Upload
truongthu
View
214
Download
0
Embed Size (px)
Citation preview
1
SUBSET 2E: QUESTIONS ON CONDITIONS
QUESTION 76
Ms. Irving owned a shopping mall with 20 spaces in Morena. She was interested in selling the mall. Dr.
Jimenez was a successful physician who specialized in scanning technology such as positron emission tomography
(PET) and magnetic resonance imaging (MRI). He was interested in purchasing the mall and using two spaces for
his own offices.
On May 1, 2011 Irving and Jimenez signed a writing providing that Jimenez would occupy two of the 20
spaces, spaces 6 and 7. The writing stated that the parties intended to close the sale on September 1, 2011 for
$3,000,000 and contained the following additional provisions:
“2. Prior to August 1, 2011 Irving must obtain from the El Dorado Medical Agency a permit for
Jimenez to conduct PET and MRI testing in suites 6 and 7. Irving is financially responsible for any
modifications to the premises necessary to obtain the permit.
7. This agreement is contingent upon Jimenez obtaining mortgage financing for $2,600,000. The
duration of the mortgage shall be no shorter than 20 years, and the interest rate must be no higher than
3.5% per annum. Jimenez must be able to obtain a final commitment for such mortgage financing before
August 20, 2011.
9. It shall be a condition that at closing, Irving produce signed agreements for at least 16 of the
remaining spaces. Each lease must terminate no earlier than September 30, 2012.”
In early May, Irving contacted the El Dorado Medical Agency to determine what alterations she would
need to make to suites 6 and 7 to enable Jimenez to obtain the permit. After contacting the agency, she hired a
general contractor at a cost of $57,000 to make the alterations. The contractor completed work by July 10. Irving
then called the agency and asked them to inspect the alterations. However, she discovered that due to a large budget
deficit, on July 10 the Governor had issued an order closing all non-essential state offices, including the agency, for
two weeks. The inspection was delayed until August 4, but the inspector found the alterations were satisfactory. The
agency issued a permit on August 6. Irving notified Jimenez the permit was available. Jimenez responded,
“Understood,” but did not stop by to pick up the permit.
In early June, Jimenez began applying for mortgage funding. In early August, he reached a tentative
agreement with Karmel Bank. The loan officer, Ms. Lion, told Jimenez that to get “a final commitment, you must
send us your last three years‟ tax returns.” The next day, Jimenez developed a serious flu. Although he had a
business manager, Jimenez did not ask the manager to copy the tax returns and send them to Lion. Jimenez did not
recover from the flu and did not return to his office until August 21. On that date, he sent the copies of the tax return
to Lion. On August 25, she emailed him a “preliminary firm funding commitment.” He did not contact her again.
On August 26, Jimenez met with his financial consultant, Mr. Maloney. Maloney told Jimenez that he,
Maloney, hoped that Jimenez had not yet finalized the purchase of the mall because Maloney had found “a much
more profitable investment opportunity” for Jimenez.
In early August, Irving began compiling the signed leases of the other mall spaces. She had 15 signed
leases. A 16h prospective tenant, Mr. Natomas, had assured Irving that he would sign on August 20. However,
Natomas died unexpectedly on August 19. Natomas‟ wife contacted Irving on August 25 and emailed that as soon as
she was appointed executrix of the estate, she “absolutely guaranteed” she would sign the lease. Irving informed
Jimenez.
On August 30 Jimenez told Irving he “was no longer interested in the deal. Why? The mortgage funding
delay has proven troublesome.” IRVING SUES JIMENEZ FOR DAMAGES FOR BREACH OF CONTRACT.
2
QUESTION 76
1 the duty to buy the property
2 conditional
11 CONDITION #1: THE PERMIT
12 is it a condition?
13 “must”
14 language of duty
15 however, a bargained-for exchange
16 therefore constructive condition of exchange
21 what happened to the condition?
22 specified date: before August 1
23 permit available on August 6
24 did the condition fail‟?
25 no “time of the essence” provision
26 time not impliedly of the essence in construction Ks
27 closing on September 1
28 plenty of time left
29 D didn‟t have to make further alterations
29.1 P had made those arrangements
31 if the condition failed, any excuses?
32 substantial performance
33 no express condition
34 therefore substantial performance applicable
41 subjective element
42 P acted in good faith
43 contacted agency in early May
44 evidently hired contractor shortly thereafter
45 objective element
46 basic purpose: allow D to do imaging on premises
47 basic purpose fulfilled
48 permit available to D
Avoidance of severe forfeiture
innocent
severe
15% rule of thumb
can be used against express conditions
relatively immaterial condition
minority view
51 impossibility
52 unanticipated event?
53 how extensive public knowledge of the budget deficit?
54 but foresee The Governor‟s order?
55 impossible?
56 illegal for agency to continuing operating
57 inspection delayed until August 6
58 immaterial condition?
59 timing critical?
59.1 supra
61 slip of the tongue
62 D told P he was refusing because of the mortgage funding
63 he did not mention the permit
64 split of authority
65 minority: slip fatal
66 majority: only if the facts give rise to estoppel waiver
67 not here
3
68 D made the statement weeks after August 1
71 CONDITION #2; THE MORTGAGE FUNDING
72 a condition?
73 “contingent upon”
74 characteristic wording
75 thus an express condition
76 in any event constructive
77 supra
78 a condition can involve D‟s conduct
79 “any” act or event other than mere passage of time
81 what happened to the condition?
82 “final” commitment by August 20
83 a commitment August 25th
84 late
85 moreover, “tentative” commitment
86 never a “final” commitment
87 condition technically failed
91 if condition failed, any excuse?
92 slip of the tongue?
93 D expressly mentioned “[t]he mortgage funding”
94 excuse inapplicable
101 substantial performance
102 inapplicable to express conditions
103 this condition express
111 impossibility
112 D‟s illness a contributing cause
113 unforeseeable?
114 render impossible?
115 D had a business manager
116 immaterial condition?
117 funding important
121 prevention by D
122 the form of the conduct
123 the evolution of the law
124 modernly passive non-cooperation substantially impeding
131 wrongful conduct
132 D responsible for obtaining the funding
133 “Jimenez obtaining mortgage financing”
134 implied duty of cooperation
135 never told business manager to send the returns
136 D neglected to contact Lion again
137 a combination of defaults
138 causation
139 facts establish
141 CONDITION #3: COLLECTING ALL THE CONTRACTS
142 a condition?
143 “It shall be a condition”
144 express condition
145 in any event constructive
146 supra
151 the nature of the condition?
152 “Signed” agreements
153 not mere agreements in principle
154 timing critical?
155 no “time of the essence” provision
156 time not impliedly of the essence in lease K
4
157 but this date was the final closing date
158 closing date more likely to be important
161 what happened to the condition?
162 as of closing only 15 signed agreements
163 Mr., Natomas agreed
164 but never signed lease
165 Mrs. Natomas
166 agreed
167 sent email
168 strong language: “guaranteed”
169 but never signed lease
169.1 condition technically failed
171 if condition failed, excuse?
172 substantial performance
173 as a practical matter the last lease
174 written email
175 “guaranteed”
176 arguably firm enough to trigger promissory estoppel
177 but express condition
178 cannot invoke substantial performance
181 estoppel waiver
182 Did P stop pursuing the last lease because of D‟s repudiation?
183 timing
184 not if time of the essence
185 D made statement on August 30th
186 P could not have obtained a signed lease by that day
187 yes if time not of the essence
188 P could have obtained the lease after that day
189 D‟s statement prompted P to forego doing so
Prospective non-performance
same facts
191 slip of the tongue
192 split of authority
193 only under the minority view
201 if even one condition neither fulfilled nor excused, no duty of imm. perf.
202 D‟s strong argument: the number of signed leases
211 if all conditions either fulfilled or excused, duty of immediate performance
212 D did not fully perform
213 facts do not establish any discharge
214 ergo, D would be guilty of breach
5
QUESTION 77
Mr. Masoli wanted to develop a 50-unit retirement home on a large parcel of land that he owned in Morena.
The parcel was zoned for commercial use rather than multi-unit residential. Ms. Nagoni was a licensed general
contractor.
On January 1, 2009, Masoli and Nagoni signed a writing. In the writing, Nagoni promised to build the
home in four phases: #1 to be completed by September 1, 2009, #2 by January 30, 2010, #3 by July 30, 2010, and #4
by December 30, 2010. Masoli promised to pay Nagoni $2,000,000 at the completion of each phase. The writing
stated that:
—”It shall be a condition that Masoli be able to have the property rezoned to multi-unit residential use. The
rezoning should be obtained by March 30, 2009.”
—“At the end of each phase and before Nagoni is to be paid, architect Lee Otto of Morena must issue a
certificate that Nagoni has strictly complied with the attached plans and specifications.”
—“Masoli will not be obliged to make the final payment for phase #4 unless, at that time, Masoli has
obtained precommitments from purchasers of at least 35 of the contemplated 50 units. Time shall be of the
essence of this written contract.”
The writing contained a merger clause. Before they signed the writing, Masoli said, “I just want it
understood that I don‟t have to make the final payment unless, at that time, I‟ve got 35 signed, sealed deals.” Nagoni
responded, “Understood.”
On January 1, 2009 Masoli applied for the rezoning. Due to budgetary problems, the city had begun
furloughing employees in the Planning Department. Consequently, the new zoning was not approved until April 1,
2009. On April 2, Nagoni asked Masoli whether he had obtained “the rezoning required by per deal.” Masoli said,
“Yes.” Nagoni responded, “OK. I‟ll begin now.” Masoli said, “Full speed ahead.”
Nagoni completed phases #1-3 and received the first three payments from Masoli. On the first two
occasions Masoli paid without demanding Otto‟s certificate, but Masoli demanded “the required certificate” for
phase three. On August 1, 2010, Nagoni began work on phase #4.
In the meantime, Masoli had learned of another business opportunity. It promised such enormous profits
that he seriously thought about diverting his resources to the other project. On September 2, 2010, Masoli spoke
with his Marketing Director, Mr. Pope, who was in charge of obtaining the precommitments. Pope told him that he,
Pope, already had 31 signed contracts and that six other families had “strongly indicated that they were eager to
come in and sign as soon as possible.” Masoli told Pope, “Let‟s slow down a bit. Don‟t get back to those folks yet.
There‟s no need for them to rush and sign their contracts yet.” Pope said, “If you say so. You‟re the boss. But,
frankly, I don‟t see any purpose to delaying.” Masoli responded, “Oh, there is one.”
On December 10, 2010, Nagoni phoned Masoli and told him that she would swing by to update him on “the
final few, very minor things I need to do on phase #4.” He told her, “You might hold off. We‟ve had problems
getting enough signed contracts; and remember the deal is contingent on that.” Nagoni was astonished. She said,
“You‟re giving me this bad news at this late date. That‟s ridiculous. If you don‟t pay, I‟ll see you in court.”
Immediately after the phone call, Masoli emailed Otto to inform him that the project might not go forward.
The next day, December 11, 2010, Nagoni asked Otto to provide a certificate that her work to date on phase #4 was
“satisfactory.” Otto responded, “This lawsuit stuff makes me uncomfortable, and besides you technically haven‟t
done all the work.”
On December 12, 2010, Masoli sent a letter “formally terminating our contract. We simply don‟t have the
required signed contracts from applicants.” NAGONI SUES MASOLI.
6
QUESTION 77
1 D‟S DUTY
2 to make the last payment
11 CONDITION #1: REZONING
12 a condition?
13 “a condition”
14 express condition
21 content of the condition
22 certainly obtain the rezoning
23 by March 30?
24 in a separate sentence
25 distinction in the wording
26 “shall” in sentence #1
27 “should” in sentence #2
28 weaker
29 well ahead of completion of project
29.1 precise date relatively unimportant
29.2 but generally language, “time of essence”
29.3 if date not part of condition, fulfilled
31 if date part of condition, failed—April 2
32 if technically failed, excused?
33 (1) substantial performance?
34 only short, two-day delay
35 but SP not for express conditions
41 (2) impossibility
42 furloughs by city
43 unanticipated?
