Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Summary Highlights of NRC/DOE Technical Exchange and Management Meeting on Range of Operating Temperatures
August 2, 2001
Rockville, Maryland
Introduction and Objectives
This Technical Exchange and Management Meeting on Range of Operating Temperatures is one in a series of meetings related to the U.S. Nuclear Regulatory Commission (NRC) key technical issue (KTI) and sufficiency review, and the potential U.S. Department of Energy (DOE) site recommendation. The objectives for this meeting were for DOE to (1) summarize the Supplemental Science and Performance Analyses (SSPA) model supplements since the Science and Engineering Report and (2) discuss differences between higher-temperature and lower-temperature operating modes based on process models. This was the first of two separate meetings on this topic. The second meeting, currently scheduled for September 2001, will focus on the NRC staffs questions pertaining to DOE's SSPA.
Consistent with NRC regulations on prelicensing consultations and a 1992 agreement with the DOE, staff-level resolution can be achieved during prelicensing consultation. The purpose of issue resolution is to assure that sufficient information is available on an issue to enable the NRC to docket a proposed license application. Resolution at the staff level does not preclude an issue being raised and considered during the licensing proceedings, nor does it prejudge what the NRC staff evaluation of that issue will be after its licensing review. Issue resolution at the staff level, during prelicensing, is achieved when the staff has no further questions or comments at a point in time regarding how the DOE is addressing an issue.
Summary of Meeting
DOE provided a general briefing on the Yucca Mountain thermal design history, the current thermal management methodology, and the scope of the SSPA and comparison of the thermal operating modes. No NRC/DOE agreements were reached at this Technical Exchange and Management Meeting. The agenda and the attendance list are provided in Attachments 1 and 2, respectively. Copies of the presenters' slides are provided in Attachment 3. Highlights from the Technical Exchange and Management Meeting are listed below.
Highlights
1) DOE's Yucca Mountain Project - Thermal Design History
DOE discussed the changes in DOE's thermal goals since the Viability Assessment (see "YMP Thermal Design History" presentation given by Paul Harrington). DOE then discussed its next steps in moving toward a possible license application and stated its license application design would include a fixed design with flexible operational modes. DOE further stated that it would be formulating the decision process for selecting the licensing operating mode. This process would establish the thermal operating mode, determine appropriate thermal limits, and select operational ranges or parameters for licensing. The NRC staff had several questions related to
EnclosureI
the design. These questions will be more fully discussed during the next meeting on this subject.
2) DOE's Current Thermal Management Methodology
DOE discussed its Yucca Mountain methodology for thermal management and the effects of this methodology on the design process (see "Current Thermal Management Methodology" presentation given by Gene Rowe). DOE discussed the design presented in the Science and Engineering Report and the SSPA and stated that it represents a single design which will work over the full range of thermal modes. DOE then discussed these different thermal modes and the potential range of operational variables. DOE stated that some of the attributes of flexible operations are: (1) ability to operate under various thermal modes, (2) ability to accommodate variations in waste stream characteristics, (3) ability to accommodate changes in receipt and emplacement rates, and (4) ability to provide for checks and balances for problem detection andi corrective action. The NRC staff had several questions related to the methodology. These questions will be more fully discussed during the next meeting on this subject.
3) Scope of the SSPA and Comparison of Thermal Operating Modes
DOE discussed the scope of the SSPA and the comparisons between the thermal operating modes (see "Scope of the SSPA and Comparison of Thermal Operating Modes" presentation given by James Blink and Robert Howard). DOE discussed the organization and scope of the SSPA and provided a summary of the supplemental modes and analyses made since the Science and Engineering Report. DOE then went into a little more detail on these changes. The NRC staff had a number of questions regarding the updated scientific information, uncertainty analysis changes, and how certain changes impacted the cooler thermal operating mode. These questions will be more fully discussed during the next meeting on this subject.
4) Public Comments
Ms. Judy Treichel (Nevada Nuclear Waste Task Force) commented that the second meeting of this subject should not occur during the Nuclear Waste Technical Review Board meeting scheduled for September 10-12, 2001. The NRC stated that it was aware of this meeting and would try to avoid scheduling it on the same days.
Ja s . Andersen, Project Manager Timothy C. Gunter h Level Waste Branch Regulatory Interactions
Division of Waste Management Office of Licensing & Regulatory Compliance Office of Nuclear Material Safety U.S. Department of Energy
and Safeguards U.S. Nuclear Regulatory Commission
2
DRAFT AGENDA DOE/NRC MEETING ON REPOSITORY THERMAL MANAGEMENT
10:00 A.M. - 4:45 P.M. (EDT) August 2, 2001 Room 03B-4
11555 Rockville Pike Rockville, MD
Via videocon to: Region IV, DOE, Las Vegas, and CNWRA, San Antonio, Texas
10:00 - 10:15 a.m.
10:15 - 10:45 a.m.
10:45 - Noon
Noon - 1:00 p.m.
1:00 - 2:45 p.m.
Introduction and Opening Remarks
Thermal Management History of the Proposed Repository
Current Thermal Management Methodology
DOE - Gunter NRC - Andersen
DOE - Harrington
DOE - Trautner/Rowe
Lunch
Supplemental Science and Performance Analyses Overview - Evaluation of the Range of Thermal Operating Modes
DOE - Blink
2:45 - 3:15 p.m.
3:15 - 4:15 p.m.
4:15 - 4:45 p.m.
Caucus
Discussion
Conclusion, Closing Remarks and Adjourn
Attachment 1
DOE/NRC
t~w tIu& C-TvftabgA -
IC.A~h4146 ~ N RC4
Th~~~~ M y~ v'r
X (*>0 v4::7
T a V a - -(--; fM\0'K H.pa A v7-c/ Aý '~t'rk, F Awýerýn t./k
~~zj0 L4Cý-*ve
~~3E?1~D C~~A~Ž
(3f/;I L'z-z
-1 b...1Iin4..v A
3o +I- -7,L
3.01 - ' Ao
3- f 5 -- ,)z
7-20 (5- *, T
7oZ~- -7'71o~
~704- US'- 3097
Attachment 2
BSC LICENSING LY ID:7022295535t HUG 06 '01J 8 23 HoA.JC2 FP.02
aan ,t~w1~v7o - ýfy -r)rs d~7aZ
6 rotbP- 9k sfý - pl,% ý,
t4 L& tibto-t4c* r- F Ci-,a) Vik4uR
,t3 Aq zV•VZ 44-51ý
-Jt'fl(eview-, Nov~vo /tv/4~A(o)Ž S5 531
p&'r 0u - ?9 ,t
lA4VttD 5A:WhU4 Pt ' de - fl -ra
Pt~ld Poo7 /49 ni (SI5X. 7c&S$ nC
BSC LICENSING LV ID:7022955351 0AL.G 0'6ý0 1 28:24 Io .00C2' P. 0 3
CENTER FOR NUCLEAR WASTE REGULATORY ANALYSES MEETING ATTENDANCE
[DATE: _____ LOCATION; ~ ~o~v~de r4S "' /4.4'i
PERSON ORGANIZATION TITLEIFUNCT1ON TELPIION NUMBDER
Afolsao Cheo(4ra7 CAsIfA294 F44Cr-k CFG (24.V)g-Vf
ldcs 44izl 5!o ______ &V o
e 4W4e 4 ePAý)Sý w
24.- JQ4A4jeo CAW_____ A.X 6')- t
per' ~ ~ ~ ~ ~ ~ ~ ~ 3 7fK~. gIt' 4s4io' ___________ ___________ L ________IF
cQaa.&AA Ail; 2Ž&Ž3t
SK~t RfsOa ?AO-MV11_
_____________1ý CW Re Ajf 1 t 1
___ _ A. _ Se .Wftt10ra r
c~~stAa 4._ _ _ _ _
__ __ __ (NII• IOU__ _ _ __ _ _
CNWRA Pomr API6
Attachment 3
Presenters' Slides
YUCCA MOUNTAIN PROJECT
U.S. Department of Energy Office of Civilian Radioactive Waste Management
YMP Thermal Design History
Presented to:U. S. Nuclear RegulatoryC(
YMP Historical Time Phases Reflecting Changes in Thermal Goals
- Viability Assessment (VA)
- License Application Design Selection (LADS)
- Nuclear Waste Technical Review Board (NWTRB) and Other Party Inputs
- Thermal Operational Scenarios Considered
- Science and Engineering Report (S&ER)
- Next Step
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt 2
