pay all costs in connection with any inspections, tests or approvals required for OWNER’s acceptance of materials or equipment to be incorporated in the Work, or of materials, mix designs, or equipment submitted for approval prior to CONTRACTOR’s purchase thereof for incorporation in the Work.

D. Paragraph 6.3 of the GENERAL CONDITIONS is supplemented by this paragraph.

E. An inspector or inspectors of the City will visit the work site to report to the OWNER as to the progress of the work and the manner in which it is being performed; also, to report whenever it appears that the materials furnished and work performed by the CONTRACTOR fail to fulfill the requirements of the specifications and contract, and to call to the attention of the CONTRACTOR any such failure or other default; but no inspection nor any failure to inspect, at any time or place, however, shall relieve the CONTRACTOR from an obligation to perform all of the work strictly in accordance with the requirement of the Contract Documents. The inspectors shall perform such other duties as are assigned to them. They shall not be authorized to revoke, alter, enlarge, relax or release any requirements of these specifications, nor to approve or accept any portion of work, nor to issue instructions contrary to the plans and specifications. Inspectors shall in

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 10

no case act as foreman or perform other duties for the CONTRACTOR, nor interfere with the management of the work by the latter. Any instructions which the inspectors may give the CONTRACTOR shall in no way be construed as binding the ENGINEER or the OWNER in any way, nor releasing the CONTRACTOR from fulfillment of the terms of the Contract.

F. The OWNER may appoint such other person or persons as he may deem necessary to inspect, at any time or times, the material and equipment furnished and the work done under this Contract, said inspections to be made at the shops or plants, at the site of the work or at any or all said places, at the discretion of the OWNER.

G. Work and materials will be inspected promptly, but if for any reason delays should occur, the contractor shall thereby have no claims for damages or extra compensation. Materials and workmanship shall always be subject to the approval of the OWNER; but no inspection, approval or acceptance of any part of the work or of the materials used therein, nor any payment on account thereof, shall prevent the rejection of said materials or work at any time thereafter during the existence of the Contract, should said work or materials be found to be defective or not in accordance with the requirements of the specifications and Contract.

H. At all times during the progress of the work, the CONTRACTOR shall, permit, or secure permission for, any duly authorized inspector or representative of the City to enter any factory, shop or other place where any materials and equipment to be supplied for the work under this contract are prepared, manufactured or constructed at any time or times while such preparations, manufacture or construction is in progress. The CONTRACTOR shall furnish and prepare or cause to be furnished and prepared without charge, all such assistance, appliances, samples of materials and test specimens as may be ordered by the OWNER or such inspector or representative for the purpose of making official tests and investigations. The CONTRACTOR shall also provide all tools, testing machines, materials, and labor necessary for the required testing, inspection and weighing at the shops, plants, and/or site of the work, of the materials and equipment and of any and all parts thereof to be supplied for the work under this contract.

I. The OWNER shall be notified of the time and place of preparation, manufacture or construction of all material, equipment and devices for all or part of the work before delivery at the site of the work. Such notification shall be given a sufficient time in advance of the beginning of the work on such material, equipment and devices to allow arrangements to be made for inspecting and testing.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 CUTTING, FITTING, AND PATCHING

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 11

A. Cut, fit, adjust, grout or patch Work and work of others to make Work complete.

B. Obtain prior written authorization of OWNER before commencing Work to cut or otherwise alter:

1. Structural or reinforcing steel, structural columns or beams, elevated slabs,trusses, or any other structural member.

2. Weather- or moisture-resistant elements.

3. Efficiency, maintenance, or safety of element.

4. Work of others.

C. Refinish surfaces to provide an even finish.

1. Refinish continuous surfaces to nearest intersection.

2. Refinish entire assemblies.

3. Finish restored surfaces to such planes, shapes, and textures that no transitionbetween existing work and Work is evident in finished surfaces.

D. Restore existing work and surfaces that are to remain in completed Work including concrete-embedded piping, conduit, and other utilities as specified and as shown.

E. Make restorations with new materials and appropriate methods as specified for new Work of similar nature; if not specified, use best recommended practice of manufacturer or appropriate trade association.

F. Fit Work airtight to pipes, sleeves, ducts, conduit and other penetrations through surfaces and fill existing voids.

G. Remove specimens of installed Work for testing when requested by OWNER.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Construction Scheduling, Coordination Richmond, VA and Sequencing

01106 - 12

PAGE LEFT INTENTIONALLY BLANK

Downtown Expressway Parking Garage - Elevator Replacement Measurement and Payment Richmond, VA

01130 - 1

SECTION 01130

MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.01 GENERAL

A. The CONTRACTOR shall receive and accept the compensation provided in the Bid Proposal(s) and the Contract(s) as full payment for furnishing all materials, labor, tools and equipment, for performing all operations necessary to complete the work under the Contract(s), and also in full payment for all loss or damages arising from the nature of the work, or from any discrepancy between the actual quantities of work and quantities herein estimated by the ENGINEER, or from the action of the elements or from any unforeseen difficulties which may be encountered during the prosecution of the work until the final acceptance by the OWNER.

B. The prices stated in the proposal(s) include all costs and expenses for taxes, labor, equipment, materials, commissions, transportation charges and expenses, patent fees and royalties, labor for handling materials during inspection, insurance permits and other fees, together with any and all other costs and expenses for performing and completing the work as indicated in the Contract Documents. The basis of payment for an item at the lump sum price shown in the proposal(s) shall be in accordance with the description of that item in this Section.

C. The CONTRACTOR’s attention is called to the fact that the quotations for the various items of work are intended to establish a total price for completing the work in its entirety. Should the CONTRACTOR feel that the cost for any item of work has not been defined by a Bid Form payment item, he shall include the cost for that work in some other applicable bid item, so that his proposal for the project reflects his total price for completing the work in its entirety.

D. The OWNER reserves the right to change the alignment, grade, form, length, dimensions or materials of the work under the contract, whenever any conditions or obstructions are met that render such changes desirable or necessary. All such alterations shall be paid for under the total lump sum bid or at a unit price bid for these items of work, except as follows:

1. In case such alterations made the work less expensive to theCONTRACTOR, a proper deduction shall be made from the contractprices and the CONTRACTOR shall have no claim on this account fordamages or for anticipated profits on the work that may be dispensed with.

Downtown Expressway Parking Garage - Elevator Replacement Measurement and Payment Richmond, VA

01130 - 2

2. In case such alterations make the work more expensive, a proper additionshall be made to contract prices. The OWNER shall determine any suchdeduction or addition.

E. The OWNER reserves the right to increase or decrease the quantity of material to be furnished or work to be done under the contract whenever he deems if advisable or necessary, and such increase or decrease shall in no way violate the contract. For the Unit Price Items included in the Bid, the CONTRACTOR will be paid for the actual quantity of the authorized work done or material furnished under each item of the proposal, at the unit price bid for such item. In case the quantity of any item is increased, the CONTRACTOR shall not be entitled to compensation over and above the unit price bid for such item. In case the quantity of any item is decreased, the CONTRACTOR shall have no claim for damages on account of loss of anticipated profits because of such decrease.

1.02 MEASUREMENT

A. The quantities for payment under this Contract shall be determined by actual measurement of the completed items, in place and accepted by the OWNER, in accordance with the General Conditions. A representative of the CONTRACTOR shall witness all field measurements.

1.03 MEASUREMENT - GENERAL

A. Weighing, measuring, and metering devices used to measure quantity of materials for Work shall be suitable for purpose intended and conform to tolerances and specifications as specified in National Institute of Standards and Technology, Handbook 44.

B. Units of measure shall be as follows:

Item Method of Measurement

CF Cubic Foot—Field Measure by ENGINEER within the limits specified or shown

CY Cubic Yard—Field Measure by ENGINEER within the limits specified or shown

SY Square Yard —Field Measure by ENGINEER within the limits specified or shown

SF Square Foot—Field Measure by ENGINEER within the limits specified or shown

LF Linear Foot—Field Measure by ENGINEER

Downtown Expressway Parking Garage - Elevator Replacement Measurement and Payment Richmond, VA

01130 - 3

Item Method of Measurement LS Lump Sum—Unit is one; no measurement will

be made.

Hours Hours – Field Measure by ENGINEER

1.04 PAYMENT FOR MATERIALS NOT INCORPORATED INTO THE WORK

A. Storage of Materials

1. Payment for equipment and materials stored on the site, or elsewhere asspecified in the GENERAL CONDITIONS, and not actually incorporatedin the Work will be made on the basis of the amount of paid invoicessubmitted to the ENGINEER for incorporation in the monthly estimate.

2. Materials not incorporated in the Work shall be any materials or pieces ofequipment that have been delivered to the site, or properly stored in anapproved, secured off-site storage facility to the satisfaction of theENGINEER, that will be incorporated into and become a part of the Workbut that have not yet been installed.

B. Authorization for Payment

1. Payment will be authorized after the delivery to the construction site orother approved location and after being certified by the ENGINEER asbeing stored in conformation with the manufacturer’s recommendationsand satisfactory evidence is provided that the items are as specified.

2. Title to all items of equipment and materials upon which payment hasbeen made shall rest with the OWNER and documents transferring titleshall be executed by the CONTRACTOR. Transfer of ownership shall notrelieve the CONTRACTOR of continuing insurance coverage and ofprotecting stored items against damage, deterioration, theft or loss of anykind.

3. Should materials or equipment become damaged or be stored improperlyor contrary to the manufacturer’s recommendations, being thereforesubject to later damage, then the ENGINEER will reduce the nextfollowing monthly payment by an amount sufficient to repair or replacesuch units.

4. To initiate a request for partial payment the CONTRACTOR shall submithis request in writing to the ENGINEER with all necessary evidence.

PART 2 - PRODUCTS (NOT USED)

Downtown Expressway Parking Garage - Elevator Replacement Measurement and Payment Richmond, VA

01130 - 4

PART 3 - EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Applications for Payment Richmond, VA

01152 - 1

SECTION 01152

APPLICATIONS FOR PAYMENT

PART 1 - GENERAL

1.01 REQUIREMENT

A. Submit Applications for Payment in accordance with the requirements established by the Contract Documents.

1.02 FORMAT and DATA REQUIRED

A. Applications for Payment shall include the following:

1. Application and Certification for Progress Payment form.2. CPM Schedule Earned Value Report. The CPM schedule submitted in

accordance with Section 01310 shall be the basis for payment.3. Invoices for stored materials.4. CONTRACTOR'S Monthly Status report in accordance with section

01310. 5. A copy of the current “Red Line” record drawing set.6. Revised Construction Schedule showing the work completed to date, work

to be completed in the next 30 days and current Substantial Completiondate.

1.03 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT

A. Application form is included in General Conditions – Forms and Attachments.

B. Application Form

1. Fill in required information on the "Application and Certification forProgress Payment" form.

2. Execute certification with signature of a responsible officer ofCONTRACTOR. An original signature should appear on each copysubmitted.

3. Attach to the Application the CPM Schedule Updated Earned ValueReport. The agreed upon Earned Value Report will be the basis for allprogress payments.

4. Attach to the Application, for payment of materials stored on or off site,original paid invoices.

5. Other Withholding from Progress Payment

Downtown Expressway Parking Garage - Elevator Replacement Applications for Payment Richmond, VA

01152 - 2

a. If it is determined that additional monies should be withheld fromthe amount otherwise due CONTRACTOR, a "Other Withholdingfrom Progress Payment" form will be completed with anexplanation of the amount and reasons for such OtherWithholding, and will be attached to each copy of the Application.Some items which, might be included in the Other Withholdingamount are, but not limited to: engineering fees for review ofsubstitutions; excessive shop drawing review; overtime requiredby CONTRACTOR's work in excess of eight hours per day; costsincurred due to CONTRACTOR caused damage to private orpublic property; etc.

1.04 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS

A. Provide any substantiating data, as requested by the ENGINEER.

B. Since the operations and maintenance information to be supplied will be reviewed initially and then resubmitted, payment for individual items of equipment shall be based on a cost loaded CPM schedule for the operations and maintenance manuals and equipment until the preliminary draft operation and maintenance data is submitted and receives a "Furnish as Corrected" annotation by ENGINEER.

C. As a prerequisite for monthly progress payments, submit a copy of redline drawings for review.

1.05 SUBMITTAL PROCEDURES

A. Submit, to the ENGINEER, Applications for Payment at the times stipulated in the Agreement.

B. Submit three copies of each Application.

C. When Application is determined to be properly completed and correct, the Application for Payment will be transmitted to OWNER for payment.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Change Order and Field Order Procedures Richmond, VA

01153 - 1

SECTION 01153

CHANGE ORDER AND FIELD ORDER PROCEDURES

PART 1 - GENERAL

1.01 REQUIREMENTS

A. Promptly implement change order procedures as follows:

1. Provide full written data required to evaluate changes.

2. Maintain detailed records of Work done on a time-and-material/forceaccount basis.

3. Provide full documentation on request.

B. Designate in writing the member of CONTRACTOR's organization:

1. Who is authorized to accept changes in the Work.

2. Who is responsible for informing others in the CONTRACTOR's employof the authorization of changes in the Work.

C. Final approval of all Change Orders will be by the City of Richmond Procurement Services.

1.02 RELATED WORK SPECIFIED ELSEWHERE

A. General Conditions, Forms and Attachments - Contract

B. Division 01010 – Summary of Work

C. Section 01152 - Applications for Payment

D. Section 01310 – Progress Schedule

1.03 PRELIMINARY PROCEDURES

A. OWNER may initiate changes by submitting a Request for Proposal (RFP) to the CONTRACTOR in accordance with the General Conditions as amended by the Supplementary Conditions. Request will include:

1. A detailed description of the change, products, and location of the changein the Project;

Downtown Expressway Parking Garage - Elevator Replacement Change Order and Field Order Procedures Richmond, VA

01153 - 2

2. Supplementary or revised Drawings and Specifications;

3. The projected time span for making the change, and a specific statementas to whether overtime work is, or is not, authorized;

4. Such request is for information only, and is not an instruction to executethe changes, or to stop work in progress.

B. CONTRACTOR may initiate a request to make a change by submitting a written notice (in a form acceptable to the OWNER) containing:

1. Description of the proposed changes;

2. Statement of the reason for making the changes;

3. Statement of the effect on the Contract Price and the Contract Time;

4. Statement of the effect on the work of separate Contractors;

5. Documentation supporting any change in Contract Price or Contract Time.

6. Such request is for information only, and is not an instruction to executethe changes, or to stop work in progress.

1.04 DOCUMENTATION OF PROPOSALS AND CLAIMS

A. CONTRACTOR shall support each quotation for a lump-sum proposal or time-and-material work, and for each unit price that has not previously been established, with sufficient substantiating data to allow evaluation of the quotation, in accordance with the General Conditions.

B. On request, CONTRACTOR shall provide additional data to support time and cost computations including, but not limited to, the following:

1. Labor required with certified payroll data to submit for review andapproval.

2. Equipment required

3. Products required

a. Recommended source of purchase and unit cost. CONTRACTORshall make every effort to obtain competitive pricing as timeallows.

b. Quantities required

Downtown Expressway Parking Garage - Elevator Replacement Change Order and Field Order Procedures Richmond, VA

01153 - 3

4. Taxes, insurance, and bonds

5. Credit for Work deleted from Contract, similarly documented

6. Overhead and profit

7. Justification for any change in Contract Time

C. Support each claim for additional costs, and for Work done on a time-and-material/force account basis, with documentation in accordance with the General Conditions, plus additional information as follows:

1. Name of OWNER's authorized agent who ordered the Work, and date ofthe order.

2. Name of Procurement Services agent who authorized the Work, and dateof the order.

3. Dates and times Work was performed, and by whom.

4. Time record, summary of hours worked, and hourly rates paid.

5. Receipts and invoices for:

a. Equipment used, listing dates, and times of useb. Products used, listing of quantitiesc. Subcontracts

1.05 PREPARATION OF CHANGE ORDERS AND FIELD ORDERS

A. ENGINEER will prepare each Change Order and Field Order with technical requirements.

B. Change Orders will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change.

C. Change Order will provide an accounting of the adjustment in the Contract Price and/or the Contract Time.

D. Field Orders will describe interpretations or clarifications of Contract Documents and/or document trade-off agreements.

E. Field Order work will be accomplished without change in the Contract Price, Contract Time, and/or claims for other costs.

F. If in agreement, the CONTRACTOR shall sign and return Field Orders for

Downtown Expressway Parking Garage - Elevator Replacement Change Order and Field Order Procedures Richmond, VA

01153 - 4

execution by the next working day at which time they will become binding on the CONTRACTOR.

1.06 CORRELATION WITH CONTRACTOR'S SUBMITTALS

A. Revise Schedule of Values and Application for Payment forms to record each change as a separate item of Work and to record the adjusted Contract Price.

B. Revise the Construction Schedule monthly to reflect each change in Contract Time. Revise sub-schedules to show changes for other items of Work affected by the changes.

C. Upon completion of Work under a Change Order, enter pertinent changes in Record Documents.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Project Meetings Richmond, VA

01200 - 1

SECTION 01200

PROJECT MEETINGS

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. The CONTRACTOR will schedule and administer a Pre-Construction Meeting, periodic progress meetings, and pre-installation meetings, and other meetings throughout the progress of the work.

1. Prepare agenda for meetings2. Make physical arrangements for meetings3. Preside at meetings4. Prepare and distribute meeting minutes

B. Representatives of the CONTRACTOR, subcontractors and suppliers attending meetings shall be qualified and authorized to act on behalf of the entity each represents.

1.02 PRECONSTRUCTION MEETING

A. A Pre-Construction Meeting will be scheduled before the CONTRACTOR starts Work at the site.

B. Location: A site designated by the OWNER.

C. Attendance:

1. OWNER's representative2. ENGINEER and his professional consultants3. CONTRACTOR's project manager and superintendent4. Major subcontractors5. Others as appropriate

D. Suggested Agenda:

1. Distribution and discussion of:

a. List of major subcontractors and suppliersb. Projected construction schedules

2. Critical work sequencing.3. Project coordination:

Downtown Expressway Parking Garage - Elevator Replacement Project Meetings Richmond, VA

01200 - 2

a. Designation of responsible personnel

4. Procedures and processing of:

a. Field decisionsb. Proposal requestsc. Submittalsd. Change Orderse. Applications for payment

5. Adequacy of distribution of Contract Documents.6. Procedures for maintaining Record Documents.7. Use of premises:

a. Office, work and storage areas.b. OWNER's requirements.

8. Construction facilities, controls and construction aids.9. Temporary utilities.10. Housekeeping procedures.11. Check of required Bond and Insurance certifications.12. Liquidated damages.13. Check of required Permits.14. Laboratory testing of material requirements.15. Inventory of material stored on site.16. Wage determination compliance and records, work hours.17. MBE/WBE fair share objective, affirmative action, nondiscrimination

policies.18. Communication lines and contact persons, including address and telephone

number.19. Manufacturers' operation and maintenance manuals, and operation and

maintenance training.20. Regulatory agency inspections.21. Progress agency inspections.22. Job site safety.23. Periodic progress meeting schedule

1.03 PROGRESS MEETINGS

A. Regular periodic Progress Meetings will be held as determined during the pre-construction meeting.

B. Additional meetings will be scheduled as required by progress of the work.

C. Location of the meetings: A site designated by the OWNER.

Downtown Expressway Parking Garage - Elevator Replacement Project Meetings Richmond, VA

01200 - 3

D. Attendance:

1. ENGINEER and his professional consultants as needed.2. CONTRACTOR and his Subcontractors (as appropriate to the agenda).3. OWNER's representative.4. Others as appropriate.

E. Suggested Agenda:

1. Review and approval of minutes of previous meeting.2. Review of work progress since previous meeting.3. Field observations, problems and conflicts.4. Problems which impede Construction Schedule.5. Review of off-site fabrication, delivery schedules.6. Corrective measures and procedures to regain projected schedule.7. Revisions to Construction Schedule.8. Progress schedule during succeeding work period.9. Coordination of schedules.10. Review submittal schedules; expedite as required.11. Maintenance of quality standards.12. Pending changes and substitutions.13. Review proposed changes for:

a. Effect on Construction Schedule and on completion date.b. Effect on other contracts of the Project.

G. The CONTRACTOR is to provide a current shop drawing submittal log and current progress schedule at each progress meeting in accordance with Section 01300.

1.04 QUALITY CONTROL AND COORDINATION MEETING(S)

A. Scheduled as necessary to review test and inspection reports, and other matters relating to quality control of Work and work of other contractors.

B. Location of the meetings: A site designated by the meeting organizer.

C. Attendance: As required

D. Agenda: As required

1.05 PRE-INSTALLATION MEETINGS

A. When required in individual Specification sections, convene at site prior to commencing Work of that section.

B. Location of the meetings: A site designated by the CONTRACTOR.

Downtown Expressway Parking Garage - Elevator Replacement Project Meetings Richmond, VA

01200 - 4

C. Attendance: Require attendance of entities directly affecting, or affected by, Work of that section.

D. Provide 7 day advance notice of meeting date.

E. Agenda: As required.

1.06 OTHER MEETINGS

A. OWNER or ENGINEER may request that CONTRACTOR schedule, conduct, or attend other meetings as required to review and resolve project issues. Such meetings may include equipment pre-installation, outage coordination, instrumentation and testing, safety, and other topics as required.

PART 2 - PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 1

SECTION 01300

SUBMITTALS

PART 1 - GENERAL

1.01 GENERAL

A. The CONTRACTOR shall submit for review and approval such shop drawings, test reports and product data on materials and equipment (hereinafter in this section called data), and material samples (hereinafter in this section called samples) as are required for the proper control of work, including but not limited to those shop drawings product data and samples for materials and equipment specified elsewhere in the Contract Documents.

B. The CONTRACTOR is to maintain an accurate updated submittal log and will bring this log to each scheduled Progress Meeting. This log should include the following items:

1. Submittal-Description and Number assigned.2. Date submitted.3. Date returned.4. Status of Submittal (Approved, Approved as Noted, Revise and Return,

Rejected).5. Date of Resubmittal and Return (as applicable).6. Date material release (for fabrication).7. Projected date of fabrication.8. Projected date of delivery to site.9. Status of O&M manuals submittal.10. Specification Section.11. Drawings Sheet Number (if applicable).

1.02 TYPES OF SUBMITTALS

A. Shop drawings for manufactured or fabricated items, schedules, diagrams and like material prepared specially for this project.

B. Product Data which include pre-printed material, manufacturer's descriptive literature, illustrations, catalog data, performance charts and the like intended to identify a part of the work but not necessarily prepared exclusively for this Contract.

C. Samples which include physical examples of products, materials, assemblies or workmanship which are identical to a portion of the work and which establish standards for materials, workmanship, or appearance of the finished work.

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 2

D. Administrative data to include information required to support the administrative requirements of the contract.

1.03 PROCEDURE FOR SUBMITTALS

A. All submittals shall be distributed electronically in PDF format. Distribution shall be as determined during the pre-construction meeting. Submittals shall be complete for each component of work or system and shall include all inter-related portions of a system.

1.04 CONTRACTOR'S RESPONSIBILITY

A. It is the duty of the CONTRACTOR to check all drawings, data and samples prepared by or for him before submitting them for review. Each and every copy of the Shop Drawings and data shall bear a CONTRACTOR's stamp showing that they have been checked. Shop drawings submitted without the CONTRACTOR's stamp will be returned to the CONTRACTOR for conformance with this requirement. Shop drawings shall indicate any deviations in the submittal from requirements of the Contract Documents.

B. Contract Documents shall not be reproduced for the purpose of making shop drawings.

C. Determine and verify:

1. Field measurements.2. Field construction criteria.3. Catalog numbers and similar data.4. Conformance with Contract Documents.

D. The CONTRACTOR shall ensure that no work is begun on any item of work requiring an approved submittal until such approval is obtained.

E. The CONTRACTOR shall not begin any work covered by a drawing, data, or a sample returned marked "REVISE AND RETURN” OR “REJECTED" until a revision or correction thereof has been reviewed and returned to him with approval.

F. One approved copy of all submittals shall be held by the CONTRACTOR at the construction site.

G. Each submittal shall be assigned a sequential number by the CONTRACTOR, for purposes of easy identification, and shall retain its assigned number with appropriate subscript, on required resubmissions. The assigned number shall consist of the specification section number where the item is specified, followed by a sequential number indicating the number of submittals in that Section (e.g., 03300-11 is the 11th separate submittal for items specified in Section 03300). Resubmittals shall be

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 3

identified with the same number as the original submittal, followed by the subscript R1, R2, etc. All products and materials submitted shall be clearly identified with the appropriate equipment name and number as it appears in the Contract Document.

