WITH THE CONSTRUCTION START OF THE I NTEGRATED S CIENCE FACILITY (ISF) THIS OCTOBER, GENESEO COLLEGE IS EMBARKING ON THE LARGEST SINGLE CONSTRUCTION PROJECT IN COLLEGE HISTORY. THE PIKE COMPANY OF ROCHESTER, NEW YORK HAS BEEN SELECTED AS GENERAL CONTRACTOR TO BUILD THE 102,000 SQUARE FOOT ADDI - TION TO GREENE HALL. T HE DESIGN IS BY HOK, ONE OF THE NATION' S LEADING ARCHITECTURAL DESIGNERS OF RESEARCH LABORATORY BUILDINGS . CONSTRUCTION WILL BEGIN WITH THE RAZING OF B LAKE “D” AND “E” AND CONTINUE WITH SITE WORK BETWEEN B LAKE , THE MILNE L IBRARY, NEWTON HALL AND GREENE HALL . CONSTRUCTION DURATION IS PROJECTED TO BE ABOUT 36 MONTHS . WHILE CONSTRUCTION IS UNDERWAY , HOK SHALL DESIGN THE RENOVATION OF GREENE HALL, WHICH WILL COMPLETE THE ISF PROJECT. ONCE THE CONSTRUCTION IS COMPLETED, WE WILL HAVE A STATE- OF - THE - ART SCIENCE RESEARCH CENTER FOR WESTERN NEW YORK S TATE THAT WILL ENHANCE OUR POSITION AS A CENTER OF EXCELLENCE FOR SCIENCE TEACHING. GETTING TO THIS END, HOWEVER , WILL NOT BE WITHOUT ITS CHALLENGES . CONSTRUCTION IS A NOISY AND COMPLEX BUSINESS, LEADING TO SOME INCONVENIENCE DURING THE COMING THREE YEARS. T HIS PAMPHLET DESCRIBES THE DIFFERENT CONSTRUCTION PHASES, WHAT ONE CAN EXPECT FROM EACH, AND HOW PEDESTRIAN CIRCULATION WILL BE MAINTAINED. NEW UPPER CAMPUS SITE PLAN Newton Lecture Hall Contractor Staging Area Lot A Greene Hall Site of New Integrated Science Facility Contractor Traffic Route Contractor Parking and Remote Staging Area Newton Lecture Hall New Integrated Science Facility Greene Hall Bailey Hall Erwin Hall Blake Hall Milne Library CONSTRUCTION SITE CIRCULATION - PHASE 1 - THRU DEMOLITION OF BLAKE CONSTRUCTION SITE CIRCULATION - PHASE 2 Construction Staging/ Greene Service ONLY exit exit exit no exit exit exit no exit Construction Staging/ Greene Service ONLY exit exit exit no exit exit exit no exit STUDENTS / FACULTY / STAFF / VISITORS CONSTRUCTION SAFETY GUIDELINES - ADHERETO CLEARLY MARKED PEDESTRIAN PATHS - OBSERVE POSTED CONSTRUCTION SIGNS AND INSTRUCTIONS - DO NOT ENTER FENCED CONSTRUCTION AREAS REPORT SAFETY CONCERNS: - BUSINESS HOURS - SUCF CONSTRUCTION TRAILER X 5135 - NON-BUSINESS HOURS - CAMPUS POLICE X 5651 OVERSIGHT OF THE ISF CONSTRUCTION IS PROVIDED BY THE S TATE UNIVERSITY CONSTRUCTION FUND, NOT BY THE COLLEGE DIRECTLY. WE HAVE MADE EVERY EFFORT TO MAKE THE CONSTRUCTION F UND AND CONTRACTOR AWARE OF THE COLLEGE' S SCHEDULE TO MINIMIZE DISRUPTION TO THE ACADEMIC ENTERPRISE . WE ASK THAT YOU BEAR WITH US DURING CONSTRUCTION AND TRY TO BE AS FLEXIBLE AS POSSIBLE . I F YOU HAVE ANY CONCERNS , PLEASE CALL THE FACILITIES PLANNING AND CONSTRUCTION OFFICE ( X5511), WHICH IS THE COLLEGE ' S OFFICIAL LIAISON WITH THE CONTRACTOR AND THE CONSTRUCTION F UND. F INALLY, LET ME THANK YOU IN ADVANCE FOR YOUR PATIENCE , UNDERSTANDING, AND PERSEVERANCE DURING THE NEXT FEW YEARS . I THINK WE WILL ALL FEEL THAT THE MINOR INCONVENIENCES WE SHALL ENDURE WILL HAVE BEEN WELL WORTH IT ONCE WE ARE ABLE TO OCCUPY THIS WONDERFUL NEW BUILDING. KENNETH H. L EVISON VICE P RESIDENT FOR ADMINISTRATION Newton Lecture Hall Greene Hall Bailey Hall Erwin Hall Blake Hall Milne Library Newton Lecture Hall Greene Hall Bailey Hall Erwin Hall Blake Hall Milne Library construction fences pedestrian walkways HOK - ARHCITECTURE AND INTERIOR DESIGN; SYSKA HENNESSY GROUP - MEP; LESLIE E. ROBERTSON, RLLP- STRUCTURAL ENGINEER; WATTS ENGINEERS, CIVIL ENGINEERING AND HAZARDOUS MATERIALS; WENDELL DUCHSCHERER, SURVEYING

