Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
poundD sr UNITED STATES ENVIRONMENTAL PROTECTION AGENCY f 2 l S R8 S^^ bull ^ i ^ ^ - REGIONS
I mM bull 1595 Wynkoop street I ^ 5 ^ ^ I DENVER CO 80202-1129 C ^ ^ ^ ^ Phone 800-227-8917
httpwlaquo|j^agov^rQgg) 8 -t PRO
REF 8EPR-F
MEMORANDUM
SUBJECT Final Explanation of Significant Differences (ESD) for Operable Unit (OU) 2
FROM Maple A Bamard Remedial Project Manager
TO Carol L Campbell Assistant Regional Administrator Office of Ecosystems Protection and Remediation
Attached is the Final ESD 0U2 along with three copies of EPAs signature page The ESD modifies 0U2s source zone treatment system for treatment of ground water on base by eliminating pre-treatment using a steam stripper The Air Stripper Treatment Plant will continue to treat TCE contamination of ground water There are no changes to the applicable or relevant and appropriate requirements (ARAR) but the means of complying has changed The UDEQ provided the required signature pages at the Hill AFB Project Managers Meeting
Attachment
reg Printed on Recycled Paper
FINAL EXPLANATION OF SIGNIFICANT DIFFERENCES
FOR
OPERABLE UNIT 2
fflLL AIR FORCE BASE UTAH
SEPTMEBER 2009
PREPARED BY
Environmental Restoration Branch 75th Civil Engineer Group
Hill Air Force Base UT
HXPIANA riUN OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
Explanation of Significant Differences Operable Unit 2 (OU 2) Hill Air Force Base Utah
INTRODUCTION
This Explanation of Significant Differences (ESD) relates to remedial actions selected by the United States Air Force (USAF) for implementation at Operable Unit 2 (OU 2) at Hill Air Force Base (AFB) Utah in a Record of Decision (ROD) issued in September 1996 (CH2M HILL 1996) Operable Unit 2 is comprised of two Installation Restoration Program (IRP) sites Chemical Pit 3 (WP007) and the Perimeter Road (SS021) Site SS021 included potential disposal sites along Perimeter Road investigated in the late 1980s (Radian 1990) Chemical Pit 3 along with the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021 Site WP007 consists of two unlined trenches that were used for the disposal of unknown quantities of chlorinated spent solvents
Operable Unit 2 is addressed in two components the source zone and the non-source zone The source zone is on-Base and is the immediate area around the former Chemical Disposal Pit 3 that is underlain by a dense non-aqueous phase liquid (DNAPL) and affected areas west of Perimeter Road This area has the highest concentrations of contaminants and occupies approximately 6 acres (Figure 1) The non-source zone is north and east of the source zone and Perimeter Road The non-source zone includes shallow groundwater and seep and spring contamination off-Base This area generally has lower contaminant concentrations and occupies approximately 25 acres
An ESD is required to address differences in the following selected remedies for the OU 2 source zone treatment of extracted source zone groundwater with the existing Air Stripper Treatment Plant (ASTP) without pre-treatment by the existing steam stripper
In July 1987 the US Environmental Protection Agency (EPA) placed Hill AFB on the National Priorities List (NPL) under Comprehensive Environmental Response Compensation and Liability Act (CERCLA) In April 1991 Hill AFB entered a Federal Facility Agreement (FFA) with the Utah Department of Environmental Quality (UDEQ) and the EPA Region VIII to establish a procedural framework and schedule for implementing the appropriate response actions in accordance with existing regulations Under the FFA and Executive Order 12580 Hill AFB is the lead agency for all CERCLA actions and UDEQ and the EPA are support agencies Hill AFB seeks concurrence from both the EPA and UDEQ for significant decisions involving cleanup strategy goals and methods
This ESD is issued in accordance with Section 117(c) ofthe CERCLA 42 USC sect 9617(c) and Section 300435(c)(2)(i) ofthe National Oil and Hazardous Substances Pollution Contingency Plan (NCP) which requires the USAF to issue such a document where a remedial action will differ in any significant but not fundamental respect from that selected by the USAF and described in the ROD A significant change to a remedy is one that incrementally changes a component of a remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) The revised remedy described in this ESD
EXP IAN ATI ON OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
EXPLANATION TCE concentrations In
microsram plaquor Htsr (tilaquo1) frMM X004300
N
Conveyance Line to Central Weber Sewer Improvement
DistrFct
System (UCS) Trench L ^ v
Air Stripper Treatment
(ASTP) Plant r T ^ M (
1 - J A J A i SRS Process r I Building
Figure I Operable Unit 2 site features
complies with the NCP and the statutory requirements of CERLCA The ESD has been prepared to provide the public with an explanation of the nature of the modification to the selected remedy set forth in the ROD and to summarize the infonnation that supports this modification The ESD will become part of the Administrative Record file (40 CFR 300825(a)(2)) and the information repository (40 CFR 300435(c)(2)(i)(A)) for Hill AFB which is located and available for public review at
75CEG CEVR 7274 Wardleigh RD Hill AFB UT 84056-5137
EXIIANA HON UF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
The Administrative Record is also available for public review at
Weber State University - Ogden Campus Weber State University - Davis Campus Stewart Library Stewart Library 3850 University Circle 2750 University Park Blvd Ogden UT 84408 Layton UT 84041-9099 (801)626-6403
The USAF EPA and UDEQ conclude that the remedy selected in the ROD as modified by this ESD will meet the objectives and performance standards of the ROD
SUMMARY OF THE SITE HISTORY SITE CONDITIONS AND SELECTED REMEDY
Site History
Operable Unit 2 is located along the northeastem boundary of Hill AFB overlooking the Weber River Valley and is one of 13 Operable Units at Hill AFB in various stages ofthe CERCLA process Records indicate that from 1967 to 1975 unknown quantities of chlorinated organic solvents generated during degreasing operations were disposed in trenches (chemical pits) at the site These compounds were placed into two unlined disposal trenches trending north northwest which are estimated to have been approximately 6 to 9 feet deep 10 feet wide and approximately 50 to 100 feet long (Radian 1992) The disposal area is underlain by an alluvial sand aquifer that is composed of a heterogeneous mixture of sand and gravel contained in a narrow buried ancient river channel incised deeply into the underlying clay deposit This clay deposit known as the Alpine Formation forms a barrier to the downward migration of DNAPL
Disposal of the spent chlorinated solvents resulted in DNAPL contaminafion of the underlying shallow aquifer (the Provo Formation) predominantly as one or more pools above the clay (the Alpine Formation) and also as a residual phase held in the aquifers pore spaces (the volume in between individual soil particles) The recovered DNAPL consists primarily of several chlorinated solvents (about 70 percent trichloroethene [TCE] with smaller amounts of 111-trichloroethane [111-TCA] tetrachloroethene [PCE] and methylene chloride) 112 trichloro-122-trifluoroethane (Freon 113) and a lesser amount of oil and grease (URS and DEampS 2001) Contaminated soils near the trenches and the pooled DNAPL are the source of shallow dissolved phase groundwater contamination extending approximately 1500 feet downgradient and beyond the Hill AFB boundary (CH2M HILL 1996) Groundwater contamination appears limited to the shallow unconfined aquifer ofthe Provo Formation