44 minor part of bargain
51 (2) slip of the tongue by D—not mentioned in December 12 letter
52 minority view
61 (3) estoppel waiver by D
62 P inquired whether zoning obtained
63 D said “Yes”
64 D added, “Full speed ahead”
65 P relied
71 CONDITION #2: ARCHITECT‟S CERTIFICATE
72 a condition?
73 -not use “a condition”
74 +but evident purpose
75 made payment dependent on certificate
76 technically failed—did not obtain certificate
81 if technically failed, excused?
82 (1) constructive fraud by Otto
83 “Lawsuit stuff ... uncomfortable”
84 fear of involvement not a proper basis for withholding
85 Masoli had contacted him
86 collusion—stronger case
87 but P had not completed the work
91 (2) slip of the tongue by D—not mentioned in December 12 letter
92 minority view
101 (3) estoppel waiver by D
102 two out of three times
103 —but D insisted last time
104 —and last time D referred to “required” certificate
105 —P evidently didn‟t form belief
7
106 P sought certificate from architect
111 (4) prevention by D
112 D emailed Otto project might not go forward
113 but P had not completed the work
114 architect should have withheld even absent email
121 (5) domino theory
122 split of authority
123 if depends on substantive condition, infra
131 CONDITION #3: THE SUBSTANTIVE WORK
132 a condition
133 no language “a condition”
134 constructive condition
141 fulfilled?
142 P admitted “few, very minor things” yet to be done
151 if technically failed, excused?
152 (1) substantial performance by P
153 objective element
154 “few, very minor”
155 subjective element
156 P contacted D in order to discuss and complete
157 can use SP against constructive conditions
161 (2) prospective non-performance of D‟s conditioned duty
162 didn‟t complete because D said project not go forward
163 P had ability to complete
171 (3) slip of the tongue by D—not mentioned in December 12 letter
172 but minority view
181 CONDITION #4: THE “PRECOMMITMENTS”
182 the nature of the condition
183 interpretation: “precommitments”
184 step #1: identify all the meanings
185 text—ambiguous
186 context—used different word “contract” in next sentence
187 extrinsic, contemporaneous—”signed, sealed”
188 extrinsic, later—P didn‟t challenge D‟s statement about “signed contracts”
189 two possible meanings: informal commitments or contracts?
191 step #2: characterize each meaning as a type of usage
192 precommitment—ordinary, popular
193 contract—mutual
194 step #3: choose a meaning
195 order of preference
196 Williston—general
197 Corbin—mutual even if not reflected on face of K
201 fulfilled or failed?
202 fulfilled if mere precommitment
203 31 plus 6 = 37, exceeding 35
204 if signed contract, technical failure
211 if technically failed, excused?
212 prevention by D
213 Pope said others “eager to come in and sign”
214 Pope said no “purpose to delaying”
215 D told to “slow down”
216 “there is one” purpose
217 the purpose: set up argument that condition failed
8
QUESTION 78
Mr. Hermanos was a general contractor. Ms. Ing was a subcontractor who specialized in building
foundations. Ms. Justin hired Hermanos to build a large cabin for her in a wooded area just outside Morena for
$600,000. As soon as Hermanos received the prime contract, he spoke with mg about the foundation for the cabin.
On April 1, 2009 Hermanos and Ing both signed a writing. In the writing, Hermanos promised to pay Ing
$45,000 for constructing the foundation for the cabin. The writing also contained the following provisions:
—Hermanos would pay Ing “at the time when Ms. Justin has paid Hermanos.”
—”It shall be a condition to Hermanos‟ duties under this contract that in timely fashion Ing obtain all the
necessary county permits for the construction work.” The writing specified that mg would have to “provide
Hermanos with the final county permit by June 2, 2009.”
—”Ing must comply with all the specifications in the prime contract, hereby attached as Exhibit A.”
Exhibit A stated that the base of the foundation “must be at least 28 inches” deep.
—”Before obtaining the final payment, Ing must provide Hermanos with a certificate from architect Daniel
Kessel to the effect that Ing has strictly complied with all the provisions of the specifications set out in
Exhibit A.” (Kessel was an old friend of Hermanos, and in the past two years most of Kessel‟s income had
come from projects with Hermanos.)
Ing wanted to begin work immediately. However, her own regular work crew was committed to a large
commercial project in Morena. Consequently, she hired Lorenzo Concrete to perform the work under her contract
with Hermanos. Mr. Lorenzo stopped by Ing‟s office to read the specifications. However, he was in a rush that day.
Hurriedly reading the specifications, he thought that the base of the foundation had to be only 23 inches deep.
The same day Ing instructed her administrative assistant, Ms. Mertel, to contact the County Planning
Department to begin processing the permit. Shortly after Ing issued that instruction to Mertel, though, Mertel went
on maternity leave. Although she had noted the permit on the office desk calendar, her temporary replacement, Mr.
Nerney, did not notice the notation.
On April 10 Lorenzo broke ground at the work site. He completed the foundation on May 25. With one
exception, his work complied with the specifications. The exception was that the foundation base was only 25 inches
deep.
When Lorenzo informed Ing that he had completed the foundation, Ing invited Kessel to visit the site and
inspect the foundation. Kessel visited the site on May 26th. He did not notice that the base was only 25 inches deep.
He told Ing, “There‟ll be no problem. The work looks fine to me. Call me whenever you want the certificate.”
On May 27th, Ing asked Nerney how soon he could obtain the county permit. Nerney said that he had not
noticed Mertel‟s notation and that since the minimum permit period is two weeks, Ing could not obtain the permit
until June 14th. Ing told Nerney to “rush it.”
On the morning of June 14, Ing obtained the final permit. The same morning Hermanos learned that Justin
had filed for bankruptcy and could not pay Hermanos. Hemanos notified Kessel. That afternoon Ing stopped by
Kessel‟s office to obtain the certificate. Kessel refused—and said that “under the circumstances—all the legal
bankruptcy mess—it wouldn‟t be advisable for me to do that.” Later that afternoon Hermanos sent Ing a latter. The
letter stated that “in light of Ms. Justin‟s financial situations it will be impossible for me to pay you.”
Ing sues Hermanos. At trial, Ing presented undisputed expert testimony that the shallower foundation base
was safe and would lower the fair market value of the property by only $7,000.
9
QUESTION 78
1 D‟S PROMISE
2 pay for the work
11 CONDITIONS
12 (1) SUBSTANTIVE: DO THE WORK IN COMPLIANCE
13 failed
14 plans: 28 inches
15 performance: 25 inches
21 excuses?
22 substantial performance
23 limited to constructive conditions
24 no indication of an express condition
31 elements
32 (1) subjective: innocent
33 P didn‟t make the mistake
34 Lorenzo independent contractor
35 Lorenzo “in a rush”
36 “hurriedly”
37 (2) objective: trivial
38 foundation stable?
39 “safe”
39.1 $600,000 vs $7,000
41 avoidance of forfeiture
42 minority view
43 severe forfeiture
44 perhaps
45 slip of the tongue
46 didn‟t mention in letter
47 Did D know about it?
48 minority view
49 no estoppel waiver here
51 (2) PERMITS
52 express condition
53 “It shall be a condition”
54 content
55 permit
56 June 2 date?
57 in separate sentence
58 no condition language in sentence
59 no indication time of essence other than „timely”
59.1 ordinarily not in construction Ks
61 fulfilled?
62 if only condition get permit
63 yes
64 if date part of condition
65 no
71 if failed, excused?
72 waiver
73 did D accept the permit on June 14?
74 facts silent
75 slip of the tongue
76 didn‟t mention in letter
77 should have known permit late
78 minority view
79 no estoppel waiver here
10
81 substantial performance
82 not vs express condition
84 avoidance of forfeiture
85 minority view
86 perhaps
91 (3) ARCHITECT‟S CERTIFICATE
92 fulfilled?
93 no
101 excused?
102 constructive fraud
103 would have issued
104 “no problem”
105 “looks fine”
106 “Call me”
111 withheld for wrong reason
112 “legal bankruptcy mess”
113 “[in]advisable”
114 old friend of Hermanos
115 most of his income in last two years
116 only supposed to evaluate quality of work
121 slip of the tongue
122 didn‟t mention in letter
123 Did D even know?
124 but close relationship
125 minority view
126 no estoppel waiver
127 domino theory
128 relation to substantive condition
131 (4) PAYMENT BY LANDOWNER
132 condition?
133 no condition language
134 “at time”
135 “when”
136 temporal connotation
137 convenient time, not condition
141 if condition, fail
142 excuse?
151 duty of immediate performance
152 not if even one condition failed
153 if a duty of immediate performance?
154 D not perform
155 no evident discharge
11
QUESTION 79
Ms. Harley owned a large, vacant manufacturing plant on the outskirts of Morena. Mr. Ing was interested in
buying the plant to begin manufacturing fireworks there.
On May 1, 2006 they both signed a writing including the following clauses:
“#2. Ing shall purchase the said facility, provided he can obtain a $900,000 loan at an interest rate no higher
than 5% for no fewer than 15 years. To that end, Ing shall exercise due diligence.
#3. Harley covenants that by June 15, 2006 she will obtain and deliver to Ing a written inspection report
certifying that the existing structure is in full compliance with local and state building codes.
#7. The purchase will be closed on condition that no later than July 15, 2006 Ing can obtain a permit from
the Morena Planning Department allowing him to expand the existing structure by at least 20,000 square
feet. Time shall be of the essence of this provision.
#9. A further requirement is that no later than July 30, 2006, Ing be able to obtain a permit from the State
Fireworks Commission authorizing him to manufacture fireworks on the premises. (At the time they signed
the writing, the state Fireworks Regulation Act both created the commission and required anyone proposing
to manufacture fireworks within the state to obtain a permit.).
#10. Closing shall occur on August 1, 2006, at which time Ing shall deliver to Harley a check for
$2,800,000 in exchange for Harley‟s deed.”
On May 15 Harley contacted a local building inspector and told him to “rush. Contact me if there‟s any
delay” preventing the delivery of an inspection certificate by June 15.
On June 1, the state legislature repealed the Fireworks Regulation Act. The new legislation transferred the
Commission‟s functions to the existing State Hazardous Activity Agency.
On June 2 Ing submitted a proposal to the Morena Planning Department to expand the existing plant. When
he submitted the application, he checked “normal processing” rather than “expedited” processing (requiring an
additional $275 fee). On July 11, the department notified Ing that since Harley was still the listed owner, she needed
to sign. Ing neglected to inform Harley of requirement until July 16. When Ing told her, Harley immediately drove
down to the department and signed the application. The department issued the permit on July 17.
The inspector Harley hired became seriously ill for several weeks. When she phoned him on June 11, he
said that he would “get to it as soon as I‟m well.” He completed the inspection and gave the report to Harley on June
20. She immediately FAXed the report to Ing. Ing acknowledged receipt of the report.
On July 1 Ing submitted his loan application to three of the 10 local banks. The lowest rate any of them
quoted him for the loan was a 5 1/4% interest rate.
On July 19, the State Hazardous Activity Agency issued Ing a permit.
On July 20 Ing learned that TNT Fireworks, a large national chain, had decided to open a huge new plant in
Morena. Fearing the competition, Ing had second thoughts about buying Harley‟s plant. On July 25, Ing informed
Harley that since “things weren‟t working out” as he had hoped, he did not intend to go through with the purchase.
When Harley asked why, Ing mentioned the “exorbitant” interest rate quoted him. At that point, Harley said, “I‟d be
willing to make up any difference for you.” Ing responded, “I‟m sorry. It‟s still no deal.”
HARLEY SUES ING FOR DAMAGES FOR BREACH OF CONTRACT. WILL SHE PROBABLY
RECOVER? DO NOT DISCUSS THE MEASURE OF DAMAGES.
12
QUESTION 79
1 CONDITION: THE AVAILABILITY OF THE SPECIFIED LOAN
2 a condition?
3 “provided”
4 ergo express
11 fulfilled?
12 did not obtain the financing
21 excused?
22 substantial performance
23 Harley offers to make up the difference
24 thus essentially the same position
25 but express condition
26 substantial performance inapplicable
31 prevention
32 wrongful?
33 duty to exercise “due diligence”
34 contacted only 3 of 10
35 no information about other 7
36 evidently still plenty of time
37 prevention can take the form of inaction
41 CONDITION #2: HARLEY DELIVER INSPECTION REPORT
42 a condition?