SUNY Geneseo brochure FINAL

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: SUNY Geneseo brochure FINAL

W ITH THE CONSTRUCTION START OF THE INTEGRATED SCIENCE

FACILITY (ISF) THIS OCTOBER , GENESEO COLLEGE IS EMBARKING ON

THE LARGEST SINGLE CONSTRUCTION PROJECT IN COLLEGE HISTORY.THE PIKE COMPANY OF ROCHESTER , NEW YORK HAS BEEN SELECTED

AS GENERAL CONTRACTOR TO BUILD THE 102,000 SQUARE FOOT ADDI-TION TO GREENE HALL. THE DESIGN IS BY HOK, ONE OF THE NATION'SLEADING ARCHITECTURAL DESIGNERS OF RESEARCH LABORATORY

BUILDINGS .

CONSTRUCTION WILL BEGIN WITH THE RAZING OF BLAKE “D” AND “E”AND CONTINUE WITH SITE WORK BETWEEN BLAKE , THE M ILNE L IBRARY,NEWTON HALL AND GREENE HALL . CONSTRUCTION DURATION IS

PROJECTED TO BE ABOUT 36 MONTHS . WHILE CONSTRUCTION IS

UNDERWAY, HOK SHALL DESIGN THE RENOVATION OF GREENE HALL,WHICH WILL COMPLETE THE ISF PROJECT.

ONCE THE CONSTRUCTION IS COMPLETED, WE WILL HAVE A STATE-OF-THE-ART SCIENCE RESEARCH CENTER FOR WESTERN NEW YORK STATE

THAT WILL ENHANCE OUR POSITION AS A CENTER OF EXCELLENCE FOR

SCIENCE TEACHING. GETTING TO THIS END, HOWEVER , WILL NOT BE

WITHOUT ITS CHALLENGES . CONSTRUCTION IS A NOISY AND COMPLEX

BUSINESS, LEADING TO SOME INCONVENIENCE DURING THE COMING

THREE YEARS. THIS PAMPHLET DESCRIBES THE DIFFERENT CONSTRUCTION

PHASES, WHAT ONE CAN EXPECT FROM EACH, AND HOW PEDESTRIAN

CIRCULATION WILL BE MAINTAINED.

NEW UPPER CAMPUS SITE PLAN

Newton Lecture Hall

ContractorStaging AreaLot A

Greene Hall

Site of New Integrated Science Facility

ContractorTraffic Route

ContractorParking and RemoteStaging Area

NewtonLecture

Hall

New IntegratedScience Facility

GreeneHall

BaileyHall

ErwinHall

Blake Hall

MilneLibrary

CONSTRUCTION SITE CIRCULATION - PHASE 1 - THRU DEMOLITION OF BLAKE CONSTRUCTION SITE CIRCULATION - PHASE 2

ConstructionStaging/GreeneService ONLY

exit

exit

exit

no exit

exit

exit

no exit

ConstructionStaging/GreeneService ONLY

exit

exit

exit

no exit

exit

exit

no exit

STUDENTS / FACULTY / STAFF / VISITORS

CONSTRUCTION SAFETY GUIDELINES

- ADHERE TO CLEARLY MARKED PEDESTRIAN PATHS

- OBSERVE POSTED CONSTRUCTION SIGNS AND INSTRUCTIONS

- DO NOT ENTER FENCED CONSTRUCTION AREAS

REPORT SAFETY CONCERNS:- BUSINESS HOURS - SUCF CONSTRUCTION TRAILER X 5135- NON-BUSINESS HOURS - CAMPUS POLICE X 5651

OVERSIGHT OF THE ISF CONSTRUCTION IS PROVIDED BY THE STATE UNIVERSITY

CONSTRUCTION FUND, NOT BY THE COLLEGE DIRECTLY. WE HAVE MADE EVERY EFFORT

TO MAKE THE CONSTRUCTION FUND AND CONTRACTOR AWARE OF THE COLLEGE'SSCHEDULE TO MINIMIZE DISRUPTION TO THE ACADEMIC ENTERPRISE . WE ASK THAT YOU