Site Conditions
The on-Base portion of OU 2 sits upon relatively flat lying ground while the off-Base portion of the site consists of a steep terraced north-facing escarpment that is the south wall of the Weber River Valley There is about 300 feet of relief between Hill AFB and the valley below Parts of this hillside are unstable and are known as the Weber Landslide Complex Numerous seeps and
EXIIANA TION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
springs occur along the hillside Depending on water table elevation and the season the springs and seeps discharge water from the shallow groundwater system Depth to groundwater in the shallow system is generally less than 10 feet below ground surface (bgs) in the off-Base area and 20 feet bgs in the on-Base area Along the hillside escarpment and just outside ofthe northeastem Base boundary is the Davis-Weber Canal a privately owned concrete-lined irrigation canal The canal parallels the northeast boundary along most of the Base adjacent to the Weber River Valley The canal provides water from the Weber River for irrigation in the surrounding areas (CH2M HILL 1996)
Selected Remedy
The remedies that were selected for the OU 2 source zone are outlined in the Record of Decision issued in 1996 (CH2M HILL 1996) Those remedies include the following
bull Installadon of a low-permeability vertical barrier around the DNAPL and associated highly contaminated groundwater in the source zone to hinder flow to and from the source zone
bull Continued operation of the Source Recovery System (SRS) to remove DNAPL to the maximum extent practicable and to treat shallow groundwater containing high concentrations of VOCs using steam stripping
bull Completion of planned treatability studies using in-situ steam stripping and surfactant flushing for enhanced DNAPL recovery
bull Soil vapor extraction (SVE) after dewatering of the shallow aquifer to remove VOCs from subsurface soils in what is currently the saturated zone
bull Construction of a surface cap once treatment is completed or it is established the innovative technologies cannot meet remedial action objectives to decrease the inflow of precipitation and prevent erosion of surface soils
bull Environmental monitoring to evaluate the effectiveness of the remedy
bull Institutional controls to minimize exposure by limiting use and preventing access to Contaminated water and soil
One of the remedies specified by the ROD is a low permeability containment wall encircling the source zone to reduce the potential for further contamination of groundwater After the wall was built however an additional accumulation of free-phase DNAPL was identified outside of the wall (URS and DEampS 1999) This accumulation is informally known as either the Griffith Pool or the G-Pool A well field was installed in 1998 to extract mobile DNAPL from the area and to hydraulically contain the groundwater to minimize further contaminant flux to the off-Base plume
DESCRIPTION OF AND BASIS FOR THE DIFFERENCES
The SRS was constructed as an interim remedial action in 1993 to recover DNAPL from the source zone and to treat groundwater containing elevated concentrations of VOCs The SRS consists of a free-product and groundwater recovery well field aboveground pipeline and a process treatment facility (Building 755) Dense nonaqueous phase liquid is recovered during the
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
FINAL EXPLANATION OF SIGNIFICANT DIFFERENCES
FOR
OPERABLE UNIT 2
fflLL AIR FORCE BASE UTAH
SEPTMEBER 2009
PREPARED BY
Environmental Restoration Branch 75th Civil Engineer Group
Hill Air Force Base UT
HXPIANA riUN OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
Explanation of Significant Differences Operable Unit 2 (OU 2) Hill Air Force Base Utah
INTRODUCTION
This Explanation of Significant Differences (ESD) relates to remedial actions selected by the United States Air Force (USAF) for implementation at Operable Unit 2 (OU 2) at Hill Air Force Base (AFB) Utah in a Record of Decision (ROD) issued in September 1996 (CH2M HILL 1996) Operable Unit 2 is comprised of two Installation Restoration Program (IRP) sites Chemical Pit 3 (WP007) and the Perimeter Road (SS021) Site SS021 included potential disposal sites along Perimeter Road investigated in the late 1980s (Radian 1990) Chemical Pit 3 along with the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021 Site WP007 consists of two unlined trenches that were used for the disposal of unknown quantities of chlorinated spent solvents
Operable Unit 2 is addressed in two components the source zone and the non-source zone The source zone is on-Base and is the immediate area around the former Chemical Disposal Pit 3 that is underlain by a dense non-aqueous phase liquid (DNAPL) and affected areas west of Perimeter Road This area has the highest concentrations of contaminants and occupies approximately 6 acres (Figure 1) The non-source zone is north and east of the source zone and Perimeter Road The non-source zone includes shallow groundwater and seep and spring contamination off-Base This area generally has lower contaminant concentrations and occupies approximately 25 acres
An ESD is required to address differences in the following selected remedies for the OU 2 source zone treatment of extracted source zone groundwater with the existing Air Stripper Treatment Plant (ASTP) without pre-treatment by the existing steam stripper
In July 1987 the US Environmental Protection Agency (EPA) placed Hill AFB on the National Priorities List (NPL) under Comprehensive Environmental Response Compensation and Liability Act (CERCLA) In April 1991 Hill AFB entered a Federal Facility Agreement (FFA) with the Utah Department of Environmental Quality (UDEQ) and the EPA Region VIII to establish a procedural framework and schedule for implementing the appropriate response actions in accordance with existing regulations Under the FFA and Executive Order 12580 Hill AFB is the lead agency for all CERCLA actions and UDEQ and the EPA are support agencies Hill AFB seeks concurrence from both the EPA and UDEQ for significant decisions involving cleanup strategy goals and methods
This ESD is issued in accordance with Section 117(c) ofthe CERCLA 42 USC sect 9617(c) and Section 300435(c)(2)(i) ofthe National Oil and Hazardous Substances Pollution Contingency Plan (NCP) which requires the USAF to issue such a document where a remedial action will differ in any significant but not fundamental respect from that selected by the USAF and described in the ROD A significant change to a remedy is one that incrementally changes a component of a remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) The revised remedy described in this ESD
EXP IAN ATI ON OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