Evolution of Design FeaturesParameter Viability Enhanced Current Reference Design and
Assessment Design Operating Mode Alternative II
High End Low End Average waste package maximum surface 230 230 -175 <85 temperature (0C) _
Maximum drift-wall temperature (0C) 200 200 <175 <85 Pillar temperature (0C) >96 Center below 50% below 96 <85
.96 Areal mass loading(MTHM/acre) 85 60 -60 -40 Area for 70,000 MTHM (acres) 741 1,050 1,050 1,600 Total excavated emplacement drift length 107 54 -60 -80 (Km) Waste-package spacing (meters) Variable 0.1 0.1 2 Line/point load Point Line Line i Point Drift spacing (meters) 28 81 81 i 81 Preclosure ventilation period (yrs) 50 50 50 I 300 Preclosure ventilation flow rate (M3/s) 0.1 2 to 10 15 15 for 50 years NVP __*driven for 250 years Waste package max heat output (KW) 18 11.8 11.8 11.8 PWR waste package avg heat output (KW) 9.3 9.8 11.3 11.3 Total waste package avg heat output (KW) 7.3 7.4 7.6 7.6 Avg linear loading (KW /meter) 0.7 1.37 1.45 1.0 Backfill in emplacement drift Not Yes Not precluded; Not precluded
precluded _ Drip shields Not Yes Yes Yes
precluded _l
7YUCCa Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington 080201 .ppt YUCCA MOUNTAIN PROJECT
3
I *NVP = Natural Ventilation Pressure
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt
Viability Assessment 1998
* Thermal loading -- High -- 85 metric tons of heavy metal (MTHM)/acre
- Specific loading slightly higher than ACD loading
* Point loaded drifts (varies, but ~5-m avg. separation)
* 5.5 m diameter drifts spaced 28 m apart
* Boiling fronts extended 100 m above/below horizon * Entire footprint temperature above boiling for
extended period
* Matrix saturation temporarily increases above the high-temperature region
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt 4
Considering Alternatives
* License Application Design Selection 1998/1999 - To reduce uncertainty in performance assessment
- 5 enhanced design alternatives (EDAs) evaluated considering low and high thermal loadings
- EDA-II recommended - 60 MTHM/acre - lower than VA * Linear loading (0.1 m spacing) and 81 m drift spacing
* 50 years forced ventilation * Boiling fronts in host rock but 50% of pillars below boiling * Draining of heat-mobilized and percolating groundwater
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington080201 .ppt 5
LADS Alternatives
V.C, Mutan---t/-rlmnryPeeiioa rf atrasBC rpisPrsnainYRrigonA2l.p YUCCA MOUNTAIN PROJECT 6
Parameters EDA-I EDA-Il EDA-III EDA-IV EDA-V
MTHM/Acre 45 60 85 85 150
Acres for 1400 1050 740 740 420 70,000 MTHM
Line or point Point Line Line Line Line load
PWR WP Size 12 21 21 21 21
Drift Spacing 43 m 81 m 56 m 56 m 32 m
Preclosure 50 years @ 2 50 years @ 2 50 years @ 2 50 years @ 2 50 years @ 2 ventilation tol10 m 3/s tol10 m3/s tol10 m 3/s tol10 m 3/s tol10 m 3/s
Total WPs 15,903 10,039 10,213 10,213 10,039
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt
Lower Thermal Operational-Modes
* Nuclear Waste Technical Review Board-- 1999/2000 Uncertainty with basis for high temperature design prompted evaluation of lower temperature alternatives
* Lower thermal operational scenarios-- 12/2000 - One: lower WP temperature through extended ventilation
(50/250 years forced/natural); minimal increase in area; increased spacing between WPs (2 m)
- Two: lower WP temperature through extended ventilation (50/250 years forced/natural); minimal increase in area; lower heat output, tightly-spaced (0.1 meter) WPs;
- Three: lower WP temperature through extended ventilation (300 years forced); minimal increase in area; reference WP size and spacing; but increased drift spacing (120 m);
YUCCA MOUNTAIN PROJECTYucca Mountain ProjectlPreliminary Predecisional Draft Materials
7BSC Graphics PresentationsYMHarrington_080201 .ppt
Yucca Mou
Lower Thermal Operational Modes (Continued)
- Four: lower WP temperature through increased area; a limited ventilation period (~125 years); no aging; increased spacing between reference WPs (6 m);
- Five: lower rock temperature and in-drift relative humidity through indefinite natural (passive) ventilation of the reference design
YUCCA MOUNTAIN PROJECT untain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt 8
Range of Thermal Operating Modes 2000/2001
Higher mode
- -60 MTHM/acre; linear load of 1.45 kW/m (0.1 m spacing); 50 years forced ventilation
* Lower mode
- -40 MTHM/acre; linear load of 1.0 kW/m (-2 m spacing); forced and natural ventilation for 300 years
* Fixed design with flexible operational modes - 5.5 m diameter drifts spaced 81 m apart
- Repository elevation and layout specified
- Two barrier waste package design
* Described in Science and Engineering Report - 2001
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt 9
Next Step 2001/2002
* License application design
- Fixed design with flexible operational modes
- Decision process for selecting licensing operating mode
""Establish the thermal operating mode
""Determined appropriate thermal limits
- Selected operational ranges or parameters for licensing
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMHarrington_080201 .ppt 10
Agenda • Introduction
• Present Repository Design
- Single SR Design
- SR Typical Waste Package Design
- SR Drift Design
- SR Layout
• Operational Modes - Potential Range of Operational Variables
- Options Considered for SR
- Thermal Response
* Attributes of Flexible Operations
* Licensing Approach with Respect to Flexible Operating Modes
• Summary YUCCA MOUNTAIN
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMRowe_080201.pptPROJECT
2
Introduction
• Purpose
The purpose of this presentation is to present Yucca Mountain's methodology for thermal management and discuss the effects of this methodology on the design process
* Background
The majority of the work to date has been to support the Site Recommendation effort. Design parameters have been selected to allow analyzing the performance of the repository for various operating modes. These parameters will be optimized during the final design process
- Need for Flexibility
Because the repository thermal goals are still evolving, operational flexibility is needed
I---I YUCCA MOUNTAIN PROJECT
Yucca Mountain Project/Prelimi nary Predecisional Draft Materials BSC Graphics PresentationsYMRowe_O802Ol.ppt 3
Single SR Design * The design presented in the S&ER and the SSPA
represent a single design and will work over the full range of thermal modes
Design Parameter Fixed for SR for all Modes Analyzed
Repository capacity 70,000 MTHM Emplacement rate 3,000 MTHM/year after 5-year ramp-up Emplacement period -23 years
Sequence of waste package Interspersed hotter and cooler packages to achieve emplacement average linear power density Waste package design Large, horizontally emplaced packages with
corrosion-resistant outer shell of alloy-22 and structural inner shell of 316NG
Number of waste packages -11,000
Initial waste package power 11.8 kW maximum Drift diameter 5.5 meters
Drift spacing 81 meters
Drip shields Titanium, continuous
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMRowe 080201 .ppt YUCCA MOUNTAIN PROJECT
4BSC Graphics PresentationsYMRowe_080201.pptYucca Mountain Project/Preliminary Predecisional Draft Materials
SR Typical Waste Package Design
Basket AssemWil
Inner Shell (316 NG) See Not 2
InnerOuter Shell (All (Alloy 22) See Note 1 -
Dy
Outer Shell (Alloy 22)
Inner Shell Support Ring (Alloy 22)
Shell Bottom Lid __. \ x
ft.
Outer Shell Flat Closure L (Alloy 22)
Inner Shell Top Lid (316 NG) .id
IN
Trunnion Collar (Geometry TBD)
Lower Trunnion Collar Sleeve (Alloy 22)
ý~Eyebolts See Note 3
Outer Shell Lid Lifting Feature (Alloy 22)
"Outer Shell Lid Lifting Feature (Alloy 22)
Outer Shell Extended Closure Lid (Alloy 22)
Upper Trunnion Collar Sleeve (Alloy 22)
Note 1: The Outer Shell is enlarged to allow for a continuous 10 mm gap from the Inner Shell to Outer Shell.
Note 2: The Inner Shell overall length was increased due to the addition of a 10 mm long, 25 mm thick skirt at the bottom end.