H. The CONTRACTOR shall submit all shop drawings, submittals and schedules within 30 days following the Notice to Proceed and allow no less than 15 calendar days for review from time of receipt.

I. All submittals shall be accompanied with a transmittal letter containing the following information:

1. Date.2. Project Title and Number.3. CONTRACTOR's name and address.4. The Number of each Shop Drawing, Project Data, and Sample submitted.5. Notification of Deviations from Contract Documents.6. Submittal Log Number conforming to Specification Section Numbers.

J. The CONTRACTOR shall be responsible for and bear all costs of damages which may result from the ordering of any material or from proceeding with any part of work prior to the completion of the review of the necessary Shop Drawings.

K. The CONTRACTOR shall be responsible for observing the need for and making any changes which may be required by the materials/equipment he proposed to supply both as pertains to his work and any work affected under other parts, heading, or divisions of drawings and specifications at no cost to the OWNER.

1.05 ENGINEER'S REVIEW OF SHOP DRAWINGS

A. The ENGINEER's review of drawings, data and samples submitted by the CONTRACTOR will be only for conformance with the design concept of the Project and for general compliance with the information given in the Contract Documents. The ENGINEER's review and approval will not constitute an approval of dimensions, quantities, and details of the material, equipment, device, or item shown.

B. The review of drawings and schedules will be general, and shall not be construed:

1. as permitting any departure from the Contract requirements;2. as relieving the CONTRACTOR of responsibility for any errors, including

details, dimensions, and materials;3. as approving departures from details furnished by the ENGINEER, except as

otherwise provided herein.4. as approving CONTRACTOR's means, methods, techniques, sequences or

procedures of construction or to safety precautions or programs incidentthereto.

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 4

C. If the drawings or schedules as submitted describe variations and show departure from the Contract requirements which are in the interest of the OWNER and to be so minor as not to involve a change in Contract Price or time for performance, the ENGINEER may return the reviewed drawings without noting an exception.

D. The ENGINEER will review, with reasonable promptness, submittals with respect to the Contract Documents and will indicate a qualified “Approval”, an “Approval As Noted”, a “Revise and Return” or “Rejected” notation. Incomplete submittals will be returned without being reviewed.

E. Resubmittals by CONTRACTOR shall be submitted within 15 calendar days from the time they are received and handled in the same manner as first submittals. On resubmittals the CONTRACTOR shall direct specific attention, in writing or on resubmitted Shop Drawings, to revisions other than the corrections requested on previous submissions. The CONTRACTOR shall make any corrections required by the ENGINEER.

F. If the CONTRACTOR considers any correction indicated on the drawings to constitute a change to the Contract Drawings or Specifications, the CONTRACTOR shall give written notice thereof.

G. Review of each original submittal and first resubmittal is included in the contract. Review time for subsequent resubmittals will be charged to the CONTRACTOR at the rate of $185 per hour.

H. When the Shop Drawings have been completed to the satisfaction of the ENGINEER, the CONTRACTOR shall carry out the construction in accordance therewith and shall make no further changes therein except upon written instructions from the OWNER.

I. No partial submittals will be reviewed. Incomplete submittals will be returned to the CONTRACTOR for resubmittal.

1.06 SHOP DRAWINGS

A. When used in the Contract Documents, the term "Shop Drawings" shall be all drawings, diagrams, illustrations, schedules and other data which are specifically prepared by or for CONTRACTOR to illustrate some portion of the Work and all illustrations, brochures, standard schedules, performance charts, instructions, diagrams, and other information prepared by a Supplier and submitted by CONTRACTOR to illustrate material or equipment for some portion of the Work.

B. Manufacturer's catalog sheets, brochures, diagrams, illustrations and other standard descriptive data shall be CLEARLY MARKED TO IDENTIFY THOSE MATERIALS, PRODUCTS OR MODELS THAT ARE PERTINENT TO THE

Downtown Expressway Parking Garage - Elevator Replacement Submittals Richmond, VA

01300 - 5

WORK. Delete information which is not applicable to the Work by striking through or cross-hatching.

C. Drawings and schedules shall be checked and coordinated with the work of all trades

involved, before they are submitted for review and shall bear the CONTRACTOR's stamp of approval as evidence of such checking and coordination. Drawings or schedules submitted without this stamp of approval shall be returned to the CONTRACTOR for resubmission.

D. Each Shop Drawing shall have a blank area 3-1/2 inches by 3-1/2 inches, located

adjacent to the title block. The title block shall display the following:

1. Project Title and Number 2. Name of project building or structure 3. Number and title of the shop drawing 4. Date of shop drawing or revision 5. Name of contractor and subcontractor submitting drawing 6. Supplier/manufacturer. 7. Separate detailer when pertinent 8. Specification title and number 9. Specification section 10. Application Contract Drawing Number

E. If drawings show variations from Contract requirements because of standard shop

practice or for other reasons, the CONTRACTOR SHALL DESCRIBE SUCH VARIATIONS IN HIS LETTER OF TRANSMITTAL. The transmittal letter shall delineate compliance and exceptions taken to Contract Documents. If acceptable, proper adjustment in the Contract shall be implemented where appropriate. If the CONTRACTOR fails to describe such variations, he shall not be relieved of the responsibility for executing the work in accordance with the Contract, even though such drawings have been reviewed.

F. Data on materials and equipment include, without limitation, materials and

equipment lists, catalog data sheets, cuts, performance curves, diagrams, materials of construction and similar descriptive material. Materials and equipment lists shall give, for each item thereon, the name and location of the supplier or manufacturer, trade name, catalog reference, size, finish and all other pertinent data.

G. For all mechanical and electrical equipment furnished, the CONTRACTOR shall

provide a list including the equipment name, and address and telephone number of the manufacturer's representative and Service Company so that service and/or spare parts can be readily obtained.

H. All manufacturers or equipment suppliers who propose to furnish equipment or

products shall submit an installation list along with the required shop drawings. The

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 6

installation list shall include at least five installations where identical equipment has been installed and has been in operation for a period of at least one (1) year.

1.07 SAMPLES

A. The CONTRACTOR shall furnish for approval, samples required by the Contract Documents or requested by the OWNER. Samples shall be delivered as specified or directed. The CONTRACTOR shall prepay all shipping charges on samples. Materials or equipment for which samples are required shall not be used in work until approved.

B. Samples shall be sufficient size and quantity to clearly illustrate:

1. Functional characteristics of the product, with integrally related parts andattachment devices.

2. Full range of color, texture and pattern.3. A minimum of three samples of each item shall be submitted.

C. Each sample shall have a label indicating:

1. Name of project2. Name of CONTRACTOR and Subcontractor3. Material or Equipment Represented4. Place of Origin5. Name of Producer and Brand (if any)6. Location of Project

(Samples of finished materials shall have additional marking that will identify them under the finished schedules).

D. The CONTRACTOR shall prepare a transmittal letter in triplicate for each shipment of samples containing the information required in subparagraph 1.04I above. He shall enclose a copy of this letter with the shipment. Approval of a sample shall be only for the characteristics or use named in such approval and shall not be constructed to change or modify any Contract requirements.

1.08 MANUFACTURER'S LIST

A. Within 30 days after receipt of a Notice to Proceed, and before ordering any equipment or materials, the CONTRACTOR shall submit for approval a complete list of proposed manufacturers and fabricators for all materials and equipment to be used in this Contract. The purpose of this submittal is to predetermine the acceptability of proposed suppliers before issuance of purchase orders by the CONTRACTOR. Submission and acceptance of the manufacturers' list shall neither relieve the CONTRACTOR from submitting detailed shop drawings and product data for all materials and equipment nor shall it constitute prior acceptance of any

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 7

specific item of equipment prior to submittal of shop drawings. After submission and acceptance of the manufacturers' list, the CONTRACTOR shall not deviate from the named suppliers and manufacturers without written approval.

1.09 OPERATION and MAINTENANCE MANUALS FOR EQUIPMENT and PRODUCTS

A. Manual Preparation:

1. Manuals shall include operation and maintenance information on all systemsand items of equipment. The data shall consist of: catalogs, brochures,bulletins, charts, schedules, approved Shop Drawings corrected to as-builtconditions and assembly drawings and wiring diagrams describing location,operation, maintenance, lubrication, operating weight, lubrication charts andschedules showing manufacturers recommended lubricants for each rotatingor reciprocating unit, and other information necessary for the OWNER toestablish an effective operating maintenance program. The following datashall also be included:

a. Title page giving name and location of facility, Contract DrawingsNo(s). where shown and Specification Section where described.

b. Approved Shop Drawings of each piece of equipment.c. Manufacturer's cuts and dimension drawings of each piece of

equipment, and details of all replacement parts.d. Manufacturer's erection, operation and lubrication instructions for all

equipment and apparatus, and complete listing of nameplate data.e. Complete wiring diagrams of all individual pieces of equipment and

systems including one line diagrams, schematic or elementarydiagrams, and interconnection and terminal board identificationdiagrams.

f. The operating version of an operating program if the piece ofequipment requires a program to perform its function. A copy of theoperating program on CD and a written version of the program.

g. Complete parts list with parts assembly drawing (preferably byexploded view), names and addresses of spare parts suppliers,recommended list of spare parts to be kept "in stock" and sampleorder forms for ordering spare parts. Lead time required for orderingparts shall be estimated.

h. Instructions with easily understood schematics or diagrams fordisassembling and assembling the equipment for overhaul or repair.

2. All items listed above that are of a sheet size of 8-1/2 inches by 11 inches orcan be folded (no more than twice) to this size shall be bound in 4-inchmaximum loose-leaf three-ring d-post type binders with black plastic-coated

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 8

covers. The contents shall be fully indexed. PAGES SHALL BE LINEN REINFORCED ON BINDING EDGE.

3. Shop Drawings 24 inches by 36 inches in size shall be folded toapproximately 12 inches by 9 inches with drawing title box exposed alongeither edge. Shop Drawings descriptive of a single item of equipment shallbe grouped together. All Shop Drawings shall be placed in accordion-typefolders similar to File Pocket No. 74CG (9-1/2 inches x 14-3/4 inches) asmanufactured by the Cooke and Cobb Company, or equal, and fully indexedon the outside of the folders in a neat and uniform manner.

4. All Shop Drawings included in the binders and/or folders shall be thosecopies previously submitted for review and approval and shall bear theENGINEER's stamp of approval and comments as originally noted thereon.

B. Approval:

1. Subsequent to the approval and return of the final manual, theCONTRACTOR shall submit four complete sets of manuals.

2. Substantial Completion certification will positively not be undertaken untilapproved Operation and Maintenance Manuals have been submitted. Partialapprovals of the final manual will not be made.

3. Delivery of manufacturer's service (O&M) manuals and installationinstructions satisfactory to the OWNER are an essential part of the equipmentdelivery. Incomplete or inadequate manuals will be returned to theCONTRACTOR for correction and/or resubmission.

1.10 MANUFACTURER’S REPRESENTATIVE

A. The definition of "manufacturer's representative" shall be as follows: a representative from the manufacturer's plant, familiar with the actual problems of manufacturing, installing and operating the particular equipment or product and with enough years of experience in this field to determine the successful operation of the equipment or product. Sales representatives or agents of the manufacturers will not be acceptable.

B. As related to his obtaining the manufacturer's certificates, the CONTRACTOR shall include in this contract price the cost of furnishing competent and experienced manufacturer's representatives who shall represent the manufacturer on equipment and products furnished and installed under this Contract, to assist the CONTRACTOR to install, adjust, start up, and test the equipment and products in conformity with the Contract Documents. After the equipment and products have been operated through the trial period for each phase of construction and before being put into permanent service, such manufacturer's representatives shall make all

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 9

adjustments and tests required to provide that such equipment and products are in proper and satisfactory.

1.11 DESIGN CALCULATIONS

A. Design calculations shall be presented in a neat, legible manner and shall bear the stamp and signature of a Registered Professional ENGINEER, registered in the State of Virginia.

1.12 RECORD DRAWINGS

A. The CONTRACTOR will keep Record Drawings in accordance with Section 01720 – Project Record Documents.

PART 2 - PRODUCTS – (NOT USED)

PART 3 - EXECUTION – (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement SubmittalsRichmond, VA

01300 - 10

PAGE LEFT INTENTIONALLY BLANK

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-1

SECTION 01310

PROGRESS SCHEDULE PART 1 - GENERAL

1.01 FORM OF SCHEDULES

A. Prepare schedules in the form of critical path method (CPM) as described herein:

1. Provide separate CPM networks (subnetworks) of activities for eachprocess or facility.

2. Each subnetwork shall be assigned a code and separate activity numberingseries.

3. Interrelationships between subnetworks and any individual activities shallbe identified.

1.02 SCHEDULING RESPONSIBILITIES

A. The Critical Path Method type construction schedule will be used to monitor job progress and as a means to make monthly payments to the CONTRACTOR except for Stored Materials which will be made in accordance with Section 6.10 of the General Conditions of the Contract. The CONTRACTOR will be responsible for providing all information concerning the sequencing, logic, and durations of all activities as well as providing the initial CPM logic network diagram and tabular report data. Once the initial logic network diagram is accepted, the CONTRACTOR will be responsible for providing monthly update information on logic changes, percent complete, actual start and finish dates, and duration changes.

B. From the CONTRACTOR’s initial schedule submittal and from information received at the monthly schedule update meetings, computerized and dated tabular schedule reports, updated network diagrams, and bar charts will be produced which will be reviewed by the CONTRACTOR for accuracy and integrity. It shall at all times remain the CONTRACTOR’s responsibility to schedule and direct his forces in a manner that will allow for the completion of the Work within the Contract Times.

C. It should be clearly understood that the initial schedule and all update information must be provided by the CONTRACTOR, and that this information is a representation of the best efforts of the CONTRACTOR and his Subcontractors as to how they envision the Work to be accomplished. Similarly, all progress information to be provided by and through the CONTRACTOR must be an accurate representation of his, or his Subcontractor’s, or Supplier’s actual performance. The schedule shall at all times remain an accurate reflection of the CONTRACTOR’s actual or projected sequencing of work. Once accepted, adherence to the established CPM Schedule shall be obligatory upon the CONTRACTOR, and his

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-2

Subcontractors for the Work under this Contract. The OWNER may require the CONTRACTOR to revise the schedule if, in his judgment, the schedule does not accurately reflect the actual execution of the Work, or is in violation of any provision of the CPM scheduling requirements; and the CONTRACTOR shall revise the schedule as often as is necessary to bring the course of performance of the Work without additional cost to the OWNER.

1.03 SUBMITTALS

A. CPM Schedule:

1. Within five (5) business days after Notice to Proceed, submit the proposedCPM network diagrams, tabular reports for the entire Contract duration andinclude both procurement and construction activities. Sort the tabularreports by total float and activity number. They shall also contain apredecessor/successor resource loading report, and project calendar. Thislogic diagram shall be drawn as described herein and will be the subject ofa schedule review meeting with the CONTRACTOR, the OWNER, andOWNER’s representatives within 2 weeks of its submission. No paymentwill be made until an approved CPM Schedule is received from theCONTRACTOR.

2. If a review of the submitted CPM Schedule indicates a work plan which willnot complete the Work within the Contract Time stated in the Contract,revise the CPM Schedule as required and resubmit it until it is acceptable.Failure to submit an acceptable schedule may, at the OWNER’s solediscretion, be cause for the withholding of any partial payment(s) otherwisedue under the Contract.

3. Acceptance of the schedule shall not constitute a representation by theOWNER that the Work can be completed as shown on the schedule.

B. Submittals Schedule:

1. In addition to the above scheduling requirements, submit a complete anddetailed listing of anticipated submittals during the course of the Contract.Coordinate submittals with those of Subcontractors and Suppliers, andidentify each submittal as specified. Indicate the anticipated submissiondate for each submittal along with the date on which its return is anticipated.Review time for submittal shall be as provided for in Section 01300,SUBMITTALS. Durations shown for review shall be to share availablefloat for that path. Submittals and the review time, of which are on thecritical path, shall be clearly marked in red with the words “Critical Path”by the CONTRACTOR at the time of submission.

2. Submit the Submittal Schedule within 7 calendar days from the Notice toProceed. The Submittal Schedule will then be accepted or revised as

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-3

required, and the CONTRACTOR will incorporate the dates and review durations into his CPM Schedule.

1.04 NETWORK REQUIREMENTS

A. The network diagram shall show the interdependence of activities, and the sequence in which the Work is to be accomplished as planned by the CONTRACTOR. The basic concept of the network analysis diagram is to show how the start of a given activity is dependent on the completion of preceding activities, and its completion restricts the start of succeeding activities. A time scaled precedence format will be followed. The detailed network diagram will be time scaled showing a continuous flow from left to right.

B. The Schedule Activities shall be developed into three major groups:

1. Procurement Activities: Procurement Activities shall include at a minimum:

a. Permits.b. Easements.c. Submittal Items.d. Approval of Submittal Items.e. Fabrication and Delivery of Submittal Items.

Permits, easements, and fabrication and delivery items shall be tied logically to the correct construction activity in the overall CPM construction schedule.

2. Construction Activities: Construction activities will be physical workactivities that describe how the job will be constructed.

3. Testing, Startup, Training, and Closeout: CPM activities for this group shallinclude all Work to meet the requirements of individual Specificationsections and meet the requirements of Substantial and Final Completion.

C. Break the Work into activities, with durations of 1 to 20 working days each, except for non-construction activities (such as procurement of materials and delivery of equipment), and other activities which may require longer durations. To the extent feasible, activities related to a specific physical area of the project shall be grouped on the network for ease of understanding and simplification.

D. Each activity on the network shall have indicated for it the following:

1. A single duration, no longer than 20 days (i.e., the single best estimate ofthe expected elapsed time considering the scope of work involved in theactivity) expressed in working days. City holidays and weather delays shallbe included. One critical path shall be shown for the schedule.

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-4

2. An activity I.D. number will be assigned to each activity. The I.D. numberwill be numeric with a maximum of 10 digits.

3. A brief description of the activity will be included. If this description is notdefinitive, a separate listing of each activity and a descriptive narrative maybe required.

4. Each activity (except for procurement activities) shall be cost loaded toindicate the total estimated costs of the activity. No activity shall exceed$60,000 except if an equipment item.

5. Each construction activity shall be man-hour loaded with the estimatedman-hours to be expended on each activity.

E. When preparing the CPM construction schedule, consider all construction sequence and critical construction activities requirements.

F. Failure to include on a network any element of Work required for the performance of this Contract shall not excuse the CONTRACTOR from completing all Work required within the applicable Contract Time.

G. A CPM Schedule which shows a completion of any portion of the construction work (not including testing and start-up) prior to the Contract Time dates may be accepted but in no event shall be acceptable as a basis for a claim for delay against the OWNER by the CONTRACTOR

H. The schedule calendar shall be a 5-day work week with holidays corresponding to those observed by the City of Richmond’s Department of Public Utilities.

1.05 COST LOADING

A. Schedule of Values:

1. Each activity for Work-in-Place on the construction schedule shall beallocated a dollar value in accordance with Article NETWORKREQUIREMENTS, Subparagraph D.4 above. Each activity’s assigned costshall consist of labor, equipment, and materials costs, and a proratedcontribution to overhead and profit. The sum of the activities costs shall beequal to the total contract price. Activities not directly related toWork-in-Place including Stored Materials, preparation and submittal ofShop or Working Drawings, or other required submittal or equipment andmaterial procurement shall not be cost loaded. In submitting cost data theCONTRACTOR certifies that they are not unbalanced, and that the valueassigned to each activity represents the CONTRACTOR’s estimate of theactual costs of performing that activity. The listing of cost loaded CPMactivities will become the Schedule of Values, and will serve as the basisfor payments to the CONTRACTOR.

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-5

2. The accepted Schedule of Values shall represent a fair, reasonable, andequitable dollar cost allocation for each activity on the CONTRACTOR’sconstruction schedule.

B. Documentation: If it is determined that the cost data do not meet the requirements for a balanced bid breakdown, provide documentation substantiating any cost allocation on the cost data. Cost allocations shall be considered unbalanced if an activity on the construction schedule has been assigned a disproportionate allocation of direct costs, overhead, and profit.

1.06 PROGRESS OF THE WORK

A. The Work shall be started on the date indicated in the Notice to Proceed, and shall be executed with such progress as may be required to prevent delay to other contractors or to the general completion of the project. The Work shall be executed at such times and in or on such parts of the project, with such forces, material, and equipment, as to assure completion of the Work in the time established by the Contract. Additionally, schedule and direct the Work so that it provides an orderly progression of the Work to completion within the specified Contract Time.

B. Whenever it becomes apparent from the current monthly CPM Schedule update that delays to the critical path have resulted; and these delays are through no fault of the OWNER, or OWNER’s representatives, and hence, that the Contract completion date will not be met, take some or all of the following actions at no additional cost to the OWNER.

1. Increase construction manpower in such quantities and crafts as willsubstantially eliminate the backlog of Work.

2. Increase the number of working hours per shift; shifts per working day, ordays, per week; the amount of construction equipment; the forms forconcrete work; etc., or any combination of the foregoing to substantiallyeliminate the backlog of Work.

3. Schedule activities to achieve maximum practical concurrence ofaccomplishment of activities, and comply with the revised schedule.

C. Submit for review a written statement of the steps to be taken to remove, or arrest the delay to the schedule. If the CONTRACTOR fails to submit a written statement of the steps he intends to take or fails to take such steps as required by the Contract; the OWNER may direct the level of effort in manpower and trades, equipment, work schedule, and overtime to remove or arrest the delay to the critical path in the accepted schedule, and the CONTRACTOR shall promptly provide such level of effort at no additional cost to the OWNER. In addition, should schedule delays persist, the CONTRACTOR’s bond agent will be asked to attend meetings to update the schedule.

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-6

D. Failure of the CONTRACTOR to comply with the requirements of this provision shall subject him to, at the OWNER’s sole discretion, withholding, in partial or in total, payments otherwise due the CONTRACTOR for Work performed under this Contract. The CONTRACTOR agrees that any withholding of moneys is not a penalty for noncompliance, but is an assurance for the OWNER that funds will be available to implement these requirements should the CONTRACTOR fail to do so, since failure of the CONTRACTOR to comply with these requirements shall mean that the CONTRACTOR failed to execute the Work with such diligence as to ensure its completion within the time for completion.

1.07 SCHEDULE UPDATES

A. Meetings: The CPM Schedule shall be updated and copies distributed for review at the Progress Meeting or as required. Actual progress of the previous period and future activities will be reviewed. The duration of activities and their logical connections may be revised as needed. Decisions made at these meetings and agreed to by all parties are binding with the exception that no contract completion dates will be modified without formal written request and acceptance as specified herein. In either case, provide the following minimum information for each Update:

1. Actual start and finish dates for all completed activities.

2. Actual dates for all started but incomplete activities including remainingdurations and/or percent completes.

B. Withholding of Payments: Failure to provide specified updated information or failure to attend progress meetings may result in the withholding of progress payments.

1.08 CAUSES FOR EXTENSIONS OF TIME

A. The Contract completion time will be adjusted only for causes specified in this Contract. In the event the CONTRACTOR requests an extension of any contract completion date, he shall furnish justification and supporting evidence per the General Conditions, and provide a detailed CPM Schedule delay analysis based on the most current updated CPM Schedule. The OWNER will, after receipt of such justification and supporting evidence, make findings of fact and will advise the CONTRACTOR in writing thereof. If the OWNER finds that the CONTRACTOR is entitled to an extension of the Contract completion date under the provisions of the Contract, the determination as to the total number of days extensions shall be based upon the current accepted and updated CPM Schedule and on all data relevant to the extension. Such data shall be included in the next monthly updating of the schedule. The CONTRACTOR acknowledges and agrees that actual delays in activities which, according to the CPM schedule, do not affect any Contract completion date shown by the critical path in the network, do not have any effect on the Contract completion date or dates, and therefore will not be the basis for a change in Contract completion time.

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-7

1.09 ABNORMAL WEATHER

A. The Contract Period will be adjusted to account for unusually severe weather conditions which prevent or inhibit the CONTRACTOR's performance of the Work and lengthen the critical path indicated on the Schedule (such unusually severe weather conditions referred to herein as "Inclement Weather"). It is the intent of this provision to offset the impact of Inclement Weather with unusually favorable weather conditions which immediately precede and/or follow the occurrence of Inclement Weather.

B. The CONTRACTOR shall notify the OWNER in writing of the occurrence of Inclement Weather within two days after the onset of such Inclement Weather and shall describe in reasonable detail the type of Inclement Weather encountered by the CONTRACTOR and the Work thereby interfered with or interrupted.

C. This provision specifies the procedure for the determination of time extensions for unusually severe weather. The following conditions must be satisfied:

1. The weather experienced at the project site during the contract period must befound to be unusually severe, that is, more severe than the adverse weatheranticipated for the project location during any given month.