EXPLANATION TCE concentrations In
microsram plaquor Htsr (tilaquo1) frMM X004300
N
Conveyance Line to Central Weber Sewer Improvement
DistrFct
System (UCS) Trench L ^ v
Air Stripper Treatment
(ASTP) Plant r T ^ M (
1 - J A J A i SRS Process r I Building
Figure I Operable Unit 2 site features
complies with the NCP and the statutory requirements of CERLCA The ESD has been prepared to provide the public with an explanation of the nature of the modification to the selected remedy set forth in the ROD and to summarize the infonnation that supports this modification The ESD will become part of the Administrative Record file (40 CFR 300825(a)(2)) and the information repository (40 CFR 300435(c)(2)(i)(A)) for Hill AFB which is located and available for public review at
75CEG CEVR 7274 Wardleigh RD Hill AFB UT 84056-5137
EXIIANA HON UF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
The Administrative Record is also available for public review at
Weber State University - Ogden Campus Weber State University - Davis Campus Stewart Library Stewart Library 3850 University Circle 2750 University Park Blvd Ogden UT 84408 Layton UT 84041-9099 (801)626-6403
The USAF EPA and UDEQ conclude that the remedy selected in the ROD as modified by this ESD will meet the objectives and performance standards of the ROD
SUMMARY OF THE SITE HISTORY SITE CONDITIONS AND SELECTED REMEDY
Site History
Operable Unit 2 is located along the northeastem boundary of Hill AFB overlooking the Weber River Valley and is one of 13 Operable Units at Hill AFB in various stages ofthe CERCLA process Records indicate that from 1967 to 1975 unknown quantities of chlorinated organic solvents generated during degreasing operations were disposed in trenches (chemical pits) at the site These compounds were placed into two unlined disposal trenches trending north northwest which are estimated to have been approximately 6 to 9 feet deep 10 feet wide and approximately 50 to 100 feet long (Radian 1992) The disposal area is underlain by an alluvial sand aquifer that is composed of a heterogeneous mixture of sand and gravel contained in a narrow buried ancient river channel incised deeply into the underlying clay deposit This clay deposit known as the Alpine Formation forms a barrier to the downward migration of DNAPL
Disposal of the spent chlorinated solvents resulted in DNAPL contaminafion of the underlying shallow aquifer (the Provo Formation) predominantly as one or more pools above the clay (the Alpine Formation) and also as a residual phase held in the aquifers pore spaces (the volume in between individual soil particles) The recovered DNAPL consists primarily of several chlorinated solvents (about 70 percent trichloroethene [TCE] with smaller amounts of 111-trichloroethane [111-TCA] tetrachloroethene [PCE] and methylene chloride) 112 trichloro-122-trifluoroethane (Freon 113) and a lesser amount of oil and grease (URS and DEampS 2001) Contaminated soils near the trenches and the pooled DNAPL are the source of shallow dissolved phase groundwater contamination extending approximately 1500 feet downgradient and beyond the Hill AFB boundary (CH2M HILL 1996) Groundwater contamination appears limited to the shallow unconfined aquifer ofthe Provo Formation
Site Conditions
The on-Base portion of OU 2 sits upon relatively flat lying ground while the off-Base portion of the site consists of a steep terraced north-facing escarpment that is the south wall of the Weber River Valley There is about 300 feet of relief between Hill AFB and the valley below Parts of this hillside are unstable and are known as the Weber Landslide Complex Numerous seeps and
EXIIANA TION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
springs occur along the hillside Depending on water table elevation and the season the springs and seeps discharge water from the shallow groundwater system Depth to groundwater in the shallow system is generally less than 10 feet below ground surface (bgs) in the off-Base area and 20 feet bgs in the on-Base area Along the hillside escarpment and just outside ofthe northeastem Base boundary is the Davis-Weber Canal a privately owned concrete-lined irrigation canal The canal parallels the northeast boundary along most of the Base adjacent to the Weber River Valley The canal provides water from the Weber River for irrigation in the surrounding areas (CH2M HILL 1996)
Selected Remedy
The remedies that were selected for the OU 2 source zone are outlined in the Record of Decision issued in 1996 (CH2M HILL 1996) Those remedies include the following
bull Installadon of a low-permeability vertical barrier around the DNAPL and associated highly contaminated groundwater in the source zone to hinder flow to and from the source zone
bull Continued operation of the Source Recovery System (SRS) to remove DNAPL to the maximum extent practicable and to treat shallow groundwater containing high concentrations of VOCs using steam stripping
bull Completion of planned treatability studies using in-situ steam stripping and surfactant flushing for enhanced DNAPL recovery
bull Soil vapor extraction (SVE) after dewatering of the shallow aquifer to remove VOCs from subsurface soils in what is currently the saturated zone
bull Construction of a surface cap once treatment is completed or it is established the innovative technologies cannot meet remedial action objectives to decrease the inflow of precipitation and prevent erosion of surface soils
bull Environmental monitoring to evaluate the effectiveness of the remedy
bull Institutional controls to minimize exposure by limiting use and preventing access to Contaminated water and soil
One of the remedies specified by the ROD is a low permeability containment wall encircling the source zone to reduce the potential for further contamination of groundwater After the wall was built however an additional accumulation of free-phase DNAPL was identified outside of the wall (URS and DEampS 1999) This accumulation is informally known as either the Griffith Pool or the G-Pool A well field was installed in 1998 to extract mobile DNAPL from the area and to hydraulically contain the groundwater to minimize further contaminant flux to the off-Base plume
DESCRIPTION OF AND BASIS FOR THE DIFFERENCES
The SRS was constructed as an interim remedial action in 1993 to recover DNAPL from the source zone and to treat groundwater containing elevated concentrations of VOCs The SRS consists of a free-product and groundwater recovery well field aboveground pipeline and a process treatment facility (Building 755) Dense nonaqueous phase liquid is recovered during the
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
HXPIANA riUN OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
Explanation of Significant Differences Operable Unit 2 (OU 2) Hill Air Force Base Utah
INTRODUCTION
This Explanation of Significant Differences (ESD) relates to remedial actions selected by the United States Air Force (USAF) for implementation at Operable Unit 2 (OU 2) at Hill Air Force Base (AFB) Utah in a Record of Decision (ROD) issued in September 1996 (CH2M HILL 1996) Operable Unit 2 is comprised of two Installation Restoration Program (IRP) sites Chemical Pit 3 (WP007) and the Perimeter Road (SS021) Site SS021 included potential disposal sites along Perimeter Road investigated in the late 1980s (Radian 1990) Chemical Pit 3 along with the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021 Site WP007 consists of two unlined trenches that were used for the disposal of unknown quantities of chlorinated spent solvents