43 “covenants”
44 language of duty
45 contrast: “provided”
46 contract: “on condition”
47 ergo, constructive condition
51 substantive condition: report
52 obtained report
53 FAXed to Ing
54 Ing received the report
61 in addition, timing requirement?
62 if a timing requirement
63 failed
64 June 15
65 delivered on June 20
66 but timing a condition?
67 specific date relatively unimportant
68 closing weeks away
69 contrast: “Time of the essence”
71 if timing a requirement, excuse?
72 impossibility
73 limited to immaterial conditions
74 delay seems unimportant
75 inspector ill
76 but she not an “essential” person
77 could have used another inspector
81 waiver
82 he “acknowledged” receipt
83 estoppel
84 but occurred after failure of condition
85 election
86 inconsistent rights?
87 “covenants”—duty
88 ergo breach
13
89 material?
89.1 intentional
89.2 split of authority
89 timing relatively unimportant provision
91 slip of the tongue
92 did not mention on July 25th
93 split of authority
94 some: not unless estoppel facts
95 relevant events had already occurred
101 CONDITION #3: PLANNING DEPARTMENT PERMIT TO EXPAND
102 a condition?
103 “on condition”
104 express
105 content of condition
106 obtaining permit
107 timing
108 “Time shall be of the essence....”
111 fulfilled?
112 required timing: July 15
113 actual receipt July 17
121 excused?
122 prevention
123 not pay for expedited processing
124 wrongful?
125 plenty of time then
126 no evident need for “expedited” processing
127 not obtain Harley‟s signature initially
128 clear instructions?
129 perhaps negligent
129.1 delay notifying Harley
129.2 Ing notified July 11th
129.3 did not notify Harley until July 16th
129.4 at least negligent
131 waiver
132 Planning issued the permit
133 Did he accept it?
134 estoppel?
135 after the failure of condition
136 election?
137 inconsistent rights?
138 intentional?
139 split of authority
141 slip of the tongue
142 did not mention on July 25th
143 split of authority
144 some: not unless estoppel facts
145 here?
151 CONDITION #4: FIREWORKS PERMIT
152 condition?
153 “[a] further requirement”
154 contrast: “provided”
155 contrast: “on the condition”
156 constructive condition
157 content of the condition
158 permit
159 specific agency?
14
161 if the permit the real substantive condition
162 substantial performance
163 permission to engage in that business
171 if also a requirement that obtain permit from specific agency
172 technically failed: issued by different agency
173 excused?
174 impossibility
175 original agency no longer exists
176 relatively immaterial condition
181 waiver
182 agency issued permit
183 Did he accept?
184 estoppel?
185 events already occurred
186 election?
187 inconsistent rights?
188 intentional?
189 split of authority
189.1 relatively unimportant requirement
191 slip of the tongue
192 did not mention on July 25th
193 split of authority
194 Some: only if estoppel facts
195 no such facts evident here
201 CONDITION #5: DEED
202 express?
203 contrast: “provided”
204 contrast: “on the condition”
205 constructive
211 if condition, fulfilled?
212 no delivery
213 not even tender
221 excuse?
222 prospective non-performance of conditioned duty
223 he stated he did not intend to go through
15
QUESTION 80
Ms. Indrikson owned an undeveloped lot in Morena. In early 2005 she hired Ms. Julian, a general
contractor, to build a large house on the lot. In turn, Julian entered into agreements with five subcontractors,
including Mr. Kalish, a roofer. On May 1, 2005, Julian and Kalish signed a writing, including the following
provisions, inter alia:
1. Kalish shall complete the work in strict compliance with the attached plans and specifications. (The
plans stated that Kalish would do the work in four phases. The plans specified the type of tile and tar that
Kalish would use on each section of the roof.)
2. Before each progress payment and the final payment, Kalish must produce a certificate from architect
James Lucero that Kalish has strictly satisfied every requirement of that phase of the work.
3. Lucero shall inform Kalish of the deadline for each phase of the work to ensure that his progress does not
delay the work of either the general contractor or the other subcontractors.
4. Julian shall pay Kalish for each phase of the work within five days after Indrikson pays Julian for that
phase of the work.
5. The last progress payment shall be 15% of the contract price.
Kalish began work on May 10. He completed the first three phases of the work without any objection from
Julian or Lucero. When Kalish ended the third phase on June 25th, Lucero informed him that the deadline for the
fourth and final phase was September 1, 2005.
Kalish started the final phase on July 1, 2005. However, starting on July 2, 2005, his employees began an
illegal strike that lasted two weeks. After the strike, Kalish realized that he would have to rush to meet the
September 1st date.
On July 17, Kalish drove to his supplier‟s warehouse to buy the material needed for the final phase. He had
left the specifications at his office. Without the specifications, he purchased the wrong type of tile. His supplier‟s
policy was that all sales are final and that purchased materials cannot be exchanged later.
On July 20, just before Kalish‟s crew was to begin the work, he finally discovered that he had purchased
the wrong type of tiles. However, he believed that the tiles he had purchased were at least as sturdy and long-lasting
as those specified in the plans and that if he reordered, the delay would make it impossible to meet the deadline.
Despite his best efforts, including paying his crew overtime, he did not finish the work until September 2, 2005.
Early on September 3, Julian noticed that Kalish had used the wrong type of tile. Later that day Julian
learned that Indrikson had filed for bankruptcy and would not be making the final payment due to Julian. On
September 4, Julian sent Kalish a letter explaining that she would not pay Kalish. In pertinent part, the letter read:
“Your failure to use the specified type of material is inexcusable.”
After reading Julian‟s letter, Kalish did not bother to contact Lucero.
KALISH SUES JULIAN FOR BREACH OF CONTRACT. WILL HE PROBABLY RECOVER? Do not
discuss the measure of damages.
16
QUESTION 80
1 MUTUAL ASSENT
2 writing
3 detailed
4 signed
11 CONSIDERATION
12 P‟s promise to do the roofing
13 bargain
14 D bargained for it
15 P gave it in exchange
16 legal value
17 detriment to P
18 no prior duty to do work
19 benefit to D
19.1 no prior right to have work done
21 D‟S DUTY TO PAY
31 condition #1: strictly comply with plans and specifications
32 express condition?
33 “strict”
34 “strictly”
35 perhaps just forceful expression of duty
36 not manifest that duty to pay depend on it
37 constructive condition
38 exchange of performances
41 fulfilled?
42 wrong type of tile
51 excuses
52 substantial performance
53 not if express condition
54 objective element
55 wrong tiles
56 but as sturdy
57 but as long-lasting
58 subjective element
59 initially a mistake
59.1 but then discovered
59.2 but as sturdy and long-lasting
61 avoidance of severe forfeiture
62 minority view
63 extreme forfeiture
64 15%
65 Restatement standard
66 inadvertent
67 initially
68 minor condition
69 just as sturdy
69.1 just as long-lasting
71 condition #2: deadline
72 express condition?
73 perhaps not
74 constructive
75 part of bargain
76 affect general and other subs
81 fulfilled?
82 September 1st
17
83 September 2
91 excuses?
92 impossibility?
93 strike
94 illegal
95 but assumption of the risk?
96 his employees
97 but minor?
98 short delay
99 but could affect general and subs
101 avoidance of forfeiture
102 supra
103 minor condition?
104 supra
111 slip of the tongue
112 did not mention delay
113 split of authority
114 minority fatal
115 here
116 majority—not unless estoppel
117 date had already passed
121 condition #3: certificate from Lucero
122 condition?
123 at least constructive
124 fulfilled?
125 not for last payment
131 excuses
132 avoidance of forfeiture
133 supra
134 minor term?
135 domino theory
136 merely evidentiary
137 substantial performance
138 supra
139 slip of the tongue
139.1 supra
141 condition #4: payment by landowner
142 condition
143 “within five days”
144 temporal connotation
145 no condition language
146 just fix convenient time for payment
151 if all conditions excused or fulfilled, duty of immediate performance
152 D not perform
153 no evident discharge
154 ergo, breach
18
QUESTION 81
Mr. Hamid owned a large piece of undeveloped land in a suburb of Morena. Ms. Ingvold was interested in
buying the land to develop a tennis club. Ingvold was personally acquainted with a popular local tennis pro, Ms.
Jasiow. Ingvold believed that the club would be a huge success if she could advertise that Jasiow was the club‟s
teaching pro.
On May 1, 2005, Hamid and Ingvold signed a writing describing a sale to be closed on October 1 for
$400,000. The writing required Hamid to pay for specified excavation to ready the site for a tennis club. The writing
also included the following provisions, inter alia:
7. The Parties shall not be obliged to proceed with this agreement unless and until:
(a) The Party of the Second Part (Ingvold) obtains a mortgage loan of no less than $800,000 for no
fewer than 10 years at an interest rate no higher than 9%;
(b) The following condition occurs, namely, she obtain a permit from the Morena City Council to
operate a tennis club on said premises. The permit will be obtained by September 1, 2005; and
(c) The further condition occurs, that is, by September 1, she is able to sign Felice Jasiow to a
contract for at least three years to serve as the teaching professional at the tennis club to be
developed on the premises.
Shortly after signing the writing, after a night of excessive drinking, Ingvold became seriously ill. She did
not fully recover until June 30. On July 1, she filed the permit application with the Morena City Council and its
Planning Commission. The commission clerk informed Ingvold that it “normally” took a month to process an
application but that she could expedite processing for an additional $100 fee. Ingvold responded, “A month is plenty
of time.”
The commission began reviewing the application and was preparing to take final action, approving the
permit, when its staff started an illegal strike on July 20. The strike lasted until August 25. Although the strike was
highly publicized in the local media, it never occurred to Ingvold that the strike would delay the approval of her
application. When she checked with the commission on August 30, she discovered that the permit would not be
issued until September 5. She accepted the permit on that date.
Ingvold's illness also delayed the start of her search for mortgage financing. (During May, June, and July,
the prevailing interest rate for commercial loans such as this one had been 8 ¾ %.) During August, Ingvold
contacted only one bank, First Northern of Morena. First Northern was willing to offer her an $820,000 loan for 11
years. However, they quoted her an interest rate of 9 ¼ %. When Hamid learned of Ingvold‟s problem, he offered to
reduce the purchase price to fully compensate Ingvold for the additional interest expense.
In early August, Ingvold had contacted Jasiow to ask whether Jasiow would be willing to become the
teaching pro at the new club. Jasiow told Ingvold to “send the papers ASAP.” The next day Ingvold‟s investment
advisor counseled her against the tennis project; he recommended that she invest in a number of bio tech firms that
he had studied. She remarked that his recommendation was causing her to have “second thoughts” about the club.
Ingvold never sent Jasiow the papers. When Ingvold telephoned Jasiow on August 30 and said she needed “a
definite Yes or No right away,” Jasiow responded that she “had no choice but to say No.”
On September 20, Ingvold sent Hamid a letter stating she would not close the sale. Her letter referred to her
problems in obtaining the permit and financing. On October 2, HAMID SUES INGVOLD FOR DAMAGES FOR
BREACH OF CONTRACT. WILL HE PROBABLY RECOVER? Prior to September 20, Hamid spent $60,000 on
the excavation work.
19
QUESTION 81
1 CONDITIONS?
2 CONDITION THAT D ABLE TO OBTAIN SPECIFIED MORTGAGE FINANCING
3 —not use “condition”
4 —contrast (b) and (c)
5 but “unless”
6 express condition
11 if a condition, fulfilled?
12 technical failure
13 9%
14 9 1/4%
21 excuses?
22 substantial performance
23 objective element
24 -8 3/4%
25 +P‟s offer
26 +”fully compensate”
27 subjective element
28 neither at fault
29 delay more D‟s fault
29.1 excessive drinking
29.2 but not against express conditions
31 prevention
32 in a broad sense
33 carelessness
34 excessive drinking
41 avoidance of forfeiture
42 minority view
43 but against express conditions
44 immaterial condition
45 given P‟s offer
46 not willful
*47 not P‟s fault at all
48 severe forfeiture
49 more than substantial performance
49.1 Restatement 15%
49.2 lose $400,000
49.3 60,000 in excavating
49.5 15% here
51 CONDITION THAT D ABLE TO OBTAIN PERMIT
52 Basic condition: obtain a permit
53 “condition”
54 express
55 fulfilled
56 in fact obtained
61 Was September 1st date part of condition?
62 —separate sentence
63 —not critical
64 —neither suffer any economic loss
65 no “time of essence” language
66 reasonable, convenient time
71 if September 1st part of condition, excuse?