Note 3: 4 one inch diameter Eyebolts were added to the Top Inner Lid to assist with handling of the Inner Shell. After placement into the Outer Shell, the eyebolts will be removed.
YUCCA MOUNTAIN PROJECTYucca Mountain Project/Preliminary Predecisional Draft Materials
Flat Lid
'�&L-'� N
BSC Graphics PresentationsYMRoweO80201.ppt 5
r 22)
ý4
#eo",
SR Drift Design
ELEVATION CAD FILE:asstOO20f Ig
.L DlrINIIS AlE S"0I0 IN MILLITE UNLESS OTERWISE NOTED
Yucca Mountain ProjectlPreliminary Predecisional Draft Materials BSC Graphics PresentationsYMRoweO8O2Ol .ppt YUCCA MOUNTAIN PROJECT 6Yucca Mountain ProjectfPreliminary Predecisional Draft Materials BSC Graphics PresentationsYMRowe-080201 .ppt
SR Underground Layout "" N!I.N237000
iAsIf VAI\\:I VI X \ SI(: ( (VRA V' 2 1: n. . ,ct /_
S .... ............ igher end of thermal -'1--........ = operating mode
1 ...-- "7N2350000
"K iLower end of thermal NII, Ioperating mode
•:'!'::I IU chieved via 2 meter aP spacing and/or
N238 000
Layoutof '•:, •. R,izl: CC K•'•• WA: NB I: 21 •
Development Areas V•V • VA
N235 000hevd iaW AVISI<OW,0Ii 001C
"N2" 4,WLower end of thermal operating mode
VA:.. r- -- achieved via 6Pmeter * ...... 00-WP spacing
'7 ---------"I -SN233 000 agin
PootentiRaolor DeelometoAeatRerya
";- LI : J SOU~l•At• i N232 000
ZYUCCA MOUNTAINAPROJECT Y M i e Pr D M .... G s P Lower end of thermal
S:, ,:operating mode S•," ,: achieved via 6Wmte
_S-_U )7: de- W sa cing
YUCAAOUTAN ROEC
Yucca Mountain Project/Preliminary Predlecisional Draft Materials BSC Graphics PresentationsYMRowe_080201 .ppt 7
Potential Range of Operational VariablesThese variables and ranges are preliminary and will continue to evolve as the
TSPA is refined and the design is optimized.
Variable Lower Limit Upper LimitVariables Associated with the Waste Stream
Assembly Age at Arrival
Assembly Burn-up Assembly Enrichment
5 years
N/A N/A
Variables Associated with Repository Operations Ventilation Duration 0 years
Ventilation Rate 0 CMS Waste Package Average Spacing 0.1 meters
PWR WP Capacity 1 assembly BWR WP Capacity 1 assembly
Duration of Assembly Staging at Site 0 years Amount of Staging at Site 0 MTHM
Waste Package Power at Emplacement N/A Areal Mass Loading 25 MTHM/acre
Linear Line Loading N/A
YucaMunan11/et111iiar reecsonlDrf MteilsBC1rphc IIIIttonY~oe8 O IpI!
N/A
75 GWd/t 5.0%
300 years
15 CMS 8 meters
21 assemblies
44 assemblies
30 years 40,000 MTHM
11.8 kW
60 MTHM/acre
1.45 kW/m
M YUCCA MOUNTAIN PROJECT
8Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMRowe_080201 .ppt
Options Considered for SR Scenario Scenario Scenario Scenario Scenario
1 2 3 4 5 Increased Increased
Waste De-Rated or Spacing and Extended S&ER package Smaller Duration of Surface Aging Extended Design Spacing and Waste Forced with Forced Natural SSPA SSPA
(MIPA Rev 0) Extended Packages Ventilation Ventilation Ventilation HTOM LTOM IVentilation _I
Design Paraueters Drift Center-to- 81 81 81 120 81 81 81 81 Center Spacing (m) Nunmer of Waste -11,000 -11,000 -15,000 -11,000 -11,000 -11,000 -11,000 -11,000 Packages Operational Parameters Average Waste 0.1 2 0.1 6 2 0.1 0.1 1.2 Package Spacing Surface Aging (years) 0 0 0 0 0 30 0 0 Emplacement Period -23 -23 -23 -23 -243 -23 -23 -23 (years)
Forced Emplacemnent 50 75 75 125 125 75 50 300 Ventilation After Start of Enmlacement(years) Natural Ventilation 0 250 250 0 0 >300 0 0 (years) Results Linear Thermal 1.45 1.00 1.00 0.7 0.5 1.45 1.35 1.12 Loading (kW/m) Total Emplacement -60 -80 -90 -130 -80 -60 -60 -75 Drift Excavation Length (kin)
Required Emplacement Area -1,150 -1,600 -1,800 -2,500 -1,600 -1,150 -1,150 -1,450 (acres)
Average Waste -160 <85 <85 <85 <85 <85 -160 <85 Package Maxinmum Temp (0CQ
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations3MRoweo8O2Ol .ppt YUCCA MOUNTAIN PROJECT
9Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentationsý_YMRowe_080201.ppt
Thermal Response HITOM and LTOM Temperature Histories
SSPA V1, ROO ICN01
200
180
160
140
120
100
80
60
40
20
00 1,000 2,000 3,000 4,000 5,000
Time, yr
6,000 7,000
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMRoweO8O2Ol .ppt
,000 9,000 10,000
YUCCA MOUNTAIN PROJECT 10
v
CL
.o
cc
c
i
8
cn 4)
- HTOM
- - -LTOM
S• m mm mm m fm im Tm hffi T hmm W m m m
I
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMRowe_080201.ppt
Attributes of Flexible Operations
• Ability to operate under various thermal modes
* Ability to accommodate variations in waste stream characteristics
* Ability to accommodate changes in receipt and emplacement rates
* Ability to provide for checks and balances for problem detection and corrective action
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMRowe_080201 .ppt 11
Licensing Approach With Respect to Flexible Operating Modes
- License application will be for a single design
* Operational parameters will be bounded and included in the License Specifications
* Thermal response will be bounded by the design parameters and operating modes analyzed in the TSPA-LA
YUCCA MOUNTAIN PROJECT12Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations_YMRowe_080201.ppt
Summary
* A set of design and operational parameters have been identified for the purpose of SR engineering and performance analyses
* The on going design and performance analyses provide us with a foundation that will allow us to continue to converge on a set of optimum design and operational parameters during the licensing phase of the program
° License application will be for a single design, with operational parameters specified in the License Specifications, and will be bounded by the TSPA-LA analyses
YUCCA MOUNTAIN PROJECT
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMRowe_080201 .ppt 13
IU w 0 C a. 2
I2 2 0
U U 2
a 0 U)
E 0
*0
CL cu cn
C,) 0
0 0n
0)
0
0
t K
J
I 0
Ct
U
0)
4)0
c4�Z 0
� 0) S
0)0
U
Objective , Summarize SSPA model supplements since the S&ER
* Synthesize higher-temperature and lower-temperature operating modes (HTOM/LTOM) contrast based on process models
Organization = SSPA Organization, volumes 1 and 2
* Subsystem
- Process model developments for SSPA studies
- Comparison of HTOM and LTOM process-level results
* Total System dose results from the TSPA-SR and SSPA
- Key model developments affecting dose
- Nominal and disruptive event scenarios YUCCA MOUNTAIN PROJECT
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 2
Relationship of SSPA Vol. 1 and Vol.