Operable Unit 2 is addressed in two components the source zone and the non-source zone The source zone is on-Base and is the immediate area around the former Chemical Disposal Pit 3 that is underlain by a dense non-aqueous phase liquid (DNAPL) and affected areas west of Perimeter Road This area has the highest concentrations of contaminants and occupies approximately 6 acres (Figure 1) The non-source zone is north and east of the source zone and Perimeter Road The non-source zone includes shallow groundwater and seep and spring contamination off-Base This area generally has lower contaminant concentrations and occupies approximately 25 acres
An ESD is required to address differences in the following selected remedies for the OU 2 source zone treatment of extracted source zone groundwater with the existing Air Stripper Treatment Plant (ASTP) without pre-treatment by the existing steam stripper
In July 1987 the US Environmental Protection Agency (EPA) placed Hill AFB on the National Priorities List (NPL) under Comprehensive Environmental Response Compensation and Liability Act (CERCLA) In April 1991 Hill AFB entered a Federal Facility Agreement (FFA) with the Utah Department of Environmental Quality (UDEQ) and the EPA Region VIII to establish a procedural framework and schedule for implementing the appropriate response actions in accordance with existing regulations Under the FFA and Executive Order 12580 Hill AFB is the lead agency for all CERCLA actions and UDEQ and the EPA are support agencies Hill AFB seeks concurrence from both the EPA and UDEQ for significant decisions involving cleanup strategy goals and methods
This ESD is issued in accordance with Section 117(c) ofthe CERCLA 42 USC sect 9617(c) and Section 300435(c)(2)(i) ofthe National Oil and Hazardous Substances Pollution Contingency Plan (NCP) which requires the USAF to issue such a document where a remedial action will differ in any significant but not fundamental respect from that selected by the USAF and described in the ROD A significant change to a remedy is one that incrementally changes a component of a remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) The revised remedy described in this ESD
EXP IAN ATI ON OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
EXPLANATION TCE concentrations In
microsram plaquor Htsr (tilaquo1) frMM X004300
N
Conveyance Line to Central Weber Sewer Improvement
DistrFct
System (UCS) Trench L ^ v
Air Stripper Treatment
(ASTP) Plant r T ^ M (
1 - J A J A i SRS Process r I Building
Figure I Operable Unit 2 site features
complies with the NCP and the statutory requirements of CERLCA The ESD has been prepared to provide the public with an explanation of the nature of the modification to the selected remedy set forth in the ROD and to summarize the infonnation that supports this modification The ESD will become part of the Administrative Record file (40 CFR 300825(a)(2)) and the information repository (40 CFR 300435(c)(2)(i)(A)) for Hill AFB which is located and available for public review at
75CEG CEVR 7274 Wardleigh RD Hill AFB UT 84056-5137
EXIIANA HON UF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
The Administrative Record is also available for public review at
Weber State University - Ogden Campus Weber State University - Davis Campus Stewart Library Stewart Library 3850 University Circle 2750 University Park Blvd Ogden UT 84408 Layton UT 84041-9099 (801)626-6403
The USAF EPA and UDEQ conclude that the remedy selected in the ROD as modified by this ESD will meet the objectives and performance standards of the ROD
SUMMARY OF THE SITE HISTORY SITE CONDITIONS AND SELECTED REMEDY
Site History
Operable Unit 2 is located along the northeastem boundary of Hill AFB overlooking the Weber River Valley and is one of 13 Operable Units at Hill AFB in various stages ofthe CERCLA process Records indicate that from 1967 to 1975 unknown quantities of chlorinated organic solvents generated during degreasing operations were disposed in trenches (chemical pits) at the site These compounds were placed into two unlined disposal trenches trending north northwest which are estimated to have been approximately 6 to 9 feet deep 10 feet wide and approximately 50 to 100 feet long (Radian 1992) The disposal area is underlain by an alluvial sand aquifer that is composed of a heterogeneous mixture of sand and gravel contained in a narrow buried ancient river channel incised deeply into the underlying clay deposit This clay deposit known as the Alpine Formation forms a barrier to the downward migration of DNAPL
Disposal of the spent chlorinated solvents resulted in DNAPL contaminafion of the underlying shallow aquifer (the Provo Formation) predominantly as one or more pools above the clay (the Alpine Formation) and also as a residual phase held in the aquifers pore spaces (the volume in between individual soil particles) The recovered DNAPL consists primarily of several chlorinated solvents (about 70 percent trichloroethene [TCE] with smaller amounts of 111-trichloroethane [111-TCA] tetrachloroethene [PCE] and methylene chloride) 112 trichloro-122-trifluoroethane (Freon 113) and a lesser amount of oil and grease (URS and DEampS 2001) Contaminated soils near the trenches and the pooled DNAPL are the source of shallow dissolved phase groundwater contamination extending approximately 1500 feet downgradient and beyond the Hill AFB boundary (CH2M HILL 1996) Groundwater contamination appears limited to the shallow unconfined aquifer ofthe Provo Formation
Site Conditions
The on-Base portion of OU 2 sits upon relatively flat lying ground while the off-Base portion of the site consists of a steep terraced north-facing escarpment that is the south wall of the Weber River Valley There is about 300 feet of relief between Hill AFB and the valley below Parts of this hillside are unstable and are known as the Weber Landslide Complex Numerous seeps and
EXIIANA TION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
springs occur along the hillside Depending on water table elevation and the season the springs and seeps discharge water from the shallow groundwater system Depth to groundwater in the shallow system is generally less than 10 feet below ground surface (bgs) in the off-Base area and 20 feet bgs in the on-Base area Along the hillside escarpment and just outside ofthe northeastem Base boundary is the Davis-Weber Canal a privately owned concrete-lined irrigation canal The canal parallels the northeast boundary along most of the Base adjacent to the Weber River Valley The canal provides water from the Weber River for irrigation in the surrounding areas (CH2M HILL 1996)
Selected Remedy
The remedies that were selected for the OU 2 source zone are outlined in the Record of Decision issued in 1996 (CH2M HILL 1996) Those remedies include the following
bull Installadon of a low-permeability vertical barrier around the DNAPL and associated highly contaminated groundwater in the source zone to hinder flow to and from the source zone