2. The unusually severe weather must actually cause a delay to the completionof the project. The delay must be beyond the control and without the fault ornegligence of the CONTRACTOR.

D. Schedule: The following Schedule of Monthly Anticipated Adverse Weather Delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The CONTRACTOR's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

SCHEDULE OF MONTHLY ANTICIPATED ADVERSE WEATHER DELAYS WORK DAYS BASED ON (5) DAY WORK WEEK

City of Richmond

JAN10

FEB 9

MAR9

APR6

MAY8

JUN7

JUL8

AUG7

SEP6

OCT5

NOV7

DEC9

E. Records: Upon acknowledgement of the Notice to Proceed and continuing throughout the contract, the CONTRACTOR will record daily, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the CONTRACTOR's scheduled work day.

F. Impacted Days: The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day in each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in the Schedule of Monthly Anticipated Adverse

Downtown Expressway Parking Garage - Elevator Replacement Progress Schedule Richmond, VA

01310-8

Weather Delays, above, convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather workdays, and issue a modification in accordance with Section 01153 – Change Order and Field Order Procedures.

1.10 APPROVAL REQUESTS

A. As the Work progresses and in the sequence indicated by the accepted progress schedule, the CONTRACTOR must submit a specific request, in writing, for each item of information or approval required of him by the Contract. These requests must be submitted sufficiently in advance of the date upon which the information or approval is actually required by the CONTRACTOR to allow for the time needed to act upon such submissions or resubmissions.

B. The CONTRACTOR shall not have any right to an extension of time on account of delays due to his failure to submit his requests for the required information or the required approval in accordance with these requirements.

1.11 ADJUSTMENT BY OWNER

A. It may be necessary for the Contract schedule and/or Contract Times to be adjusted by the OWNER due to the effects of job conditions, acts or omissions of other contractors not directly associated with this Contract, weather, technical difficulties, strikes, unavoidable delays on the part of the OWNER or his representatives, and other enforceable conditions which may indicate schedule adjustments and/or completion time extension. Under such conditions, the OWNER shall direct the CONTRACTOR to reschedule the Work to reflect the changed conditions, and the CONTRACTOR shall revise his schedule accordingly. Schedule extensions affecting the Contract Times shall be granted only by the OWNER in writing. It is specifically pointed out that the use of available total float in the CPM Schedule may be used by the OWNER and his representatives, as well as, by the CONTRACTOR.

B. Without obligation to extend the Contract Times or any intermediate completion dates set out in the CPM network, the OWNER may initiate changes to the Contract Work that absorb float time only. OWNER initiated changes that affect the critical path on the CPM network shall be the sole grounds for extending or shortening the Contract times. CONTRACTOR initiated changes that encroach on the float time, identified in the CPM network, may be accomplished with the OWNER’s concurrence. Such changes, however, shall give way to OWNER initiated changes competing for the same float time.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Construction Photographs Richmond, VA

01380 - 1

SECTION 01380

CONSTRUCTION PHOTOGRAPHS

PART 1 - GENERAL

1.01 DESCRIPTION

A. The CONTRACTOR shall have construction record photographs taken prior to start of the Work and periodically during the course of the Work.

1.02 DIGITAL PHOTOGRAPHY

A. All photographs shall be taken digitally. The minimum digital resolution shall be 8 mega-pixels. The CONTRACTOR shall provide to the OWNER a labeled CD or DVD on which the photographs are stored.

1.04 COSTS OF PHOTOGRAPHY

A. The Contractor shall pay costs for specified photography.

1. Parties requiring additional photography or prints will pay photographerdirectly.

PART 2 - PRODUCTS

2.01 PHOTOS

A. Adequately identify each photo using a numbered list. At a minimum, identify each photo in the list to include:

1. Photo file name2. Date photo was taken3. Description of vantage point, indicating location and direction (by compass

point)

PART 3 - EXECUTION

3.01 CONSTRUCTION PHOTOGRAPHS

A. General: Take photographs using the maximum range of depth of field, and that are in focus, to clearly show the Work. Photographs with blurry or out-of-focus areas will not be accepted.

B. Digital Images: Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-

Downtown Expressway Parking Garage - Elevator Replacement Construction Photographs Richmond, VA

01380 - 2

editing software.

1. Date and Time: Include date and time in file name for each image.

C. Preconstruction Photographs: Before starting construction, take photographs of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by OWNER.

D. Periodic Construction Photographs: Take photographs of each repair, provide a minimum of 2 views per repair, and 20 general construction progress photographs. Photographs shall be submitted with each application for payment. Select vantage points to show status of construction and progress since last photographs were taken.

E. Final Completion Construction Photographs: Take 20 photographs after date of Substantial Completion for submission as project record documents.

3.02 VIEWS REQUIRED

A. Photograph from locations to adequately illustrate condition of construction and state of progress.

3.03 DELIVERY OF PHOTOS, DATA

A. Deliver CDs to the OWNER to accompany each Application for Payment.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Quality ControlRichmond, VA

01400 - 1

SECTION 01400

QUALITY CONTROL

PART 1 - GENERAL

1.01 CODES AND RULES

A. General:

1. The CONTRACTOR shall comply with the City of Richmond BuildingCodes as well as the requirements of all permits obtained by the OWNER orthe CONTRACTOR.

2. The CONTRACTOR shall give all necessary notices, obtain all permits(except as otherwise noted herein) and pay all governmental taxes, fees, andother costs in connection with the work, file all necessary plans, prepare alldocuments and obtain all necessary approvals of all government departmentshaving jurisdiction, obtain all required Certificates of Inspection andApproval for the work and deliver same to the OWNER, except as otherwisenoted herein.

B. Included Items:

1. The CONTRACTOR shall include in his work, all labor, materials, services,apparatus, and drawings required to comply with all applicable laws,ordinances, rules and regulations, whether or not shown in the ContractDocuments.

C. Compliance:

1. All materials furnished and all work installed shall comply with the rules andregulations of the National Fire Protection Association, with all requirementsof local utility companies, with the recommendations of the fire insurancerating organization having jurisdiction, and with the requirements of allgovernmental departments having jurisdiction.

2. The CONTRACTOR shall arrange for inspection and approval by theappropriate City Inspectors and shall pay all costs of these services.

1.02 MATERIALS and WORKMANSHIP

A. All materials and equipment required for the work shall be new, unless otherwise specified, and of the best quality and especially adapted to the services required.

B. The CONTRACTOR shall furnish a Superintendent who shall be constantly in

Downtown Expressway Parking Garage - Elevator Replacement Quality ControlRichmond, VA

01400 - 2

charge of the installation of the work, together with all skilled workmen and labor required to unload, transfer, erect, connect up, adjust, start, operate, and test each system.

C. The CONTRACTOR shall locate and install all equipment which must be serviced, operated, or maintained in fully accessible positions. Minor deviations from Contract Documents may be made to allow for better accessibility, but changes of significant magnitude or changes involving extra cost shall not be made without approval of the OWNER.

D. In as much as Drawings are generally diagrammatic, the Drawings do not indicate all supports, hangers, fittings or offsets for piping, conduits, and duct work, or all valves, traps, access panels, or other specialties which the CONTRACTOR shall provide. All piping, conduit and duct work exposed to view shall be run parallel with the lines of the structure and as close to walls, columns, and ceilings as may be practical and consistent with proper grade and the maintenance of proper clearances for access to all parts requiring servicing. No piping, conduit, or duct work shall cross below the head of any window or door.

1.03 STANDARDS

A. Any reference to standards in the Contract Documents shall always imply the latest issue in effect including all amendments and errata at the time bids are taken, of said standards unless otherwise stated.

B. Abbreviations for various organizations which may be used in these Specifications are listed in Section 01092 – Reference Standards.

1.04 VERIFICATION OF DIMENSIONS

A. The CONTRACTOR shall be responsible for field verification of all dimensions of existing facilities and other items which are shown on the Contract Documents.

1.05 TESTS OF MATERIALS and EQUIPMENT

A. All material shall be subject to inspection, testing and approval before being incorporated in the work. Any work in which such materials are used without prior testing and approval shall be considered defective and unauthorized and will not be paid for. The CONTRACTOR shall perform such tests as required by the specifications in a timely fashion taking into account when the items will be incorporated in the work.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

Downtown Expressway Parking Garage - Elevator Replacement Quality ControlRichmond, VA

01400 - 3

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Quality ControlRichmond, VA

01400 - 4

PAGE LEFT INTENTIONALLY BLANK

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-1

SECTION 01500

CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

PART 1 - GENERAL

1.01 SUBMITTALS

A. Administrative Submittals:

1. Copies of permits and approvals for construction as required by Laws andRegulations and governing agencies.

2. The CONTRACTOR shall develop, maintain and submit a copy of theSite Safety Plan. Such Plan shall be in accordance with the City ofRichmond Health, Safety and Environmental Management Plan.

B. Shop Drawings:

1. Temporary Construction Submittals:

a. Staging area location to be determined by OWNER.

C. Traffic Control

1. Limited Parking is available on-site.

1.02 MOBILIZATION

A. Mobilization shall include, but not be limited to, these principal items:

1. Obtaining required permits.

2. Providing on-site sanitary facilities and potable water facilities asspecified and as required by Laws and Regulations, and governingagencies.

3. Arranging for and erection of the CONTRACTOR’s work and storageyard.

4. Posting OSHA required notices and establishing safety programs andprocedures.

5. Having the CONTRACTOR’s superintendent at the site full time.

1.03 PERMITS & FINES

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-2

A. The CONTRACTOR shall obtain and pay for all construction permits and licenses. OWNER shall assist the CONTRACTOR, when necessary, in obtaining such permits and licenses. The CONTRACTOR shall pay all governmental charges and inspection fees necessary for the prosecution of the Work

B. The CONTRACTOR shall be responsible for all fines and be responsible for addressing all work stop orders received by the General and his Sub-Contractors.

1.04 SAFETY AND PROTECTION

A. The OWNER and ENGINEER, under this Contract, are not responsible for the safety of the CONTRACTOR's employees.

B. The CONTRACTOR shall initiate, maintain, and supervise all safety precautions and programs in connection with the Work. Provide safe working conditions during the building of all parts of the work under the Contract and abide by all applicable OSHA regulations. Work under this Contract will be subject to inspection by OSHA and Virginia Department of Labor inspectors. Take all necessary precautions for the safety of, and provide the necessary protection to prevent damage, injury, or loss to:

1. All persons on the Work site or who may be affected by the Work.

2. All the Work and materials and equipment to be incorporated therein,whether in storage on or off the site.

3. Other property at the site or adjacent thereto, including trees, shrubs, lawns,walks, pavements, roadways, structures, utilities and Underground Facilitiesnot designated for removal, relocation or replacement in the course ofconstruction.

4. CONTRACTOR shall meet all safety requirements for working over andaround water.

5. CONTRACTOR shall restrict access and clearly mark all newly excavatedor otherwise hazardous areas when not working for more than 1 hour orovernight.

6. CONTRACTOR shall meet all safety requirements for working aroundHigh Voltage power facilities.

C. Safety Plan:

1. The CONTRACTOR shall make available the following items for review:OSHA-200 Log for the past five years, current safety program, trainingprogram, and experience with other related processes. Documented

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-3

evidence showing compliance with lockout/tagout, emergency response, and safe work practices are required.

2. Before any Work at the site is started, prepare written plan for Projectspecific safety precautions and programs, complete with respect toprocedures and actions that the CONTRACTOR, and all others, intend tofollow in order for CONTRACTOR and all others to comply with allapplicable Laws and Regulations, as well as specific site requirements.

3. Revise plan for safety precautions and programs at appropriate times toreflect changes in construction conditions, the Work, means, methods,techniques, sequences and procedures of construction.

D. Safety Representative: Designate a qualified and experienced safety representative at the site whose duties and responsibilities shall be the prevention of accidents and the maintaining and supervising of safety precautions and programs.

E. Hazard Communication Programs: Be responsible for coordinating any exchange of material safety data sheets or other hazard communication information required to be made available to or exchanged between or among employers at the site in accordance with Laws or Regulations.

F. Emergencies: In emergencies affecting the safety or protection of persons or the Work or property at the site or adjacent thereto, the CONTRACTOR, without special instruction or authorization from the OWNER, is obligated to act to prevent threatened damage, injury or loss. The CONTRACTOR shall give the OWNER prompt written notice if CONTRACTOR believes that any significant changes in the Work or variations from the Contract Documents have been caused thereby. If the OWNER determines that a change in the Contract Documents is required because of the action taken by the CONTRACTOR in response to such an emergency, a Work Change Directive or Change Order will be issued to document the consequences of such action.

1.05 SITE SECURITY

A. Provide the OWNER with an up-to-date list of employees, sub-contractors, and sub-contractor employees who will be coming to the site.

B. The CONTRACTOR shall notify the OWNER of work or deliveries a minimum of 24 hours prior to the start of work or material deliveries. For deliveries, provide description of material to be delivered, date and time, and Delivery Company with the notification.

C. The CONTRACTOR shall notify the OWNER if any suspicious activity is noted around or near the work area.

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-4

D. No private vehicles are allowed on site. All CONTRACTOR vehicles shall be identified with the CONTRACTOR’s name.

E. CONTRACTOR personnel are ONLY allowed in the associated work areas. No CONTRACTOR personnel should be present anywhere else on the site, except for transit from off-site parking to job site.

F. The CONTRACTOR will establish site security procedures for his equipment on the project site.

G. The OWNER will define areas out of bounds for contractor personnel.

1.06 SITE CONDITIONS

A. The CONTRACTOR shall be required to abate any contribution to air, water, or land pollution including such nuisances as odors, noise, surface or groundwater contamination, or other conditions resulting from the CONTRACTOR’s activities.

B. The CONTRACTOR shall comply with all traffic regulations. It shall be the CONTRACTOR responsibility to inspect the condition of the road and plan the Work to accommodate the road condition. The CONTRACTOR shall be responsible for repairing any damage to roadways and other surfaces harmed by the CONTRACTOR’s operations at no additional cost to the OWNER.

C. Examination: After Effective Date of the Agreement and before Work at site is started, CONTRACTOR and OWNER shall make thorough examination of pre-existing conditions including existing roads, structures, and other improvements in vicinity of the work to be performed. The pre-existing condition of surfaces and structures on or near the area of work shall be documented with photographic media.

1.07 PROTECTION OF WORK AND PROPERTY

A. Comply with the OWNER’s safety rules while on the OWNER’s property.

B. Keep OWNER informed of serious accidents on the site and related claims.

C. Use of Explosives: No blasting or use of explosives will be allowed on the site.

D. During the performance of the Work, CONTRACTOR is responsible for adapting its means, methods, techniques, sequences and procedures of construction to allow OWNER to maintain operation at the facility and consistent with applicable permit requirements, and Laws and Regulations. In performing such Work and in cooperating with the OWNER to maintain operations, it may be necessary for the CONTRACTOR to plan, design, and provide various temporary services, utilities,

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-5

connections, temporary piping and heating, access, and similar items which will be included within the Contract Price.

E. The CONTRACTOR shall, at his own cost and expense, protect from direct or indirect injury any and all water and gas mains, sewers or drains, conduits, service pipes, roadways, bridges, buildings and all other structures or property in the vicinity of this work, and along his route of travel, whether over or under the ground, and he shall assume all costs for repairing them and all other costs resulting from his damages to them.

1.08 WORKING LIMITS

A. The CONTRACTOR shall confine his operations within the areas of new work as indicated on the drawings. Since working space is limited, the CONTRACTOR is responsible for securing any off-site space or any additional area required for performing the work if required.

B. Access to the buildings and roads must be maintained at all times.

C. All areas which the CONTRACTOR uses shall be restored to a condition at least equal to that which existed at the start of the work.

PART 2 – PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.01 TEMPORARY UTILITIES

A. See Section 01510 – Temporary Utilities.

3.02 PROTECTION OF WORK AND PROPERTY

A. General:

1. Perform Work in a systematic manner that minimizes inconvenience toproperty owners and the public.

2. No residence or business shall be cut off from vehicular traffic unlessspecial arrangements have been made.

3. Maintain in continuous service all existing oil and gas pipelines,underground power, telephone or communication cable, water mains,irrigation lines, sewers, poles and overhead power, and all other utilitiesencountered along the line of work, unless other arrangements satisfactoryto owners of said utilities have been made.

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-6

4. Where completion of Work requires temporary or permanent removaland/or relocation of an existing utility, coordinate all activities with ownerof said utility and perform all work to their satisfaction.

5. Protect, shore, brace, support, and maintain structural elements beingrepaired, conduits, drains, and any other element affected by constructionoperations.

6. Keep fire hydrants and water control valves free from obstruction andavailable for use at all times.

7. In areas where the CONTRACTOR’s operations are adjacent to or near autility such as gas, telephone, television, electric power, water, sewer, orirrigation system and such operations may cause damage orinconvenience, suspend operations until arrangements necessary forprotection thereof have been made by the CONTRACTOR.

8. Notify property owners and utility offices which may be affected by theconstruction operation at least 2 days in advance.

9. Do not impair operation of existing sewer systems. Prevent constructionmaterial, pavement, concrete, earth, volatile and corrosive wastes, andother debris from entering sewers, pump stations, or other sewerstructures. Maintain original site drainage wherever possible.

B. Site Security: Temporary fencing or full time watchmen will not be specifically required as a part of the Contract, but the CONTRACTOR shall provide inspection of work area daily and shall take whatever measures are necessary to protect the safety of the public, workmen, and materials, and provide for the security of the construction site, both day and night.

C. Barricades and Lights:

1. Provide as necessary to prevent unauthorized entry to construction areas,and as required to ensure public safety and the safety ofCONTRACTOR’s employees, other employer’s employees, and otherswho may be affected by the Work.

2. Provide to protect existing facilities and adjacent properties from potentialdamage.

3. Locate to enable access by facility operators and property owners.

D. Signs and Equipment: Conform to requirements of the manual published by the City of Richmond and in accordance with the General Conditions.

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-7

E. Existing Structures: Where the CONTRACTOR contemplates removal of small structures such as mailboxes, signposts, and culverts that interfere with CONTRACTOR’s operations, obtain approval of property owner. Replace those removed in a condition equal to or better than original.

F. Waterways: Keep ditches, culverts, and natural drainages continuously free of construction materials and debris.

3.03 TEMPORARY CONTROLS

A. Air Pollution Control:

1. Minimize air pollution from construction operations.

2. Burning of waste materials, rubbish, or other debris will not be permittedon or adjacent to the site.

3. Conduct operations of carrying debris away in trucks to cause a minimumof dust. Give unpaved streets, roads, detours, or haul roads used in theconstruction area a dust-preventive treatment or periodically water toprevent dust. Strictly adhere to applicable environmental regulations fordust prevention.

B. Noise Control:

1. Provide acoustical barriers so noise emanating from tools or equipmentwill not exceed legal noise levels.

2. Comply with local noise control ordinance.

3. Noise Control Plans: Proposed plan to mitigate construction noise impactsand to comply with noise control ordinances including method ofconstruction, equipment to be used, and acoustical treatments.

4. Comply with appropriate sections of Section 01106.

C. Water Pollution Control:

1. Divert sanitary sewage and non-storm waste flow interfering withconstruction and requiring diversion to sanitary sewers. Do not cause orpermit action to occur which would cause an overflow to an existingwaterway.

2. Comply with procedures outlined in U.S. Environmental ProtectionAgency manuals entitled, “Guidelines for Erosion and SedimentationControl Planning” and “Implementation, Processes, Procedures, andMethods to Control Pollution Resulting from All Construction Activity,”

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-8

and “Erosion and Sediment Control-Surface Mining in Eastern United States.”

3. Do not dispose of volatile wastes such as mineral spirits, oil, chemicals, orpaint thinner in storm or sanitary drains. Disposal of wastes into streamsor waterways is prohibited. Provide acceptable containers for collectionand disposal of waste materials, debris, and rubbish.

D. Spill Prevention and Response Plan Requirements

1. Before mobilizing onsite, the CONTRACTOR shall prepare and submit aSpill Prevention and Response Plan (SP&RP). The Plan shall be projectspecific and designed to protect human health and the environment fromspills and releases of “hazardous materials,” including but not limited tochemicals, dangerous waste, problem waste, petroleum products, andhazardous substances.

2. The CONTRACTOR and all SUBCONTRACTORS will use this SP&RPfor the duration of the Project and will update the Plan throughout Projectconstruction so that the Plan reflects actual site conditions and practices.The CONTRACTOR will maintain an updated copy of this Plan on theProject site and all Project employees will have immediate access to thisPlan.

3. The CONTRACTOR will implement the spill prevention measuresidentified in this Plan before performing any of the following on theProject site:

a. Placing materials or equipment in staging or storage areas;b. Refueling, washing, or maintaining equipment;c. Stockpiling contaminated materials.

4. Spill Response Procedures: Provide a detailed description of allhazardous material present on the site and actions to take, and the order inwhich the actions should take place. At a minimum include:

a. Notification procedures – list names and phone numbers of thosewho must be notified. This will typically be the primary staffpersons at the facility (include a back-up person) fire departmentand agencies such as DCR.

b. Initial response procedures - actions to take immediately bywhomever discovers the spill. May include different actions basedon what has spilled.

c. Spill cleanup procedures - what happens to material used tocleanup the spill and who assures that the cleanup is complete.

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-9

d. Incident documentation - what reports are prepared and who willcomplete them.

5. Spill Prevention: Describe the steps that help prevent spills fromhappening and structures that contain or treat spills. Employee trainingand material handling procedures (e.g., fueling procedures) are examplesof steps that help prevent spills. Concrete containment structures for fueltanks and oil/water separators for road runoff are typical structures forcontaining or treating spills.

3.04 STORAGE YARDS AND BUILDINGS

A. Temporary Storage Yards: Construct temporary storage yards for storage of products that are not subject to damage by weather conditions.

B. Temporary Storage Buildings:

1. Provide environmental control systems that meet recommendations ofmanufacturers of equipment and materials stored.

2. Arrange or partition to provide security of contents and ready access forinspection and inventory.

3. Store combustible materials (paints, solvents, fuels, etc.) in a well-ventilated and remote building meeting safety standards.

3.05 SITE RESTORATION

A. Comply with the requirements in the Contract Documents. Submit a site restoration plan for approval.

B. Remove temporary storage buildings. Clean up the area and restore to existing site conditions to the satisfaction of the OWNER.

C. Completely remove temporary facilities when their use is no longer required.

D. Clean and repair damage caused by temporary installations or use of temporary facilities.

E. Restore permanent facilities used for temporary services to specified condition.

3.06 CLEANING DURING CONSTRUCTION

A. In accordance with the General Conditions, as may be specified in Specification sections, and as required herein.

Downtown Expressway Parking Garage - Elevator Replacement Construction Facilities and Temporary Controls Richmond, VA

01500-10

B. Provide approved containers for collection and disposal of waste materials, debris, and rubbish. At least at weekly intervals, dispose of such waste materials, debris, and rubbish offsite.

C. At least weekly, brush sweep the entry drive and roadways, and all other streets and walkways affected by Work and where adjacent to Work.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Temporary Facilities Richmond, VA

01510 - 1

SECTION 01510

TEMPORARY FACILITIES

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. Furnish, install and maintain temporary utilities required for construction and remove those temporary utilities upon completion of Work.

1.02 REQUIREMENTS OF REGULATORY AGENCIES

A. Comply with National Electric Code.

B. Comply with Federal, State, and local codes and regulations and with utility company requirements.

C. Comply with City and State Health Department Regulations.

PART 2 - PRODUCTS

2.01 MATERIALS

A. Materials may be new or used, but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

2.02 TEMPORARY ELECTRICITY AND LIGHTING

A. CONTRACTOR to provide temporary electricity and lighting as required. CONTRACTOR may coordinate use of 120V power at site with OWNER.

2.03 TEMPORARY HEAT and VENTILATION

A. To be provided and paid for by CONTRACTOR, if required.

2.04 TEMPORARY TELEPHONE SERVICE

A. To be provided and paid for by CONTRACTOR, if required.

B. Pay all costs for installation, maintenance and removal, and service charges.

2.05 TEMPORARY WATER

Downtown Expressway Parking Garage - Elevator Replacement Temporary Facilities Richmond, VA

01510 - 2

A. The OWNER shall not provide potable water to the Contractor for use during construction. The Contractor is responsible for all meters, backflow prevention devices, piping, valves and fittings required to convey water to construction site.

B Each and every connection by the CONTRACTOR to a fire hydrant for temporary potable water must comply with City of Richmond metering and backflow prevention requirements and CONTRACTOR to pay all fees.