* Vol. 1 provides technical bases for analyses documented in Vol. 2
2
° "One-off" sensitivity analyses in Vol. 2 and guidance from Vol. 1 determine the content of the supplemental TSPA model
Significant changes in input
forwarded to TSPA
UU analyses comparing to
TSPA Rev 00, ICN 01
Only a portion of UU info input
forwarded to TSPA
Analysis of Range of thermal operating
modes plus UU
Chapter 3 Chapter 4
VOLUME 1 - SCIENCE ANALYSES "• New Science "• Unquantified Uncertainty Analyses "• Range of thermal operating modes
Yucca Mountain Project/Preliminary Predecisional Draft Materials
VOLUME 2 - PERFORMANCE ANALYSES
154_0269a. ai
YUCCA MOUNTAIN PROJECT
BSC Graphics PresentationsYMBlink_08/02/01 .ppt 3
i
1 -. 0000%
Scope of SSPA Volume 1
* Volume 1 Covers the major process expected to occur at Yucca Mountain and supplements the information described in Analyses and Model Reports and Process Model Reports
* Subjects are organized in a manner similar to the organization found in the Yucca Mountain Science and Engineering Report
* Volume 1 focuses on the technical work within each process model area, encompassing uncertainty quantification, updated scientific bases, and analyses of a range of operating modes
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01 .ppt 4
Scope of SSPA Volume 1 (Continued)
Three General Types of Information * Unquantified Uncertainties Analysis
- Specific uncertainties that were not treated explicity in the AMRs and PMRs supporting the S&ER have been quantified including parameter bounds, conceptual models, assumptions, and in some cases input parameters consisting of statistically biased or skewed distributions
* Updates in Scientific Information
- This includes new experimental results, new conceptual models, new analytical approaches, and the identification and discussion of multiple lines of evidence
• Thermal Operating Mode Analyses
- Includes process level information regarding thermal dependencies; how the process responds to a range of thermal inputs and the impacts on uncertainty in process level results
YUCCA MOUNTAIN PROJECT
Yurcca. Mnountain Prmiect/Pr liminarv Pr.dpeciuinal Draft Mateials BSC Graohics Presentations YMBlink 08/02/01 .Dt 5S...... r- .................... _ ........... _ ......... FI.-.I . . .. . .... .I.......I . .. I jt::.... .......... II .. jr F I. .. . . ......... . ...af . ........... tI
Scope of SSPA Volume 1 (Continued)
* Sections 3-14 include a summary of the conceptual basis for models used in the S&ER
* Specific content and level of detail of each section varies depending on:
- Extent of the analyses performed
- Amount of new information and data that has been generated since the publication of the S&ER and supporting documents
- Amount of information necessary required to evaluate the range of thermal operating modes
* Each section contains a summary of information and recommendations for use in Volume 2 if appropriate
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 6
Outline of SSPA Volume 2* Introduction
• Methods and Approach
* Sensitivity Analyses
- 3.1 System-Level Evaluation--Nominal Scenario
- 3.2 Subsystem-Level Evaluations--Nominal Scenario
- 3.3 Evaluations of Disruptive Performance
• Supplemental Total System Performance Assessment Model
- 4.1 System-Level Evaluations--Nominal Scenario
- 4.2 Subsystem-Level Evaluations--Nominal Scenario
- 4.3 System-Level Evaluation of Igneous Disruption
* Summary and Conclusions
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBIink 08/02101.ppt YUCCA MOUNTAIN PROJECT 7Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01.ppt
Attributes of Repository Performance
Climate
Unsaturated Zone Row V.ste Seepage Package
Z Degradiation
Waste Form Degradation
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBIink 08/02/01 .ppt YUCCA MOUNTAIN PROJECT 8Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
RN
Summary of Supplemental Modes and Analyses
Performance Assessment
Reason For Supplemental Scientific Treatment Of Supplemental Model Or Analysis Scientific Model Or AnalysisW
Cooler Topic Of Supplemental Unquantified Update in Thermal TSPA Included in
Key Attributes Process Model Scientific Model Uncertainty Scientific Operating Section of Sensitivity Supplemental
Of System (Section of S&ER) Or Analysis Analysis Information Mode Analysis Volume 1 Analysis TSPA Model
Limited Water Climate (4.2.1) Post-I0,000-year Climate Model X 3.3.1 X X Entering Net Infiltration (4.2.1) Infiltration for post-10,000-year 3.3.2 X X Emplacement Climate Model Drifts Unsaturated Zone Flow in PTn x _3.3.3
Flow (4.2.1) 3-D flow fields for cooler design;
flow fields for post-i0,000 yr climate, lateral flow; variable x X 3.3.4 thickness of PTn; fault property uncertainty
Effects of lithophysal properties on x 3.3.5 thermal properties
Coupled Effects on Mountain-scale Thermal- x X 3.3.5 UZ Flow (4.2.2) Hydrologic effects
Mountain-scale Thermal- x x 3.3.6 Hydrologic-Chemical effects
Mountain-scale Thermal- x x 3.3.7 Hydrologic-Mechanical effects
Seepage into Flow-focussing within 4.3.1, Emplacement Drifts heterogeneous permeability field; X X 4.3.2, X X (4.2.1) episodic seepage 4.3.5
Effects rock bolts and drift X 4.3.3, degradation on seepage 4.3.4
Coupled Effects on Thermal effects on seepage X X 4.3.5 X X Seepage (4.2.2) Thermal-Hydrologic-Chemical x X 4.3.6
effects on seepage
Thermal-Hydrologic-Mechanical X 4.3.7 effects on seepage_ x
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink_08/02/01 .pptYUCCA MOUNTAIN PROJECT
9BSC Graphics PresentationsYMBlink_08/02/01 .pptYucca Mountain Proj ect/Prelimi nary Predecisional Draft Materials
Summary of Supplemental Modes and Analyses
(Continued) Performance Assessment
Treatment of Supplemental Process Model Reason for Supplemental Scientific Scientific Model or Analysis
(Section of Yucca Model or Analysis (Discussed in Volume 2) Mountain Science Unquantified Update in Cooler Thermal TSPA Included in
Key Attributes and Engineering Topic of Supplemental Uncertainty Scientific Operating Mode Section of Sensitivity Supplemental of System Report) Scientific Model or Analysis Analysis Information Analysis Volume 1 Analysis TSPA Model
Long-Lived Water Diversion Multiscale thermal-hydrolic Waste Package Performance of EBS model, including effects of X X 5.3.1 X and Drip Shield (4.2.3) rock dryout
Thermal property sets X X 5.3.1 X
Effect of in-drift convection on temperatures, humidities, invert x X 5.3.2 saturations, and evaporation rates
Composition of liquid and gas entering drift x x 6.3.1 x x
Evolution of in-drift chemicalxx 6.3.3 X X environment
Thermo-Hydro-Chemical model comparison to plug-flow reactor X 6.3.1 and fracture plugging experiment Rockfall X 6.3.4
In-Drift Moisture Environment on surface of drip X 5.3.2 Distribution (4.2.5) shields and waste packages
Condensation under drip shields X 8.3.2 X
Evaporation of seepage X X 8.3.1 X X 5.3.2
Effect of breached drip shields x X 8.3.3 X X or waste package on seepage
Waste package release flowx8.34 x geometry (flow-through, bathtub)
Drip Shield Local chemical environment on Degradation and surface of drip shields (including Performance (4.2.4) Mg, Pb) and potential for X 7.3.1
initiating localized corrosion
Blink 34 ai
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/0 1 .ppt YUCCA MOUNTAIN PROJECT 10Yucca Mountain Project/Preliminary Predlecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
Summary of Supplemental Modes and Analyses
(Continued)Performance Assessment
Treatment of Supplemental
Process Model Reason for Supplemental Scientific Scientific Model or Analysis
(Section of Yucca Model or Analysis (Discussed in Volume 2)
Mountain Science Unquantified Update in Cooler Thermal TSPA Included in Key Attributes and Engineering Topic of Supplemental Uncertainty Scientific Operating Mode Section of Sensitivity Supplemental
of System Report) Scientific Model or Analysis Analysis Information Analysis Volume I Analysis TSPA Model
Long-Lived Waste Package Local chemical environment on Waste Package Degradation and surface of waste packages and Drip Shield Performance (4.2.4) (including Mg, Pb) and potential X 7.3.1
for initiating localized corrosion
Aging and phase stability effects x x 7.3.2 X on A-22
Uncertainty in weld stress state X 7.3.3 X X following mitigation
Weld defects X 7.3.3 X X
Early failure due to improper x X 7.3.6 X X heat treatment
General corrosion rate of A-22: X x 7.3.5 X X Temperature dependency
General corrosion rate of A-22:. X 7.3.5 X X Uncertainty/variability partition
Long-term stability of passive X 7.3.4 films on A-22
Stress threshold for initiation of x x 7.3.3 X X stress corrosion cracking
Probability of non-detection of X 7.4.3 X X manufacturing defects
Number of defects X 7.3.5 X X