bull Continued operation of the Source Recovery System (SRS) to remove DNAPL to the maximum extent practicable and to treat shallow groundwater containing high concentrations of VOCs using steam stripping
bull Completion of planned treatability studies using in-situ steam stripping and surfactant flushing for enhanced DNAPL recovery
bull Soil vapor extraction (SVE) after dewatering of the shallow aquifer to remove VOCs from subsurface soils in what is currently the saturated zone
bull Construction of a surface cap once treatment is completed or it is established the innovative technologies cannot meet remedial action objectives to decrease the inflow of precipitation and prevent erosion of surface soils
bull Environmental monitoring to evaluate the effectiveness of the remedy
bull Institutional controls to minimize exposure by limiting use and preventing access to Contaminated water and soil
One of the remedies specified by the ROD is a low permeability containment wall encircling the source zone to reduce the potential for further contamination of groundwater After the wall was built however an additional accumulation of free-phase DNAPL was identified outside of the wall (URS and DEampS 1999) This accumulation is informally known as either the Griffith Pool or the G-Pool A well field was installed in 1998 to extract mobile DNAPL from the area and to hydraulically contain the groundwater to minimize further contaminant flux to the off-Base plume
DESCRIPTION OF AND BASIS FOR THE DIFFERENCES
The SRS was constructed as an interim remedial action in 1993 to recover DNAPL from the source zone and to treat groundwater containing elevated concentrations of VOCs The SRS consists of a free-product and groundwater recovery well field aboveground pipeline and a process treatment facility (Building 755) Dense nonaqueous phase liquid is recovered during the
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXP IAN ATI ON OF SIGNIFICANT DIFFERENCES OUl HILL AFB UTAH
EXPLANATION TCE concentrations In
microsram plaquor Htsr (tilaquo1) frMM X004300
N
Conveyance Line to Central Weber Sewer Improvement
DistrFct
System (UCS) Trench L ^ v
Air Stripper Treatment
(ASTP) Plant r T ^ M (
1 - J A J A i SRS Process r I Building
Figure I Operable Unit 2 site features
complies with the NCP and the statutory requirements of CERLCA The ESD has been prepared to provide the public with an explanation of the nature of the modification to the selected remedy set forth in the ROD and to summarize the infonnation that supports this modification The ESD will become part of the Administrative Record file (40 CFR 300825(a)(2)) and the information repository (40 CFR 300435(c)(2)(i)(A)) for Hill AFB which is located and available for public review at
75CEG CEVR 7274 Wardleigh RD Hill AFB UT 84056-5137
EXIIANA HON UF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
The Administrative Record is also available for public review at
Weber State University - Ogden Campus Weber State University - Davis Campus Stewart Library Stewart Library 3850 University Circle 2750 University Park Blvd Ogden UT 84408 Layton UT 84041-9099 (801)626-6403
The USAF EPA and UDEQ conclude that the remedy selected in the ROD as modified by this ESD will meet the objectives and performance standards of the ROD
SUMMARY OF THE SITE HISTORY SITE CONDITIONS AND SELECTED REMEDY
Site History
Operable Unit 2 is located along the northeastem boundary of Hill AFB overlooking the Weber River Valley and is one of 13 Operable Units at Hill AFB in various stages ofthe CERCLA process Records indicate that from 1967 to 1975 unknown quantities of chlorinated organic solvents generated during degreasing operations were disposed in trenches (chemical pits) at the site These compounds were placed into two unlined disposal trenches trending north northwest which are estimated to have been approximately 6 to 9 feet deep 10 feet wide and approximately 50 to 100 feet long (Radian 1992) The disposal area is underlain by an alluvial sand aquifer that is composed of a heterogeneous mixture of sand and gravel contained in a narrow buried ancient river channel incised deeply into the underlying clay deposit This clay deposit known as the Alpine Formation forms a barrier to the downward migration of DNAPL
Disposal of the spent chlorinated solvents resulted in DNAPL contaminafion of the underlying shallow aquifer (the Provo Formation) predominantly as one or more pools above the clay (the Alpine Formation) and also as a residual phase held in the aquifers pore spaces (the volume in between individual soil particles) The recovered DNAPL consists primarily of several chlorinated solvents (about 70 percent trichloroethene [TCE] with smaller amounts of 111-trichloroethane [111-TCA] tetrachloroethene [PCE] and methylene chloride) 112 trichloro-122-trifluoroethane (Freon 113) and a lesser amount of oil and grease (URS and DEampS 2001) Contaminated soils near the trenches and the pooled DNAPL are the source of shallow dissolved phase groundwater contamination extending approximately 1500 feet downgradient and beyond the Hill AFB boundary (CH2M HILL 1996) Groundwater contamination appears limited to the shallow unconfined aquifer ofthe Provo Formation
Site Conditions
The on-Base portion of OU 2 sits upon relatively flat lying ground while the off-Base portion of the site consists of a steep terraced north-facing escarpment that is the south wall of the Weber River Valley There is about 300 feet of relief between Hill AFB and the valley below Parts of this hillside are unstable and are known as the Weber Landslide Complex Numerous seeps and
EXIIANA TION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
springs occur along the hillside Depending on water table elevation and the season the springs and seeps discharge water from the shallow groundwater system Depth to groundwater in the shallow system is generally less than 10 feet below ground surface (bgs) in the off-Base area and 20 feet bgs in the on-Base area Along the hillside escarpment and just outside ofthe northeastem Base boundary is the Davis-Weber Canal a privately owned concrete-lined irrigation canal The canal parallels the northeast boundary along most of the Base adjacent to the Weber River Valley The canal provides water from the Weber River for irrigation in the surrounding areas (CH2M HILL 1996)
Selected Remedy
The remedies that were selected for the OU 2 source zone are outlined in the Record of Decision issued in 1996 (CH2M HILL 1996) Those remedies include the following
bull Installadon of a low-permeability vertical barrier around the DNAPL and associated highly contaminated groundwater in the source zone to hinder flow to and from the source zone
bull Continued operation of the Source Recovery System (SRS) to remove DNAPL to the maximum extent practicable and to treat shallow groundwater containing high concentrations of VOCs using steam stripping
bull Completion of planned treatability studies using in-situ steam stripping and surfactant flushing for enhanced DNAPL recovery
bull Soil vapor extraction (SVE) after dewatering of the shallow aquifer to remove VOCs from subsurface soils in what is currently the saturated zone