2.06 TEMPORARY SANITARY FACILITIES

A. Approved sanitary convenience for the use of laborers and others employed on the work, properly secluded from public observation shall be constructed and maintained by the CONTRACTOR, in such manner and at such points shall be approved or directed and their use shall be strictly enforced. The collections in the same shall be disinfected and/or removed when and as required.

B. The CONTRACTOR shall provide and maintain, in a neat and sanitary condition, such accommodations for the use of his employees, as may be necessary to comply with the requirements and regulations of the Department of Health or of other bodies or tribunals having jurisdiction thereof. The CONTRACTOR shall commit no public nuisance.

2.07 TEMPORARY PUMPING and SITE DRAINAGE

A. Keep the site free from water at all times to permit continuous access and to prevent damage to the work.

2.08 DUST and MUD CONTROL

A. Take all necessary precautions to control dust and mud associated with the Work of this Contract, as required by the Virginia Erosion and Sediment Control Manual. In dry weather, spray dusty areas daily with water or provide other approved means in order to control dust. Take necessary steps to prevent the tracking of mud onto adjacent streets and highways.

2.09 CONTRACTOR'S STORAGE SHEDS

A. Provide storage shed(s) for the performance of the work and protection of materials and equipment.

1. Provide commercial grade chain link fence to prevent trespass by the publiconto the construction trailer and storage site.

2. Coordinate location of temporary fencing with property owner and OWNER.

PART 3 - EXECUTION

Downtown Expressway Parking Garage - Elevator Replacement Temporary Facilities Richmond, VA

01510 - 3

3.01 REMOVAL

A. Completely remove temporary materials and equipment when their use is no longer required.

B. Clean and repair damage caused by temporary installations or use of temporary

facilities. C. Restore permanent facilities used for temporary services to specified condition.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Temporary Facilities Richmond, VA

01510 - 4

PAGE LEFT INTENTIONALLY BLANK

Downtown Expressway Parking Garage - Elevator Replacement Product Requirements Richmond, VA

01600-1

SECTION 01600

PRODUCT REQUIREMENTS

PART 1 – GENERAL

1.01 SUMMARY

A. Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; and comparable products.

1.02 DEFINITIONS

A. Products: Items obtained for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name,including make or model number or other designation shown or listed inmanufacturer's published product literature, which is current as of date ofthe Contract Documents.

2. New Products: Items that have not previously been incorporated intoanother project or facility. Products salvaged or recycled from otherprojects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved throughsubmittal process to have the indicated qualities related to type, function,dimension, in-service performance, physical properties, appearance, andother characteristics that equal or exceed those of specified product.

B. Basis-of-Design Product Specification: A specification in which a specific manufacturer's product is named including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of additional manufacturers named in the specification.

1.03 SUBMITTALS

A. Comparable Product Requests: Submit request for consideration of each comparable product. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and/or Drawing numbers and titles.

Downtown Expressway Parking Garage - Elevator Replacement Product Requirements Richmond, VA

01600-2

1. Include data to indicate compliance with the requirements specified in"Comparable Products" Article.

B. Basis-of-Design Product List: Prepare a schedule showing specified products. Schedule shall show the following minimum information:

1. Related specification section number2. Product name, model number and similar designations3. Manufacturer’s and supplier’s name4. Installer’s name and certification that installer has previous experience

installing the product and/or has received training for installation of theproduct

5. Indicate whether on-site installation training is available and will besupplied by the manufacture

1.04 QUALITY ASSURANCE

A. Source Limitations: Provide products of the same kind from a single source.

B. Compatibility of Options: If CONTRACTOR is given option of selecting between two or more products for use on Project, select product compatible with products previously selected, even if previously selected products were also options.

1.05 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft and vandalism. Comply with manufacturer's written instructions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and toprevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holdingtime for items that are flammable, hazardous, easily damaged, or sensitiveto deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition inmanufacturer's original sealed container or other packaging system,complete with labels and instructions for handling, storing, unpacking,protecting, and installing.

4. Inspect products on delivery to determine compliance with the ContractDocuments and to determine that products are undamaged and properlyprotected.

C. Storage:

Downtown Expressway Parking Garage - Elevator Replacement Product Requirements Richmond, VA

01600-3

1. Store products to allow for inspection and measurement of quantity orcounting of units.

2. Store materials in a manner that will not endanger Project structure.3. Store products that are subject to damage by the elements, under cover in

a weathertight enclosure above ground, with ventilation adequate toprevent condensation.

4. Protect foam plastic from exposure to sunlight, except to extent necessaryfor period of installation and concealment.

5. Comply with product manufacturer's written instructions for temperature,humidity, ventilation, and weather-protection requirements for storage.

6. Protect stored products from damage and liquids from freezing.

PART 2 – PRODUCTS

2.01 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, are undamaged and, unless otherwise indicated, are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, andother items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products ornonstandard options are specified, provide standard products of types thathave been produced and used successfully in similar situations on otherprojects.

3. OWNER reserves the right to limit selection to products with warrantiesnot in conflict with requirements of the Contract Documents.

4. Descriptive, performance, and reference standard requirements in theSpecifications establish salient characteristics of products.

5. Or Equal: For products specified by name and accompanied by the term"or equal," or "or approved equal," or "or approved," comply withrequirements in "Comparable Products" Article to obtain approval for useof an unnamed product.

B. Product Selection Procedures:

1. Proprietary Specification Requirements: Where only a single product ormanufacturer is named, provide the product indicated. Comparableproducts or substitutions for CONTRACTOR's convenience will not beconsidered.

2. Semi-proprietary Specification Requirements: Where two or more productsor manufacturers are named, provide one of the products indicated.Comparable products or substitutions for CONTRACTOR's conveniencewill not be considered.

Downtown Expressway Parking Garage - Elevator Replacement Product Requirements Richmond, VA

01600-4

3. Non-proprietary Specification Requirements: When the ContractDocuments list products or manufacturers that are available and may beincorporated in the work, but do not restrict the CONTRACTOR to use ofthese products only, the CONTRACTOR may propose any availableproduct that complies with Contract requirements. Comply withrequirements in "Comparable Products" Article for consideration of anunnamed product.

4. Descriptive Specification Requirements: When the Contract Documentsdescribe a product or assembly, listing exact characteristics required, withor without use of a brand or trade name, provide a product or assembly thatprovides the characteristics and otherwise complies with Contractrequirements.

5. Performance Specification Requirements: When the Contract Documentsrequire compliance with performance requirements, provide products thatcomply with these requirements, and are recommended by the manufacturerfor the application indicated. General performance of a product is impliedwhere the product is specified for a specific application.

6. Compliance with Standards, Codes and Regulations: When the ContractDocuments only require compliance with an imposed code, standard orregulation, select a product that complies with the code, standard, orregulation specified.

C. Visual Matching Specification: Where Contract Documents require “match existing” or similar phrase, provide a product that complies with requirements and matches existing. OWNER’s decision will be final on whether a proposed product matches.

D. Visual Selection Specification: Where Contract Documents include the phrase "as selected from manufacturer's standard colors, patterns, textures…" or similar phrase, select a product that complies with performance requirements. OWNER will select color, gloss, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.02 COMPARABLE PRODUCTS

E. Conditions for Consideration: OWNER will consider CONTRACTOR's request for comparable product when the following conditions are satisfied. If the following conditions are not satisfied, OWNER may return requests without action, except to record noncompliance with these requirements:

1. Evidence that the proposed product does not require revisions to theContract Documents, that it is consistent with the Contract Documents andwill produce the indicated results, and that it is compatible with otherportions of the Work.

2. The request is directly related to an “or equal” clause or similar phrase.

Downtown Expressway Parking Garage - Elevator Replacement Product Requirements Richmond, VA

01600-5

3. Detailed comparison of significant qualities of proposed product withthose named in the Specifications. Significant qualities include attributessuch as performance, weight, size, durability, visual effect, and specificfeatures and requirements indicated.

4. Evidence that proposed product provides specified warranty.

F. Alternate Conditions for Consideration: In addition to the above noted conditions, the OWNER will consider CONTRACTOR's request for comparable product in the following situations.

1. The specified product or method of construction cannot be provided withinthe Contract time. The request will not be considered if the product ormethod cannot be provided as a result of failure to pursue the workpromptly or coordinate activities properly.

2. The specified product or method of construction cannot receive necessaryapproval by the Authority having Jurisdiction, and the requestedsubstitution can be approved.

3. A substantial advantage is offered the OWNER, in terms of cost, time,energy conservation or other considerations of merit, after deductingoffsetting responsibilities the OWNER may be required to bear. Additionalresponsibilities for the OWNER may include additional compensation to theENGINEER for redesign and evaluation services, increased cost of otherconstruction by the OWNER, and similar considerations.

4. The specified product or method of construction cannot be provided in amanner that is compatible with other materials, and where theCONTRACTOR certifies that the substitution will overcome theincompatibility.

5. The specified product or method of construction cannot be coordinated withother materials, and where the CONTRACTOR certifies that thesubstitution can be coordinated.

6. The specified product or method of construction cannot provide a warrantyrequired by the Contract documents and where the CONTRACTORcertifies that the substitution will provide the required warranty.

PART 3 – EXECUTION

3.01 INSPECTION

A. Inspect materials and equipment for signs of pitting, rust decay, or other deleterious effects of storage. Do not install material or equipment showing such effects. Remove damaged material or equipment from the site and expedite delivery of identical new material or equipment. Delays to the Work resulting from material or equipment damage that necessitates procurement of new products will be considered delays within CONTRACTOR’s control.

3.02 INSTALLATION

Downtown Expressway Parking Garage - Elevator Replacement Product Requirements Richmond, VA

01600-6

A. Comply with manufacturer’s instructions and recommendations for installation of products in the applications intended. Anchor each product securely in place, accurately located and aligned with other work.

1. Clean exposed surfaces and protect as necessary to ensure freedom fromdamage and deterioration at time of substantial completion.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Contract Closeout Richmond, VA

01700-1

SECTION 01700

CONTRACT CLOSEOUT

PART 1 - GENERAL

1.01 SUBMITTALS

A. Contract Closeout Submittals: Submit prior to application for final payment.

1. Project Record Documents.

2. Approved Shop Drawings and Samples.

3. Bonds, Warranties, and Service Agreements.

4. Consent of Surety to Final Payment.

5. Releases or Waivers of Liens and Claims.

6. Releases from Agreements.

7. Final Application for Payment.

8. Final Completion Construction Photographs

9. Spare Parts and Special Tools.

1.02 WARRANTIES AND BONDS

A. Description:

1. Compile specified warranties and bonds.

2. Co-execute submittals when so specified.

3. Review submittals to verify compliance with Contract Documents.

B. Submittal Requirements

1. Assemble warranties, bonds and service and maintenance contracts,executed by each of the respective manufacturers, suppliers, andsubcontractors.

2. Number of original signed copies required: Two each.

Downtown Expressway Parking Garage - Elevator Replacement Contract Closeout Richmond, VA

01700-2

3. Table of Contents: Neatly typed, in orderly sequence. Provide completeinformation for each item.

a. Product or work item covered.b. Firm, with name of principal, address and telephone number.c. Scope.d. Date of beginning of warranty, bond or service and maintenance

contract.e. Duration of warranty, bond or service maintenance contract.f. Provide information for OWNER’S personnel:

1) Proper procedure in case of failure.2) Instances which might affect the validity of warranty or

bond.

g. CONTRACTOR and Subcontractors name, street address andtelephone number of responsible principal.

C. Form of Submittals

1. Prepare in duplicate packets.

2. Format:

a. Size 8-1/2 inches x 11 inches, punch sheets for standard three postbinder. Fold larger sheets to fit into binders.

b. Cover: Identify each packet with typed or printed title"WARRANTIES AND BONDS". List:

1) Title of Project2) Name of CONTRACTOR

c. Binders: Commercial quality, three post binder, with durable andcleanable plastic covers and maximum post width of two inches.

D. Warranty Submittals Requirements

1. For all major pieces of equipment, the CONTRACTOR shall submit awarranty from the equipment manufacturer. The manufacturer's warrantyperiod shall be concurrent with the CONTRACTOR’S for two (2) years,unless otherwise specified, commencing at the time of SubstantialCompletion for the entire project.

2. The CONTRACTOR shall be responsible for obtaining certificates forequipment warranty for all major equipment specified under any Divisionthat lists for more than $1,000. The OWNER reserves the right to request

Downtown Expressway Parking Garage - Elevator Replacement Contract Closeout Richmond, VA

01700-3

warranties for equipment not classified as major. The CONTRACTOR shall still warrant equipment not considered to be "major" in the CONTRACTOR’S one year warranty period even though certificates of warranty may not be required.

3. In the event that the equipment manufacturer or supplier is unwilling toprovide a two year warranty commencing at the time of SubstantialCompletion, the CONTRACTOR shall obtain from the manufacturer, athree (3) year warranty commencing at the time of equipment delivery tothe job site. This three year warranty from the manufacturer shall notrelieve the CONTRACTOR of the two year warranty starting at the timeof Substantial Completion for the entire project.

1.03 RELEASES FROM AGREEMENTS

A. Furnish OWNER written releases from property owners or public agencies where side agreements or special easements have been made, or where CONTRACTOR’s operations have not been kept within the OWNER’s construction right-of-way.

B. In the event CONTRACTOR is unable to secure written releases, inform the OWNER of the reasons:

1. OWNER or its representatives will examine the site, and OWNER willdirect CONTRACTOR to complete Work that may be necessary to satisfyterms of the easement.

2. Should CONTRACTOR refuse to perform this Work, OWNER reservesthe right to have it done by separate contract and deduct the cost of samefrom the Contract Price, or require the CONTRACTOR to furnish asatisfactory Bond in a sum to cover legal claims for damages.

3. When OWNER is satisfied that Work has been completed in agreementwith the Contract Documents and terms of easements, the right is reservedto waive the requirement for written release if: (i) CONTRACTOR’sfailure to obtain such statement is due to the grantor’s refusal to sign, andthis refusal is not based upon any legitimate claims that CONTRACTORhas failed to fulfill the terms of the easement, or (ii) CONTRACTOR isunable to contact or has had undue hardship in contacting the grantor.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 COMPLETION

Downtown Expressway Parking Garage - Elevator Replacement Contract Closeout Richmond, VA

01700-4

A. Substantial Competition

1. When CONTRACTOR considers the entire Work ready for its intendeduse CONTRACTOR shall notify OWNER in writing that the entire Workis substantially complete (except for items specifically listed byCONTRACTOR as incomplete) and request a certificate of SubstantialCompletion. Within a reasonable time thereafter, OWNER andCONTRACTOR shall make an inspection of the Work to determine thestatus of completion.

2. If OWNER does not consider the Work substantially complete, theCONTRACTOR will be notified in writing giving the reasons therefore.

3. If OWNER considers the Work substantially complete, a Certificate ofSubstantial Completion will be issued that shall fix the date of SubstantialCompletion. There shall be attached to the certificate a tentative list of itemsto be completed or corrected before final payment.

4. OWNER shall have the right to exclude CONTRACTOR from the Workafter the date of Substantial Completion, but OWNER shall allowCONTRACTOR reasonable access to complete or correct items on thetentative list.

B. Partial Utilization:

1. Use by OWNER at OWNER’s option of any completed part of the Work,which: (i) has specifically been identified in the Contract Documents, or(ii) constitutes a separately functioning and usable part of the Work that canbe used by OWNER for its intended purpose without significant interferencewith CONTRACTOR’s performance of the remainder of the Work, may beaccomplished prior to Substantial Completion of all the Work subject to thefollowing:

a. OWNER at any time may request CONTRACTOR in writing topermit OWNER to use any such part of the Work which OWNERbelieves to be ready for its intended use. The OWNER shall operatethe equipment but the CONTRACTOR shall supply and provide allmaintenance, maintenance materials and equipment services untilsubstantial completion.

b. No occupancy or separate operation of part of the Work will beaccomplished prior to compliance with the requirements ofSection 01106 - Construction Scheduling, Coordination andSequencing, in respect of property insurance.

C. Final Inspection: Upon written notice from CONTRACTOR that the entire Work or an agreed portion thereof is complete, the OWNER will conduct a final inspection

Downtown Expressway Parking Garage - Elevator Replacement Contract Closeout Richmond, VA

01700-5

and will notify CONTRACTOR in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. CONTRACTOR shall immediately take such measures as are necessary to complete such work or remedy such deficiencies.

D. Final Application for Payment: After CONTRACTOR has completed all corrections following final inspection and delivered in accordance with the Contract Documents all maintenance and operating instructions, schedules, guarantees, Bonds, certificates or other evidence of insurance, certificates of inspection, marked-up record documents, and other documents, CONTRACTOR may make application for final payment following the procedure for progress payments. The final Application for Payment shall be accompanied (except as previously delivered) by: (i) all documentation called for in the Contract Documents, (ii) consent of the surety, if any, to final payment, and (iii) complete and legally effective releases or waivers (satisfactory to OWNER) of all Liens arising out of or filed in connection with the Work. In lieu of such releases or waivers of Liens and as approved by OWNER, CONTRACTOR may furnish receipts or releases in full and affidavit of CONTRACTOR that: (i) the releases and receipts include all labor, services, material and equipment for which a Lien could be filed, and (ii) all payrolls, material and equipment bills, and other indebtedness connected with the Work for which OWNER or OWNER’s property might in any way be responsible have been paid or otherwise satisfied. If any Subcontractor or Supplier fails to furnish such a release or receipt in full, CONTRACTOR may furnish a Bond or other collateral satisfactory to OWNER to indemnify OWNER against any Lien.

3.02 FINAL CLEANING

A. At completion of Work or of a part thereof and immediately prior to CONTRACTOR’s request for certificate of Substantial Completion; or if no certificate is issued, immediately prior to CONTRACTOR’s notice of completion, clean entire site or parts thereof, as applicable.

1. Leave the Work and adjacent areas affected in a cleaned conditionsatisfactory to the OWNER.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Contract Closeout Richmond, VA

01700-6

Downtown Expressway Parking Garage - Elevator Replacement Cleaning Up Richmond, VA

01710 - 1

SECTION 01710

CLEANING UP

PART 1 – GENERAL

1.01 GENERAL

A. During the construction duration, the Work and the adjacent areas affected thereby shall be kept cleaned up and all rubbish, surplus materials, and unneeded construction equipment shall be removed and all damage repaired so that the public and property owners will be inconvenienced as little as possible.

B. Where material or debris has washed or flowed into or been placed in existing watercourses, ditches, gutters, drains, pipes, structures, work done under this contract, or elsewhere during the course of the CONTRACTOR’s operations, such material or debris shall be entirely removed and satisfactorily disposed of during the progress of the Work. Ditches, channels, drains, pipes, structures and work, etc., shall, upon completion of the Work, be left in a clean and neat condition,

C. On or before the completion of the Work, the CONTRACTOR shall, unless otherwise directed and permitted in writing, tear down and remove all temporary buildings and structures built by him; shall remove all temporary works, tools and machinery or other construction equipment furnished by him; shall remove, acceptably disinfect, and cover all organic matter and material containing organic matter in, under and around privies, houses and other buildings used by him; shall remove all rubbish from any grounds which he has occupied; and shall leave the roads and all parts of the premises and adjacent property affected by his operations in a neat and satisfactory condition.

D. The CONTRACTOR shall thoroughly clean all materials and equipment installed by him and his subcontractors, and on completion of the Work shall deliver it undamaged and in fresh and new-appearing condition.

E. The CONTRACTOR shall restore or replace, when and as directed, any public or private property damaged by his work, equipment or employees to a condition at least equal to that existing immediately prior to the beginning of operations. To this end, the CONTRACTOR shall do all required street, alley, walk, and landscaping work. Suitable materials, equipment and methods shall be used for such restoration. The restoration of exiting property or structures shall be done as promptly as practicable as work progresses and shall not be left until the end of the Contract Period.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

Downtown Expressway Parking Garage - Elevator Replacement Cleaning Up Richmond, VA

01710 - 2

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Project Record Documents Richmond, VA

01720-1

SECTION 01720

PROJECT RECORD DOCUMENTS

PART 1 – GENERAL

1.01 SUMMARY

A. CONTRACTOR shall maintain at the site one record copy of:

1. Drawings.

2. Project Manual.

3. Addenda.

4. Change orders and other modifications to Contract.

5. Field orders, written instructions, or clarifications.

6. Approved submittals.

7. Field test records.

8. Construction photographs.

9. Associated permits.

10. Certificates of inspection and approvals.

11. Building Permits

1.02 SUBMITTALS

A. With Pay Requests

1. With each Pay Request provide a copy of the current “Red Line” recorddrawing set.

B. At Substantial Completion:

1. Deliver one marked up set of record documents to OWNER. The recorddocuments shall consist of: “Red Line” record drawings; and “Red Line”specifications.

C. Accompany submittals with transmittal letter containing following.

1. Date.

Downtown Expressway Parking Garage - Elevator Replacement Project Record Documents Richmond, VA

01720-2

2. Project title and number.

3. CONTRACTOR’S name and address.

4. Title of record document.

5. Signature of CONTRACTOR or authorized representative.

1.03 QUALITY ASSURANCE

A. Furnish qualified and experienced person, whose duty and responsibility shall be to maintain record documents.

B. Accuracy of Records:

1. Coordinate changes within record documents, making legible and accurateentries on each page of Specifications and each sheet of Drawings andother documents where such entry is required to show change.

2. Purpose of Project record documents is to document factual informationregarding aspects of Work, both concealed and visible, to enable futuremodification of Work to proceed without lengthy and expensive sitemeasurement, investigation, and examination.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION

3.01 MAINTENANCE OF DOCUMENTS and SAMPLES

A. Store documents and samples on-site apart from documents used for construction.

1. Provide files and racks for storage of documents.

2. Provide secure storage space for storage of samples.

B. Maintain documents in clean, dry, legible condition and in good order. Do not use record documents for construction purposes.

C. Make documents and samples available for inspection by ENGINEER or OWNER.

D. Failure to properly maintain record documents may be reason to delay a portion of progress payments until records comply with Contract Documents.

E. Make entries within 24 hours after receipt of information that a change in work has occurred.

Downtown Expressway Parking Garage - Elevator Replacement Project Record Documents Richmond, VA

01720-3

3.02 RECORD DOCUMENTS

A. Label each document “PROJECT RECORD” in neat, large printed letters.

B. Maintain a record set of “Red Line” Record Drawings and Specifications legibly annotated to show all changes made during construction.

1. Graphically depict changes by modifying or adding to plans, details,sections, elevations, or schedules.

2. Make changes on each sheet affected by changes.

C. Record information concurrently with construction progress.

1. Do not conceal Work until required information is recorded.

2. Record changes made by Written Amendment, Field Order, Change Orderor Work Directive Change.

D. Information to be recorded on Record Drawings:

1. Record field changes.

2. Provide details not on original Drawings.

3. Record size of equipment and location including connections.

E. Specifications:

1. Mark Specification sections: to show substantial variations in actual Workperformed in comparison with test of Specifications and modifications.Give particular attention to substitutions, selection of options and similarinformation on elements that are concealed or cannot otherwise be readilydiscerned later by direct observation.

2. Note related record drawing information and Product Data.

a. Manufacturer, trade name, and catalog model number of eachproduct and item of equipment actually installed.

F. Indication of Changes:

1. All changes shall be annotated in the color red.

2. Annotations to delete or remove items shall be identified in the color blue.

Downtown Expressway Parking Garage - Elevator Replacement Project Record Documents Richmond, VA

01720-4

3. Comments to the work or instructions to the work and not to be translatedto the final shall be annotated in the color green.

4. All changes shall be dated at time of entry

5. Call attention to entry by “cloud” drawn around area or areas affected.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Selective Demolition Richmond, VA

01732-1

SECTION 01732

SELECTIVE DEMOLITION

PART 1 - GENERAL

1.01 DESCRIPTION

A. This Section includes requirements for demolition and removal of designated por-tions of the building and structures, equipment and utilities.

1.02 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to OWNER.

C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

1.03 SUBMITTALS

A. Schedule of Selective Demolition Activities: Indicate detailed sequence of selective demolition and removal work, with starting and ending dates for each activity, interruption of utility services, and locations of temporary support.

B. Pre-demolition Photographs: Show existing conditions of adjoining construction and of the site, including finish surfaces that might be misconstrued as damage caused by selective demolition operations.

C. Landfill Records: The CONTRACTOR shall submit a receipt and acceptance of hazardous wastes (if any) by a landfill facility licensed to accept hazardous wastes.

1.04 QUALITY ASSURANCE

A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

Downtown Expressway Parking Garage - Elevator Replacement Selective Demolition Richmond, VA

01732-2

B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

C. Standards: Comply with ANSI A10.6 and NFPA 241.

D. Pre-demolition Conference: Conduct conference at Project site.

E. Before demolition begins, disconnect all mechanical and electrical services affected by the Work. Interconnecting piping and electrical services that are to remain in service either permanently or temporarily shall be capped, rerouted or reconnected in a manner that will not interfere with the operation of the existing facilities to remain and the demolition work.

