ENGAGED PROJECT THIS MONTH
System Support System Development
- Develop the BCS
> Budget System > POS System
> Premium Collection
> FYC method
- Data Center of N’orch
- Data Center of DaNang
- Data Center of DongNai
- Data Center of TWC
Data Center of N’orch
Sign the IBM AIX MA Contract for year 2010.A
Sign the PCMA with Tien My Company for year 2010. B
Clean the pipes of chiller machine for DC air conditioner.C
Data Center of DaNang
Support to move all IT devices (Network device. PBX system) to new building.
A
Support to change the leased line to new building.B
Data Center of DongNai
Finish the approval report and send back the quotations to suppliers.
A
Sign the contracts of all devices for DongNai.B
Deploy the MPLS fiber cable for N’orch building.C
Develop the BCS system
AS attaining Quota(%)
BFinish the six statistics reports for POS:
• Suspend Data Enquiry• Surrender Data Enquiry• Monthly Surrender Enquiry• No-Taken Data Enquiry• Monthly Not-Taken Enquiry• Not-Taken Analysis Report Enquiry
Complete the second phase of Budget System.
A
Develop the BCS system (Cont.)
CProcess to modify FYC method:1. Finish FYC target of daily report into system.2. Finish FYC rate of new products into system.3. Finish SPEC documents and test for agent performance
salary.4. Finish the agent performance of 200913 in testing
system and pass these data to AA and Planning dep. to confirm.
5. The remainder performance scores for agent salary are already paid in one time at 200913.
Develop the BCS system (Cont.)
Install function for Premium Collection:1. The reasons for non-receipt of premium.2. Habits that policy owners pay the premium.
D
Support to test Bancassurance product in BCS system.E
PLANNING PROJECT FOR NEXT MONTH
Continue to trace the DongNai CS schedule.A
Finish to modify FYC method and Install the FYC daily report to BCS system.
B
Maintain BCS and B2E system.C