Distribution of crack growth x x 7.3.7 X X exponent (repassivation slope)
Limited In-Package Effect of HLW glass degradation Release of Environments (4.2.6) rate and steel degradation rate X X 9.3.1 X X Radionuclides on in-package chemistry from the Engineered Cladding Effect of initial perforations, Barriers Degradation creep rupture, stress corrosion X X 9.3.3 X X
and Performance cracking, localized corrosion, (4.2.6) seismic failure, rock overburden
failure, and unzipping velocity on cladding degradation
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink 08/02/01 .ppt YUCCA MOUNTAIN PROJECT 11Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
I
Summary of Supplemental Modes and Analyses
(Continued)
Performance Assessment Treatment of Supplemental
Process Model Reason for Supplemental Scientific Scientific Model or Analysis (Section of Yucca Model or Analysis (Discussed in Volume 2) Mountain Science Unquantified Update in Cooler Thermal TSPA Included in
Key Attributes and Engineering Topic of Supplemental Uncertainty Scientific Operating Mode Section of Sensitivity Supplemental of System Report) Scientific Model or Analysis Analysis Information Analysis Volume 1 Analysis TSPA Model
Limited DHLW Degradation HLW glass degradation rates Release and Performance x x x 9.3.1 of (4.2.6) Radionuclides Dissolved Solubility of neptunium, thorium, from the Radionuclide plutonium, and technetium X X X 9.3.2 X X Engineered Concentrations Barriers (4.2.6)
Colloid-Associated Colloid mass concentrations Radionuclide x 93.4 x Concentrations (4.2.6)
EBS (Invert) Diffusion inside waste package X X 10.3.1 X x Degradation and Transport pathway from inside Transport (4.2.6, waste package to invert x x 10.32 4.2.7) Sorption inside waste package X X 10.3.4 X X
Sorption in invert X X 10.3.4 X X
Diffusion through invert X 10.3.3 X X
Colloid stability in the invert X 10.3.5
Microbial transport of colloids X X 10.3.6
Blink 36.ai
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01 .ppt YUCCA MOUNTAIN PROJECT 12Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
Summary of Supplemental Modes and Analyses
(Continued)
Performance Assessment Treatment of Supplemental
Process Model Reason for Supplemental Scientific Scientific Model or Analysis (Section of Yucca Model or Analysis (Discussed in Volume 2)
Mountain Science Unquantified Update in Cooler Thermal TSPA Included in Key Attributes and Engineering Topic of Supplemental Uncertainty Scientific Operating Mode Section of Sensitivity Supplemental
of System Report) Scientific Model or Analysis Analysis Information Analysis Volume I Analysis TSPA Model
Delay and Unsaturated Zone Effect of drift shadow zone - X X 11.3.1 X X Dilution of Radionuclide advection/diffusion splitting Radionuclide Transport (Advective Effect of drift shadow zone Concentrations Pathways; concentration boundary X 11.3.1 by the Natural Retardation; Barriers Dispersion; Dilution) condition on EBS release rates
(4.2.8) Effect of matrix diffusion X 11.3.2, 11.3.3
3-D transport X 11.3.2
Effect of coupled ThermoHydrologic, Thermo-HydroChemical, and Thermo-Hydro- X X 11.3.5 Mechanical processes on transport
Saturated Zone Groundwater specific discharge X X 12.3.1 X Radionuclide Flow and Transport Effective diffusion coefficient in X 12.3.2 X (4.2.9) volcanic tuffs
Flowing interval spacing 12.3.2 X
Flowing interval (fracture) X 12.3.2 X porosity Effective porosity in the alluvium X 12.3.2 X
Correlation of the effective diffusion coefficient with matrix X 12.3.2 X porosityII
Bulk density of the alluvium X X _12.3.2 X X
Blink_37.ai
Yucca Mountain ProjectfPreliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink_08/02/01 .ppt YUCCA MOUNTAIN PROJECT 13Yucca Mountain Project/Preli mi nary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
Summary of Supplemental Modes and Analyses
(Continued) Performance Assessment
Treatment of Supplemental Process Model Reason for Supplemental Scientific Scientific Model or Analysis
(Section of Yucca Model or Analysis (Discussed in Volume 2) Mountain Science Unquantified Update in Cooler Thermal TSPA Included in
Key Attributes and Engineering Topic of Supplemental Uncertainty Scientific Operating Mode Section of Sensitivity Supplemental of System Report) Scientific Model or Analysis Analysis Information Analysis Volume 1 Analysis TSPA Model
Delay and Saturated Zone Retardation for radionuclides Dilution of Radionuclide irreversibly sorbed on colloids X X 12.3.2 X Radionuclide Transport (4.2.9) in the alluvium Concentrations No matrix diffusion in volcanic 1252 X by the Natural tuffs case Barriers Presence or absence of alluvium 12.5ý2 X
Sorption coefficient in alluvium X 123.2 X for I, Tc
Sorption coefficient in alluvium X X 12.32 X for Np, U
Sorption coefficient for Np in X 12.3.2 X volcanic tuffs Kc model for groundwater colloid concentrations Pu, Am X 12.5.2 X
Enhanced matrix diffusion in 1252 X volcanic tuffs
Effective longitudinal dispersivity X X 12.3.2 X New dispersion tensor X 12.3.2 Flexible design X 12.3.2 Different conceptual models of the large hydraulic gradient and X 12.3.1 their effects on the flow path and specific discharge Hydraulic head and map of X 12.3.1 potentiometric surface
Biosphere (42.10) Receptor of interest X 13.3.1 Comparison of dose X 13.3.2 assessment methods Radionuclide removal from soil X 13 3 3 by leaching Uncertainties not captured by X 13.3.4 GENII-S Influence of climate change on X 13.3.5 groundwater usage and BDCFs 13.37 BDCFs for groundwater and 1336. X X igneous releases 13.38.
X__ _13.438
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01 .ppt
Blic~k-38 a,
YUCCA MOUNTAIN PROJECT 14BSC Graphics PresentationsYMBiink_08/02/01 .pptYucca Mountain Project/Preliminary Predlecisional Draft Materials
Summary of Supplemental Modes and Analyses
(Continued)
Performance Assessment Treatment of Supplemental
Process Model Reason for Supplemental Scientific Scientific Model or Analysis
(Section of Yucca Model or Analysis (Discussed in Volume 2)
Mountain Science Unquantified Update in Cooler Thermal TSPA Included in Key Attributes and Engineering Topic of Supplemental Uncertainty Scientific Operating Mode Section of Sensitivity Supplemental
of System Report) Scientific Model or Analysis Analysis Information Analysis Volume 1 Analysis TSPA Model
Low Mean Volcanism/Igneous Probability of dike intersection of Annual Dose Activity (4.3.2) repository for the operating X 14.3.3.1 X Considering mode described in S&ER Potentially Scaling factors to evaluate Disruptive impacts of repository design X 14.3.3.2 Events changes
Contribution to release of Zones 1 and 2 X 14.3.3.3 X
Sensitivity to waste particle size 14.3.3.4 X distribution X_14.3.3.4_X
New wind speed data X 14.3.3.5 X X
Explanation of method for handling ash/waste particle size X 14.3.3.6 and density Volcanism inputs for Supplemental TSPA Model X 14.3.3.7
New aeromagnetic data X 14.3.3.8 X .,;", '3. i
NOTE: S&ER = Yucca Mountain Science and Engineering Report a Performance assessment treatment of supplemental scientific model or analysis discussed in SSPA Volume 2
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink_08/02/01 .ppt YUCCA MOUNTAIN PROJECT 15
IBllnK ,3.al
BSC Graphics PresentationsYMBlink_08/02/01 .pptYucca Mountain Proj ect/Prel imi nary Predecisional Draft Materials
Subsystems, UZ flow , Thermal seepage
, In-drift thermal hydrology
0 Thermal-hydrologic-mechanical (THIM) effects
- Thermal-hydrologic-chemical (THC) effects, in-drift water and gas chemistry
0 Waste package (WP) corrosion
0 Water diversion in the engineered barrier system (EBS)
* Waste form mobilization
* EBS transport
* Unsaturated zone (UZ) transport
* Saturated Zone (SZ) transport
* Biosphere
• Disruptive events YUCCA MOUNTAIN PROJECT
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 16
0 0.4
a. L
.UwJ
0 *
(U C a) U C,)
(U C
0 z I
a) U, 0 a CU 0 I-
cc
C0 0
0) 0 c 0
0
00,J >hC0
E4-o = 6o' CL-0 m >
S
(jAlwejw) eso] lenuuV ueevJ
a a -o � o o et o � m
a -o C a a
'a
a,
a) S
C a
40
xo0
.0 ClE
0
CLi
"co -Q
)w
0 E
0
0
c0
RU
UZ Flow Developments since TSPA-SR
* Examined lateral flow in the PTn
* Expanded 3-D flow fields
* Included lithophysae in thermal properties
° New Thermal Hydrologic Chemical (THC) model development-addressed processes beyond scope of drift-scale THC models
* New Thermal Hydrologic Mechanical (THM) model development-addressed multi-phase flow and calculated stress-induced permeability changes
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 18
*0
- N � CO
- 6 a a 0 0
C
u=0
(W) uoiIEA919
0r~0
<USC (D -D.C
a a C C 0 0) cC N - a C C
E
00
(0
a)&S.S 0 40 %C
00
E U
SE
U) E
--- A
a C) � 0)
a � C) -n Z
0 Al a *�
I>1
*
B (U a) E L. a) 0�
(U
(3
a) I
(U E Ia) I-
L.