1.05 PROJECT CONDITIONS

A. Conditions existing at time of inspection for bidding purpose will be maintained by OWNER as far as practical.

B. Notify OWNER of discrepancies between existing conditions and Contract Documents before proceeding with selective demolition.

C. Hazardous Materials: No hazardous materials are expected to be encountered in the Work.

1. If materials suspected of containing hazardous materials, other than notedabove, are encountered, do not disturb; immediately notify the OWNER.

D. Storage or sale of removed items or materials on-site is not permitted.

E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolitionoperations.

1.06 PROTECTION

A. Provide scaffolding, protective coverings, temporary walks, shoring and bracing during demolition to protect personnel, structures and equipment.

B. Provide adequate lighting at all times during demolition operations.

C. Provide and maintain barriers of cloth, plastic or wood to prevent debris and dust associated with the demolition work from leaving the demolition area.

Downtown Expressway Parking Garage - Elevator Replacement Selective Demolition Richmond, VA

01732-3

D. Provide warning signs as required, for personnel and the public.

1.07 EXTERIOR DUST CONTROL

A. To prevent unnecessary spread of dust during performance of exterior demolition work thoroughly moisten surfaces and debris as required to prevent dust being a nuisance to the public, neighbors and concurrent performance of other work on the site. Water for use in dust control shall be obtained from CONTRACTOR’s own source.

PART 2 - MATERIALS (NOT USED)

PART 3 - EXECUTION

3.01 EXAMINATION

A. Verify that utilities have been disconnected and capped.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to the OWNER.

D. Survey of Existing Conditions: Before demolition begins, the CONTRACTOR shall inspect existing structures, equipment and paving that will remain in-place within and adjacent to the demolition area for existing defects and damage.

E. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

3.02 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems: Maintain services/systems indicated to remain and protect them against damage during selective demolition operations.

B. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Arrange to shut off indicated utilities with utility companies.

2. If services/systems are required to be removed, relocated, or abandoned,before proceeding with selective demolition provide temporaryservices/systems that bypass area of selective demolition and that maintaincontinuity of services/systems to other parts of building.

Downtown Expressway Parking Garage - Elevator Replacement Selective Demolition Richmond, VA

01732-4

3. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, orplug and seal remaining portion of pipe or conduit after bypassing.

3.03 PREPARATION

A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

3.04 TEMPORARY SUPPORT/JACKING

A. The CONTRACTOR shall submit plans and design computations for review prior to the installation of any system. Plans and design computations shall bear the seal of a Professional Engineer licensed in the Commonwealth of Virginia.

3.05 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Neatly cut openings and holes plumb, square, and true to dimensionsrequired. Use cutting methods least likely to damage construction toremain or adjoining construction. Use hand tools or small power toolsdesigned for sawing or grinding, not hammering and chopping, tominimize disturbance of adjacent surfaces. Temporarily cover openings toremain.

2. Cut or drill from the exposed or finished side into concealed surfaces toavoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammablematerials. At concealed spaces, such as duct and pipe interiors, verifycondition and contents of hidden space before starting flame-cuttingoperations. Maintain fire watch and portable fire-suppression devicesduring flame-cutting operations.

4. Locate selective demolition equipment and remove debris and materials soas not to impose excessive loads on supporting walls, floors, or framing.

5. Dispose of demolished items and materials promptly and properly.

Downtown Expressway Parking Garage - Elevator Replacement Selective Demolition Richmond, VA

01732-5

B. Do not demolish building elements beyond what is indicated on Contract Documents without OWNER's approval.

C. Removed and Salvaged Items: Clean salvaged items.

D. Removed and Reinstalled Items: As required for construction.

E. Existing Items to Remain: Protect construction indicated to remain against damage, soiling and dust during selective demolition. When permitted by OWNER, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

F. Leave the work area at the end of each day broom clean. Remove waste, litter and debris from the work site and place in dumpster type containers.

G. As required for partially dismantled structures, provide protection from inclement weather for materials, equipment and personnel.

3.06 DISPOSAL OF DEMOLISHED MATERIALS

A. General: Except for items or materials indicated to be recycled, reused, salvaged, reinstalled, or otherwise indicated to remain OWNER's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.

B. Burning: Do not burn demolished materials.

C. Disposal: Transport demolished materials off OWNER's property and legally dispose of them.

3.07 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.08 FIELD QUALITY CONTROL

A. OWNER will visually inspect demolition and adjacent areas for completeness of demolition, damage that may have resulted from the demolition operation and for completeness of clean-up.

B. New construction shall not begin until the inspection by the OWNER is complet-ed and accepted.

Downtown Expressway Parking Garage - Elevator Replacement Selective Demolition Richmond, VA

01732-6

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 1

SECTION 142211

MODERNIZATION OF EXISTING TRACTION ELEVATORS

PART 1 - GENERAL

1.01 DESCRIPTION

A. Scope: Provide materials, labor, and services necessary for the complete and safe modernization of two (2) existing elevators as shown and specified including related building work and all inspection and permit fees. The intent of the project is to renovate elevator no. 2 first.

B. Scope of Work:

1. The Elevator Contractor will act as the Prime Contractor and shall bear theresponsibility of obtaining and coordinating all trades and subcontractorsrequired in performing the work as specified herein in order to provide a“Turn – Key” type project.

2. Provide elevator operation service during construction for miscellaneouslifts by contractors, inspections involving other trades and requiredjurisdictional inspections.

3. Scope of Work:

a. Provide new microprocessor based operational and control system.Provide new Variable Voltage Variable Frequency AC Solid StateMotor Drive units.

b. Provide new Hoist Machines and Deflector Sheaves.c. Provide new AC hoist motors.d. Provide new over speed governors and tail sheaves.e. Retain and refurbish car safeties and associated equipment.f. Provide unintended movement of car and ascending car overspeed

devices.g. Provide new floor landing optical or solid state type selector and

landing system.h. Provide new hoist and governor ropes with adjustable wedge

clamp shackles.i. Provide new cable and machine guards.j. Provide new car door operator, clutch, and door restrictor and

associated equipment.k. Provide new car door hanger, guides, cables, tracks, headers and

gate switch.l. Retain and reuse hoistway entrance frames and entrances sills.

Refinish as specified.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 2

m. Retain and reuse hoistway door panels.n. Retain and refurbish existing hoistway door panels and door tracks.

Provide new hoistway door equipment including but not limited torollers, interlocks, unlocking devices or rollers, hoistway doorretainers and door closers.

o. Provide new electronic door detector edges.p. Provide new car and counterweight roller guides.q. Retain and reuse counterweight frame and counterweights. Re-

balance elevators as specified.r. Retain and reuse car sling and platform.s. Provide new elevator car door panels and wrap or re-clad the

existing return panel and transom. Retain and reuse the elevatorcab shell. Provide new interior wall panels, interior finishes andceiling as specified. Provide new interior flooring.

t. Provide new hoistway wiring, conduit, junction boxes, limitswitches and traveling cables.

u. Provide new pit stop switches.v. Retain and reuse car and counterweight buffers.w. Provide new car and hall pushbutton stations and signal fixtures.x. Provide new car travel lanterns.y. Provide handicap features to comply with code.z. Provide fire service features to comply with code.aa. Adjust all safety and emergency control related devices and

provide code safety and balance tests. bb. Provide all required inspections and testing. Include required

elevator testing, fire alarm, sprinkler and emergency power operation. Provide independent third party elevator inspector.

cc. Provide parts cabinet and trash container in the machine room.

4. Related Required Building Work:

a. Verify that the electrical power is adequate to support newequipment. Furnish new conduit and wiring from the machineroom disconnect switch to the elevator controller. Provide anynew electrical service and wiring required to support installedelevators, machine room and/or building support equipment.Provide an adequate grounding conductor in the main linedisconnect switch.

b. Provide new machine room and pit lighting with diffuser lenses.Provide a minimum of 20 ftc. of lighting throughout the machineroom and 10 ftc of lighting throughout the elevator pits.

c. Provide GFCI electrical outlets in the elevator machine room andelevator pit.

d. Provide additional devices, modifications and programming to theexisting building fire alarm and smoke detector system and

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 3

associated devices for elevator recall. Provide required third zone for the elevator machine room. Provide modifications to the existing sprinkler system along with required additional piping, flow switches, valves and associated equipment.

e. Retain and reuse fused main line disconnect switch. Confirm and/or provide required grounding conductor in each switch.

f. Retain and reuse car lighting disconnect switch. g. Provide new machine room air conditioning unit(s) as required to

adequately support the equipment. h. Provide all required machine room and hoistway patching and

repairs required for the elevator system and associated spaces to pass inspection. Including all required patching and fire stopping of hoistway and machine room penetrations.

i. Provide complete cleaning of elevator hoistways, machine room and elevator pits.

j. Guarding and protecting of hoistways and equipment spaces during construction.

k. Provide painting of elevator machine room floors and walls and the elevator pit floor slabs.

l. Sand and paint the machine room entry door and frame in a similar color.

5. Removal and proper disposal of all material, trash and components as

herein specified and affected by this project. Contractor shall not use RMA’s trash and/or refuse containers.

1.02 REFERENCES

A. Applicable Codes:

1. American National Standard, Safety Code for Elevators and Escalators (ANSI/ASME A17.1).

2. International Building Code (IBC)

3. National Electric Code (NEC)

4. American National Standard Specification for Making Buildings and

Facilities Accessibility To and Usable By Physically Handicapped People (ANSI A117.1).

5. Commonwealth of Virginia modifications and Addendum to the ASME

Elevator Code. 6. City of Richmond Addendums, rules and regulations.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 4

7. Authorities having jurisdiction.

1.03 OPERATION PERFORMANCE

A. The control system shall provide smooth acceleration and deceleration with 1/4" leveling accuracy at all landings from no load to full rated load in the elevator. The floor-to-floor performance time under the above criteria shall be 14.0 seconds (floor-to-floor time is measured from the start of door close at one floor to 3/4 open at the next floor).

B. The door open time shall be 2.5 seconds from start of door open to fully open.

C. The speed of the elevator shall not vary +/- 5% under loading conditions.

D. The door close time shall be based on the Code requirements with a door delay feature. The door delay is the minimum acceptable time from notification that a car is answering a call (lantern and audible signal) until the doors of the car start to close. Time shall be calculated by the following equation:

1. T = D/(1.5ft/s)

2. T = Total time in seconds.

3. D = Distance from a point in the lobby 60 inches directly in front of thehall station to the centerline of the door opening.

4. For elevators with in car lanterns, T begins when the lantern is visiblefrom the vicinity of the hall call station and the audible signal is sounded.

E. Car Call: The minimum acceptable time for doors to remain fully open shall not be less than 5 seconds.

F. The speed of the elevator shall not vary +/- 5% under loading conditions.

G. Prior to final acceptance and prior to the termination of the maintenance period, the elevators shall be adjusted as required to meet these performance requirements.

1.04 REPLACEMENT PARTS AND TECHNICAL SUPPORT

A. Elevator component manufacturers and elevator contractor shall make available to The Owner or their representative all parts and technical support required to service and maintain the equipment installed.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 5

1. Elevator manufacturers and elevator contractor shall not have establishedcompany policies which would prevent the Owner or their representativefrom obtaining service parts on a timely basis.

2. In no event shall the elevator contractor or elevator manufacturer chargeprices for service parts to the Owner or their representative that are morethan that charged to any other customer of the elevator componentmanufacturers or contractor, for the same or substantially similar goods insimilar quantities.

3. The elevator contractor or elevator manufacturer shall maintainavailability of service parts to the Owner or their representative for aperiod which matches that of the reasonable life of the elevator equipment.

4. Provide elevator components from manufacturers that provide online andlive telephone elevator technical support to any and all elevatorinstallation, service, and maintenance contractors. Provide elevatorcomponents from manufacturers that guarantee accessibility to allreplacement and repair parts and components to any and all elevatorinstallation, service, and maintenance contractors. Elevator componentmanufacturers shall provide published price lists for all elevator parts andcomponents.

5. Equipment and component systems shall not employ any experimentaldevices or proprietary designs that could hamper and/or otherwise prohibitsubsequent maintenance repairs or adjustments by all qualifiedcontractors. Product support on-site or by phone and factory training shallbe available to any subsequent maintenance contractor chosen by theOwner.

1.05 SUBMITTALS

A. Provide a standard submittal register that identifies all items scheduled for submittal and required by this section. Arrange register by specification section and item number for project tracking and coordination. Contractor should provide a submittal package with a table of contents, tabs and/or notes that clearly identify the information provided, where it is located. If additional information or a re-submittal is required, contractor shall clearly identify what information has been modified and/or updated since the previous submission in order to expedite the review process and to encourage a collaborative and efficient process for all involved parties.

One copy of the submittal package and project specifications shall be maintained on site by each installation team.

B. Shop Drawings and Samples:

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 6

1. Shop Drawings: Provide complete shop drawings, to scale. Include layoutof pits, machine rooms, overhead requirements, power and heat data for allequipment, static and impact loads, reaction points and requiredclearances. Provide manufacturers standard catalog literature andbrochures of all components scheduled for use as part of this project.Provide cab and fixture drawings for review. Final layout of equipmentand components submitted shall be determined by the Owner.

If required in conjunction with the permitting process, drawings shall bear a Professional Engineer’s Stamp of a PE licensed in the jurisdiction of this project, in plans, sections and elevations and details of the machine room equipment, secondary level, car enclosures and hoistway entrances.

Include the following information:

a. Location of the traction machine, controller, Solid State MotorDrive unit, isolation transformer, choke coil, governor and othercomponents located in the machine room.

b. Existing car, frame and platform, counterweight, sheaves,supporting beams, guide rails, buffers and other componentslocated in the hoistway.

c. Weights of components.d. Reactions at support points.e. Maximum vertical and horizontal forces on guide rails.f. Top and bottom clearance and overtravel of car and counterweight.g. Location of fused, externally operable mainline disconnect switch

and shunt-trip circuit breaker (CB) without overcurrent trip, lightswitches, hands free communication, communication with elevatorcar device and feeder termination at controller.

h. Location of outlets for connection of traveling cables for car lightsand telephone in elevator machine room or hoistway.

i. Location of hoistway access switches.j. Names of manufacturer, type or style designation of all

components provided.k. Cuts or drawings showing details of hoistway access switches.l. Provide reference drawings for Owner approval showing details of

intended mounting brackets and mounting methods for all newdevices (tachometers, rope grippers, etc.) to be attached to existingelevator machines or other existing elevator equipment.

m. Provide the following drawings for approval:

1. Complete drawings of cab, showing details of constructionand/or alteration and the location of car equipment.

2. Complete drawings of signal and control fixtures, showingall switches, push buttons lights, signage and all other

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 7

components of each signal or control fixture and operating device.

3. Corridor elevations, showing the location of each corridorfixture in relation to the hoistway entrance frames and the finished floor.

4. Other drawings, as required, requested or specified withinthe document.

2. The manufacturer's name, type or style designation, and the informationlisted below shall be included on the shop drawings for each elevator. Inaddition, submit the manufacturer's catalog data for approval.

a. Solid state drive set and Watt emissionb. Hoist machine.c. Microprocessor based controller.d. Landing control device.e. Governor.f. Unintended Movement of Car Device, including mounting details.g. Power door operator assembly.h. Hoistway door interlocks and electrical contacts.i. Buffers including stroke, piston diameter, certified maximum and

minimum loads and maximum striking speeds.j. Firefighters' Emergency Operation.k. Isolation transformer, chokes, etc.l. Machine room monitors, diagnostic tools, service tools, data

recording and/or printing equipment.m. Signal fixtures, corridor and car operating stations, main floor

elevator lobby panel and/or firefighters' service panel.n. Door protective device.

3. Calculations:

a. Submit the following calculations and data signed and sealed bythe qualified professional engineer responsible for its preparation,as applicable to the equipment involved, within three (3) weeks ofNotice to Proceed:

1. Machine room equipment BTU output.2. Power supply data sheets, indicating equipment power

demand; main line fuse and auxiliary circuit breaker or fusesizes; and other pertinent electrical data, relative to theelevators.

4. Samples: Materials and finishes exposed to public view, 6" by 6" panels or12" lengths as applicable.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 8

5. No specifications, drawings, sketches, models, samples, tools, computerprograms, technical information or data, written, oral or otherwise,furnished by Contractor to The Owner as part of this proposed project orin contemplation hereof shall be considered by Seller to be confidential orproprietary. Technical documentation shall be submitted to The Owner todetermine equivalency. The system, method, or device shall be approvedfor the intended purpose by The Owner prior to being utilized.

6. Provide basic project schedule and billing schedule as directed.

7. Provide preventative maintenance schedule and “check-in/check-out”procedures. Submit sample service ticket and preventative maintenancerecords. Electronic maintenance records that do not provide sufficientdetail for The Owner’s use shall be modified as required to provide allnecessary information. On site records are required.

8. Key Personnel Names: Within 15 days of starting construction operations,submit a list of key personnel assignments, including superintendent andother personnel in attendance at Project site. Identify individuals and theirduties and responsibilities; list addresses and telephone numbers,including home and office telephone numbers. Provide names, addresses,and telephone numbers of individuals assigned as standbys in the absenceof individuals assigned to Project.

C. Equipment Brochure and Service Manuals:

1. Before acceptance of work, furnish three sets of manufacturer's equipmentbrochures and service manuals. Assemble manuals in chronological orderaccording to the specification alpha-numerical system. Provide in heavyduty three ring binders consisting of:

a. Equipment and components, descriptive literature.b. Performance data, model number.c. Installation instructions.d. Operating instructions and technical field adjustment manuals

including all fault codes and troubleshooting information.e. Maintenance and repair instructions.f. Spare parts lists.g. Lubrication instructions.h. Detailed, record and as-built layout drawings.i. Detailed, simplified, one line, wiring diagrams. Provide one

complete set per manual.j. Field test reports.

D. Machine Room Prints. Provide three complete sets of "as-built" field wiring and straight line wiring diagrams showing all electrical circuits in the hoistway as well

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 9

as the machine room. One set of these diagrams shall be laminated and/or protected and mounted in the elevator machine room as directed.

E. Provide one set of all submittals, shop drawings, wiring diagrams and manuals in electronic format for long term document storage.

F. Maintenance Control Program (MCP): Provide MCP specifically designed for the equipment included under this contract. Include any unique or product specific procedures or methods required to inspect or test the equipment. In addition, identify weekly, bi-weekly, monthly, quarterly, and annual maintenance procedures, including statutory and other required equipment tests.

1.06 QUALITY ASSURANCE

A. Quality and gauges of materials:

1. New, best of their respective kinds, free from defects.

2. Materials, equipment of similar application; same manufacturer, except asnoted.

3. Gauges as noted.

1.07 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Ship in original crated sections of a size to permit passage through available space.

B. Obtain approval and schedule delivery of material to meet The Owner's requirements.

C. Storage of equipment and materials shall be coordinated with The Owner.

1.08 SEQUENCING AND SCHEDULING

A. Schedule of operations:

1. Before commencing work, the Contractor shall submit a complete planand schedule of its proposed operations for approval. In preparation of itsplan and schedule, the Contractor shall make due allowance for andinclude the following:

a. Preparation of equipment and material submittals.b. Review of each submittals.c. Delivery lead times for equipment.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 10

2. The schedule may be in the form of a bar chart, graph or other approvedsystem by which are shown predicted starting and completion dates for thevarious work units or trades involved, together with such otherinformation relative to job progress and completion.

3. The schedule shall be revised, resubmitted and be kept reasonably current.

B. Interruptions of Building Elevator Service:

1. All work shall be done with a minimum amount of interference to theoperation of the building. The Contractor shall not interrupt the serviceswithout the expressed written permission of the Owner.

2. Each elevator shall be tested and accepted by the Owner prior to startingwork on another elevator. Punch list items must be rectified prior tobeginning work on another phase.

3. Work may begin after:

a. Detailed work schedule has been approved.b. A 30 day written notification of elevator shutdown has been given

to The Owner stating:

1. Date the elevator is to be removed from service.2. Date the elevator shall be returned to service.

1.09 WARRANTY

A. The elevators and associated equipment shall be free of defective material, imperfect work and faulty operation not due to ordinary wear and tear or improper use or care, for a period of 12 months from final acceptance of all elevator work. Defective work shall be repaired or replaced at no additional cost to the Owner.

1.10 MAINTENANCE SERVICE

A. Interim and Warranty Maintenance Service: Provide interim maintenance and testing of the elevator equipment from Award of Contract or Formal Notice to Proceed until the elevator equipment has been returned to service for public use. In conjunction with the equipment warranty, provide full maintenance on the elevators for a period of 12 months after final acceptance and turnover of the elevator and associated equipment for public use. Include all required costs associated with interim maintenance and warranty maintenance.

B. Maintenance Requirements:

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 11

a. On a monthly basis, regularly and systematically examine, adjust,lubricate, clean and, when conditions warrant, repair or replace thefollowing items and all other mechanical or electrical equipment:

1. Machine: Thrust bearings, lateral bearings, shaft bearings,drive sheave, and other machine components. Motorwindings, rotating elements, commutators, brushes, brushholders, bearings field coils, rotators, stator slip rings.

2. Brake pulley, brake coil, brake pins, brake contacts, liningsand other brake components.

3. Controller, selector, and dispatching equipment: Allcomponents including all relays, solid state components,resistors, condensers, transformers, contacts, leads,computer devices, selector switches, mechanical orelectrical driving equipment, coils, magnet frames, contactswitch assemblies, springs, solenoids, resistance grids,hoistway vanes, magnets and inductors.

4. Governor: Including governor sheave, shaft assemblygears, bearing contacts, jaws and pit tension assembly.

5. Sheaves: Including defector, secondary, compensatingsheaves, shafts, bearings, grease retainers, compensationsheave frame, contacts and hold down devices.

6. Hoistway door interlocks or locks and contacts, hoistwaydoor hangers, tracks, bottom door gibs, cams, rollers, andauxiliary door closing devices for power operated doors.Chains, tracks, cams, interlocks, sheaves for vertical bi-parting doors.

7. Hoistway limit switches, slowdown switches, levelingswitches and associated cams, vanes and electroniccomponents.

8. Guide shoes including rollers or replaceable guides.9. Automatic power operated door operators, door protective

devices, car door hangers, tracks and car door contacts.10. Traveling cables.11. Elevator control wiring in hoistway and machine room.12. Hoist cables, governor cables, compensating cables and

compensating chains, including adjustment of tension on allcables.

13. Car safety mechanism and load weighing equipment.14. Buffers.15. Fixture contacts, pushbuttons, key switches, locks, lamps

and sockets or button stations (car and hall), hall lanterns,position indicators (car and hall), direction indicators.

16. The guide rails shall be kept free of rust and dry.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 12

17. Examine all safety devices and governors, and conduct anannual no load test, and every fifth year perform a full load,full speed test of safety mechanism, overhead speedgovernors, car and counterweight buffers. The car balanceshall be checked and governor set. If required, thegovernor shall be recalibrated and sealed for propertripping speed. All tests shall be performed in accordancewith the provisions of the American National Standard,Safety Code for Elevators and Escalators (ANSI/ASMEA17.2), current edition.

18. Furnish lubricants compounded specifically for elevatorusage.

b. The Elevator Contractor shall not be required to install newattachments on the elevator whether or not recommended ordirected by insurance companies or by governmental authorities,nor make any replacements with parts of a different design. TheContractor shall not be required to make renewals or repairsnecessitated by reason of negligence or misuse of the equipment orby reason of cause beyond the Contractor's control.

c. The Elevator Contractor shall not be responsible for the followingitems of elevator equipment: car enclosure (including removablepanels, door panels, car gates, plenum chambers, hung ceilings,light diffusers, light tubes and bulbs, handrails, mirrors, andcarpets), hoistway enclosure, hoistway doors, frames and sills.

d. All preventative maintenance work is to be performed duringregular working hours of regular working days of the elevatorindustry. Emergency calls shall be responded to on twenty fourhour basis. Provide overtime service calls and repairs at noadditional charge.

e. The Contractor shall check the group dispatching systems andmake necessary tests to insure that all circuits and time settings areproperly adjusted, and that the system performs as designed andinstalled.

f. Elevator contractor shall provide 24 hour telephone monitoringservice as required at no additional cost during the duration of themaintenance contract.

g. Elevator contractor shall be responsible to provide an authorizedthird party elevator inspector to perform a periodic annualinspection of their elevator unit and notify the Owner thescheduled date for this inspection a minimum of 30 days inadvance.

h. The Contractor shall have a technician on site to respond to allservice calls in accordance with the following:

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 13

1. Within one (1) hour for all entrapments or critical shutdowns.

2. Within two (2) hours for all after hours service calls orentrapments.

3. For all after hours service calls, the Contractor shallconfirm receipt of the service call and notify the propertymanager within 15 minutes and provide an estimated timeof arrival (ETA) for the on - call service technician.