72 avoidance of forfeiture
73 supra
81 impossibility—(l) D‟s illness
20
82 not P‟s fault
83 D‟s excessive drinking
84 length of illness more than accounts for lateness
85 but only immaterial condition
86 supra
*
91 impossibility—(2) strike
92 could not anticipate
93 illegal
94 not P‟s fault
95 length of strike more than accounts for lateness
96 but only immaterial conditions
97 supra
101 prevention
102 “highly publicized”
103 D should have known
104 didn‟t seek expedited processing
105 mere $100
106 could have hired agent
107 inaction now recognized form of prevention
111 CONDITION THAT D ABLE TO HIRE TENNIS PRO
112 “further condition”
113 express
114 technical failure
115 not hire
121 excuses?
122 avoidance of forfeiture
123 supra
*131 prevention
132 intentional misconduct?
133 at first mere negligence
134 -then conversation with advisor
*13 5-”second thoughts”
136 -motive to walk away
137 “papers ASAP”
138 delayed
139 not sent “papers”
139.1 telephone call
141 waiver
142 sent letter
143 mention other conditions
144 omit this one
145 slip of the tongue
146 minority view
147 weak intentional waiver rationale
151 CONDITION THAT P COMPLETE EXCAVATION
152 express?
153 evidently before “unless”
154 not use “condition”
155 constructive
156 part of exchange of performances
157 ready site for tennis club
161 fulfilled
162 evidently completed work
171 D‟S DUTY OF IMMEDIATE PERFORMANCE
172 not perform
22
QUESTION 82
Mr. Ellering owned a landscape business in Morena. Ms. Fuentes wanted to purchase the business. On
April 1, 2004, they signed a writing including these provisions, inter alia:
“3. Closing will occur on June 1 provided that Fuentes then has a Morena Landscape License.
6. At closing, Fuentes must pay Ellering $400,000, subject to the proviso that Fuentes be able to
obtain loan financing for at least $350,000 of the purchase price. The loan term must be no shorter
than 10 years; and the annual interest rate must be no higher than six percent (6%). Time shall be
of the essence.
7. Prior to closing, Ellering must make satisfactory progress toward computerizing the company‟s
business operations. The equipment installed must be first rate competitive.”
After signing, on April 10 Fuentes submitted a loan application at a local lending institution. (She applied
to only one bank because her attorney correctly informed her that that was the only bank offering a 6% interest rate
on commercial loans.) However, when Fuentes submitted the application, she misread the form. The form called for
copies of her income tax returns for the past four years, but she submitted copies for only the last two years. In
addition, she neglected to tender a check for the $200 loan application fee.
On April 20 she submitted her application for a Morena Landscape License. When she did so, the form was
complete. However, on April 25, when the City Council met, it amended the ordinance governing such applications.
The amended required additional information, namely, a set of fingerprints to be checked through the F.B.L‟s
database. The amendment specifically provided that the amendment applied retroactively to pending applications.
On April 30, Ellering hired Giang Computer Solutions to upgrade his computer equipment. He explained to
Ms. Giang that he wanted “as good a computer system as any landscape business in the state.” He paid her
$35,000.00, and she began installing the equipment.
On May 1, the bank left a voicemail for Fuentes to alert her that she had not submitted the check and the
two missing tax returns. However, Fuentes‟ message machine malfunctioned and did not record the caller‟s
reference to the tax returns. On May 2, she mailed the bank the $200 check. The bank received the check on May 4.
On May 5, the city clerk‟s office phoned Fuentes to tell her that she needed to submit fingerprints and that
she could have the fingerprints taken at any local police station. On May 20, Fuentes went to the closest station, had
the prints taken, and delivered them to the clerk‟s office.
On May 21, Fuentes learned of another investment opportunity that promised a much larger return than the
landscape business. She lost enthusiasm for the landscape business. On May 25, she visited Ellering‟s business and
cursorily examined the new computer equipment. The equipment Giang had installed was superior to that of any
landscaping business in Morena, but it was inferior to the equipment used by Morena financial institutions.
On May 28, Fuentes learned that: (1) due to her failure to submit the tax returns, the bank would not
approve her loan until June 5 at the earliest; and (2) the F.B.L would not complete her background check until June
10. (If she had submitted the fingerprints any time in the first half of May, the check would have been finished by
May 25th and the license issued by May 29.)
On May 30, Fuentes wrote Ellering a letter stating that she did not intend to appear for closing. Her letter
cited “the inferior computer equipment installed by Giang” and “my inability to obtain timely, satisfactory loan
funding.”
ELLERING SUES FUENTES FOR DAMAGES FOR MATERIAL BREACH OF CONTRACT. WHO
WILL PROBABLY PREVAIL?
23
QUESTION 82
1 D‟s duty: to close and buy
2 Conditions to D‟s duty
11 FINANCING
12. a condition?
13 “subject to the proviso”
14 wording
15 express
21 fulfilled or fail?
22 specified date June 1
23 June 5 at earliest
24 but strictly on time
25 “time of essence”
26 express
27 therefore, at least a technical failure
31 excused?
32 prevention by D
33 wrongful?
34 misread form
35 submitted incomplete application
36 negligence
37 machine malfunctioned
38 negligence
41 avoidance of forfeiture
42 minority view
43 but respectable authority
44 even against express condition
45 here already paid $35,000
46 really lose that amount?
47 recoup if sell to third party
48 severe enough?
49 triple the loss in Jacob
51 COMPUTERIZATION
52 a condition?
53 “must make”
54 express duty
55 but not an aleatory K
56 therefore constructive condition of exchange
61 fulfilled or fail?
62 one theory of fulfillment—made progress”
63 not required to fully computerize
71 second theory of fulfillment—computer equipment fulfilled condition
72 “satisfactory”
73 if subjective, perhaps actually satisfied with performance
74 ulterior motive—more profitable business opportunity
75 “cursorily”
76 case for objective standard
77 does not specify subjective standard
78 commercial subject-matter
79 person to be satisfied party to K
79.1 but in favor of objective standard
79.2 reasonable businessperson would be satisfied
79.3 superior to any landscaping business
81 third theory of fulfillment—”first rate competitive”
82 admittedly not as good as financial institutions
24
83 but as good as any landscaping business
84 “competitive” qualifies “first rate”
85 more sensible interpretation
91 fourth theory of fulfillment—time to cure any deficiency
92 no express “time of essence” provision
93 express unius est exclusio alterius
94 infer time not of essence under this clause
95 P still has a reasonable period of time to cure
101 If fail, excused?
102 avoidance of forfeiture
103 elements, supra
104 applicable here as well
105 stronger case because constructive condition
111 substantial performance
112 applicability
112 not against express conditions
113 this condition constructive
114 elements
116 objective
117 facts here
118 subjective
119 facts here
121 LICENSE
122 a condition?
123 “provided”
124 express
131 fulfilled or fail?
132 no express time of essence provision
133 expressio unius
134 normal inference
141 excused?
142 prevention?
143 wrongful?
144 not at the outset
145 but notified of amendment
146 delay
147 long delay—May 5 to May 20
148 if any time in first half of May
149 a week and a half
151 impossibility-delay not wrongful?
152 amendment
153 legal impossibility
154 must be unforeseeable
155 not enough facts here
156 limited to immaterial conditions
157 license could be important
158 lawful to operate business without license?
161 waiver
162 slip of the tongue
163 minority view
164 weak inference of intent to waive
165 majority view-strong showing of subjective intent
166 not on these facts
171 avoidance of forfeiture
172 elements, supra
173 applicable here as well
25
174 even against express conditions
181 TENDER DEED
182 a condition?
183 at least constructive
191 fulfilled or fail?
192 not deliver deed
193 concurrent condition
194 but not even tender
201 excuses?
202 prospective non-performance of D‟s conditioned duty
203 D said did not intend to appear at closing
211 if excuse all conditions, duty of immediate performance
212 no evident discharge doctrine applicable
213 ergo, D guilty of breach
214 material breach?
215 outright refusal to perform
216 therefore material
26
QUESTION 83
Ms. Chang was the most successful interior designer in El Dorado. She leased the premises, 1837 Style
Lane, where she operated her design house, Modern Style, from Mr. Danzig. The area had been zoned exclusively
for residential use, but she had obtained the Planning Commission‟s permission to conduct a business at that
location. In part, her business was so successful because of the quality of her staff. Her design associates, Ms. Ehret
and Mr. Fernandez, had stellar reputations in the industry. Ms. Chang was contemplating retirement.
Mr. Giannelli was interested in buying Ms. Chang‟s business. He realized, though, that the business would
have the best chance of success if he could maintain the location where it had become so well known and if he
retained the services of Ehret and Fernandez. In early March 2003, Giannelli approached Chang about buying her
business.
They signed a writing on March 10, 2003. The writing had been prepared by Giannelli‟s attorney. The
writing included the following provisions:
B. It shall be a condition and undertaking of this agreement that no later than April 10, Chang must obtain a
permit from the Planning Commission, extending the right to operate a business at 1837 Style Lane until at
least January 1, 2008.
E. It is a further proviso of this agreement that Chang must obtain landlord‟s consent to the assignment of
the lease of the premises to Giannelli. Chang can obtain such consent by having the landlord personally
execute the attached form.
H. Chang shall deliver to Giannelli signed employment contracts for both Michelle Ehret and Ian
Fernandez, obligating them to work for Modem Style until at least January 1, 2008.
F. At closing on April 30, Giannelli shall pay Chang $650,000.
Chang set about to get the permit. She spent $15,000 in attorneys‟ and consulting fees. She would have
obtained the permit well before April 10, but there was an illegal strike by city employees. Due to the strike, she did
not obtain the permit until April 12. When she obtained the permit, she phoned Giannelli. Giannelli said that he was
“not happy with the delay” and that he expected her to “live up to both the spirit and strict letter of every other
contract provision.”
On April 13, Chang attempted to contact Danzig to obtain his consent to the lease assignment. She was
shocked to learn that he had just died. On April 15, she reached Ms. Hoing, the attorney who was the executrix of
Danzig‟s estate. She said she was willing to consent, but she pointed out that on March 15, a new state statute had
taken effect, prescribing a new statutory form for all commercial lease assignments. She gave that signed form to
Chang.
Meanwhile Giannelli had had second thoughts about his deal with Chang. Some other investment
opportunities had presented themselves, and Giannelli thought that he could put his $650,000 to better use. On April
17, he had an interview with Ehret and Fernandez. Before signing, they wanted to know what type of boss he would
be. They had heard accurate reports that he was normally a pleasant, laidback boss. They were taken aback when he
told them that “I‟m the toughest boss you‟ll .ever have. I don‟t stand for any nonsense at all. If you work for me, it‟s
my way or the highway. You need to dot absolutely every i and cross every t.” After that conversation, they phoned
Chang to say that they would not sign new employment contracts. They said Giannelli‟s remarks “scared them.”
Giannelli called to say “the deal is off.”
Chang suspected that Giannelli had sabotaged her efforts to persuade Ehret and Fernandez to sign CHANG
SUES GIANNELLI FOR DAMAGES FOR MATERIAL BREACH OF CONTRACT. DO NOT DISCUSS THE
MEASURE OF DAMAGES.
27
QUESTION 83
1 the duty to pay
2 CONDITION #1: OBTAIN THE PERMIT
3 a condition?
4 “a condition”
5 express
6 alternatively, “undertaking”
7 not an aleatory K
8 also a constructive condition
11 fulfilled?
12 “no later than”
13 sufficient to make time of essence?
14 if so, technical failure
21 excused?
22 substantial performance
23 objective
24 only two days late
25 subjective
26 not her fault
27 but not against express conditions
31 impossibility
32 illegal strike
33 foresee?
34 not at fault
35 an immaterial part of the bargain?
36 relevance of TOE
election waiver
41 duty as well as condition “undertaking”
42 breach
43 material?