bull Construction of a surface cap once treatment is completed or it is established the innovative technologies cannot meet remedial action objectives to decrease the inflow of precipitation and prevent erosion of surface soils
bull Environmental monitoring to evaluate the effectiveness of the remedy
bull Institutional controls to minimize exposure by limiting use and preventing access to Contaminated water and soil
One of the remedies specified by the ROD is a low permeability containment wall encircling the source zone to reduce the potential for further contamination of groundwater After the wall was built however an additional accumulation of free-phase DNAPL was identified outside of the wall (URS and DEampS 1999) This accumulation is informally known as either the Griffith Pool or the G-Pool A well field was installed in 1998 to extract mobile DNAPL from the area and to hydraulically contain the groundwater to minimize further contaminant flux to the off-Base plume
DESCRIPTION OF AND BASIS FOR THE DIFFERENCES
The SRS was constructed as an interim remedial action in 1993 to recover DNAPL from the source zone and to treat groundwater containing elevated concentrations of VOCs The SRS consists of a free-product and groundwater recovery well field aboveground pipeline and a process treatment facility (Building 755) Dense nonaqueous phase liquid is recovered during the
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXIIANA HON UF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
The Administrative Record is also available for public review at
Weber State University - Ogden Campus Weber State University - Davis Campus Stewart Library Stewart Library 3850 University Circle 2750 University Park Blvd Ogden UT 84408 Layton UT 84041-9099 (801)626-6403
The USAF EPA and UDEQ conclude that the remedy selected in the ROD as modified by this ESD will meet the objectives and performance standards of the ROD
SUMMARY OF THE SITE HISTORY SITE CONDITIONS AND SELECTED REMEDY
Site History
Operable Unit 2 is located along the northeastem boundary of Hill AFB overlooking the Weber River Valley and is one of 13 Operable Units at Hill AFB in various stages ofthe CERCLA process Records indicate that from 1967 to 1975 unknown quantities of chlorinated organic solvents generated during degreasing operations were disposed in trenches (chemical pits) at the site These compounds were placed into two unlined disposal trenches trending north northwest which are estimated to have been approximately 6 to 9 feet deep 10 feet wide and approximately 50 to 100 feet long (Radian 1992) The disposal area is underlain by an alluvial sand aquifer that is composed of a heterogeneous mixture of sand and gravel contained in a narrow buried ancient river channel incised deeply into the underlying clay deposit This clay deposit known as the Alpine Formation forms a barrier to the downward migration of DNAPL
Disposal of the spent chlorinated solvents resulted in DNAPL contaminafion of the underlying shallow aquifer (the Provo Formation) predominantly as one or more pools above the clay (the Alpine Formation) and also as a residual phase held in the aquifers pore spaces (the volume in between individual soil particles) The recovered DNAPL consists primarily of several chlorinated solvents (about 70 percent trichloroethene [TCE] with smaller amounts of 111-trichloroethane [111-TCA] tetrachloroethene [PCE] and methylene chloride) 112 trichloro-122-trifluoroethane (Freon 113) and a lesser amount of oil and grease (URS and DEampS 2001) Contaminated soils near the trenches and the pooled DNAPL are the source of shallow dissolved phase groundwater contamination extending approximately 1500 feet downgradient and beyond the Hill AFB boundary (CH2M HILL 1996) Groundwater contamination appears limited to the shallow unconfined aquifer ofthe Provo Formation
Site Conditions
The on-Base portion of OU 2 sits upon relatively flat lying ground while the off-Base portion of the site consists of a steep terraced north-facing escarpment that is the south wall of the Weber River Valley There is about 300 feet of relief between Hill AFB and the valley below Parts of this hillside are unstable and are known as the Weber Landslide Complex Numerous seeps and
EXIIANA TION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
springs occur along the hillside Depending on water table elevation and the season the springs and seeps discharge water from the shallow groundwater system Depth to groundwater in the shallow system is generally less than 10 feet below ground surface (bgs) in the off-Base area and 20 feet bgs in the on-Base area Along the hillside escarpment and just outside ofthe northeastem Base boundary is the Davis-Weber Canal a privately owned concrete-lined irrigation canal The canal parallels the northeast boundary along most of the Base adjacent to the Weber River Valley The canal provides water from the Weber River for irrigation in the surrounding areas (CH2M HILL 1996)
Selected Remedy
The remedies that were selected for the OU 2 source zone are outlined in the Record of Decision issued in 1996 (CH2M HILL 1996) Those remedies include the following
bull Installadon of a low-permeability vertical barrier around the DNAPL and associated highly contaminated groundwater in the source zone to hinder flow to and from the source zone
bull Continued operation of the Source Recovery System (SRS) to remove DNAPL to the maximum extent practicable and to treat shallow groundwater containing high concentrations of VOCs using steam stripping
bull Completion of planned treatability studies using in-situ steam stripping and surfactant flushing for enhanced DNAPL recovery
bull Soil vapor extraction (SVE) after dewatering of the shallow aquifer to remove VOCs from subsurface soils in what is currently the saturated zone
bull Construction of a surface cap once treatment is completed or it is established the innovative technologies cannot meet remedial action objectives to decrease the inflow of precipitation and prevent erosion of surface soils
bull Environmental monitoring to evaluate the effectiveness of the remedy
bull Institutional controls to minimize exposure by limiting use and preventing access to Contaminated water and soil
One of the remedies specified by the ROD is a low permeability containment wall encircling the source zone to reduce the potential for further contamination of groundwater After the wall was built however an additional accumulation of free-phase DNAPL was identified outside of the wall (URS and DEampS 1999) This accumulation is informally known as either the Griffith Pool or the G-Pool A well field was installed in 1998 to extract mobile DNAPL from the area and to hydraulically contain the groundwater to minimize further contaminant flux to the off-Base plume
DESCRIPTION OF AND BASIS FOR THE DIFFERENCES
The SRS was constructed as an interim remedial action in 1993 to recover DNAPL from the source zone and to treat groundwater containing elevated concentrations of VOCs The SRS consists of a free-product and groundwater recovery well field aboveground pipeline and a process treatment facility (Building 755) Dense nonaqueous phase liquid is recovered during the