C. Maintenance Responsibility:

1. The Contractor shall keep the elevator maintained to operate at theoriginal contract speed, keeping the original performance times, includingacceleration and retardation as designed and installed by the manufacturer.The door operation shall be adjusted as required to maintain the originaldoor opening and door closing times, within legal limits.

2. The Owner reserves the right to make inspections and tests as and whendeemed advisable. If it is found that the elevator and associated equipmentare deficient either electrically or mechanically, the Contractor will benotified of these deficiencies in writing, and it shall be his responsibility tomake corrections within 30 days after his receipt of such notice. In theevent that the deficiencies have not been corrected within 30 days, theOwner may terminate the contract and employ a Contractor to make thecorrections at the original bidder's expense.

3. Approximately six months prior to the end of the contract term, the Ownerwill make a through maintenance inspection of all elevators covered underthe contract. At the conclusion of this inspection, the Owner shall give theContractor written notice of any deficiencies found. The Contractor shallbe responsible for correction of these deficiencies within 30 days afterreceipt of such notice.

D. Maintenance Service Records

1. The Contractor shall provide and keep current suitable records in themachine room for each elevator. Upon completion of maintenance, theContractor shall properly document the service or repair performed. Thisinformation shall be entered into a log by the contractor or employee. Theinformation shall include columnar line entries for date, employee name,employee position classification, time of arrival, time of departure, hoursworked and type and extent of work performed by elevator.

2. The Contractor shall prepare for approval a schedule listing preventivemaintenance to be performed for the entire year. Each month prior to

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 14

performance of any work, a proposed work schedule shall be submitted to the Owner.

3. At the end of each month an itemized list of work performed shall besubmitted to the Owner. The list, which will include regular andemergency callbacks will include the following information:

a. Date and time of call.b. Building location and ID number.c. Description of shutdown and corrective measures taken.d. Class of work. i.e., routine maintenance or call back service.e. Time elevator returned to service.f. Note on list all extra charges to contract.

4. All records shall become the property of the Owner and turned over to TheOwner upon request.

E. Diagnostic Tools and Spare Parts: At the completion of the work as specified, the Contractor shall provide items listed. The items shall become the Owner's property.

1. One complete set of all diagnostic tools and equipment required for thecomplete maintenance of all aspects of the control and dispatch systemand solid-state motor drive units. The diagnostic system shall be anintegral part of the controller and provide user-friendly interactionbetween the serviceman and the controls. All such systems shall be freefrom secret codes and decaying circuits that must be periodicallyreprogrammed by the manufacturer. Provide all necessary technical fieldadjustment manuals.

2. A list of vendors for all parts used in the installation.

1.11 ELECTRIC SERVICE

A. Power: 460 volts, 3 phase, 60 hertz. Elevator Contractor to verify and certify voltage.

B. Lighting: 120 volts, 1 phase, 60 hertz.

1.12 PROTECTION OF PERSONS AND PROPERTY

A. The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the work.

B. The Contractor shall take reasonable precautions for the safety of, and shall provide reasonable protection to prevent damage, injury or loss to:

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 15

1. Employees on the Work and other persons who may be affected thereby.

2. The work, materials, and equipment to be incorporated therein, whether instorage on or off the site, under the care, custody or control of theContractor or any of his Subcontractors or Sub-Subcontractors.

C. The Contractor shall comply with all applicable laws, ordinances, rules, regulations and lawful orders of public authority having jurisdiction for the safety of persons, property or to protect them from damage, injury or loss. He shall erect and maintain, as required by existing conditions and progress of the work, all partitions for safety and protection, including posting danger signs, and other warnings against hazards, promulgating safety regulations and notifying the Owner and users of adjacent utilities.

D. The Contractor shall designate a responsible member of his organization at the site whose duty shall be the prevention of accidents. This person shall be the Contractor's superintendent unless otherwise designated in writing by the Contractor to the Owner.

E. In any emergency affecting the safety of persons or property, the Contractor shall act, at his discretion, to prevent threatened damages, injury or loss.

F. The Contractor shall schedule a pre-construction meeting with the Tenant, the Owner and Engineers to introduce the project superintendent perform a pre-construction inspection of all common areas, including restroom and areas not affected by the renovation work and discuss project specifics including schedules. Any pre-existing damages or deficiencies will be noted at that time and copies provided to all parties. Upon completion of work the Contractor shall return these areas in the same condition in which they were originally viewed. Any damages occurring during construction shall be corrected and the cost of such corrections is the responsibility of the Contractor.

G. The Owner, Property Manager and Consultant reserve the right to shut the job or a portion of the job down immediately if any danger to the building or an existing Tenant is noted. The Owner reserves the right to require certain portions of the project which create objectionable noise or odors (i.e. polymix, oil-based paint, etc.) be performed after hours, dependent on the sensitivity of existing Tenants adjacent to, above, or below space being constructed.

H. Contractor is responsible for cleanup of their work area and trash including the removal of waste foods, milk and soft drink containers, from the building on a daily basis. The building’s trash receptacles and compactors are not available for use by the Contractor and at no time is the Contractor to place any construction debris in the building’s trash compactor or dumpster without prior approval of the Owner. The Contractor shall obtain the Owner’s prior approval before locating

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 16

any dumpster on the site. Trash and debris must be removed off-site. If ceiling tile or fire stopping is disturbed, they must be replaced immediately.

I. Public spaces, corridor, elevators, bathrooms, lobby, etc. must be cleaned immediately after use. Construction debris or materials found in public areas will be removed at the Contractor's expense.

J. Upon completion of the work, space is to be thoroughly cleaned prior to being turned over to the Owner. This includes vacuuming of carpets, washing of all interior walls, windows and windowsills. Additionally, cleaning and wiping of all existing hardware and doors of dust and speckles of paint, cleaning of all restrooms that Contractor has used. The Owner reserves the right to bill contractor for any cost incurred to clean up debris left by Contractor.

K. The Contractor shall ensure that their employees and Subcontractors protect the building and roof system against damage resulting from the performance of work and transportation of materials to or from the premises. Transportation of all materials in or out of the building shall not cut, mark or otherwise damage any area of the building.

L. The Contractor shall provide whatever protection is required to adequately protect carpets, stonework, wall coverings, floors, roof systems, stairwells and elevators at the premises from damage. If carpeting is to remain, it is to be protected by heavy plastic cover or removed for future reinstallation upon completion of the work. Plastic, masonite or carpet runners should be used from the elevators to the mechanical rooms. The Contractor shall also provide heavy plastic screening or a temporary wall of suitable appearance, as required by the Owner, to screen in and protect adjacent areas from dust or debris.

M. During the course of the work the Contractor shall be responsible, to the extent necessitated by such work, for the safety of the building its occupants and their workmen and shall protect the same as required by good construction practice and law.

N. Contractor will be responsible for the behavior of its employees and Subcontractors employees. Harassment and/or "teasing" of tenants, occupants, guests and general public are specifically prohibited.

1.13 NOISE AND VIBRATION

Any noise, vibration or deficiencies due to faulty equipment or workmanship shall be corrected immediately without additional charge.

1.14 PERMITS AND INSPECTION FEES

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 17

The Contractor shall obtain without cost to the Owner, all permits and certificates as required for the necessary elevator and associated work.

1.15 SIGNAGE

Provide "Temporarily Out Of Service For Renovation" signs and post at all elevator entrances.

PART 2 - PRODUCTS

2.01 MANUFACTURERS

A. Product of individuals, firms or corporations regularly engaged in rehabilitating elevators comparable with this contract and in satisfactory operation for a period of not less than five years.

B. Qualified Bidders:

1. Priority Elevator Company

2. ThyssenKrupp Elevator Company

3. Otis Elevator Company

4. Southern Elevator Company

2.02 OUTLINE OF EQUIPMENT

A. Elevator number(s): 1

1. Elevator use: Passenger

2. Manufacturer: Otis Elevator Company

3. Contract load, in pounds: 2,000

4. Contract speed: 350 FPM

5. Travel distance: Field verify.

6. Number of stops: Eight (8) – G3, G2, G1, 1, 2, 3, 4, 5

7. Number of openings: Eight (8), front

8. Machine location: Overhead

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 18

9. Machine type: Geared Traction

10. Type of control: VVVF Solid State Drive

11. Operation, Presently: Simplex After Modernization: Simplex

12. Car and hoistway door size: 3' - 0" wide by 6' - 8" high

13. Car and hoistway door type: Single Speed Side Slide

14. Car and hoistway door operation: power

a. Medium -speed, linear type

15. Hoistway entrance: Refinish Existing.

16. Cab enclosure: Renovate as specified.

17. Door-reversal device: Provide new as specified.

18. Car operating panel: Provide new as specified.

19. Car position indicator (in car): Provide new as specified.

20. Hall call stations: Provide new as specified.

21. Lobby position indicator: Provide new as specified.

22. Car Travel Lantern: Provide new as specified.

23. Fire Control Panel: Incorporate in lobby hall station.

24. Communication system: ADA Compliant, Hands Free Type.

B. Elevator number(s): 2

1. Elevator use: Passenger

2. Manufacturer: Otis Elevator Company

3. Contract load, in pounds: 2,000

4. Contract speed: 350 FPM

5. Travel distance: Field verify.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 19

6. Number of stops: Seven (7) – G3, G2, 1, 2, 3, 4, 5 7. Number of openings: Seven (7), front 8. Machine location: Overhead

9. Machine type: Geared Traction

10. Type of control: VVVF Solid State Drive

11. Operation, Presently: Simplex

After Modernization: Simplex

12. Car and hoistway door size: 3' - 0" wide by 6' - 8" high 13. Car and hoistway door type: Single Speed Side Slide

14. Car and hoistway door operation: power

a. Medium -speed, linear type

15. Hoistway entrance: Refinish Existing.

16. Cab enclosure: Renovate as specified.

17. Door-reversal device: Provide new as specified.

18. Car operating panel: Provide new as specified.

19. Car position indicator (in car): Provide new as specified.

20. Hall call stations: Provide new as specified.

21. Lobby position indicator: Provide new as specified.

22. Car Travel Lantern: Provide new as specified.

23. Fire Control Panel: Incorporate in lobby hall station.

24. Communication system: ADA Compliant, Hands Free Type.

2.03 MACHINE ROOM EQUIPMENT

A. Provide equipment to fit existing space and project conditions.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 20

B. Hoist Machine. Provide new worm geared traction type with brake, worm, gear and sheave mounted on a common bedplate. Provide ball or roller type bearings arranged to eliminate backlash. Provide vibration isolation, of an approved type, which shall effectively prevent transmission of machine vibration to the building structure. Provide new deflector sheaves.

C. Machine Beams: Existing machine beams, anchors and floor slabs may be reused in place. Contractor shall provide any necessary blocking or support beams as required to complete the renovation or to facilitate the installation of necessary safety devices or support equipment.

D. Hoist Ropes: Provide new traction steel type, designed for hoist machine manufacturer’s requirements and fasten with adjustable wedge shackles. Hoist ropes shall be properly tensioned with tensioning device. Submit documentation upon turnover of elevator.

E. Emergency Brake: Provide means to prevent ascending car overspeed and unintended car movement per Code.

1. Acceptable emergency brake devices:

a. BODE Rope Brakeb. Hollister-Whitney Rope Gripperc. Draka Rope Brake

2. Mount the auxiliary brake on suitable structural steel supports. Provide adrawing showing the supports, stamped by Professional Engineerverifying the adequacy of the support provided

3. Provide control circuits to enable the device to function as required byCode.

F. Hoist Motor: Provide new Alternating Current type, rated NEMA "D" and Type "F" insulation or better and designed to develop high starting torque with low starting current.

G. Deflector: Provide steel machined and grooved for diameter of ropes and supported by an "A Frame" type mounting. Provide cable guards designed to withstand shock and prevent ropes from leaving their proper grooves. All bearings are to be shielded or sealed.

H. Motor Drive Unit: Provide new variable voltage, variable frequency (VVVF) drive.

1. Provide elevator with new solid state motor drives, providing variablevoltage and regenerative power controls by means of devices that can

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 21

control current without moving parts and that use static switching by means of solid state devices. Provide an isolation transformer.

2. The static control system shall be arranged that during acceleration andretardation periods, graduated voltage shall be applied to the armature ofthe elevator hoisting motor by the use Variable Voltage VariableFrequency (VVVF). The system shall accomplish this gradual voltagechange automatically and without interruption of power. The system shallprovide smooth and practically uniform acceleration and retardation whichshall be obtained electrically and independent of the car load. The controlshall be equipped with overcurrent, overload and overvoltage protectivedevices to automatically limit current drawn by hoisting motor to thatrequired for specific duty to prevent damage to hoisting motor and VVVFDrive Unit.

3. Provide electronic feedback sensing circuits which shall cause the electricpower to be removed from the motor armature and brake, unless there issufficient current to prevent overspeeding of the motor.

4. The motor drive unit shall be provided with high speed fuses connected inseries to protect each unit against current surges.

5. Fans or other devices shall be provided to extract heat emitted by the driveunit as required for proper operation.

6. Motor drive unit components shall be installed in a NEMA 1 enclosurelocated in the control cabinet. All components shall be conservativelyrated to provide a life of not less than 100,000 hours. All electricconnections between the electric feeder, the motor drive unit, and theelevator hoist motor shall be made with suitable connectors or to suitableterminal blocks.

7. Power to the car lighting and car fan or blower shall not be interrupted if amotor drive unit is shut down by an overload, blown fuse, or otherabnormal conditions.

8. Elevator manufacturers shall provide necessary isolation transformers,reactors, capacitors, filters and other devices to limit the overall DistortionFactors at the point connection of the elevator converter feeder to theelectrical distribution system to a maximum of 3 percent. This shallinclude compensation for the following:

a. Harmonic Distortionb. Power Factorc. Flickerd. Line Notching

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 22

9. All control wiring shall be isolated from power wiring to minimize

inductive coupling.

10. Submit for approval, applicable brochures and technical information as required for solid state equipment (motor drives, system processors, etc.)

11. The use of solid state equipment shall not interfere with any of the

Owner's sensitive electronic equipment. In addition, provide adequate sound suppression equipment acceptable to the Owner to control airborne and/or structure-borne noises and vibration.

12. Inform the Owner of any possible or foreseeable problems associated with

noise, vibrations, electrical interferences, etc., as related to solid state equipment.

I. Controller and Selector: Disconnect and completely remove the existing

controller and selector for the elevator and replace with new controller, installed and connected in place, all complete as hereinafter specified. The system shall utilize isolated solid state input/output interface for the majority of signals. It is understood, where required by Code, relays contacts are to be utilized for safety and power control considerations. The use of relays as input or output devices are not acceptable.

1. All controller components shall be designed to provide the required

operation as herein specified.

2. All assemblies, power supplies, switches, relays and other items shall be securely mounted on a substantial, self-supporting steel frame of angles or channels and shall be totally enclosed with covers in a floor mounted cabinet. Equipment shall not be mounted on any of the covers.

3. All controller switches and relays shall be magnet operated with contacts

of design and material to insure maximum conductivity, long life and reliable operation without overheating or excessive wear and shall provide a wiping action to prevent sticking due to fusion.

4. Where time delay relays are used in the circuits, they shall be of an

acceptable design that is reliable and consistent, such as condenser timing or electronic timing circuits. No dashpot time relays shall be used.

5. Each device on all panels shall be properly identified by name, letter, or

standard symbol which shall be neatly stencil painted (or otherwise marked), in an indelible and legible manner, on device or panel. Identification markings shall be coordinated with identical markings used

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 23

on wiring diagrams. The ampere rating shall be marked adjacent to all fuse holders. All spare conductors shall be neatly formed, laced and identified.

6. Safety switch shall cut off current, automatically apply brake and stop car

upon current failure or upon operation of any electrical safety device.

J. Dispatch System Operation:

1. Provide a solid state microprocessor dispatch system to provide operation as follows:

Provide a solid-state microprocessor system which shall provide for continuously changing operations in various traffic situations, and efficiently handle the varying passenger traffic demands. Control system shall be non-proprietary in all respects. Technical support shall be available to the Owner without cost, regardless of who is providing ongoing maintenance support. System shall incorporate on-board diagnostics as part of the standard control design. Use of portable or removal diagnostic equipment is unacceptable.

No specifications, drawings, sketches, models, samples, tools, computer programs, technical information or data, written, oral or otherwise, furnished by Contractor to the Owner as part of this proposed project or in contemplation hereof shall be considered by Seller to be confidential or proprietary.

Technical documentation shall be submitted to the Owner’s Engineering

and Elevator staff to determine equivalency. The system, method, or device shall be approved for the intended purpose by the Owner prior to being utilized.

a. Acceptable control system providers:

1. GAL Galaxy, GAL Manufacturing Corporation, Bronx, NY 2. Motion Control Engineering (MCE), Rancho Cordova, CA

3. Virginia Controls, Richmond, VA 4. Smart Rise Elevator, Sacramento, CA b. Simplex Selective Collective:

1. Momentary pressure of car or hall button, other than landing at which car is parked, shall automatically start the car and dispatch the car to the corresponding floor for which that call was registered. If a call is registered at the floor when the car is idle, the doors shall automatically

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 24

open. 2. When the direction of travel has been established, the car

shall answer all calls corresponding to the direction oftravel and shall not reverse direction until all car and hallcalls, in that direction, have been answered.

3. Calls registered for the opposite direction of car travel shallremain registered and shall be answered after car hascompleted its calls in the direction of travel.

4. If no car buttons are pressed, and car starts up in responseto several down calls, the car shall answer highest downcall first and then reverse to collect other down calls.

5. The car shall remain at the arrival floor for an adjustableinterval to permit passenger transfer. Doors shall close aftera predetermined interval after opening unless closing isinterrupted by car door reversal device or door open buttonin car.

6. Lighting and Fan Control: Provide automatic shut off ofinterior car lighting and fan system when the elevator is notin use.

c. Independent Service: Provide controls to remove elevator fromnormal operation and provide control of the elevator from carbuttons only. Car shall travel at contract speed and shall notrespond to corridor calls.

d. Car Top Operation: Provide top of car operating controls anddevices in accordance with ASME Code requirements.

e. Fire Service Emergency Recall Operation: Provide operation andequipment per Code requirements. Elevator Contractor shallprovide relays, wiring, and terminal strips to receive signals fromsmoke detectors, sprinklers, or fire alarm systems. Provide thirdcircuit that will enable the car station fire symbol to flash andsound alarm if the elevator machine room or hoistway smokedetectors have activated.

f. Provide automatic shut down of elevator car lighting and fan whenthe elevator is not in use. Provide features in accordance withASME A17.1, rule 2.14.7.2.2.

g. There shall not be any special codes or devices introduced into thesystems that are not available to the Owner.

h. Any special components manufactured by the Contractor shall bemade available to the Owner for a period of not less than 20 years.

i. Load Weighing: Provide automatic load weighing device set atapproximately 80% of full load. The device when activated shallcause the elevator to bypass corridor calls and shall initiatedispatch of car at main terminal prior to elapse of normaldispatching interval. Provide adjustable setting from 50 - 80% offull load. Cross head deflection type is unacceptable.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 25

K. Components: The microprocessor based group dispatcher and communications network shall be designed and installed to meet the following requirements:

1. Provisions shall be made in the dispatch computer so that the elevatorsystem dispatching can be modified at a future time. The system shall beso designed that the modifications to the software shall be all that isrequired to revise the dispatching. It shall be further designed so that therewill be minimum shut down time should changes be required.

2. The latching circuitry (outputs) shall be fail-safe design which turns off allthe outputs in the event of a processor malfunction.

3. Power Supplies: All power supplies utilized shall be UL recognized. Theyshall all have short-circuit protection.

4. Frame: All assemblies, power supplies, chassis, switches, relays, and otheritems shall be securely mounted on a substantial, self-supporting steelframe. The equipment shall be completely enclosed with covers. Noequipment is to be mounted on the covers.

5. Wiring: All factory wiring shall utilize UL labeled copper wires. Allwiring interconnections shall be neatly routed. All wiring connections tostuds of terminals shall be made by means of solder or solderless lugs.

6. Marking: All components shall be clearly and permanently identifiedadjacent to each device and shall be identical to the wiring diagram.

7. Provide extender boards when computing devices are used inside acomputer chassis so as to have access to the printed circuit cards utilized.

8. Electronic time delay devices shall use stable capacitor or crystals as thetime base.

9. Terminals shall be provided for a future connection to a computerized testsystem. An adequate number of terminals shall be provided so as tomonitor all of the various functions of the elevators. These shall includebut not be limited to car positions, running functions up and down, dooropen and close, hall and car calls, door protective devices, safety circuits,elevator recapture, etc.

L. Printed Circuits and Related Hardware:

1. All printed circuit boards shall be fabricated with G10 glass epoxymaterial with a minimum equivalent one ounce copper.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 26

2. All printed circuitry shall be coated with tin-lead.

3. All double sided boards shall have plated-through holes.

4. All printed circuit board edge connections shall be gold plated.

5. All solid state hardware and devices shall have built-in noise suppressiondevices which provide a high level of noise immunity.

6. Power supplies shall have noise suppression devices provided.

7. All inputs from external devices (such as pushbuttons) and all outputs toexternal devices (such as indicators, relays) shall be isolated with opto-isolation modules.

8. The use of relays as input/output devices is not acceptable.

9. A separate regulated power supply shall be used for each computerchassis.

10. The control circuits shall be so designed so that one side of the powersupply is grounded to provide for testing.

11. Under no circumstances shall the safety circuits be affected by accidentalgrounding of any part of the system.

12. In the event of a power failure or interruption, the system shall bedesigned so that it will start properly when power is returned.

13. System memory shall be provided so that data shall not be lost in the eventof a power failure or disturbance.

14. The Elevator Contractor shall provide any dedicated power supplyrequired to the machine room Group Controller.

15. Required power will be furnished from existing power panels. ElevatorContractor shall coordinate location and requirements with The Owner.

Note: Conduits or other wiring shall not be exposed in the lobby or other occupied parts of the building.

M. Speed Regulation:

1. The rate of acceleration and deceleration of the cars under any conditionof load shall be as nearly constant as is possible with the method of control

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 27

specified and employed and shall be independent of the operating devices in the car.

2. The acceleration, deceleration and velocity shall all be computercontrolled. The detection of velocity and position of the car shall be fedinto the computer. The computer shall compare this information with thevelocity profile and adjust as necessary to insure a fast and smoothacceleration and deceleration curve. The maximumacceleration/deceleration shall be 4 feet/sec2 and shall change uniformly.

3. Entire elevator equipment including hoisting machines and controllersshall operate without irregularities and quietly by use of high gradematerials, first class workmanship and adjustments.

N. Overspeed Governor and Tension Sheave:

1. Governor: Provide new. Properly calibrate and test in accordance withCode requirements.

2. Tension Sheave: Provide new.

3. Governor Rope: Provide new.

4. Adjustment: The governor shall be accurately adjusted and full-load, full-speed tested to operate within limits specified by code. All adjustable partsshall be sealed. Provide each unit with a test tag.

5. Switches: The operation of the governor over-speed switch shall open aswitch disconnecting the power from the elevator before a safetymechanism has tripped. A second switch shall be provided to reduce thespeed of the elevator prior to the actuation of the governor.

6. Marking Plate: A metal marking plate shall be securely fastened to thegovernor and marked with governor tripping speed, pull through data andrope size and construction.

O. Templates, Forms, Sleeves and Guards: All templates, forms and sleeves for providing necessary openings in the concrete slab over the hoistway shall be provided as part of this work. Sleeves for conduit and other small holes shall project 4" above the concrete slab. Provide 6" steel angle guards around cable or duct slots.

P. Machine Blocking Beams: Provide steel beams, channels and bearing plates to support or attach machine, governor, sheaves and rope hitches. Include any required clip angles, tie rods, etcetera as may be required.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 28

2.04 HOISTWAY EQUIPMENT

A. Guide Rails and Brackets:

1. Retain existing car and counterweight guide rail brackets.

2. Thoroughly clean all guide rails of grease, oil and other foreignsubstances, file and remove all rough edges and surfaces. Realign, andtighten bracket bolts and guide rail clips for smooth and quiet operation ofcar and counterweight. Clean, wire brush and paint all guide rails andbrackets.

3. Guide rail loads shall be shown on Elevator Contractor's drawings. Includesafety application, running, loading and seismic loads.