44 If TOE
45 material breach puts victim to election
46 obviously elected to treat as minor and continue
47 intentional waiver
48 split of authority
49 seemingly minor aspect of the bargain
49.1 avoidance of forfeiture
51 against express conditions
52 $15,000
53 relative to $650,000
54 but minority view
61 CONDITIONS: CONSENT TO LEASE ASSIGNMENT
62 a condition?
63 “proviso”
64 express
65 alternatively, duty
66 “must”
67 not an aleatory K
68 constructive condition
71 fulfilled?
72 if specific form not part of condition
73 separate sentence
74 “can”
75 suggestive that alternatives permissible
76 contrast with “must”
28
77 if so, fulfilled
81
82 excused?
83 substantial performance
84 objective element
85 same legal effect
86 subjective element
87 not at fault
88 Danzig‟s death
but not against express conditions
91
92 impossibility—the legislation
93 not foresee
94 requires use of prescribed form
specific form immaterial
101
102 impossibility—Danzig‟s death
103 “personally”
104 not foresee
105 not at fault
106 her signature has the same legal effect
executrix of estate
111 avoidance of forfeiture
112 already spent the $15,000
113 how much additional time and expense
114 missing facts
115 but only a minority view
121
122 CONDITION #3: SIGNED EMPLOYMENT CONTRACTS
123 condition?
124 “must”
125 no language such as “condition” or proviso”
126 duty
127 but not an aleatory K
constructive condition of exchange
131
132 fulfilled?
clearly a technical failure
141 excused?
142 avoidance of forfeiture
143 already spent the $15,000
144 additional time and expense?
145 missing facts
146 but only a minority view
151 prevention
152 form
153 active interference
154 substantially impede
155 “scared them”
161 wrongful?
162 ulterior motive
163 second thoughts about the contract
164 other investment opportunities
155 changed behavior
166 accurate reports
167 “normally”
29
168 “toughest boss”
169 “any nonsense at all”
169.1 “my way or the highway”
169.2 “dot every....”
171 if all three conditions fulfilled or excused, duty of immediate performance.
173 present breach
173 when did P file suit?
174 anticipatory breach
181 if duty, not performed
182 no evident discharge
191 alternative theory: implied duty of cooperation
192 breach
201 breach material or minor?
202 P has not yet what she bargained for
203 intentional breach?
204 prevention, supra
205 automatically material in some jurisdictions
30
QUESTION 84
Mr. and Mrs. Fong lived on a large parcel of land in Morena. Mrs. Fong‟s elderly parents, the Grants, lived
in New York City. In early 2002, Mrs. Fong persuaded them to move Morena. At the time, the New York City realty
market was hot, and Mrs. Fong assumed that her parents would be able to sell their house quickly and be ready to
relocate to Morena no later than July 30. Although the Grants agreed to move to Morena, they did not want to move
in with the Fongs. Consequently, the Fongs decided to have a small guest house built on their property.
On April 1, 2002, the Fongs signed a written contract with Ms. Harris, a licensed general contractor in El
Dorado. The writing contained the following provisions, inter alia:
—A clause reading “WHEREAS Mrs. Fong‟s parents, the Grants, contemplate immediately relocating to
El Dorado;”
—#2. “Harris shall obtain a requisite permit from the Morena Building Office by April 30, 2002.”
—#3. “It is expressly agreed that Harris will strictly comply with the attached plans and specifications.
$300,000 is payable on completion.” (The plans contained numerous features to tailor the house for an
elderly couple, including a walk-in shower, wider door frames to facilitate the use of a wheelchair, and
lower placement of the fixtures in the shower.)
—#6 “Timely performance is generally essential in this contract.”
—#9 “Harris shall not be liable for unanticipated acts of government, nature, or providence.”
On April 10, Harris submitted the application for the building permit. The permit would normally have
been issued by April 25. However, on April 20 there was a fire at the building office. The fire shut down the office
until May 1. The office issued the permit to Harris on May 3. (Harris did not inform the Fongs that she was late
obtaining the permit.)
On May 10, Harris‟ subcontractor began working on the foundation for the guest house. He read the plans
hurriedly and consequently misread the dimensions. When his crew began pouring the foundation, they made it two
feet wider and one foot deeper than the plans called for. The added depth made the foundation more solid than it
otherwise would have been. Harris did not notice the subcontractor‟s mistakes.
On May 15, Harris‟ own employees began erecting the house. On May 25, they installed the plumbing
fixtures, including the fixtures in the shower. Harris‟ employees did not pay careful attention to the plans and
installed the shower fixtures at normal height rather than the lower height specified in the plans. Harris did not
discover their mistake until June 1. By then, the plumbing had been walled in and the tiles added to the walls. When
Harris discovered the problem, it would have cost approximately $5,700 to correct. He instructed his employees not
to mention the problem to the Fongs. (The height of the fixtures actually increased the fair market value of the guest
house by $2,000.)
Harris‟ employees continued working on the house until July 10th. At that time, their union staged an
illegal strike for increased wages. Harris threatened the employees and the union with a lawsuit, but they did not
return to work until July 25th. At that time there were still two weeks‟ worth of work remaining to complete the rest
of the house according to the plans.
In the meantime, the New York real estate market had cooled off. The Grants had yet to sell their New
York residence. On July 26, the Grants flew out to Morena to inspect the guest house. Mr. Grant, a retired architect,
pointed out to the Fongs the problems with the foundation and shower as well as the fact that Harris would be unable
to complete the project by July 30. The Fongs immediately took possession of the work site and fired Harris. Harris
sued for material breach of contract. WILL SHE RECOVER? Do not discuss the measure of damages.
31
QUESTION 84
1 D‟S DUTY
2 pay
11 P‟S CONDITION TO THE DUTY
12 THE PERMIT
13 fulfill?
14 Specified date April 30
15 late—May 3
16 time of the essence?
17 “generally”
18 a bit vague
19 slight delay practically unimportant
19.1 why not tell?
19.2 Did she think time of essence?
21 if fail, any excuse?
22 K clause
23 “not liable”
24 not justify affirmatively imposing liability
25 impossibility
26 fire
27 no fault
28 inconsequential delay
29 time of the essence, supra
31 substantial performance
32 not an express condition
33 subjective element
34 good fifth effort
35 beyond her control
36 objective element
satisfied essential purpose, project proceeding
37 waiver by D
38 P never told D
39 avoidance of forfeiture
39.1 minority view
39.2 relatively immaterial
39.3 extent of forfeiture
39.4 all the money at the end
39.5 perhaps if the only provision preventing recovery
39.6
41 THE FOUNDATION
42 Type of condition
43 “expressly”
44 but “agreed”
45 language of duty
46 constructive condition
47 fulfill?
48 Two feet wider
49 One foot deeper
51 if fail, any excuses?
52 Substantial performance
53 if constructive condition
54 subjective element
55 subcontractor, not P
56 “hurriedly”
57 unintentional
32
58 objective element
59 more, not less
59.1 better
59 2 more solid
59.3 serve the same purposes
61 waiver
62 election?
63 Later took possession of site
but on their property
64 voluntariness
65 avoidance of forfeiture
66 supra
67 weaker case: more material provision
68
71 SPECIAL DESIGN FEATURES FOR THE ELDERLY
72 Type of condition
73 supra
74 fulfill?
75 Placement of fixtures
81 if fail, any excuse?
82 Substantial performance
83 if constructive condition
84 subjective element
85 his employees‟ mistake
86 not “pay careful attention”
87 mere negligence
91
92 objective element
93 more
94 increase fair market value
economic waste
95 $5,700
96 generally serviceable
97 but special purpose
98 for the elderly
101 waiver
102 election
103 supra
104 avoidance of forfeiture
105 supra
106 again more material
111 ON TIME COMPLETION?
112 Fulfill?
113 Two weeks late
114 time of the essence?
115 Generally not in construction Ks
116 +WHEREAS clause—”immediately”
117 +”essential”
118 but “generally” weakens the language
119 if so, what happens later irrelevant
119.1 immaterial that Grants didn‟t sell immediately
119.2 August 1st in the contract?
121 if fail, any excuses?
122 Impossibility
123 strike
124 “illegal”
33
125 threatened suit
126 but his employees
127 not industry-wide
128 no threats of violence
129 inconsequential provision?
129.1 Time of essence, supra
substantial performance
131 not if time of essence
132 avoidance of forfeiture
133 supra
134 how material?
135
141 if excuse all conditions, duty of immediate performance
142 not performed
143 no evident discharge
144 ergo, breach.
145 material?
146 Withhold all the money
34
QUESTION 85
The Dongs owned an undeveloped lot on Lake Elston. They eventually wanted to retire to the lake. They
had a large family and hoped that during their retirement, their children and grandchildren would visit frequently,
especially during the summer. However, local environmentalists believed that the lake area was too densely
developed and had mounted a well publicized campaign to lobby the county board of supervisors to declare a
moratorium on new construction. When the Dongs heard about the environmentalists‟ campaign, they decided that
they needed to move quickly to build on their lot. They chose Ms. Falco as their contractor
The parties entered into a signed contract in early March 2000. In the writing, the Dongs promised to pay
Ms. Falco $250,000: $200,000 for a main house and $50,000 for a boat shed. Both sums were payable on May 31.
The writing read: “The Dongs undertake their duties on the understanding that Ms. Falco will strictly fulfill her side
of this bargain.” In addition, the writing: required Falco to obtain any necessary building permits; specified a high-
grade, expensive type of insulation, since the winters at Lake Elston could be quite cold; gave the Dongs the right to
choose the lighting and plumbing fixtures; established the following “strict deadlines” for the phases of the work-
March 31 for the foundation, April 30 for the boat shed, and May 31 for the entire project; and set out the
dimensions for the boat shed, permitting the Dongs during the winter “to store a 22‟ boat, the type capable of seating
eight persons.”
Falco began work in late March. She hired a subcontractor to install the insulation. When the subcontractor
went to the warehouse to order the insulation, another, very similar brand was on sale for a lower price. That type of
insulation was just as good as the kind of insulation specified in the contract during the winter but not as efficient
during the summer. Because the former type of insulation was so much cheaper, the subcontractor purchased and
installed the former. He never told Falco that he had substituted another type of insulation.
On April 1, the county board adopted an emergency ordinance that took effect immediately. While the
ordinance did not halt all new construction, it imposed new restrictions, including limitations on the size of
lakeshore boat sheds. Under the new restrictions, the maximum length of a boat shed could be only 16—as a
practical matter, the shed would only be big enough for a boat that could accommodate four passengers. When Falco
applied for her permit on April 3, she learned of the new restrictions. She reluctantly complied with the terms of the
permit and built a 16‟ boat shed before April 30. (The undisputed expert testimony is that the small size of the shed
reduces the fair market value of the Dongs‟ property by $30,000.)
In late April, it was time for Falco to order fixtures. She asked the Dongs to make their selections.
However, when Falco called, Mr. Dong had just come down with a very serious case of influenza. Mr. Dong was
hospitalized for two weeks. Mrs. Dong spent a good deal of her time at the hospital and did not bother to return
Falco‟s calls. On May 15, Falco finally reached Mrs. Dong and explained that she need to finalize the choices
“yesterday” to keep the construction project on schedule. Mrs. Dong made the choices by May 22.
On May 28, the Dongs visited the lot and became angry when they discovered that the boat shed was much
smaller than the contract specifications. On May 29, they ordered Falco‟s crew off their property. On May 29, they
also sent Falco a letter, explaining that “your failure to live up to the requirements for the boathouse is intolerable.”
Falco sues the Dongs on the contract for damages for breach. CAN FALCO RECOVER ON ALL OR PART OF
THE CONTRACT? DO NOT DISCUSS THE MEASURE OF RECOVERY. There is undisputed expert testimony
that Falco could have completed the main house by June 5th.
35
QUESTION 85
1 CONDITION #1: INSULATION
2 type of condition
3 at least constructive
4 express?
5 “The Dongs undertake”
6 refers to both sides‟ commitments
7 probably sufficient
11 fulfill?
12 no
21 excuses
22 SUBSTANTIAL PERFORMANCE
23 objective element
24 +winter
25 -summer
26 subjective element
27 +subcontractor
28 +not tell general
29 -intentional
29.1 -bad faith: cut costs
29.2 not against express conditions
31 INTENTIONAL WAIVER
32 split of authority
33 knowledge?