*
(0 q) 'mm.
Cu
0 I.
b
(U
0 I-4
U Iii
0 rr a2 I
2
0
4 U U
a a a 0
a C
5
U) C 0
C 0, (0 S
(0 C,
C a 0 C-)
m
0,
0)
0
C 0 U) 0 0) V 0)
C E 0, a 0 C, p
0C
C 0
0 0
0
Seepage Developments since TSPA-SR
• Expanded seepage model to include Tptpll
* Reduced conservatism in flow focusing factor
* Used a more realistic 3-D drift degradation seepage model
* TH, THC, THM-Examined range of thermal operating modes
* THM-Developed a fully coupled THM Continua Model and improved the THM Distinct Element Model
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 20
In
00
C C CC z C
C L�JL C
2
C
C
2 C C C
C
CO
C
C
(JAICuJ) awje8UO
E R:
-Th1-� C
0)
C,
0)
0 .j
Cl)
0
Sc
0D
2
00
0
0
Sc 0 E
0. C,) I*6� C a) E (0 (0 4) (0 (0 NC
IC 0� Co IC
CL
al)
E Lm
0,
CD
0
0
(3 hi
0 ft 0. 2
I2
0
'C U U
a
a c'J 0 cc a
C 5
�6 a C
fl a C Co 0> AU, 0 r a
U C) cc) m
D
0
Key Thermal-Hydrologic Environment Uncertainties Evaluated in SSPA Vol. 1
* Model (Conceptual) Uncertainty * Process * Input Data
- Use of effective thermal conductivity Uncertainty Uncertainty and thermal radiation approaches - Hysteresis - Invert
- Neglecting dryout during ventilation of imbition properties
- Coupling of submodels - THM & THC - Host rock changes to bulk
- Localized effects of seepage hydrologic permeabil
- Neglecting fracture heterogeneity properties - Host rock impacts on seepage thermal conductiv
- Neglecting effects of mountain-scale (wet & dry gas-phase convection
-Host rock - Effects of lithophysal porosity on heat capak
vapor storage
NOTE:
DKM = dual permeability model
THM = thermal-hydrologic-mechanical
THC = thermal-hydrologic-chemical
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBIink 08/02/01 .ppt
ity
ity r)
city
Host rock lithophysal porosity
WP thermal output
Ventilation duration and eficiency
YUCCA MOUNTAIN PROJECT 22BSC Graphics PresentationsYMBlink-08/02/01 .pptYucca Mountain Project/Preliminary Predlecisional Draft Materials
The LTOM Thermal History is Similar to theHTOM after a
w 100
(D 80
E 6) a
Few Thousand LTOM 2600 yr Shifts (Optimal)
H TOM _LTOM + 2600-yr shift
U -102 103 104 105 106
Time (yr) 8,,0m_ a0
* HTOM models include the LTOM environments
* High temperature parts of the models could increase HTOM uncertainty compared to LTOM
HTOM and L TOM performance are similar because the HTOM thermal pulse does not significantly affect the EBS or Natural Barrier System
Yucca Mountain ProjectfPreliminary Predecisional Draft Materials BSC Graphics PresentationsYMBIink 08/02/01.ppt YUCCA MOUNTAIN PROJECT 23
Years
BSC Graphics PresentationsYMBlink_08/O2/01.pptYucca Mountain Project/Preliminary Predlecisional Draft Materials
WP Temperature Sensitivity to Location and WP Type
Location in Footprint Waste Package Type
104 105 10
Time (yr) Blink lb.ai
* The variability range for location and WP type ~200C
is
* The variability range for operating mode is ~9 00C
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC GraUhics Presentations YMBlink 08/02/01. ot 24
180
160
140
120
100
80
60
C) 0
E F.
40
20
0
Time (yr)
106
m
o6
J J I m • I I
Sensitivity of WP Relative Humidity (RH) to Infiltration Rate and Operating Mode
(All WP Types and Locations)Location in Footprint
102 10 3
LTOA
Waste Package Type
104 105 106 102 103 104 105 106
Time (yr) Time (yr) Blink_28a.ai
4 low RH duration is similar to HTOM
Yucca Mountain ProjectlPreliminary Predecisional Draft Mate�aIs BSC Graphics PresentationsYMBlink 08/02/0 1 .ppt YUCCA MOUNTAIN PROJECT 25
-4
V E I
'4-,
Yucca Mountain Project/Preli mi nary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
C) 0 'A
CD
0 0 A (A �4 (A (� 0�
I'll'- H 01 -4 -4 -4�(*� C)
�0
-. 8
C
C
C r. -4-4
5 z 0-. -s K
0 Ni
�1 C
H
-� 0, 0, � 0 .,, C O� 0
-. La
0~
Cl,
CD. 4
0,D) ow
(0 - S
0 r)-3*
0
0 0
0
C, 0 0
qI
y M)( 15
I -4 0-4 0
0, 0 -. 0� * O)0,-4�JL� 0 0 0 0 0 0O�CO!0d)0
77:
0 0 C 0, 0
0
-I 'C
C,
-u
-a -I CD 2 CD
U
C -I CD
H
'A �A * (P 0, (P 0) 0)0
VJfln(J)
9�1��
.4 C C C,
0 C 2 -I
2
0 L N. C,
-1
4)
E
4)
3
LU
4)
CD Z CD
0
E E
co
0
Ol.-
U) 4"
0 m
rL=
E a.U) U)
0
(D
LU
a 0
U)
Cf)
E2
0
2
(,Oý X) (W) A
0
0 J
0
Sensitivity of Waste Package Temperature to Infiltration Rate and Operating Mode
(All Waste Package Types and Locations)
1.0 -", j,.. • WPs in the HTOM
0.8 - Exhibit larger SLMNtemperature LTOM ICN01
co - variability S0.60.6 \Stronger
I-o IHTOM \, nitainfu " ,M \dependence on
M 0.4- infiltration flux
£1 L) 0.2 -
C) 0.2 __Mean Infiltration Flux
................. Lower Infiltration Flux - - - - Upper Infiltration Flux
01 60 80 100 120 140 160 180 200
Peak Waste Package Temperature (1C) Blink-7c.ai
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01.ppt 28. .
i ainsolooid uo 1394D aouapuadaU awii Aoua*1143 uOIIIJI'IuQA
%SZ
4SOJOd esAqdoqjjj
bula4dS dM Alped
V4011 #7 !qDv 10 PoLlion
Ouioeds UP(] BO dM
luejsuooý
4) LM
0
0
0.