B. Buffers:

1. Retain and reuse buffers. Provide struts, braces or mounting componentswhere needed. Clean, wire brush and paint.

2. Load reactions, on buffer application, shall be indicated on the ElevatorContractor's drawings.

C. Counterweight and Roller Guides:

1. Retain and reuse existing counterweight frame and counterweights.Provide necessary retainer rods and tie down assemblies. Thecounterweight shall weigh the same as the complete elevator car plusapproximately 40% of the specified capacity load. Filler weights shall beheld securely in alignment with tie rods passing through holes in theweights and frame members. Rods shall be equipped with double locknutssecured by cotter pins at each end.

2. Roller Guides: Provide new roller type with three or more sound-deadening rollers per guide with adjustable springs or other method tomaintain rail contact. Provide retainer plates top and bottom.

3. Counterweight Guard: Retain existing. Clean, wire brush and paint.

D. Normal and Final Terminal Stopping Devices:

1. Normal Device Operation: Normal terminal stopping devices shall beprovided new, consisting of electrical contacts located on top of theelevator car which are operated by cams mounted at the top and bottom ofthe hoistway or shall consist of electrical contacts located at the top andbottom of the hoistway and operated by a cam or cams located on top of

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 29

the elevator car. This device shall automatically bring the elevator to a stop at the top and bottom terminal landings with any load up to and including 125% of the contract capacity from any speed attained in normal operation. This device shall operate independently of any other operating devices and shall continue to function until the final limit switch operates.

2. Final Device Operation: Final limit switches located at top and bottom ofthe hoistway shall be arranged to automatically stop the car andcounterweight within the predetermined overtravel limits, independentlyof all other devices.

3. Rollers: Switches shall be equipped with engaging arms provided withpolyurethane-tired rollers for engagement with cams.

E. Electrical Wiring: Terminal connections for all conductors at equipment panels, center of hoistway and on elevator car shall be made with terminal blocks or studs having identifying numbers. All conductor connections shall be made with terminal eyelets of the solderless type.

1. Wiring, Duct and Conduit:

a. Stranded or Solid copper wiring throughout.b. All required new wiring from the controller, selector, dispatch

panels, etc., and from the separate outlet for car lights andtelephone to all elevator equipment, shall be furnished installed aspart of this work. Wiring shall be properly insulated and have aflame-retarding and moisture-resistant outer cover shall be run ingalvanized metallic conduit or duct, using strain boxes as required.Interlock wiring from the hoistway riser to each new interlock shallbe fire resistant NEC Code type SF-2 or equivalent.

c. Conduits or other wiring shall not be exposed in the lobby or otheroccupied parts of the building.

2. General Wiring Requirements:

Provide a completely properly operating system for each item of electricalequipment required to complete the project. Installations shall be inaccord with manufacturer’s instructions, the best industry standards andpractices and the contract documents.

a. Install all wiring and conduit in accordance with National ElectricCode requirements and industry standards and practices.

b. Rout wire and cable as required to meet project conditions.c. Make installation in a neat, finished and safe manner, according to

the latest published NECA Standard of Installation undercompetent supervision.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 30

d. Neatly train and secure wiring inside boxes, equipment, and panelboards.

e. Install systems, materials, and equipment level and plumb, paralleland perpendicular to other building systems and components. Asmuch as practical, connect equipment for ease of disconnecting,with minimum of interference with other installations.

f. Riser cables shall have cable supports as required by Code.g. Identify all wire and cable as required. Identify each conductor

with its circuit number and/or designation.h. Connect all conductors. Torque each terminal connection to the

manufacturers recommended torque value.i. Support conductors installed in vertical raceways at intervals not

exceeding those distances indicated in the National Electric Code.Support conductors in pull boxes with strain reducing supportsprovided for the size and number of conductors in the raceway.Do not splice conductors in pull boxes used for vertical cablesupport.

j. Control, communications or signal conductors shall be installed inseparate raceway systems from branch circuit or feeder raceways.

k. Where mounting heights are not detailed or dimensioned, installsystems, materials, and equipment to provide maximum headroompossible.

l. Properly ground and bond all electrical conduits and raceways inaccordance with National Electric Code requirements.

3. Electrical Cables:

a. Traveling Cables shall be provided new. Pad cab platforms wherecables rub. Provide hardware cloth or antichaf protection for fulltraveling cable movement height between cables and all hoistwaydivider beams.

b. The car operating panel, position indicator, and other electricequipment on the car shall be connected with the controller bymeans of flexible cable run from the bottom of the car to anapproved outlet in the hoistway.

c. Cables shall have a flame-retarding and moisture-resistant outercover, and shall be suitably suspended to relieve strain inindividual conductors.

d. Each traveling cable shall contain 10% spare wires and in anyevent not less than five spare wires. At least one travel cable shallcontain a minimum of eight (8) shielded twisted pair and one (1)coaxial cable for The Owner’s use.

e. Provide a separate junction box on the cartop and at the controllerthat is clearly identified as “Security and Communication Wiringand Coaxial Cable”. All unused conductors shall be neatly coiledand stored within the junction boxes.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 31

f. Provide on the cartop a separate 120 volt power source andjunction box for use with elevator security cameras.

F. Pit Stop Switch: Provide new red colored stop switches to meet Code requirements.

2.05 DOOR AND ENTRANCE EQUIPMENT

A. General: Retain existing entrance frames and entrance sills. All retained entrance frames shall be sanded, re-finished and painted with an electro-static finish in a color selected by The Owner.

B. Frames: Retain existing entrance frames. All retained entrance frames shall be sanded, re-finished and painted with an electro-static finish in a color selected by The Owner.

C. Provide handicapped designations at a height of 60" above the floor.

1. The plaques shall have light colored numerals on a black background. Thenumeral color is to be eggshell finish (11 to 19 degree gloss).

2. Designations shall be flush with inconspicuous mechanical mounting.

D. Sills: Retain existing.

E. Struts: Retain existing.

F. Header: Retain existing.

G. Hanger Cover Plates: Retain existing. Replace any missing cover plates with new removable, full length No. 14 gauge steel. Covers shall be made in sections for convenient access to hangers.

H. Fascia: Retain existing. Clean and paint as specified.

I. Toe Guard: Retain existing. Clean and paint as specified.

J. Dust Cover: Retain existing. Clean and paint as specified.

K. Door Bumpers: Provide new on vertical struts at top and bottom.

L. Door Panels: Retain and reuse existing. Door panels shall be provided with two new removable, non-metallic gibs, located at the leading and trailing edge of the door panel. Landing designations shall be permanently applied to the inside of each door panel. Provide door retainers.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 32

M. Sight guards: Retain and reuse existing.

N. Hangers: Provide new hanger rollers designed to meet the manufacturer’s original requirements. Rollers shall utilize sealed ball or roller bearings.

O. Tracks: Retain and reuse existing. Clean, wire brush and paint. Bottom of track shall be in contact with upthrust roller.

P. Closer: Provide new spring or spirator type.

Q. Door Protection: Provide new.

1. Electronic Entrance Protection: Provide car door with full heightprotective device which projects infrared light beams across the entireopening and beyond the leading edge of the door panels. Doors shallautomatically return to open position if any light beam is blocked orobstructed. Doors shall not be required to contact an obstruction to initiatethe reopening process. Provide onboard automatic diagnostic circuits.

2. Differential Door Timing Feature: Provide adjustable timers to vary thetime that the doors remain open in response to a car or hall call. The doorsshall remain open for one second in response to a car call and five to eightseconds for a hall call. This time shall be reduced to ½ second if the lightray is interrupted. The doors shall remain open as long as passengers arecrossing the threshold.

3. Nudging: When doors are prevented from closing for 20 seconds due tofailure of the light ray or obstruction, the doors shall close at reducedspeed and a buzzer shall sound. Provide all required fire service operatingfeatures.

R. Door Operator: Provide a GAL of Canada, VFE2500-HL linear type operator or similar, equipped with a closed loop continuous feedback controller. Door operator shall automatically open and close the car and hoistway doors. The doors shall be capable of smooth and quiet operation without slam or shock.

1. Opening speed shall not be less than 2.0 f.p.s. with reversal in no morethan 2-1/2 inches.

2. Hoistway doors shall be automatically closed by an auxiliary closingdevice if car leaves the landing zone.

3. Provide restricted car door opening and clutches in accordance with coderequirements.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 33

S. Hoistway Door Interlocks: Provide new. All hoistway doors shall be equipped with a new electro mechanical interlock, designed to prevent the starting of the car until the doors are closed and locked. The interlock shall be of a type to meet all requirements of the Code. Engaging components of the mechanical-locking device shall be free of noises.

T. Car Door Gate Switch or Contacts: Provide new electrical contacts shall prevent the operation of the elevator by normal operating devices unless car doors are closed or within tolerances allowed by Code.

U. Door Unlocking Rollers: Provide new as required to accommodate new door operators and door clutches.

V. Unique Identifier: Provide elevator identification number at the main landing in accordance with ASME A17.1, rule 2.29.1.

2.06 CAR EQUIPMENT

A. Car Frame and Safety Device: Retain existing car frame.

1. Car and Platform Safety Device: Retain and reuse car safety system andall associated connecting and carrier rods and components. Properlyadjust and test in accordance with Code requirements.

2. Safety Contact: If required, provide an electrical contact, connectedelectrically in the safety circuit and mechanically to the safety device shallbe arranged to shut off power to the elevator motor upon engagement ofthe safety jaws.

B. Platform: Retain existing.

C. Roller Guides: Provide new roller type with three or more sound-deadening rollers per guide assembly with adjustable springs or other method to maintain rail contact.

D. Toe Guard: Provide new, minimum length 48 inch toe guard.

E. Car Door Hanger: Provide two-point suspension sheave type with provisions for vertical and lateral adjustments. Sheaves shall be minimum 2 1/4 inch in diameter with sealed ball or roller bearings.

F. Tracks: Provide new cold drawn steel shaped and finished to permit free movement of sheaves. Bottom of track shall be in contact with upthrust roller.

G. Car Enclosure: Retain the existing interior cab shell and walls and ceiling. Wrap or re-clad the existing return panel and transom.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 34

Provide the following features:

1. Shell: Retain the existing cab shell and interior dome.

2. Suspended ceiling and lighting:

a. Provide manufacturer's standard metal down light ceiling. Finish shall be stainless steel no. 4.

b. Furnish and install a new island style ceiling constructed of fire rated wood substrate faced with no. 4 satin finish stainless steel incorporating six (6) recessed LED down lights. Panel configuration to be six (6) equally sized panels with one (1) light at the center of each panel. Provide dimmer control.

c. Interior lighting shall provide a minimum of 10 ftc. throughout the elevator interior.

d. Provide clear access to the emergency exit per Code requirements. e. Emergency Car Lighting and Alarm System: Elevator interior

emergency lighting shall be provided by an independent battery system that provides power to the interior lighting system and alarm system. Unit shall provide emergency light in car upon failure or interruption of normal car lighting. Emergency lighting unit shall provide a minimum illumination of 0.2 foot-candle at 4 feet above car floor approximately 1 foot in front of car operating panel for not less than 4 hours. Battery shall be sealed and rechargeable. Battery charger shall be capable of restoring battery to full charge within 16 hours after resumption of normal power. Provide an external means for testing battery, lamps and alarm bell.

3. Front return panels, transom and entrance columns: Wrap or resurface the

existing front of the elevator cabs with 14 gauge sheet steel. Provide fixed type return panel with necessary cutouts for car station and fixtures. Note: The existing return panel measures 3.5” deep. Finish shall be stainless steel No. 4 brushed finish.

4. Car Door Panels: Provide new, door panels shall be hollow metal

construction, 16 gauge furniture steel. Fill with fireproof, sound deadening material. Provide reinforcement by formed vertical sections running full height of door. Doors shall be provided with two removable, non-metallic gibs, located at the leading and trailing edge of the door panel. Center opening doors shall be provided with full length rubber astragal at leading edge of each door. Finish shall be stainless steel No. 4 brushed finish.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 35

5. Interior Panels: Panels shall be either applied or removable of plywood orwood core board construction with rigidize stainless steel facing andstainless steel reveals. Provide mounting method which prevents rattlingor vibration.

6. Handrail: Provide one (1) 1/4 inch thick by 2 inch high stainless steel flatbar handrails at the sides and rear of the car. Return ends. Provideadequate through bolt type mounting and flat bar reinforcement on theexterior of the cab.

7. Base: Provide a 4 inch high base. Finish shall be stainless steel No. 4brushed finish.

8. Ventilation: Provide new two-speed exhaust fan.

9. Sill: Retain existing. Clean thoroughly.

10. Finished flooring: Provide Burke Endura resilient industrial raised rubberflooring as selected by the Owner.

a. Prepare the car platform sub-surface, as required, to accept theflooring so that no imperfections are visible.

b. Top of finished flooring shall be flush with the top of the carthreshold.

c. Provide all required assistance to the flooring contractor and allrequired standby labor, relative to the installation of the finishedflooring in the car enclosure.

H. Car Top Safety Railing: Provide a car top safety railing and toe guard kick plates on each elevator car. Installed safety railings shall be designed and installed in accordance with current ASME A17.1 and OSHA safety standards.

2.07 SIGNALS AND FIXTURES

A. Provide metal disc pushbutton modules with blue L.E.D. illuminated halos. The intent is not to furnish buttons or modules with plastic bezels or bases or those of an integral design. All illumination shall utilize L.E.D. technology. Applied signage of any kind is unacceptable.

B. Car Operating Panel:

1. Provide one fixed type car operating panel integral with the front returnpanel. Panel shall have illuminating pushbuttons numbered to conform tofloors served. Provide buttons that will identify each floor and shall lightto show registration and extinguish when car stops in response to a call.Each panel shall include an emergency stop switch, alarm bell button,

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 36

DOOR OPEN, and DOOR CLOSE buttons for the front and rear openings. All operating controls shall be located no higher than 48" above the car floor, (35" for stop switch and alarm button). Provide main car panel with locked Fireman’s Service cabinet and required Phase II emergency fire operation. Provide hands free type surface mounted telephone/intercom system. Braille/Arabic designations shall be flush with inconspicuous mechanical mounting. Finish shall be stainless steel no. 4 finish. Provide Independent Service key switch mounted in the face of the car station.

2. Provide the following toggle or key switch type controls within locked service cabinet:

a. A light switch (toggle). b. Two Speed Fan switch (toggle). c. Emergency Stop Switch (keyed). d. Inspection Service Operation (keyed).

3. Engrave the panels with the following:

a. No Smoking. b. Elevator Number over operating buttons. c. Elevator Capacity. d. Fire service operating instructions.

C. Car Position Indicator: Provide new digital readout type with 2 inch high

(minimum) indications over the car operating panel. Color of the position indicator shall match car pushbutton illumination. Provide voice annunciation.

D. Hall Position Indicators: Provide within the hall pushbutton station at the main

landing digital readout type indications and direction of travel arrows for each elevator. Color of the position indicator shall match car pushbutton illumination.

E. Car Travel Lanterns: Provide one (1) UP and DOWN lantern mounted in the car

entrance jamb. Mount in jamb in order to be visible from the proximity of the hall station. Electronic chimes shall sound twice for the down direction of travel. Finish shall match the hall pushbutton stations.

F. Hall Buttons: Provide one new riser of hall pushbuttons with direction of travel

arrows incorporated into the button design. Stations shall include flush mounted oversized faceplate to eliminate patching or repair of existing wall covering. Finish shall be stainless steel No. 4 brushed finish. Fire and Emergency Exit signage (Appendix O) shall be engraved on the faceplate. Incorporate Fire

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 37

Service operating features in the main lobby hall station. Provide communication failure indicator. Provide blue L.E.D. illumination.

G. Hoistway Access: Provide hoistway inspection access key switches at the terminal landings. Mount adjacent to entrance frames. Finish shall be stainless steel No. 4 brushed finish.

H. Provide Firefighters rescue key box mounted in the main lobby.

2.08 COMMUNICATION SYSTEM

A. Telephone System: Provide ADA hands free telephone system integral with main car return panel. Engrave all required signage and operating instructions.

B. Provide wiring from car to telephone terminal box in elevator machine room.

C. Provide in car system that allows for two-way communication between the elevator car and machine room as required by ASME A17.1 - 2013.

PART 3 - EXECUTION

3.01 EXAMINATION OF EXISTING BUILDING AND CONTRACT DOCUMENTS

A. Bidder shall carefully examine all existing building conditions and be informed as to facilities for delivery of materials and equipment, floor loading limitations, and be familiar with difficulties that may be encountered in completing execution of all work, prior to bid.

B. Bidder will be held to have examined all specifications and all other data or institutions pertaining to work.

C. The Owner shall bear no responsibility for any incomplete or missing wiring diagrams or other data which may be needed to adapt the new equipment to the existing equipment. Obtaining such information from other sources is the Contractor's responsibility.

D. No consideration or allowance will be granted for failure to visit site, or for alleged misunderstanding of materials to be furnished, or work to be done, it being understood that tender of proposal carries with it agreement to all items and conditions referred to herein.

3.02 MAJOR ALTERATION - INCREASE IN DEAD WEIGHT

A. The original car and counterweight shall be weighed and documentation furnished to the enforcing Code authorities prior to the addition of any specified items.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 38

B. After the addition of any specified items to the car, the car is to be reweighed to ensure that the additions do not exceed ASME A17.1, Rules 8.7.2.9 and 8.7.2.15.2 limit of 5%. Documentation shall be furnished to the enforcing Code authorities verifying the results. If the load exceeds the 5% limit the rated load shall be increased.

3.03 FIELD QUALITY CONTROL

A. Tests:

1. Perform as required by code, and authorities having jurisdiction.

2. Provide labor, material, equipment and connections.

3. Repair or replace defective work as required.

4. Pay for restoring or replacing damaged work due to tests.

B. Final Inspection: When all work is completed, and tested, notify The Owner in writing that the elevator is ready for final inspection and acceptance test. A testing and inspection date shall then be arranged. The proper operation of every part of the elevator system and compliance with contract requirements of the Code shall be demonstrated to The Owner. Furnish all test instruments, weights, and materials, required at the time of final inspection.

A. Final System Tests for Smoke Detection/Fire Elevator Recall: After work is completed, conduct a final test of entire system. Submit results on approved test report forms.

B. Reinsertion: If any equipment is found to be damaged or defective, or if the performance of the elevator does not conform to the requirements of the contract specifications or the Safety Code, no approval or acceptance of the elevators shall be issued until all defects have been corrected. When the repairs and adjustments have been completed and the discrepancies corrected. The Owner shall be notified and the elevator shall be reinspected. Rejected elevators shall not be used until they have been reinspected and approved.

If deficiencies are found, or if the consultant/The Owner deems it to be necessary the contractor shall perform the following tests at no additional charge immediately following the final inspection.

1. Test Period: The elevator shall be subjected to a test for a period of onehour continuous run, with full specified load in the car. During the testrun, the car shall be stopped at all floors in both directions of travel for astanding period of 10 seconds per floor.

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 39

2. Speed Load Tests: The actual speed of the elevator car shall be determinedin both directions of travel with full contract load and with no load in theelevator car. Speed shall be determined by a tachometer. The actualmeasured speed of elevator car with full load shall be within 5% of ratedspeed. The maximum difference in actual measured speeds obtained underthe various conditions outlined between the "UP" and the "DOWN"directions shall be checked.

3. Floor-to-floor times with no load in the car, balanced load in the car andfull load in the car shall be checked.

4. Car Leveling Tests: Elevator car leveling devices shall be tested foraccuracy of landing at all floors with no load in the car, balanced load in;the car and full load in the car, in both directions of travel. Accuracy offloor landing (plus or minus 1/4 inch) shall be determined both before andafter the full-load run test.

5. Insulation Resistance Tests: The complete wiring systems of the elevatorshall be free from short circuits and grounds, and the insulation resistanceshall be determined by use of a "Megger." Conductors shall have aninsulation resistance of not less than one megohm between each conductorand ground and between each conductor and all other conductors.

6. Reinspection: If any equipment is found to be damaged or defective, or ifthe performance of the elevator does not conform to the requirements ofthe contract specifications or the Safety Code, no approval or acceptanceof the elevators shall be issued until all defects have been corrected. Whenthe repairs and adjustments have been completed and the discrepanciescorrected. The Owner shall be notified and the elevator shall bereinspected. Rejected elevators shall not be used until they have beenreinspected and approved.

3.04 ADJUSTING AND CLEANING

A. All equipment shall be adjusted prior to final testing and acceptance.

B. Paint exposed work soiled or damaged during installation. Repair to match adjoining work prior to final acceptance. At a minimum all hoistway and machine room components shall be field painted with at least one coat of machine grade enamel. Paint the machine room and pit floors in a standard grey and machine room walls in an off-white color. The intent is to provide a final product that is neat, clean and painted.

3.05 INSTRUCTIONS

Downtown Expressway Parking Garage - Elevator Replacement Modernization of Existing Traction Elevators Richmond, VA

142211 - 40

Upon completion of all work, the Elevator Contractor shall provide an instruction period. Instructions shall be given by competent supervisory personnel and shall apply to actual field conditions. The instructions shall cover, but shall not be limited to the following:

A. Operation of elevators under emergency conditions.

B. Operation and maintenance of smoke detector and elevator fire recall system.

C. Operation of elevator communication, electronic entrance detector, hoistway access devices, etc.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 1

SECTION 210000

SPRINKLER SYSTEMS MODIFICATIONS

PART 1 - GENERAL

1.01 SUMMARY

A. Section Includes:

1. Pipes, fittings, and specialties.

2. Sprinklers.

1.02 SYSTEM DESCRIPTIONS

A. Sprinkler System: Automatic sprinklers are attached to piping that is connected to water supply through alarm valve. Water discharges from sprinklers when they are opened. Sprinklers open when heat melts fusible link or destroys frangible device. The work includes provision of sprinklers in Elevator 1 & 2 pits, and Elevator 1 Machine Room.

1.03 PERFORMANCE REQUIREMENTS

A. Standard-Pressure Piping System Component: Listed for 175-psig minimum working pressure.

B. Delegated Design: Design sprinkler system(s), including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.

C. Sprinkler system design shall be approved by authorities having jurisdiction.

1. Margin of Safety for Available Water Flow and Pressure: 10 percent,including losses through water-service piping, valves, and backflowpreventers.

2. Sprinkler Occupancy Hazard Classifications:

a. Automobile Parking Areas: Ordinary Hazard, Group 1.b. Building Service Areas: Ordinary Hazard, Group 1.c. Electrical Equipment Rooms: Ordinary Hazard, Group 1.d. General Storage Areas: Ordinary Hazard, Group 1.e. Mechanical Equipment Rooms: Ordinary Hazard, Group 1.

3. Minimum Density for Automatic-Sprinkler Piping Design:

a. Light-Hazard Occupancy: 0.10 gpm over 1500-sq. ft. area.

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 2

b. Ordinary-Hazard, Group 1 Occupancy: 0.15 gpm over 1500-sq. ft.area.

c. Ordinary-Hazard, Group 2 Occupancy: 0.20 gpm over 1500-sq. ft.area.

4. Maximum Protection Area per Sprinkler: Per UL listing.

5. Maximum Protection Area per Sprinkler:

a. Office Spaces: 225 sq. ft.b. Storage Areas: 130 sq. ft.c. Mechanical Equipment Rooms: 130 sq. ft.d. Electrical Equipment Rooms: 130 sq. ft.e. Other Areas: According to NFPA 13 recommendations unless

otherwise indicated.

6. Total Combined Hose-Stream Demand Requirement: According toNFPA 13 unless otherwise indicated:

a. Light-Hazard Occupancies: 100 gpm for 30 minutes.b. Ordinary-Hazard Occupancies: 250 gpm for 60 to 90 minutes.

1.04 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: For wet-pipe sprinkler systems. Include plans, hydraulic calculations, elevations, sections, details, and attachments to other work.

C. Delegated-Design Submittal: For sprinkler systems indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation or NICET Level III Designer.

1.05 INFORMATIONAL SUBMITTALS

A. Qualification Data: For qualified Installer.

B. Approved Sprinkler Piping Drawings: Working plans, prepared according to NFPA 13, that have been approved by authorities having jurisdiction, including hydraulic calculations if applicable.

C. Field Test Reports and Certificates: Indicate and interpret test results for compliance with performance requirements and as described in NFPA 13. Include "Contractor's Material and Test Certificate for Aboveground Piping."

D. Field quality-control reports.

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 3

1.06 QUALITY ASSURANCE

A. Installer Qualifications:

1. Installer's responsibilities include designing, fabricating, and installingsprinkler systems and providing professional engineering services neededto assume engineering responsibility. Base calculations on results of fire-hydrant flow test.

a. Engineering Responsibility: Preparation of working plans,calculations, and field test reports by a qualified professionalengineer.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. NFPA Standards: Sprinkler system equipment, specialties, accessories, installation, and testing shall comply with the following:

1. NFPA 13, "Installation of Sprinkler Systems."

1.07 EXTRA MATERIALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Sprinkler Cabinets: Finished, wall-mounted, steel cabinet with hingedcover, and with space for minimum of six spare sprinklers plus sprinklerwrench. Include number of sprinklers required by NFPA 13 and sprinklerwrench. Include separate cabinet with sprinklers and wrench for each typeof sprinkler used on Project.