BEAR WITH US DURING CONSTRUCTION AND TRY TO BE AS FLEXIBLE AS POSSIBLE . IF YOU

HAVE ANY CONCERNS , PLEASE CALL THE FACILITIES PLANNING AND CONSTRUCTION

OFFICE (X5511), WHICH IS THE COLLEGE'S OFFICIAL LIAISON WITH THE CONTRACTOR

AND THE CONSTRUCTION FUND.

F INALLY, LET ME THANK YOU IN ADVANCE FOR YOUR PATIENCE , UNDERSTANDING, AND

PERSEVERANCE DURING THE NEXT FEW YEARS . I THINK WE WILL ALL FEEL THAT THE MINOR

INCONVENIENCES WE SHALL ENDURE WILL HAVE BEEN WELL WORTH IT ONCE WE ARE

ABLE TO OCCUPY THIS WONDERFUL NEW BUILDING .

KENNETH H. LEVISON

VICE PRESIDENT FOR ADMINISTRATION

NewtonLecture

Hall

GreeneHall

BaileyHall

ErwinHall

Blake Hall

MilneLibrary

NewtonLecture

Hall

GreeneHall

BaileyHall

ErwinHall

Blake Hall

MilneLibrary

construction fencespedestrian walkways

HOK - ARHCITECTURE AND INTERIOR DESIGN; SYSKA HENNESSY GROUP - MEP; LESLIE E. ROBERTSON, RLLP- STRUCTURAL ENGINEER; WATTS ENGINEERS, CIVIL ENGINEERING AND HAZARDOUS MATERIALS; WENDELL DUCHSCHERER, SURVEYING

Page 2: SUNY Geneseo brochure FINAL

2ND & 3RD FLOOR FIRST FLOOR

INTEGRATED SCIENCE FACILITY STATE UNIVERSITY OF NEW YORK AT GENESEO

new class rooms

faculty loungeteaching labs

student lounge

faculty/studentresearch labs

teaching labs

chair’s offices

new class rooms

faculty offices

atrium

YEAR 03 04 05 06MONTH S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

1 Mobilization and Site Prep1 Sep-7 Nov 03

2 Demoliton of Blake D & E 3 Nov-12 Dec 03

3 Site Utilities22 Oct- 22 Mar 04

4 Foundations and Rock Removal2 Dec- 28 Jul 04

5 Steel Erection29 Jul- 8 Sep 04

6 Slabs & Roof9 Sep- 13 Oct 04

7 Enclose West Half of ISF30 Sep- 15 Dec 04

8 Interior Finishes West Half of ISF16 Dec- 21 Sep 05

9 Enclose East Half of ISF2 May- 19 Aug 05

10 Interior Finishes East Half of ISF18 Jul-21 May 06

11 Landscape and Site Work1 May- 15 Sep 06

12 Commissioning1 Dec 05- 2 Oct 06

13 Move-in2-Oct-06

Sept 03

Oct 06

2 week exam quiet period

RockRemoval!Expect Noise!

SteelErection!

YEAR 03 04 05 06MONTH S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

1 Mobilization and Site Prep1 Sep-7 Nov 03

2 Demoliton of Blake D & E 3 Nov-12 Dec 03

3 Site Utilities22 Oct- 22 Mar 04

4 Foundations and Rock Removal2 Dec- 28 Jul 04

5 Steel Erection29 Jul- 8 Sep 04

6 Slabs & Roof9 Sep- 13 Oct 04

7 Enclose West Half of ISF30 Sep- 15 Dec 04

8 Interior Finishes West Half of ISF16 Dec- 21 Sep 05

9 Enclose East Half of ISF2 May- 19 Aug 05

10 Interior Finishes East Half of ISF18 Jul-21 May 06

11 Landscape and Site Work1 May- 15 Sep 06

12 Commissioning1 Dec 05- 2 Oct 06

13 Move-in2-Oct-06

Sept 03Sept 03

Oct 06

2 week exam quiet period

RockRemoval!Expect Noise!

SteelErection!

FINAL DESIGN