0
cn
juopuad*p-owij
sieex ooý
sJ89A ZZE uoileincl uoijoiIjuaA
$JeeA OLZ
V4011 %OL'VqOIH %09
0jaz
uoilelpeH
dm ýJmd sisee ubisac]
A W/M PO c dwai
AojeU 9Z 0
U01
Aip t's o
19M ýl W/AA ý L L
VqOil %08'V401H %OL
Aouaiawg UOIjMT1r-VIOi-l %06 'NOiH %09
6-99(D LM
mw bs 9-a L
IAj!j!qcOWJOd JIV;41JP-u
uoilepoleo-joildx
jewlaqj ulj(]-Ul 10 juawle
dMI ?JaAV
SdAA 6uowe AliljqB'JeA P?
poseq-uoppico
dM SSE10 M-IH
H
) IOWJ9qi IJaAUI
z
ADJBO
ýjp tq I
lam N W/M Lo z
A W/M 9
PaAUJ UO l09JJ3 AJIAilonpuoý
A
OOAUOO aSUqd suz) tueAon
(UP LZ L 'IOM L2 I
AIIAIlonpuoo jewjoq
(0ý) (eseo aseq snuiw) einjejedwei ýeed
0
L
z
Supplemental Engineered Barrier System Chemical Environment Model
* Main improvement for the TSPA-SR supplemental chemical environment model is the propagation of uncertainty associated with the composition of water and gas entering the emplacement drifts
Different PCO2 soil horizon starting conditions (high PCO2
and low PCO2 cases)
- HTOM versus LTOM
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 30
Key Chemical Environment Uncertainties
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink 08/02/01 .ppt
Blink_32.ai
YUCCA MOUNTAIN PROJECT 31
Key Uncertainty Not Included in Model Improvements Included in Supplemental S&ER Models Discussed in SSPA TSPA Model
Volume 1
Composition of liquid and gas Yes Yes entering drifts
Seepage/Invert mixing and interactions Yes No
Trace elemental compositions and Yes No effects on chemistry
Radionuclide sorption onto corrosion Yes Yes products
Cement leachate effects on in-drift Yes No chemistry
Generation of colloids from corrosion Yes No products
Yucca Mountain Project/Prelimi nary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
E
E
ýD
LM
E
LM
CL
0
0
cn
Hd (ý/6w) uoljejju@ouoo
t
75
(Awdd) uoileiluaouoo (-IIF)W) uoilejluaouoo
In-Drift Water and Gas Chemistry (after temporal abstraction,
prior to gas-liquid equilibration)9.
8
7
6-
-r Cl
E
CL
0 10
100
1,000
HTOM Displaced by Water Vapor
LTOM
II I-I . I - I L 10,000
1 100 10,000 1,000,000 Time (yr) Blink_17.ai
HTOM and LTOM are similar after a few 1000 years
YUCCA MOUNTAIN PROJECT
Yucca Mnountain Pro•ict/Preliminarv Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01.ppt 33
LTOM
HTOM
S........ r -- -- I II . . . . . .... .....La i ..I F .I j . . . ..I ..........I . . . . . ......... .... .... ......
Invert Evaporation Sensitivity to Location
30
1-1 E
,D 4-0
0
0
4-a
25
20
15
10
5
0102 10 3 104 105
Time (yr)
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01 .ppt
106
Blink 4b.ai
YUCCA MOUNTAIN PROJECT 34Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
pH for Higher CO2 Case Pore Water - Type Seepage
8
7
I6
5
4
0.01 0.1
1 - Qe/Qs (also known as 1 - Res)
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYM Blink 08/02/0 1 .ppt
10 Blink_30.ai
YUCCA MOUNTAIN PROJECT 35
0.001
Yucca Mountain Project/Preli mi nary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
Waste Package Corrosion Developments Since TSPA-SR
* Range of water chemistries affect salt development
- The WP Critical RH Model in TSPA-SR considered only carbonate base brines
- The SSPA considered near-neutral pH brines, and the possibility of soluble calcium and magnesium halides
* Considered potential effect of soluble Pb and other minor constituents in natural systems
* Also considered other sources of soluble salts
- Entrained matter in ventilation air
- Rock dust
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01.DPt 36
a I • m I g
Alloy 22 Phase Stability in SSPA
* New data increases confidence in TSPA-SR - Theoretical modeling of base metal does not show phase
instabilities under repository conditions
- Long-range ordering (LRO) not expected below 3000C
- Preliminary weld data do not indicate instabilities below approximately 2000C
• Alternative lines of evidence
- Degradation in mechanical and corrosion properties due to aging does not appear likely at temperatures below 3000C
- Two-phase metastable structures in Josephinite stable for more than 100 million years
YUCCA MOUNTAIN PROJECT
BSC Graphics PresentationsYMBlinkO8/O2/Ol.ppt 37Yucca Mountain Project/Preliminary Predecisional Draft Materials
- ~~General Corrosion Rate(mlr
-0 oD r- v
0) o='- o- EM (D 0
~tm - M 0. 2 0 *
~~0- 0
o ~ ~ ~ ~ 3 flf ' j - i
oD CD s..
Tim toCrodahogh2c f~ly2 (r O 0 11u '. N
MI 3 '- 0000 o* r* >D~
a -. (-n
cf C) 0
>C (D 0 M
-. 0) g) z 0 - (D D 0Di
z - A Lb -C801
r* 0-. z M.0m M 900,000 ') M . 0D(
1,0000 I 0 liet ordeTruh2mof*o 2(r
U) U)
t3)
cto
0-0
00 00
0
(D
V
cc
0, Eu
LL
L.1
RENE
4)
U.
- N o a C C I?
0
0
>1
m0
Lo C4
o N
00
00
Co. 0
S00
-0
0
0 0
C,
C
0 0 0 0 0
C 0 0 0
>1
a)
E) 2z
C C C
-40
saile.n !Ej kJE /m uoOijoi. EunjI!eJ ueeVIt dMA
71
I I
0 0
U uJ
0 ft a. 2
I2 0
4 U U
a a
C N 0 0, C
C
m
Cs C 0
C
0to C,
a
0 0
U,
0
0
C 0 Os 0 S 0 S 0
C
2 0)
0C 0l C
0
(I 0
S.
U) a) I.. Cu
0 I
0 I-4
a C
WP Temperature-Humidity Trajectories and the Crevice Corrosion Initiation Window of
Susceptibility 100 0 Crevice corrosion initiates by
IPE HTOM breaching the passive film 80-E 8aC_ The process model crevice
60 y O corrosion initiation window
60- includes T, [Cl] and pH =3 -3000 yr/ 1I
STOM - The pH dependence dominates T 40- and [CI-]
The TSPA crevice corrosion 2 MgC,2 initiation is based on pH
Window
0 410 80I,,iII I I I , ,0 Both LTOM and HTOM avoid 020040 60 80 100 120 140 160 180 200 crevice corrosion
Temperature (1C) Blink-9f.ac
- LTOM: Temperature criterion
- HTOM: Chemistry (pH) criterion
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 40
WF Mobilization Developments Since TSPA-SR
• In-Package Chemistry
- Effects of HLW glass and steel degradation rates (on pH-time trajectories and actinide dissolution)
• Dissolved Concentrations of Th, Np, Pu and Tc
- Effects of thermodynamic data uncertainties, oxygen fugacity, concentration-limiting solid
- Updated solubilities have lower means and wider ranges
• Cladding
- Effects of creep rupture and stress corrosion cracking, localized corrosion rate uncertainty, seismic failures, rock overburden failure, unzipping velocity uncertainty
* Colloids
- Simplified model with expanded range, includes reversible and irreversible Pu attachment
YUCCA MOUNTAIN PROJECT
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01.ppt 41
0
E m<
CO
4% co
0
0.
CL
0
00
-1 *.,
w
z
z 3 0
0
4)
4)
(D CL
(D
-0
'0
4)
0
10
6 0 Lf) 04
r. L
a.
Q CL
CL 4) a) a)
0
0
0
0
CL
0
0
U)
L. a)
Ou
r
m CL 4.0 4)
0-0
(1)
r
0
CL
4) 0 13
c
0 0).he
m
CL 0
0
W m0
U)
r.
LM 0
U.
m
0(jAwd) Ajiý[lA 6utddizun Polo
E
19
(-1/10w) [JejOj1dN(Aa,,-ýwjbw) aleý uoPnl,,ss!o ANSO
Supplemental Engineered Barrier System Flow and Transport Model
* Main improvements for the TSPA-SR supplemental EBS flow and transport model are
- Seepage evaporation at the DS
- DS and WP flux models
- In-package diffusion
- Radionuclide sorption
YUCCA MOUNTAIN PROJECT
Yucca Mountain Proiect/Preliminarv Predecisional Draft Materials BSC Graohics Presentations YMBlink_08/02/01 .ppt 43I. . . . . - -. . . .. . . .- j -. .. . .-.. ....... ..- . . . . . . . -- _ . ,
Key Flow and Transport Uncertainties
Blink 33.ai
YUCCA MOUNTAIN PROJECT 44Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBIink 08/02/01 .ppt
Key Uncertainty Not Included in Model Improvements Included in Supplemental S&ER Models Discussed in SSPA TSPA Model
Volume 1
Seepage evaporation Yes Yes
Drip shield and waste package fluxes Yes Yes
Drip shield condensation Yes No
Bath-tub flow Yes No
Diffusion in waste package Yes Yes
Diffusion from waste package to invert Yes No
Diffusion through invert Yes Yes
Microbial sorption and transport Yes No
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
Impact of Thermal Operating Mode on Engineered Barrier System Transport
* EBS Flow
- Evaporation rates are a function of thermal response
* EBS transport
- Diffusion coefficient is a direct function of temperature
- Diffusion coefficient is a function of the time-dependent saturation
- Adsorption of water vapor is a function of RH
YUCCA MOUNTAIN PROJECT
Yucca Mountain Proiect/Preliminarv Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 45I.. ... .J- . I - I . . . .y • _ _ . ,
00»
CD -w 0)
Za 0.