34 latent defect
35 no indication they knew
41 FAILURE TO MENTION
42 minority view
43 not mention in letter
51 AVOIDANCE OF FORFEITURE
52 +express condition
53 +extreme forfeiture
54 no $ until May 31
55 -only inconsequential conditions
55 insulation important
57 -only inadvertent
58 intentional
59 minority view
61 CONDITION #2: BOATHOUSE
62 type of condition
63 at least constructive
64 express?
65 supra
71 fulfill?
72 no
81 excuses?
82 SUBSTANTIAL PERFORMANCE
83 objective element
84 22‟ vs. 16‟
85 8 vs. 4 people
86 large family
87 $30,000 FMV
88 more than 10% of K price
89 subjective element
89.1 negligence
36
89.2 but unintentional
91 IMPOSSIBILITY
92 legal impossibility
93 unforeseen event?
94 well publicized campaign
95 but so soon
96 emergency ordinance
97 fault?
98 if had applied immediately
99 delayed
99.1 but so soon
99.2 “emergency”
99.3 only immaterial conditions
99.4 important part of bargain
99.5 $50,000 absolute terms
99.6 1/5 of K price
101 AVOIDANCE OF FORFEITURE
102 +forfeiture
103 all $ at the end
104 +against express conditions
105 -minority view
106 -only immaterial parts of bargain
107 no
108 inadvertent
109 not intention
109.1 at most negligent
111 CONDITION #3: FINAL DEADLINE
112 type of condition
113 at least constructive
114 express?
115 supra
121 fulfill?
122 -no “time of essence”
123 +but “deadline”
124 +”strict
125 +Dongs in rush
126 +”well publicized”
127 +Falco should have known
128 thus, failure
131 excuses
132 INTENTIONAL
133 voluntary?
134 they owned the land
135 minority view
141 FAILURE TO MENTION
142 not mention in letter
143 minority view
151 AVOIDANCE OF FORFEITURE
152 +vs express conditions
153 +extreme forfeiture
154 all $ at the end
155 +inadvertent
155 the Dongs‟ fault
157 -immaterial
158 at least debatable
161 PREVENTION
37
162 (1) ORDER OFF PREMISES
163 three days early
164 but need five days
171 (2) DELAY IN SELECTING FIXTURES
172 -understandable
173 serious illness
174 +but long delay
175 a week after “yesterday”
175 +not even return calls
177 more than enough time
178 need only five days
181 IF FULFILL OR EXCUSE ALL CONDITIONS
182 duty of immediate performance
183 no evident discharge
184 ergo, breach
191 RECOVER ON PART OF THE CONTRACT?
192 divisibility
193 parts?
194 yes
195 Pairs?
196 yes
197 mini-Ks?
198 proportionate benefit
199 two prices stated
38
QUESTION 86
Ms. Chen was the owner of the Morena Marauders, a professional co-educational tennis team in Morena,
which played at the municipal stadium. The club had two of the league‟s three star players, Jane Escarra and John
Fishburne. (The third was Sergio Gamba, who played for Kansas City. For the past two years Gamba had been the
league‟s Most Valuable Player.) Mr. Diaz, who operated a local realty development firm, was interested in buying
the team. On March 1, 1999, Chen and Diaz entered into a written contract. The contract provided that the parties
would close the transaction on July 1, 1999 and that at that time, Diaz would pay Chen $ 10,000,000 for the club.
The writing contained the following provisions:
1. It is understood and recited that Mr. Diaz will need to obtain a loan of at least $8,000,000. To be
satisfactory to Mr. Diaz, the terms must provide for repayment in no fewer than 20 years and at an interest
rate no higher than 6%.
2. It is stipulated that total attendance for the Marauders‟ home matches between March 1, 1999 and June
25, 1999 must be no less than 15,000.
3. It shall be another proviso that at the time of closing Ms. Chen must produce signed employment
contracts binding Jane Escarra and John Fishburne to continue playing for the Marauders until at least
January 1, 2002.
Just before Diaz signed, he commented that he “would love to have Gamba as a player, but that‟s just too
much to hope for.”
On June 1, his accountant informed Diaz that Diaz had suffered financial reverses. Diaz decided to try to
get out of the contract. In mid-June, at Chen‟s urging Morena Bank, the largest local bank, tried to contact Diaz to
arrange his loan to purchase the Marauders. Diaz didn‟t return the call for a week. When the bank called again, they
reached Diaz and told him that “as soon as possible you need to send us your tax returns for 1995-98.” Diaz relayed
the request to his accountant but said: “It‟s nothing urgent. You don‟t need to drop everything just to make the
bankers happy.” Two weeks later the accountant gave Diaz a packet to be sent to the bank. The packet included
Diaz‟ tax returns for 1994-97. Diaz sent the packet without noticing that his 1998 return was missing.
In early June Ms. Chen began contract renegotiations with Escarra and Fishburne. She initially signed
Escarra to a contract extension lasting until January 1, 2002. Fishburne orally agreed to a similar extension; but just
before he could sign, he died unexpectedly. To replace him, Ms. Chen immediately signed Gamba to a contract
lasting until January 1, 2003. Ms. Chen sent Diaz a copy of the two contracts and Fishburne‟s death certificate.
By June 20, the attendance at Marauders home games had reached 14,000. The minimum attendance at any
game this season had been 2,200 fans. However, when the former El Dorado Governor died, the incumbent
Governor declared June 24 a state day of mourning and ordered that all government facilities be closed. A
Marauders home game had been scheduled for that date. The game was rescheduled for June 26, and 4,300 fans
attended.
On June 30, Chen phoned Diaz and updated him on all relevant developments since March 1. On July 1,
Diaz wrote Chen a letter. Diaz‟ letter read: “Sorry the financing didn‟t work out. However, I guess that you couldn‟t
hold up your end of the deal either. I‟ve been following the attendance figures I see you didn‟t make the 15,000. The
deal just wasn‟t meant to happen. It‟s best if we just forget about the whole thing.” Diaz refused to close the deal.
CHEN SUES DIAZ FOR BREACH OF CONTRACT. IF THERE IS A BREACH, IS IT MATERIAL?
39
QUESTION 86
1 DUTY TO BUY
11 CONDITION #1: FINANCING AVAILABLE
12 a condition at all
perhaps recital of fact
14 “understood”
15 “recited”
16 “will”
17 but “another proviso”
18 context
19 moreover, what other purpose
19.1 thus, an express condition
21 what happened to the condition?
22 not technically fulfilled?
excuse?
31 prevention
32 wrongful conduct
33 need not be active
34 passive misconduct suffices
35 intentional
36 “nothing urgent”
37 “don‟t need to drop”
38 “as soon as possible”
39 negligent
39.1 1995-98
39.2 1994-97
39.3 accountant‟s error
39.4 impute?
39.5 D did not notice
41 CONDITION #2: ATTENDANCE
42 a condition at all?
43 “it is stipulated”
44 but evident purpose
45 and “another proviso”
46 context
52 but is date part of the condition
52 no “tune of the essence”
53 but “must”
54 if date not part of the condition, fulfilled
55 if date part of the condition, technically failed
61 excuses
62 legal impossibility
63 unexpected death
64 unexpected day of mourning
65 municipal stadium
66 but cannot excuse material part of bargain
67 short delay
68 no economic injury to D
69 but if time impliedly of essence, automatically material
71 substantial performance
72 subjective element
73 good faith by P
74 no fault on P‟s part
75 objective element
76 met attendance requirement after short delay
40
77 no economic injury to D
78 but limited to constructive conditions
79 if express condition, excuse inapplicable
81 avoidance of forfeiture
82 applicable against express conditions
83 only immaterial part of bargain
84 date important?
85 supra
86 but minority view
87 even if court adopt, must show extreme forfeiture
88 what forfeiture other than benefit of bargain?
91 CONDITION #3: EMPLOYEE‟S CONTRACTS
92 condition at all?
93 “proviso”
94 generally means a condition
95 thus, an express condition
101 what happened to the condition?
102 one employee signed
103 the other employee did not
104 technically failed
105 excuses?
111 impossibility
112 death
113 renders fulfillment impossible
114 “unexpectedly”
115 but only immaterial part of the bargain
116 personal services contract
117 a star
118 probably material
121 substantial performance
122 subjective element
123 good faith
124 no fault
125 objective element
126 replacement player
127 another star in league
128 MVP
129 twice
129.1 D “love to have”
129.2 “too much to hope for”
131 but only constructive conditions.
132 express condition here
133 ergo, excuse inapplicable
141 avoidance of extreme forfeiture
142 true can be used against express conditions
143 immaterial condition?
144 supra
145 have to show extreme forfeiture
146 what loss other than mere benefit of bargain?
147 minority view
151 waiver
152 estoppel?
153 not induce change of position
154 election?
155 no choice between inconsistent rights
156 intentional?
41
157 not under realistic, DAHL view
158 weak inference of intent to waive
159 but did not mention in the letter
159.1 p had updated D
159.2 even then a weak inference.
159.3 distinct minority view
161 if fulfilled or excused all conditions, duty of immediate performance
162 not perform
163 no discharge
164 thus, a breach
171 IF A BREACH, MATERIAL?
172 in limine
173 at the outset
174 some say automatically material
175 intentional
176 financial reverses
177 wanted to get out of contract
178 some say automatically material
179 the essence of D‟s part of the bargain
179.1 probably material
42
QUESTION 87
Mr. Falco owned a burglar alarm company in Morena. His clients included several government agencies He
decided to diversify his company by providing security services for businesses and civilian government agencies In
order to do so, he created a new department, Patrol Services. He began searching for a new employee to head the
department
On July 1, 1998, he spoke with Ms. Guyton. For five years, she had been the head of operations for the
government secret service of a small Middle Eastern country. She had an excellent reputation in the security
business. When Falco and Guyton spoke, she indicated that she was “very interested in the job” but “only if” Falco
was willing to “invest the level of resources needed to do the job right, first class. You know, a decent training
facility, etc.” Falco assured her that he would place “adequate” resources at her disposal.
On July 10, 1993 Falco and Guyton entered into a written personal services contract running until July 1,
2003. Under the terms of the contract, Guyton “promise[d]” to report to Falco‟s headquarters “no later than August
1, 1998 to assume” her duties. Since many of the contemplated clients were government agencies, the contract
provided that Guyton “further committed” to apply for a Top Secret government security clearance and to “obtain
said clearance by September 1, 1998 at the latest.” The contract stated that “time” was “of the essence” of Guyton‟s
promise to obtain the clearance. Another clause stated that the writing “voids and renders nugatory all prior and
contemporaneous agreements between the parties.”
After signing the contract, Guyton returned home to pack for the move. When she arrived home, she
tendered her resignation as secret service director; her contract with the foreign government gave her the right to do
so. However, the prime minister decided that “national interests” required that she remain to train a replacement.
The prime minister ordered the immigration authorities to refuse to allow her to leave until they received orders
from him. She reluctantly complied and consequently did not arrive in Morena until August 15, 1998. When she
arrived, Falco gave her her initial paycheck but “caution[ed]” her about “timely performance.”
As soon as Guyton arrived in Morena, she applied for the Top Secret security clearance. However, when
her application arrived, it was mislaid by the U.S. government official. Guyton repeatedly called, but the
government delayed. Guyton asked Falco to help; “with all your government contacts, you could put in a good word
and expedite the process.” At the time, though, Falco was preoccupied with another business deal; he told Guyton
that it was her problem, “not mine.” Guyton did not obtain the clearance until September 15, 1998.
On October 1 Falco gave Guyton another paycheck but deducted $3,000. A notation on the check read:
“Deduction for delay in obtaining contractually required clearance.”
On October 2 Guyton stormed into Falco‟s office. She objected to “this nonsense about my check. You
never lifted a damn finger to help with the clearance. Moreover, you‟ve given me only a $50,000 training budget.
That‟s a joke. You‟re asking me to do this job on a shoe string. I want assurances in black and white right now that
you‟ll give me $200,000 for training, or at the end of this month I‟m headed out the door.” Falco said, “Show me
where it says in your contract that I have to fork over that much money to build you a fancy playground for your
rent-a-cops.” Guyton responded, “That does it. I‟ll serve out the month, but then I‟m history.” Falco responded,
“There‟s the door. It hasn‟t been nice knowing ya.” Guyton then left.