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXIIANA TION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
springs occur along the hillside Depending on water table elevation and the season the springs and seeps discharge water from the shallow groundwater system Depth to groundwater in the shallow system is generally less than 10 feet below ground surface (bgs) in the off-Base area and 20 feet bgs in the on-Base area Along the hillside escarpment and just outside ofthe northeastem Base boundary is the Davis-Weber Canal a privately owned concrete-lined irrigation canal The canal parallels the northeast boundary along most of the Base adjacent to the Weber River Valley The canal provides water from the Weber River for irrigation in the surrounding areas (CH2M HILL 1996)
Selected Remedy
The remedies that were selected for the OU 2 source zone are outlined in the Record of Decision issued in 1996 (CH2M HILL 1996) Those remedies include the following
bull Installadon of a low-permeability vertical barrier around the DNAPL and associated highly contaminated groundwater in the source zone to hinder flow to and from the source zone
bull Continued operation of the Source Recovery System (SRS) to remove DNAPL to the maximum extent practicable and to treat shallow groundwater containing high concentrations of VOCs using steam stripping
bull Completion of planned treatability studies using in-situ steam stripping and surfactant flushing for enhanced DNAPL recovery
bull Soil vapor extraction (SVE) after dewatering of the shallow aquifer to remove VOCs from subsurface soils in what is currently the saturated zone
bull Construction of a surface cap once treatment is completed or it is established the innovative technologies cannot meet remedial action objectives to decrease the inflow of precipitation and prevent erosion of surface soils
bull Environmental monitoring to evaluate the effectiveness of the remedy
bull Institutional controls to minimize exposure by limiting use and preventing access to Contaminated water and soil
One of the remedies specified by the ROD is a low permeability containment wall encircling the source zone to reduce the potential for further contamination of groundwater After the wall was built however an additional accumulation of free-phase DNAPL was identified outside of the wall (URS and DEampS 1999) This accumulation is informally known as either the Griffith Pool or the G-Pool A well field was installed in 1998 to extract mobile DNAPL from the area and to hydraulically contain the groundwater to minimize further contaminant flux to the off-Base plume
DESCRIPTION OF AND BASIS FOR THE DIFFERENCES
The SRS was constructed as an interim remedial action in 1993 to recover DNAPL from the source zone and to treat groundwater containing elevated concentrations of VOCs The SRS consists of a free-product and groundwater recovery well field aboveground pipeline and a process treatment facility (Building 755) Dense nonaqueous phase liquid is recovered during the
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPLANA TIONOF SIGNIFICANT DIFFERENCES 0U2HIUAFB UTAH
treatment process using three phase separators while dissolved VOCs are removed from the groundwater using a packed-bed steam stripper In 1996 the Air Stripper Treatment Plant (ASTP) was constructed at OU 2 to provide secondary treatment of groundwater frorn the source zone following initial treatment with the steam stripper Prior to 2005 water was discharged from the ASTP to the on-base industrial wastewater treatment plant In 2005 an agreement was signed with Central Weber Sewer Improvement District (CWSID) allowing discharge oftreated water from OU 2 into the sanitary sewer Figure 2 provides a simplified process flow diagram illustrating the difference in the treatment process described in this ESD
Previous process flow
SRS Stop 1 DNAPL
separation
SRS Step 2 Steam
stripping
Pumped water from source zone
Discharge to sanitarYscver
Current process fiovi^
ASTP Air
stripping
Pumped water from source zone
Discharge to sanitary sewer
Figure 2 Simplified process flow diagram for OU 2 water treatment
Since 1992 approximately 44400 gallons of DNAPL have been recovered and over 20 million gallons of contaminated groundwater have been treated by steam stripping Of the total volume of DNAPL recovered 41000 gallons have been recovered primarily as mobile DNAPL via pump-and-treat operations and 3400 gallons have been recovered using enhanced-removal techniques Because the DNAPL recovery from the source zone has been successful DNAPL can no longer be extracted from the existing well field As the amount of DNAPL has decreased within the source zone the average concentration of VOCs in water extracted from the source zone has declined The average concentration of total VOCs in the influent to the SRS historically has ranged from 100 to 300 milligrams per liter (mgL) but concentrations generally have decreased to less than 100 mgL since the beginning of 2006 Hill AFB decided to evaluate
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
altemative treatment options because the concentrations of VOCs being treated by the steam stripping process were decreasing
In 2007 Hill AFB proposed testing to determine if source zone water could be treated with the existing ASTP without pre-treatment by the steam stripper (January 25 2007 Project Managers meeting and letter dated March 152007) Piping modifications were completed during the fall of 2007 and initial testing was conducted during January and Febmary 2008 The results of this initial testing clearly showed that the ASTP is capable of achieving the treatment required to maintain compliance with the existing CWSED wastewater discharge permit without preshytreatment by the steam stripper Based on the initial results treatment of source zone water using the ASTP was continued to collect additional data to verify VOC removal efficiency over a one-year prove-out period This prove-out period included increased monitoring of both influent and effluent to the ASTP to allow evaluation of variability in either ASTP operating efficiency andor influent water concentrations
Currently the discharge limit to the CWSID is 2100 ^gL total volatiles (Method E624) The ASTP effluent concentrations remained below this discharge limit during 2008 as shown in Table 1 The calculated treatment efficiency was nominally 100 percent during 24 of 26 sampling events The remaining two sampling events had treatment efficiencies of 998 and 999 percent Figure 3 presents the ASTP effluent concentration over time As is evident from Figure 3 the total VOC concentration in the ASTP effluent has consistentiy been below the discharge limit and has not increased since piping modifications were completed during the fall of 2007
The fact that extracted source zone groundwater at OU 2 is no longer being pre-treated using the steam stripper constitutes a significant but not fundamental difference to the selected remedy outlined in the ROD This modification to the OU 2 source zone treatment system still provides safe and effective groundwater treatment with no additional environmental risk and with no added time to achieve cleanup
PUBLIC PARTICIPATION