Cl0) o a
LU.
LM0
LMC
C S 0
E mo
Engineered Barrier System Transport 30-1.0 I I I I lIIll I t I I I III I I I i I I l
ONon-sorbing RNs 25 i LTOM "T-averaged over breakthrough period
0.8
20-'
0 0.6 / ,/
o 0.6
.0 Q .. 15
z 0.2- //
z 0.2. ,' HTOM : ,s/
7' LTOM
o04-L 0 Maximum 1,000 10,000 40,000 100,000 0.1 1 10 100 1000
Time (yr) 8- .24-. Tim e (Years) Bh n,_25A,
* Parameters depend on T - Diffusion coefficient is f(T, Sinvert)
- Absorption of water vapor (condensate thickness)
- Evaporation/condensation fluxes
Negligible difference between HTOM and L TOM because very few WPs fail when temperatures are different
YUCCA MOUNTAIN PROJECT V.,,, . M Iintn n Proiec--f/Preliminanr Pree, n Iio aIDraft IMaxterials R RC .CG ranhics Pr•entation . YMR~link 08/02/101 _nt 47Yucca mouniain rrOjeGTJrrellMlrlaFy r-FeUeL;JblUFldl Uldit IVIULUF]Ulb 00%., %;11 CLPI I JUO F I týWll I LCXLIVIIO- I IVIWII I IRVVIVý/V I PFL
UZ Transport Developments Since TSPA-SR
* Transport times in the drift shadow are orders of magnitude longer than predicted by the existing PA model. The transport times in the drift shadow model are significant relative to the 10,000 year regulatory time frame
* Process model representation of matrix diffusion is conservative due to matrix discretization effects, resulting in shorter predicted breakthrough times. The PA model is conservative relative to the process models over most of the breakthrough curve
* Including the southern extension to the potential repository block results in slightly longer transport times to the water table
* Local dryout from TH processes will delay or reduce radionuclide transport immediately beneath potential waste emplacement drifts for 2000 to 3000 years. Other thermally-driven coupled process effects are expected to have minimal effects on transport
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 48
Unsaturated Zone Transport
• Calico Hills peak temperature (~750C HTOM)
- Is not high enough
- For long enough
- For significant zeolite alteration which could change flow patterns or sorption
YUCCA MOUNTAIN PROJECT
Yrucca Mntant~in Proi•ct/Preliminarv Predrecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01.pDt 490
S....... r -- i i IT . . .. . .... ........ I . ..7 1 jV U. ... .... l.I.I ... a • .F.I . ......... ................ I
SZ Developments Since TSPA-SR
* New Data
- Lithology of Nye County wells
- Hydraulic head and water level elevations
* New Field Test Results
- Alluvial Testing Complex (ATC) hydraulic measurements
- Preliminary ATC single-well tracer test results
• New Model Analyses (Process model level)
- Alternate conceptual model for Large Hydraulic Gradient
- Alternate representation of Solitario Canyon Fault
YUCCA MOUNTAIN PROJECT Yucca Mountain Proiect/Preliminarv Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01.pot 50
I - -. . - . . . i - . . . I -- -- I I
SZ Developments Since TSPA-SR (Continued)
* New Model Analyses (total system level)
-Dispersion and matrix diffusion analyses
- Sensitivity to flow path length in alluvium
- Sensitivity to reversible colloid model uncertainty
- Location of accessible environment (EPA final rule)
* New Values Used in SSPA
- Bulk density of alluvium
- Sorption coefficients (Tc and I)
YUCCA MOUNTAIN PROJECT
Yucca Mountain Proiect/Preliminarv Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01.ppt 51. "- -- -j- I
Biosphere Developments Since TSPA-SR
0 Updated FEPs
0 Relative exposures to receptor groups
• Improved distributions for input factors in External and Inhalation exposure analyses
• Climate effects on water usage & ingestion exposure
0 Improved transfer coefficients (soil to plant, etc.) for Pb, Bi and Po
0 Revised BCDFs
0 Increased GENII-S sample size
• Revised volcanic eruption BDCF analysis
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01 .ot 52I.. . . . . i . . . . . . . . . . . . . . . . . . . . . . .
S........ r ..................... • ........... • ........ rr-
Disruptive Events Developments Since TSPA-SR
* Use of wind speed data that extend to the height of the eruptive column
* New analyses of the probability of dike intrusion, considering changes in layout parameters and alternate models of eruptive center development
* Characterization of uncertainty associated with emplacement drift damage zones due to igneous intrusion
* Evaluation of dose sensitivity to waste particle size distribution in an igneous eruption
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics Presentations YMBlink 08/02/01 .pot 53o
Mean Annual Dose (mrem/yr)
a a 0 0 0 C -. A
S
CL- Z
o 2rm (D <D am (
(I) -D (D0
a aa
3
CD q CD
m E-h
0
0.
CL
CL 0*
0 a. CD
Lfl
C"
0
C., 9 OS
a a a a a a
0 c
z
0 L
'C
0)
x
-1
z
z 0 0
x 0
0 r.L
CD
'00
ZOLM
cn
0
0.00
0 ch
0 0
0
.0
cn 0
cc E cn
0
om 0 0 x
ý oc 0 0
M Cc
E o r. 0 .- m cc O-Z m >
cc
0
0 0
0
0 rm
0 ri
ca
z
10
X
(D
E
(jA/wajw) es(ýo ie-nuu-V u-eeA-
Annual Dose (mnremn/yr) 0~~ 0 0 0
(In Ow
Annual Dose (mnrem/lyr)
C)
0
00
C
* I fl* (D CD
* (pa) -r -n 0 -, * (p 0
(p * r x (p =
(p
A + r
1%
L
I
Annual Dose (mnrem/lyr)
a a C a
-1 -t
$
CF 0)
K -�
2 , 0 p a � a CL
3
I C
7 �0
* C a
0 0
>0 mc
CO0(D C c. INIc r-l M
-'0 o) (j
>-
UCD U)
0 ( U =r
r--j -1(0
�tQ.
0 cm 0
,� a - a � 0�
0 0
0
I
z 0
0
-
I
--m 0
0 (I) (D
CD
Co I.
Co a)
C a 0� o a �;
a C 0 C
0 *
4)
- 0)
0 a L- ,g
00) LL 4)4 Z 0 V C4CCUQ)
00 U rn.L0 (D~C a.~U Ew)0 ~u
O~0.0JM I-a
ZO
'V E
FC,
.00
U) +a %
40) oo2> o~~2v.-
00 0
'3
0
0
0
�Iu-I
Ca
Ca a) -I CD Ca
-S
a) -It
-ml 0
a)
am
�ml
0
C C C
H
'C
Ct
C C 0 0
0
0 0 C
Annual Dose (mremlyr) 0 ,0 C 0 0 0 0 0
o 04 S C
Annual Dose (mremAyr)
'p o
r --Im
III - C0 ,
Annual Dose (mrem/yr)
o8 8 8 0 8 0 8 8 8
""'I M ~ A
9 C,
C,
(A
0o 0
0o 0o
9 CD -I C *0
0
C,) C, CD
-I
0
CD 0
0 0
0 0 !3
CD
0 M MT
'Cl
I
Co
S
v
-
Process Model Effects on Dose
• Updated Np solubility- l Ox peak dose decrease
• 1,000,000 year climate model - 1Ox dose variation
* Temperature-dependent general corrosion
- 700,000 year delay in peak dose
- -350,000 year delay in 1 mrem/yr dose rate
* Early failure of a few WPs - dose rate -10-4 mrem/yr
YUCCA MOUNTAIN PROJECT Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt 59
Yucca Mountain Project/Preliminary Predecisional Draft Materials BSC Graphics PresentationsYMBlink_08/02/01 .ppt
YUCCA MOUNTAIN PROJECT 60