On October 3 Falco files suit. At trial, there is undisputed expert testimony that it would cost “at least
$2000,000 to initially fund adequate training for a security force of the size contemplated by” the contract between
Falco and Guyton.
43
QUESTION 87
1 P‟s conditions to D‟s duty to work
11 condition: payments
12 to date
13 one made
14 another made
15 but deficient
16 but assume prior breach
17 self-help remedy?
18 under UCC
19 this not under UCC
19.1 policy argument in favor
19.2 if not, condition failed
21 future payments
22 prospective non-performance?
23 why did D refuse
24 claimed prior breach by P
25 protested failure to pay
26 payment duty as well as condition
27 if no self-help remedy, breach
28 perhaps no prospective non-performance.
31 condition: cooperation
32 implied?
33 prior contacts
34 relevant to this business
35 D requested aid
36 P did not lift a finger
37 if condition failed, no duty of immediate performance
41 condition: investment of resources
42 parol evidence problem
43 “only if”
44 specifically refer to training facility
45 but not in writing
51 step #1: integration?
52 test finality
53 obviously yes
61 step #2: complete integration?
62 UCC not govern here
63 personal services contract
64 Wigmore: subject-matter
65 debatable
66 Williston: normally and naturally
67 merger clause
68 more complete
69 presume complete
69.1 Corbin
69.2 no
69.3 UCC
69.4 power to apply by analogy
69.5 “certainly” would have included
71 if a condition, fulfilled?
72 undisputed expert testimony $200,000
73 only $50,000
81 D‟s duties
82 -----get there “on time”
44
83 August 1
84 August 15
91 discharge?
92 prime minister
93 legal impossibility
94 but foreign law
95 modernly
96 but specific order, not general law change
97 modernly
98 if so, no breach
101 if breach, material?
102 contract says “of the essence” of clearance
103 but not of arrival
104 expressio unius
105 +in limine
106 in some jurisdictions automatic
107 -no identifiable economic harm
108 -not her fault
109 -in any event, P elects to treat as minor
109.1 continued K
111 -----get the security clearance
112 September 1
113 “at the latest”
114 September 15
121 discharge: impossibility
122 government‟s delay
123 could she have applied before arriving in the US?
124 her fault?
125 if so, breach
131 if breach, material?
132 another early breach
133 in some jurisdictions automatically material
134 moreover, “time” “of the essence”
135 automatically material
136 -but inadvertent
137 -but no identifiable economic harm
138 probably material
139 but P elects to treat as minor
139.1 continues K
139.2 merely tries to deduct $3,000
141 departure
142 anticipatory breach?
143 threat before actually left
144 time #1: time of alleged breach
145 D‟s threat
146 relatively categorical
147 conditional
148 legality of condition, supra
149 P‟s position
149.1 remaining conditions
149.2 remaining duties
151 time #2: interim between breach and trial
152 P elects
153 before D retracts
45
QUESTION 88
Mr. Cardonez is a general contractor in El Dora do Ms Dalton owned a warehouse business in El Dorado
Her business, founded m 1995, had grown rapidly She was in a rush to construct a new warehouse to accommodate
the expansion of her business She contacted only one contractor, Cardonez, because she had dealt with him once in
the past,
On March l, 1997, Cardonez and Dalton entered into a written contract to erect a new warehouse on land
Dalton owned. The writing set out “deadlines” for the work pouring the foundation by May 1, the erection of the
entrances and wails by June 1, the addition of the roof by July 1, and completion by August 1. The writing stated
that 10 days after the completion of each phase, Dalton would pay Cardonez $200,000. The writing included the
following clauses:
1. Cardonez “promised that the finished building would be completely satisfactory. The building shall be in
compliance with both the attached plans and specifications.”
2. Before receiving each progress payment, Cardonez had to obtain a certificate of completion and
compliance from Mr. Ehito, a local architect. Ehito was Dalton‟s college classmate.
3. The attached plans and specifications stated that “In order to recover under this contract, the Contractor
shall strictly comply with the following specifications.” Under a subheading entitled “Functional
Requirements,” the specifications provided that “the building shall be exactly 60,000 square feet in size.”
Under a subheading entitled “Aesthetic Guidelines,” the specifications stated that the tile at the entrance
must be “turquoise colored, Eagle brand tile AA14.”
4. Cardonez “should stay on schedule, since timely completion is important” to Dalton.
After signing the writing, Dalton learned that if she had competitively hid the project, she probably could
have gotten the job done for under $500,000. She regretted entering into the contract with Cardonez and told Ehito
that “frankly, I‟m looking for a way out.”
Cardonez began performance in April 1997. By the end of April, he had poured the foundation. However,
the foundation was larger than the plans called for; when completed, the square footage would be 60,500. (The
larger size would make the building even more useful to Dalton as a warehouse, but it would slightly increase the
annual property tax on the building.) When Cardonez sought the first certificate from Ehito, Ehito discovered the
error. Ehito issued the certificate but gave Cardonez “a stem warning to stick to the letter of the specs in the future.”
In early May, Cardonez laid the entrance tile. Cardonez had hired a subcontractor to do the tiling. The
subcontractor read the specifications cursorily. He ordered a tile manufactured by Classic rather than Eagle. With
one exception, the tile was identical to “turquoise colored, Eagle brand tile AA14”: Eagle gave a 2 year warranty
while Classic offered a 3 year warranty.
In late May, Cardonez‟ foreperson had a heated argument with Dalton. The foreperson was so incensed that
Cardonez‟ employees went on a three day strike. Due in part to the strike, Cardonez did not finish erecting the walls
until June 7.
On June 10, Cardonez approached Ehito for the second certificate. Ehito noticed that the tile was Classic
rather than Eagle. Ehito told Dalton “not to worry-it‟s essentially the same tile with a better warranty.” However,
Dalton blew up and told Ehito that “that idiot Cardonez has done it again, in addition, he‟s late. If you know what‟s
good for you, you won‟t even think of issuing that clown a certificate. This deal is off” Ehito decided not to issue the
certificate.
On June 11, Dalton wrote to Cardonez. The letter barred Cardonez from the work site. The letter stated that
“I‟m dissatisfied, since you [Cardonez] violated the agreement again by installing the wrong type of tile.” On June
46
12, Dalton took possession of the work site. Since her existing warehouse was full, she began using the new
warehouse. On June 20, Cardonez sues.
47
QUESTION 88
1 conditions to D's duty to pay
11 CONDITION: SIZE
12 a condition
13 “In order to recover”
14 “specifications”
15 included in the specifications
16 “Functional Requirements”
17 express
21 failed
22 “exactly”
23 larger
31 excused?
32 substantial performance
33 objective element
34 more property tax
35 but only “slightly increase”
36 subjective element
37 probably mere negligence
38 but express condition
41 avoidance of severe forfeiture
42 alternative to substantial performance
43 apply to express conditions
44 but minority view
51 waivers
52 intentional
53 voluntary relinquishment of known right
54 Ehito knew
55 impute to D
56 election
57 D elects to continue contract
58 but was it a major breach?
59 did D really have an election?
61 waiver when D takes possession of new building
62 voluntary
63 but on her land
71 CONDITION: TILE
72 a condition?
73 true subheading under “specifications”
74 but subheading (mere) “Guidelines”
75 contrast “Functional Requirements”
81 if a condition, failed
82 wrong type of tile
91 if failed, excused?
92 substantial performance
93 objective element
94 “essentially the same”
95 longer warranty
96 subjective element
97 sub's mistake
98 hurried
99 perhaps this was not an express condition
101 alternatively, avoidance of severe forfeiture
102 waiver in later letter
103 mentioned that failure
48
104 waiver when took possession
105 supra
111 CONDITION: TIMING OF COMPLETION OF SECOND PHASE
112 a condition?
113 “deadline”
114 constructive condition of exchange
121 if a condition, failed?
122 no “time of the essence” clause
123 no identifiable economic harm
124 but “timely completion” important
125 true for overall project
126 also true for this phrase?
131 if failed, excused?
132 impossibility
133 strike
134 render truly impossible?
135 not the cause of entire delay
136 three day strike
137 seven days later
138 assumption of the risk
139 his employees
139.1 not excuse material part of the bargain
139.2 “timely completion” important
141 prevention
142 D contributed to strike
143 Was D at fault?
144 perhaps P's foreperson at fault
145 missing facts
146 again, not account for entire delay
147 three day strike
148 seven day delay
151 waiver
152 not mention in letter
153 “again ambiguous”
154 minority view
155 no facts giving rise to an estoppel
161 waiver by taking possession
162 Supra
171 CONDITION: CERTIFICATE
172 a condition?
173 no other evident purpose for provision
181 if condition, failed
182 Ehito did not issue
191 if failed, excused?
192 substantial performance
193 the domino theory: if fulfill substantive condition
194 constructive fraud
195 D's college friend
196 probably being paid by D
197 D threatens, “If you know. . . .”
198 prevention
199 D threatened architect
199.1 waiver by not mention in letter
199.2 minority view
199.3 waiver by take possession
119.4 supra
49
201 CONDITION: “SATISFACTORY”
202 interpretation
203 subject-matter commercial
204 favors objective standard
205 person the opposing litigant
206 favors subjective standard
207 wording
208 not specify the standard
211 if objective, satisfied
212 some small defects
213 but reasonable person
214 if subjective, fulfilled?
215 says “dissatisfied”
216 but was told served essential purpose
217 “looking for a way out”
221 if failed, excused?
222 waiver by taking possession
223 supra
224 avoidance of severe forfeiture
225 minority view
231 CONDITION: COMPLETION OF THE WORK
232 did not fulfill
233 excused?
234 prospective non-performance of the conditioned duty
235 prevention
236 barred form work site
241 if all conditions fulfilled or excused, duty of immediate performance
242 no discharge
243 therefore breach
244 material?
245 intentional
246 essence of the bargain
247 the work for the pay
50
QUESTION 89
Ms. Dunston owned a shopping mall in Morena. A tenant had just vacated a space in the mall. Mr. Elow
had recently moved to Morena and wanted to open a restaurant. He was looking for space when a realtor informed
him of the vacancy at Dunston's mall.
On March 1, 1994, Dunston and Elow discussed the possibility of Elow renting the empty space. On March
10, they signed a valid, enforceable written contract. The writing stated that the lease would run from July 1, 1994 to
June 30, 1997 with a $4,000 monthly rental. The writing included the following provisions:
#2. Landlord understands that Tenant may require Landlord's assistance in obtaining a loan to finance the
opening of a restaurant in the demised premises. Landlord promises to exert reasonable efforts to aid Tenant in
obtaining a loan. #5. This lease is subject to Tenant's ability to obtain a timely liquor license for the premises.
Landlord promises to cooperate in Tenant's efforts to obtain a license and promptly furnish any documents needed
for a license.
#11. Landlord promises to renovate the premises according to the attached specifications. (Elow had
furnished Dunston with plans prepared by his architect, and the plans were physically attached to the writing.) It is
agreed that Tenant's duty to occupy the demised premises is contingent upon Landlord's strict compliance with this
provision. The renovations shall be completed by June 30, 1994.
On March 20, Dunston took Elow to her bank, First Interstate, to introduce Elow to the loan officer. Elow
unsuccessfully applied for a loan from First Interstate.
On March 25, Dunston carried a loan application from Elow to Granite City Federal. The same day Elow
went alone to Halston Bank, which was affiliated with the bank Elow had previously done business with. Halston
Bank granted Elow's loan application.
On March 30, the Liquor Control Board gave Elow an application form requiring a certification from
Dunston. They told him that it takes two months to process a completed application. Elow immediately gave
Dunston the certification form.
On April l, Elow learned that he could have rented a similar space for $2,500 per month. He told Dunston
he expected her to “adjust” his rent. She said that she expected him to “stand behind” their contract. On May 10,
after thinking the matter over, Elow informed Dunston that he would “live up to” his word. She then handed him the
signed certification, and he submitted it to the Liquor Control Board. On June 15th, the Board informed Elow that it
would not issue him a permit until July 10. The contractor Dunston hired to do the renovation completed work on
June 29. Dunston paid the contractor $30,000.