This ESD was discussed during the July 30 2009 Restoration Advisory Board (RAB) meeting Discussion will include public notification procedures for ESDs The RAB will be requested to review both the process Hill AFB is using to prepare this ESD and the technical differences documented in this ESD
The RAB will be notified of the submission of the finalized ESD at the first quarterly RAB meeting after the ESD is signed Hill AFB will publish a notice of availability and a brief description ofthe ESD in the local newspaper Ogden Standard Examiner the week following
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPIANA TION OF SIGNIFICNT DIFFERENCES OU 2 HILL AFB UTAH
TABLE 1 ASTP Total VOC Influent and Effluent Concentrations During 2008
Sample Date
012508
012908
020508
020808
021908
022908
030608
032508
040208
040408
040708
040808
040908
041008
041108
051408
052808
061008
062608
070808
072108
081808
090908
100808
111308
120908
Influent Concentration
(MgL) 104997
14603
159587
209442
3119
63952
72079
637
345
511
462
630
955
1013
1177
1015
1346
940
1342
1644
1239
1318
572
54466
158879
126171
Effluent Concentration
(ugL) 189
182
360
209
130
092
043
000
000
020
000
000
000
000
020
000
000
000
000
140
000
000
000
050
040
080
Treatment Efficiency (percent)
1000
1000
998
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1000
999
1000
1000
1000
1000
1000
1000
NOTES ngL = Micrograms per Liter VOC = Volatile Organic Compound Total VOCs calculated based on Method E624
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
j
bull9
c o
5 c o c o o o O gt
o 1 -
1000000
100000
10000
1000
100
10
1
0
i 1
reg Influent
bull Effluent
^ 1 1 1
copy
9 c
raquo copy
CWSID Discharge Permit Concentration 2100 |igL Total Volatiles
s bull bull
c c ra
- 3
reg
regreg reg
1 bull
reg
reg
Jan-04
Jan-05 lt lt
Jan-06 1
Jan-07
1
Jan-08
Jan-09
Figure 3 ASTP Influent and Effluent Total VOC (Method E624) Concentration over Time
that RAB meeting This ESD and the infonnation upon which it is based will be included in the Administrative Record for this Site The Administrative Record also includes the ROD and all documents that formed the basis for USAFs selection and EPA and UDEQs concurrence ofthe remedial action for the Site These components meet the public participation requirement set out in Section 3()0435(c)(2)(i) of the NCP
REFERENCES
CH2M HILL 1996 Record of Decision and Respomiveness Summary for Operable Unit 2 Final Hill AFB Utah September
CH2M HILL 200 Performance Standard Verification Plan Operable Unit 2 Final Hill AFB Utah November
Radian 1990 Site Evaluation Report for Perimeter Road and the Spoils Area Final Hill AFB Utah August
Radian 1992 Remedial Investigation Report for Operable Unit 2 Hill AFB Utah July
URS and DEampS 1999 Dense Nonaqueous Phase Liquid (DNAPL) Source Delineation Project Final Report Operable Unit 2 Hill AFB Utah September
URS and DEampS 2001 SEAR Technology Application at Operable Unit 2 Volumes I and II Hill AFB Utah May
8
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPIANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
AGENCY COMMENTS
The USAF submitted this ESD to the EPA and UDEQ for their review and comment Comments from both the EPA and UDEQ along with the USAF response are included as follows
UDEQ Comments viith Air Force responses in italics
GENERAL COMMENTS bull Please number all the pages throughout the document bull Please include a figure depicting the 0U2 layout bull Please include separate signature page for each agency It will facilitate the signing
process
Response Page numbers will he added to all pages A figure will be included showing the OUl site The signature pages will be separated as requested
SPECIFIC COMMENTS
i Introduction First Paragraph 5th line Please replace the word ROD with Remedial Investigation
2 Introduction First Paragraph Last line Please insert spent prior to chlorinated solvents 3 Public Participation First Line Please change This ESD will be discussed to This
ESD was discussed
Response Because this part ofthe section caused confusion for multiple reviewers the sentence Based on the ROD Site SS021 is free of contamination with the exception of a few areas being evaluated as part of other Operable Units and this site was recommended for no further remedial action will be replaced with Site SS02I included potential disposal sites along Perimeter Road investigated in the late I980s (Radian J990) Chemical Pit 3 and the North Gate Dump Sites (now part of Operable Unit 4) were the only sites where contamination was identified The ROD for OU 2 concluded that no further action was required for SS021
Response spent will be added as requested
Response The text was updated as requested
EPA Comments with Air Force responses in italics
Introduction First Paragraph states Perimeter Road (SS021) is free of contamination with the exception of a few areas being evaluated else as part of other OUs and this site was recommended for NFRAP Can you state or show on a map the areas being tracked under other OUs
Response Please see response to Specific Comment 1 above
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPhXNATION OF SIGNIFICANT DIFFERENCES ou 2 HILL AFB UTAH
Fifth Paragraph states that this ESD is issued in accordance with Section 117(c) which requires the USAF to issue a document where a remedial action will differ in any significant but not fundamental respect from the ROD Significant and Fundamental should be defined here instead of under the Description and Basis for the Differences
Response Agreed The sentence A significant change to a remedy is one that incrementally changes a component ofa remedy (such as cost) but does not fundamentally alter the remedy (such as a change in the selected pump-and-treat remedy) will be added after the sentence ending USAF and described in the ROD in the fifth paragraph ofthe Introduction section The sentence will be removed from the fifth paragraph ofthe Description and Basis for the Differences section
STATUTORY DETERMINATIONS
The Applicable or Relevant and Appropriate Requirements (ARARs) addressed by the ROD for OU 2 are not modified by this ESD Considering the clarifications regarding the selected remedies presented in this ESD the USAF EPA and UDEQ all concur that the remedies at OU 2 remain protective of human health and the environment comply with federal and state requirements that were identified in the ROD as ARARs and are cost-effective There are no changes to the anticipated remediation time frame as a result of the Air Forces adoption of these differences from the ROD The remedy satisfies CERCLA Section 121
Signatures
10
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
75TH AIR BASE WING (AFMC) HILL AIR FORCE BASE UTAH
^ T R I C K C HI Commander
Date
n
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPUNA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
UNITED STATES ENVIORNMENTAL PROTECTION AGENCY
CAROL L CAMPBELL 0 Date ^ Assistant Regional Administrator Office of Ecosystems Protection and Remediation US EPA Region VIII
12
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13
EXPLANA TION OF SIGNIFICANT DIFFERENCES OU 2 HILL AFB UTAH
STATE OF UTAH DEPARTMENT OF ENVIORNMENTAL QUALITY
)A SMITH Executive Director Utah Department of Environmental Quality
O fCO^L^ Date
13