PART 2 - PRODUCTS

2.01 PIPING MATERIALS

A. Comply with requirements in "Piping Schedule" Article for applications of pipe, tube, and fitting materials, and for joining methods for specific services, service locations, and pipe sizes.

2.02 STEEL PIPE AND FITTINGS

A. Standard Weight, Galvanized Pipe: ASTM A 53/A 53M. Pipe ends may be factory or field formed to match joining method.

B. Schedule 30, Galvanized Pipe: ASTM A 135; ASTM A 795/A 795M; or ASME B36.10M, wrought steel; with wall thickness not less than Schedule 30

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 4

and not more than Schedule 40. Pipe ends may be factory or field formed to match joining method.

C. Galvanized Pipe Nipples: ASTM A 733, made of ASTM A 53/A 53M, standard-weight, seamless steel pipe with threaded ends.

D. Galvanized Steel Couplings: ASTM A 865, threaded.

E. Galvanized Gray-Iron Threaded Fittings: ASME B16.4, Class 125, standard pattern.

F. Malleable- or Ductile-Iron Unions: UL 860.

G. Grooved-Joint, Steel-Pipe Appurtenances:

1. Pressure Rating: 175 psig minimum.

2. Galvanized, Grooved-End Fittings for Steel Piping: ASTM A 47/A 47M,malleable-iron casting or ASTM A 536, ductile-iron casting; withdimensions matching steel pipe.

2.03 SPRINKLER SPECIALTY PIPE FITTINGS

A. Branch Outlet Fittings:

1. Mechanical T fittings shall not be used.

2.04 SPRINKLERS

A. Automatic Sprinklers with Heat-Responsive Element:

1. Nonresidential Applications: UL 199.

2. Characteristics: Nominal 1/2-inch orifice with Discharge Coefficient K of5.6, and for "Ordinary" temperature classification rating unless otherwiseindicated or required by application.

B. Sprinkler Finishes:

1. Bronze.

C. Sprinkler Escutcheons: Materials, types, and finishes for the following sprinkler mounting applications. Escutcheons for concealed, flush, and recessed-type sprinklers are specified with sprinklers.

1. Ceiling Mounting: Chrome-plated steel, two piece, with 1-inch verticaladjustment.

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 5

2. Sidewall Mounting: Chrome-plated steel, one piece, flat.

D. Sprinkler Guards:

1. Standard: UL 199.

2. Type: Wire cage with fastening device for attaching to sprinkler.

PART 3 - EXECUTION

3.01 PIPING INSTALLATION

A. Locations and Arrangements: Drawing plans, schematics, and diagrams indicate general location and arrangement of piping. Install piping as indicated, as tight to structure as practical. Coordinate pipe and sprinkler locations with other trades.

1. Deviations from approved working plans for piping require writtenapproval from authorities having jurisdiction. File written approval withArchitect before deviating from approved working plans.

B. Piping Standard: Comply with requirements for installation of sprinkler piping in NFPA 13.

C. Use listed fittings to make changes in direction, branch takeoffs from mains, and reductions in pipe sizes.

D. Install unions adjacent to each valve in pipes NPS 2 and smaller.

E. Install sprinkler piping with drains for complete system drainage.

F. Install hangers and supports for sprinkler system piping according to NFPA 13. Comply with requirements for hanger materials in NFPA 13.

3.02 JOINT CONSTRUCTION

A. Install couplings, flanges, flanged fittings, unions, nipples, and transition and special fittings that have finish and pressure ratings same as or higher than system's pressure rating for aboveground applications unless otherwise indicated.

B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

C. Remove scale, slag, dirt, and debris from inside and outside of pipes, tubes, and fittings before assembly.

D. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 6

1. Apply appropriate tape or thread compound to external pipe threads.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that arecorroded or damaged.

E. Steel-Piping, Cut-Grooved Joints: Cut square-edge groove in end of pipe according to AWWA C606. Assemble coupling with housing, gasket, lubricant, and bolts. Join steel pipe and grooved-end fittings according to AWWA C606 for steel-pipe joints.

F. Dissimilar-Material Piping Joints: Make joints using adapters compatible with materials of both piping systems.

3.03 IDENTIFICATION

A. Install labeling and pipe markers on equipment and piping according to requirements in NFPA 13.

B. Identify system components, wiring, cabling, and terminals. Comply with requirements for identification specified in Division 26 Section "Identification for Electrical Systems."

3.04 FIELD QUALITY CONTROL

A. Perform tests and inspections.

B. Tests and Inspections:

1. Leak Test: After installation, charge systems and test for leaks. Repairleaks and retest until no leaks exist.

2. Flush, test, and inspect sprinkler systems according to NFPA 13, "SystemsAcceptance" Chapter.

C. Sprinkler piping system will be considered defective if it does not pass tests and inspections.

D. Prepare test and inspection reports.

3.05 CLEANING

A. Clean dirt and debris from sprinklers.

B. Remove and replace sprinklers with paint other than factory finish.

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 7

3.06 PIPING SCHEDULE

A. Sprinkler specialty fittings may be used, downstream of control valves, instead of specified fittings.

B. Wet-pipe sprinkler system, NPS 2 and smaller, shall be one of the following:

1. Standard-weight or Schedule 30, galvanized-steel pipe with threaded ends;galvanized, gray-iron threaded fittings; and threaded joints.

3.07 SPRINKLER SCHEDULE

A. Use sprinkler types in subparagraphs below for the following applications:

1. Rooms without Ceilings: Upright sprinklers.

2. Wall Mounting: Sidewall sprinklers.

3. Spaces Subject to Freezing: Upright, pendent, dry sprinklers; andsidewall, dry sprinklers as indicated.

B. Provide sprinkler types in subparagraphs below with finishes indicated.

1. Upright Pendent and Sidewall Sprinklers: Chrome plated in finishedspaces exposed to view; rough bronze in unfinished spaces not exposed toview; wax coated where exposed to acids, chemicals, or other corrosivefumes.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Sprinkler Systems Modifications Richmond, VA

210000 - 8

PAGE LEFT INTENTIONALLY BLANK

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 1

SECTION 283100

CONVENTIONAL FIRE DETECTION AND ALARM SYSTEM

PART 1 - GENERAL

1.01 SCOPE

A. The work includes modifying existing interior fire alarm system. Existing panel is a Simplex 4002 conventionally zoned fire alarm control with 2 spare zones. The features and capacities described in this specification are required as a minimum for this project and shall be furnished by the successful contractor as follows: Installation of heat detectors within 24" of sprinklers in Elevator 1 & 2 pit, and Elevator 1 Machine Room. Installation of smoke detectors in Elevator 1 Machine Room.

B. The system shall be in full compliance with applicable National Codes and the 2012 Virginia Uniform Statewide Building Code.

C. The system shall include all required hardware, raceways, interconnecting wiring and software to accomplish the requirements of this specification and the contract drawings, whether or not specifically itemized herein.

D. Contractor shall provide all materials to include but not be limited to (conduit, wire, labor, trenching machines, etc.) to provide a complete pathway and fully supervised monitoring of switch(es) by the fire alarm system. Circuit(s) shall also be protected against surges and lightning strikes by employing surge suppressors that are properly grounded to good building ground.

E. All equipment furnished shall be new products of a single manufacturer engaged in the manufacturing and sale of fire detection devices for over five years.

F. All equipment shall be installed per its listings and the manufacturer’s installation instructions.

G. All equipment shall be listed for its intended use.

H. The system as specified shall be supplied, installed, tested, and approved by the local authority having jurisdiction (AHJ), and turned over to the owner in an operational condition.

I. In the interest of job coordination and responsibilities the installing contractor shall contract with a single supplier for fire alarm equipment, engineering, programming, and final connections.

J. The locations and types of fire alarm system devices to include alarm initiating appliances, alarm notification appliances, control and trouble signaling equipment, and the location of major components shall not be altered by the

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 2

Contractor without prior written approval by the Engineer and the Building Official. Changes to the design depicted within the Construction Documents shall be considered substitutions in accord with the General Conditions and are to be documented by Change Order.

K. It shall be the responsibility of the Contractor to ensure that all devices are installed according to their ratings and specifications (i.e. operating temperature, humidity, etc.).

1.02 POSSIBLE RELATED WORK

A. Division 01: Bidding Requirements and Conditions of the Contract.

B. Division 21: Fire Suppression

1.03 STANDARDS & CODES

A. The publications listed below form a part of this publication to the extent referenced. The publications are referenced in the text by the basic designation only. The editions of the referenced standards found in Chapter 35 of the Virginia Uniform Statewide Building Code shall be met.

B. Factory Mutual (FM)

1. FM AG Approval Guide.

C. National Fire Protection Association (NFPA)

1. NFPA 13 – 2010 Standard for the Installation of Sprinkler Systems.

2. NFPA 70 – 2011 National Electrical Code.

3. NFPA 72 – 2010 National Fire Alarm Code.

D. Underwriters' Laboratories, Inc. (UL) Appropriate “UL” equipment standards.

1. “UL” 864 9th Edition Control Panels.

2. “UL” 268 Smoke Detectors.

3. “UL” 268A Smoke Detectors (HVAC).

4. “UL”1076 Security.

5. “UL” 1971, Standard for Visual Signaling Appliances.

E. Building Codes

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 3

1. Virginia Uniform Statewide Building Code 2012

2. State and Local Building Codes as adopted and/or amended by TheAuthority Having Jurisdiction.

1.04 QUALIFICATIONS OF INSTALLERS

A. Before commencing work, submit data showing that the contractor has successfully installed fire alarm systems of the same scope, type, and design as specified.

B. The contractor shall submit copies of all required Licenses and Bonds as required in the State having jurisdiction within the submittals.

C. The contractor shall employ on staff a minimum of one NICET level II technician and provide proof of such employment within the submittals.

1.05 MANUFACTURER'S REPRESENTATIVE

A. Provide the services of a factory trained and certified representative or technician, experienced in the installation and operation, maintenance, and service of the Simplex 4002. The representative shall be licensed in the State if required by law. The technician shall supervise installation, adjustment, preliminary testing, final testing, and certification of the system. The technician shall provide the required instruction to the owner's personnel in the system operation, maintenance, and programming. Provide copies within the submittals of all applicable certifications of training only from technicians that will actually be assigned and deployed to this project. Engineer may at any time visit site to ensure the technicians on site are the ones that were submitted on.

B. The contractor shall include the following information in the equipment submittal:

1. Power calculations. Battery capacity calculations. Battery size shall be aminimum of 125% of the calculated requirement.

2. Supervisory power requirements for all equipment.

3. Alarm power requirements for all equipment.

4. Power supply rating justification showing power requirements for each ofthe system power supplies. Power supplies shall be sized to furnish thetotal connected load in a worst-case condition plus 25% spare capacity.

5. Voltage drop calculations for wiring runs demonstrating worst-casecondition.

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 4

6. NAC circuit design shall incorporate a 20% spare capacity for futureexpansion.

7. Complete manufacturers catalog data including supervisory power usage,alarm power usage, physical dimensions, finish, and mountingrequirements.

8. Complete drawings covering the following shall be submitted by thecontractor for the proposed system:

a. Floor plans in a CAD compatible format showing all equipmentand raceways, marked for size, conductor count with type and size,showing the percentage of allowable National Electric Code fillused. Wiring for the fire alarm system is not shown on the contractdrawings. The contractor shall lay out the wiring arrangementbetween the system components in the most convenient form fortheir installation and show it on the floor plans. At the conclusionof the project, the contractor shall correct and modify this wiringlayout to conform with the actual runs and connections forinclusion into the final set of record drawings.

b. A complete fire alarm job specific riser diagram showing allinitiating, notification, communication, shutdown, and powercircuits and their relative service areas in the building (i.e. 1st floornotification circuit) that are attached to the fire alarm system.Include all candela ratings and room numbers.

c. Typical job specific wiring diagrams for all field devices used inthe proposed system. Diagrams shall be sized and laid out so thatindividual wire detail can be determined.

d. A job specific wiring diagram of the fire alarm control panel andall associated control panels (i.e. NAC extender panels,communicators, remote annunciators, etc.).

e. Provide a fire alarm system function matrix as referenced byNFPA 72-2010, Annex A Explanatory Material, FigureA.14.6.2.4(9). Matrix shall illustrate alarm input/output events inassociation with initiation devices. Matrix summary shall includesystem supervisory and trouble output functions. Include any andall departures, exceptions, variances or substitutions from thesespecifications and/or drawings at time of bid.

9. Incomplete submittals may be returned without review.

1.06 SYSTEM REQUIREMENTS

A. The system shall be a complete, electrically supervised fire detection and notification system, microprocessor based operating system having the following; capabilities, features and capacities:

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 5

1. The local system shall provide status indicators and control switches forall of the following functions:

a. Visual status indicators (alarm & trouble) for each individual zonewithin the system.

b. System bypass capabilities.

2. Each conventional zone on the system shall be displayed at the main firealarm control panel and any remote annunciators required on the contractdrawings. Zones shall be descriptive enough to lead the responder to thegeneral area of off normal condition (i.e. Zone1, Zone 2, is unacceptable).

1.07 SYSTEM OPERATION

A. Activation of any system fire, trouble, supervisory, or status initiating device shall cause the following actions and indications at all visual displays in the system.

B. Fire Alarm Condition:

1. Sound an audible alarm and illuminate the alarm LED’s for the specificzone initiating the alarm at the control panel and remote annunciatorlocations.

2. Log to the system history archives the alarm condition.

3. Sound the ANSI 117-1 signal with synchronized audibles andsynchronized strobes throughout the facility.

4. Audible signals shall be silenced from the fire alarm control panel by analarm silence switch. Visual signals shall be programmable to flash untilsystem reset or alarm silencing, as required.

5. The alarm information shall be displayed on remote annunciators (ifapplicable) located where shown on drawings.

6. Activation of any smoke detector in a single elevator lobby or an elevatorequipment room shall cause the recall of that bank of elevators to the 1st

floor and the lockout of controls. In the event of recall initiation by adetector in the first floor lobby, the recall shall be to the alternate floor.

7. HVAC shut down shall be accomplished by system operated ductdetectors as per local requirements.

C. Supervisory Condition:

1. The supervisory information shall be displayed on remote annunciators (ifapplicable) located where shown on drawings.

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 6

2. Activate supervisory audible and dedicated visual signal at control panel.

3. Audible signals shall be silenced from the control panel by the supervisoryacknowledge switch.

4. Record within system history, the occurrence of the event, the time ofoccurrence and the zone or circuit initiating the event.

D. Trouble Condition:

1. The trouble information shall be displayed on remote annunciators (ifapplicable) located where shown on drawings.

2. Activate trouble audible and visual signals at the control panel and asindicated on the drawings.

3. Audible signals shall be silenced from the fire alarm control panel by atrouble acknowledge switch.

4. Record within system history, the occurrence of the event, the time ofoccurrence and the zone or circuit initiating the event.

PART 2 - PRODUCTS

2.01 CONTROL PANEL

A. The existing fire alarm control panel is a microprocessor based, conventional, and zoned unit.

2.02 CONVENTIONAL INITIATION DEVICES

A. Smoke Detector - The smoke detector shall be the photoelectric type. Detectors shall be listed for use as open area protective coverage, in duct installation and duct sampling assembly installation and shall be insensitive to air velocity changes. The smoke detector shall contain a multi colored LED indicator that will flash green to indicate that the detector is operational and flash red when the detector is in alarm. The detector shall be continually self-testing and shall be designed to eliminate calibration errors associated with field cleaning of the chamber. Detector shall twist lock into a base assembly with screw clamp terminals. A detector activation shall provide alarm input to the system and alarm output from the system within four (4) seconds. The detector and associated control functions (relays, annunciator) shall operate off of the zone power. Detectors shall not require any separate power supplies to operate. Where auxiliary relays are necessary but would require a separate power supply to operate within the duct housing, separate control modules shall be provided in lieu of the housing relays and power supply. The detector shall support the use of a relay or LED remote indicator. Detector spacing and location shall be in

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 7

accordance with manufacturer’s recommendations, the requirements of NFPA 72, and as indicated. No detector shall be located closer than 12 inches to any part of any lighting fixture nor shall any detector be mounted closer that 36” from any AHU air diffuser. The detector shall operate off of the addressable loop power. Detectors shall not require any separate power supplies to operate.

B. Heat Detector (System) - Thermal Detectors shall be rated at 135 degrees fixed temperature and 15 degrees per minute rate of rise. Detectors shall be constructed to compensate for the thermal lag inherent in conventional type detectors due to the thermal mass, and alarm at the set point of 135 degrees Fahrenheit. The detectors furnished shall have a listed spacing for coverage up to 2,500 square feet and shall be installed according to the requirements of NFPA 72 for open area coverage.

PART 3 - EXECUTION

3.01 INSTALLATION

A. Perform work in accordance with the requirements of NFPA 70 and NFPA 72.

B. Fasten equipment to structural members of building or metal supports attached to structure, or to concrete surfaces.

C. All fire alarm cabling shall be supplied in conduit.

3.02 BOXES, ENCLOSURES AND WIRING DEVICES

A. Boxes shall be installed plumb and firmly in position.

B. Extension rings with blank covers shall be installed on junction boxes where required.

C. Junction boxes served by concealed conduit shall be flush mounted.

D. Upon initial installation, all wiring outlets, junction, pull and outlet boxes shall have dust covers installed. Dust covers shall not be removed until wiring installation when permanent dust covers or devices are installed.

3.03 CONDUCTORS

A. Each conductor shall be identified as shown on the drawings at each with wire markers at terminal points. Attach permanent wire markers within 2 inches of the wire termination. Marker legends shall be visible.

B. All wiring shall be supplied and installed in compliance with the requirements of the National Electric Code, NFPA 70, Article 760, and that of the manufacturer.

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 8

C. Wiring for strobe and audible circuits shall be a minimum 14 AWG, signal line circuits shall be minimum 18 AWG.

D. All splices shall be made using solderless connectors. All connectors shall be installed in conformance with the manufacturer recommendations.

E. Crimp-on type spade lugs shall be used for terminations of stranded conductors to binder screw or stud type terminals. Spade lugs shall have upset legs and insulation sleeves sized for the conductors.

F. Permanently label or mark each conductor at both ends with permanent alphanumeric wire markers. Labels shall identify the circuit and terminal numbers of the panel that it lands on (i.e. NAC 1 + (5), NAC 1 – (6)).

G. A consistent color code for fire alarm system conductors shall be used throughout the installation.

H. Wiring within sub panels shall be arranged and routed to allow accessibility to equipment for adjustment and maintenance.

3.04 DEVICES

A. Relays and other devices to be mounted in auxiliary panels are to be securely fastened to avoid false indications and failures due to shock or vibration.

B. Wiring within sub-panels shall be arranged and routed to allow accessibility to equipment for adjustment and maintenance.

C. All devices and appliances shall be mounted to or in an approved electrical box.

3.05 FIELD QUALITY CONTROL

A. Testing, general

1. All Alarm Initiating Devices shall be observed and logged for correct zoneand sensitivity. These devices and their bases shall be tagged withadhesive tags located in an area not visible when installed, showing theinitials of the installing technician and date.

2. Wiring runs shall be tested for continuity, short circuits, and groundsbefore system is energized. Resistance, current, and voltage readings shallbe made as work progresses.

3. A systematic record shall be maintained of all readings using schedules orcharts of tests and measurements. Areas shall be provided on the loggingform for readings, dates and witnesses.

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 9

4. The acceptance inspector shall be notified before the start of the requiredtests. All items found at variance with the drawings or this specificationduring testing or inspection by the acceptance inspector shall be corrected.

5. Test reports shall be delivered to the acceptance inspector as completed.

6. The installing contractor shall make instruments, tools and labor requiredto conduct the system tests available.

7. The following equipment shall be a minimum for conducting the tests:

a. Ladders and scaffolds as required to access all installed equipment.b. Multimeter for reading voltage, current and resistance.c. Two way radios, and flashlights.d. A manufacturer recommended device for measuring airflow

through air duct smoke detector sampling assemblies.e. Decibel meter.

B. In addition to the testing specified to be performed by the installing contractor, the installation shall be subject to test by the Engineer of Record and the AHJ.

3.06 ACCEPTANCE TESTING

A. The contractor shall be responsible for demonstrating the function of the system and verifying the correct operation of all system components, circuits, and programming.

B. A program matrix shall be prepared by the installing contractor referencing each alarm input to every output function affected as a result of an alarm condition on that input.

C. The installing contractor, prior to the final test shall prepare a complete listing of all zone labels for remote annunciator displays.

D. The Contractor shall be responsible for contacting the Regional Office of the State Fire Marshal to coordinate their witness of the below tests (at a minimum).

E. In conducting the acceptance test, the inspector may request demonstration of any or all input and output functions.

F. The items tested shall include but not be limited to the following:

1. System wiring shall be tested to show the following results and the systemsubsequence operation:

a. Open, Shorted or Grounded Circuits.b. Primary and Battery power disconnected.

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 10

2. System notification circuits and appliances operate as programmed.Audibility and Visual levels meet required standards.

3. System shall demonstrate the LED zone indications at the FACP andremote annunciator (if applicable).

4. System off site reporting shall be verified for alarm, supervisory, andtrouble.

5. System shall be tested for stand-by battery back up as outlined in thisspecification.

3.07 DOCUMENTATION

A. System documentation shall be supplied to the owner and shall include but not be limited to the following:

1. System record drawings and wiring details to include circuit diagramscomplete with wire color codes, a parts list by name, model number, andmanufacturer. Include one set of reproducible drawings, and a CD ROMwith copies of the record drawings in DXF format for use in a CADdrafting program. Provide 6 copies.

2. System operating, installation and maintenance manuals. Provide sixcopies, bounded in durable binders. Include instructions for operating andmaintaining system components, assemblies, and accessories. Include adetailed description of the control panel and system operation under bothroutine and emergency conditions.

3. System matrix showing input signals to output commands.

4. Warranty letter that details what is covered under the warranty and thestart and end dates.

5. NFPA 72 record of completion form filled out in its entirety by the firealarm contractor.

3.08 WARRANTY AND SERVICES

A. The contractor shall warranty the system additions for electrical and mechanical failures for a period of one year. This warranty shall include all parts, labor, maintenance, and firmware/software upgrades. The warranty shall begin with the completion of the acceptance testing or when beneficial use to the owner is determined.

B. Any future system additions shall include a separate breakdown of both parts and labor. Labor breakdown must include anticipated number of technician hours

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 11

necessary to complete the addition. Future submittals or cost proposals that do not include this information shall be considered incomplete and be returned without review.

C. The contractor performing the contract services shall be qualified, factory trained, and certified in the service and maintenance of the system provided and listed to maintain ongoing certification of the completed system to the “UL” installed system listing.

D. This warranty service shall be provided on a 24-hour basis, for all service work that includes a compromise of building protection, with the technician arriving within 2 hours of the notification of the need for warranty service. Failure to arrive on time and provide corrective actions may result in the contractor being charged and being responsible for all costs associated with providing an adequate fire watch in order to resume building operations.

E. No preventative maintenance clauses within the manufacturer’s or distributor’s warranty shall be grounds for revocation of the system warranty. If preventative maintenance is required within the first year of system warranty, the contractor shall include such work within their bid price and perform the maintenance work as required during the warranty so as to not provide any reason to void the warranty. Further, it shall be the responsibility of the contractor to specifically list out, in writing, at shop drawing submittal stage, what preventative maintenance is necessary for a period of ten years from the date of substantial completion. Failure to provide this information at this time will result in the contractor forfeiting his/her right to void the system warranty for failure to keep up with preventative maintenance.

F. Purchaser will notify the contractor of their need for service by a telephone call or e-mail to the service department of the contractor. No restrictions on how a service request can be made shall be imposed.

G. All replacement parts shall be new. Under no circumstances will used parts be considered to be equal to new parts.

H. The installation contractor shall furnish training as follows:

1. Training in the receipt, handling, and acknowledgment of alarms.

2. Training in the system operation including manual control of outputfunctions from the system control panel.

3. The total training requirement shall be a minimum of 1 hour, but shall besufficient to cover all items specified. The contractor shall provide twosuch training sessions.

END OF SECTION

Downtown Expressway Parking Garage - Elevator Replacement Conventional Fire Detection and Alarm System Richmond, VA

283100 - 12

PAGE LEFT INTENTIONALLY BLANK