Method Statement A.) TREATMENT FOR CONSTRUCTION JOINT WITH “SpECbuild SG 15” POLYMER MODIFIED REPAIR COMPOUND 1. Cut a V – grove along the constriction joints approx. 20 x 20mm. 2. Clean and prepare the surface thoroughly to remove dust etc. 3. Wet and saturate the concrete with water and allow the surface to partly dry so that it is damp. 4. Apply “SpECbuild Primer S 1” by brush after removing any standing water. 5. Once the primer becomes tacky, apply “SpECbuild SG 15” mixed with correct amount of water with a gloved hand to ensure thorough compaction and finish with steel trowel. 6. Cure with water. B.) WATERPROOFING FOR SWIMMING POOL WITH “SpECtite CW100” FLEXIBLE CEMENTITIOUS WATERPROOFING SYSTEM 7. Wire brush and remove all loose material and prepare the surface to receive the waterproofing. 8. Wet the concrete and allow the surface to partly dry so that it is damp. 9. Apply 1 st coat of “SpECtite CW 100” 2-part flexible cementitious waterproof membrane by brush in one direction at wet film thickness of 0.75 – 1.0mm on the floor and wall. Allow to dry for minimum 3 hrs. 10. Apply 2 nd coat of “SpECtite CW 100” flexible cementitious waterproof membrane by brush in one direction at wet film thickness of 0.75 – 1.0mm on the floor and wall. Solico International (Pvt) ltd

Swimming Pool

Embed Size (px)

DESCRIPTION

Tecnical Daata

Citation preview

Page 1: Swimming Pool

Method Statement

A.) TREATMENT FOR CONSTRUCTION JOINT WITH “SpECbuild SG 15” POLYMER MODIFIED REPAIR COMPOUND

1. Cut a V – grove along the constriction joints approx. 20 x 20mm.

2. Clean and prepare the surface thoroughly to remove dust etc.

3. Wet and saturate the concrete with water and allow the surface to partly dry so that it is damp.

4. Apply “SpECbuild Primer S 1” by brush after removing any standing water.

5. Once the primer becomes tacky, apply “SpECbuild SG 15” mixed with correct amount of water with a gloved hand to ensure thorough compaction and finish with steel trowel.

6. Cure with water.

B.) WATERPROOFING FOR SWIMMING POOL WITH “SpECtite CW100” FLEXIBLE CEMENTITIOUS WATERPROOFING SYSTEM

7. Wire brush and remove all loose material and prepare the surface to receive the waterproofing.

8. Wet the concrete and allow the surface to partly dry so that it is damp.

9. Apply 1st coat of “SpECtite CW 100” 2-part flexible cementitious waterproof membrane by brush in one direction at wet film thickness of 0.75 – 1.0mm on the floor and wall. Allow to dry for minimum 3 hrs.

10. Apply 2nd coat of “SpECtite CW 100” flexible cementitious waterproof membrane by brush in one direction at wet film thickness of 0.75 – 1.0mm on the floor and wall.

11. Allow to cure for 2 days.

12. Carry out water testing by ponding the relevant area with water for 3 days (water shall be supplied by the client / main contractor at the point of working)

13. The client / main contractor shall lay cement sand protective screed (tile bedding) on the waterproofing soon after water test is complete.