On July 1, Elow refused to move into the mall. DUNSTON SUES ELOW. DOES DUNSTON HAVE A
CAUSE OF ACTION FOR BREACH? IF SO, IS THE BREACH MAJOR OR MINOR? At trial, there was
undisputed expert testimony that; There was one deficiency in the contractor's work—some of the tile in the kitchen
was the wrong color; the tile installed was as functional as the tile the specifications called for; the customers sitting
in the dining area could not see the tile in the kitchen; and it will cost $2,000 to correct the deficiency.
51
QUESTION 89
1 duties
2 move in
3 pay
11 condition #1: loan
12 “promises”
13 on its face a duty
14 condition
15 not express
16 but constructive
21 nature of condition
22 not to actually get a loan
23 interpretation
24 “may”
25 “assistance”
26 “efforts”
27 “reasonable”
31 nature-bona fide effort
32 once
33 twice
34 unsuccessful
35 but still satisfy the standard
41 if condition fail, excuse?
42 prevention
51 condition #2: permit
52 “subject to”
53 express
54 “promises”
55 also duty
61 fulfill?
62 “timely”
63 “promptly”
64 time of the essence?
71 if fail
72 excused?
73 prospective non-performance of the conditioned duty
74 “adjust”
75 threat not to perform
76 suspend
77 not remove until May 10
81 delay
82 two months
83 July 10
84 his fault
91 condition #3: specifications
92 “promises”
93 duty
94 condition
95 express?
96 “contingent”
97 at least constructive
101 if fail, excused?
102 substantial performance
103 objective component
104 10% rule of thumb
52
105 $30,000
106 $2,000
107 structural problem
108 not here
109 broad purpose test
109.1 as functional
109.2 not see
111 subjective component
112 who made the error?
113 why?
114 insufficient facts
115 but express condition?
116 if so, not apply substantial performance
121 avoidance of a severe forfeiture
122 a minority view
123 against express conditions as well
124 extreme enough?
125 $30,000
131 duty of immediate performance
132 not perform
133 discharge?
134 financial impracticability?
135 if no discharge, breach
141 major or minor breach?
142 how much has P already received
143 none
144 probability P receive the rest
145 outright refusal
146 character of the breach
147 if
148 insufficient facts
149.1 extent of D's forfeiture
149.2 minimal
149.3 therefore material
53
QUESTION 90
Mr. Denton was a general contractor in Morena, El Dorado. Ms. Edberg was the president of a charitable
corporation, Friends of the Homeless (FOTH), headquartered in Morena. FOTH recently completed a successful
fundraising campaign. On January 1, 1992, the board of directors authorized Edberg to hire a contractor to build a
new homeless shelter. Edberg contacted Denton.
Before signing a written agreement, Edberg told Denton's wife that if “we bring this baby in on time, we
can expect some real goodies from Uncle Sam.” (If FOTH was able to occupy the shelter by September 20, 1992,
FOTH would receive a $200,000 federal grant to furnish the shelter.) The same day Denton's wife told him that
Edberg had said “something about some government money.”
On January 20, 1992, Denton and FOTH entered into a valid, enforceable written contract. In addition to
prescribing the specifications for the shelter, the writing stated the following:
3. Denton “promised” to provide FOTH with a performance bond from a commercial surety “at the very
latest by 2/1/1992.”
6. All work done by Denton “must be satisfactory.” The next sentence of the clause mentioned a local
architect, Ms. Grant. Although she had her own architecture business, Grant was also a member of FOTH's
board of directors.
7. Denton would be paid $320,000-four $80,000 payments on March 15, May 15, July 15, and September
15. Denton had to present a certificate from Grant to obtain each payment. The clause described September
15 as the “firm” completion date for the project.
Denton did not obtain a performance bond, but FOTH permitted Denton to begin and continue work.
Denton completed the first three phases of the work, and FOTH made the March, May, and July progress payments
without demanding a certificate from Grant.
Denton began the last phase of the work on July 16th. However, he lost ten workdays when there was an
unexpected strike by the employees of the subcontractor Denton had hired to paint the shelter.
Edberg drove to the work site on September 14th. It was obvious that the shelter would not be completed
by the 15th or even the 20th. Denton approached when he saw her. Edberg angrily said that there was “no way”
FOTH would pay him the final installment. Edberg immediately phoned Grant and said that “as FOTH members, we
can't tolerate this delay. As president, I'm telling you that you can't give a certificate to that jerk.” Later that day
Denton called Grant to tell her that he would finish by September 22nd (that statement was accurate). He added that
he would then ask for her final certificate. Grant replied that she did not want to “get embroiled in a potential
lawsuit” and that “given the circumstances,” she could not issue a certificate. Denton then pulled his crew off the
work site. At that time, it would have cost $15,000 to hire another contractor to complete the remaining painting and
cosmetic finish work.
(1) DENTON SUES FOTH FOR BREACH OF CONTRACT. CAN HE RECOVER?
At trial, it is undisputed that with the exception of the delay and the $15,000 of unfinished work, Denton
complied with the contract. Do not discuss the measure of damages.
(2) ASSUME ARGUENDO THAT FOTH COUNTERCLAIMED AND THAT THE
JURY FOUND THAT DENTON WAS GUILTY OF A MATERIAL BREACH. DISCUSS
ONLY WHAT WOULD BE FOTH'S MEASURE OF RECOVERY.
54
QUESTION 90
1 DUTY
2 PAY THE LAST INSTALLMENT
11 Condition #1—performance bond
12 on its face duty
13 “promised”
14 but constructive condition of exchange
non-aleatory contract
21 condition technical failed
22 but excuse
23 if duty breached
24 arguably material breach
25 important protection
26 if so, put to election
27 treat as material and immediately terminate
28 or treat as minor and continue
29 allowed to begin and continue
29.1 election waiver
31 Condition #2—satisfaction
32 on face duty
33 “must”
34 again constructive condition of exchange
35 non-aleatory
41 meaning—subjective or reasonable
42 commercial subject-matter
43 objective standards
44 but third party
45 less reason to mistrust
46 differing tendencies among the courts
47 but here third party tied to D
48 member of board
49 cut in favor of objective
51 if objective fulfilled
52 with exceptions. contractor complied
53 hypothetical architect would be satisfied
61 if subjective, failed
62 excuses
63 domino theory
64 if substantive condition satisfied or substantially performed
65 infra
66 prevention
67 Edberg
68 “as president”
69 “we can‟t”
69.1 constructive fraud
69.2 exceeds proper scope of judgment
69.3 “not get embroiled”
69.4 “potential lawsuit”
71 Condition #3—certificate
72 technically failed
73 excuses
74 estoppel waiver
75 on all 3 prior occasions
76 create reasonable belief
77 but revocable
55
78 prevention
79 could have completed
79.1 timing?
79.2 time of essence, infra
79.3 domino theory: if substantive condition fulfilled, this excused
81 Condition #4—substantive
82 “prescribed”
83 duty
84 but constructive condition of exchange
85 non aleatory contract
91 technically failed
92 excuses
93 prevention
94 their statements
95 timing, infra
96 prospective non-performance
97 their statements
98 if wrongful
99 timing, infra
101 substantial performance
102 objective
103 $15.000
104 $320.000
105 10% rule
106 “cosmetic”
107 nonstructural
108 subjective
109 not intentional
109.1 strike
109.2 not even his employees
111 Condition #5—Time of Essence
112 construction contracts
113 generally no
114 exceptional tacts?
115 text
116 “firm”
117 but context
118 another provision “at the very latest”
119 their statement
119.1 somewhat vague
119.2 “goodies”
119.3 statement to wife
119.4 but no evidence she business agent
119.5 her statement to him
119.6 vague
121 if time of essence, failed
122 excuse
123 impossibility
124 strike
125 unexpected
126 impossibility as discharge
127 material
128 but here impossibility as excuse
129 not apply to material provision
131 DAMAGES
132 General damages
56
133 diminished value
134 explanation
135 no expert testimony as diminution in fair market value
136 cost of completion
137 $15,000
138 but expression means the excess
139 as in employment contracts
139.1 they save $80,000
139.2 windfall
141 Delay damages
142 rental value
143 no testimony
144 profits
145 in the form of the grant?
146 foreseeability
147 special damages
148 statement to wife
149 but she not business agent
149.1 her statement to him
149.2 vague
57
QUESTION 91
Dr. Darien, a licensed dentist in Morena” was contemplating retiring and selling her business. A Mend of
hers had acquired an option on realty which a major developer was interested in. The friend told Darien that he
needed $300,000 in cash to exercise the option and then resell at a “huge” profit to the developer. The Mend said
that if Darien could “come up with $150,000 in cash by October 12, 1992,” she could have a half interest in the
option and the profits from the resale.
In late 1991, Dr. Effram graduated from the University of El Dorado Dental College. He passed the El
Dorado licensing examination in early 1992. On March 1, 1992, Effram sent Darien a resume and sought
employment Darien invited him to stop by the office. On March 5, they met there. Darien explained that she was not
only interested in hiring him; if he “worked out,” she would sell her practice to him.
On March 20, Darien and Effram signed a written agreement including the following provisions:
1. Effram “promise[d]” to serve a six-month “apprenticeship” between April 1 and October 1, 1992.
During that period, Effram would render “all” services in an “absolutely competent, professional” manner.
2. “Before or on” October 10, Effram would deliver to Darien $150,000 in cash and a promissory
note for another $150,000 in specified monthly installments. The note would be guaranteed by “a
satisfactory commercial surety.”
After Effram signed but just before she signed, Darien told Effram that she needed the $150,000 “pronto
by” October 10th to take advantage of a “once in a lifetime business opportunity. I have all my money sunk in this
dental practice, and I need to free it up to capitalize on” this opportunity.
Effram began work on April. Effram and the chief dental technician, Fernandez, developed a personality
conflict After Effram screamed at him several times, Fernandez quit Darien was upset told Effram that Fernandez
was “the best employee I've ever had” and a “terrible loss,” but added that she would give Effram “one last chance”
to complete the apprenticeship. He did so without further incident
On September 1, Effram began making the financing arrangements with Granatelli Surety. (Ten years ago
Granatelli had almost gone bankrupt However, it was now the largest and financially soundest surety in Morena.)
Effram did not finalize the arrangements until October 13, when he tendered the cash, note, and surety guarantee to
Darien. She rejected the tender.
On October 11, Darien's Mend had phoned to ask whether she had the $150,000 cash. She said No. (On
October 1, Darien began to suspect that Effram would not meet the October 10 deadline, but her efforts to obtain a
loan by October 11 were unsuccessful.) The Mend contacted another acquaintance, the two of them exercised the
option, and each realized a $150,000 profit on resale to the developer in late October.
Effram sues Darien, and Darien counterclaims. At trial, Darien testifies that Granatelli was “unsatisfactory
as a surety,” as a former president of the Morena Chamber of Commerce, she knew about Granatelli's financial
problems a decade before.
(1) MAY EFFRAM RECOVER FOR BREACH OF CONTRACT? DO NOT DISCUSS MEASURE
OF DAMAGES.
(2) ASSUME THAT THE JUDGE HOLDS EFFRAM MATERIALLY BREACHED HIS
CONTRACT WITH DARIEN. ON HER COUNTERCLAIM, MAY SHE RECOVER THE $150,000 PROFIT SHE
WOULD HAVE REALIZED BY PURCHASING THE HALF INTEREST IN THE REAL ESTATE OPTION?
58
QUESTION 91
(1)
1 D's duty to turn over the business
11 condition #1: complete apprenticeship
12 “promise”
13 express duty
14 constructive condition
14 not aleatory K
15 condition fulfilled
16
21 condition #2: perform apprenticeship in particular manner
22 “all”
23 “absolutely”
24 “competent”
25 “professional”
26 again “promised”
27 express duty
28 constructive condition
31 condition not fulfilled
32 “all”
33 “absolutely”
34 screamed
35 several times
36 at best employee
37 however, promissory condition
38 duty as well
39 duty breached
39 arguably materially breached
39.2 best employee
39.3 “terrible loss”
39.4 material breach puts to choice
39.5 chose to allow to continue
39 6 treated as minor breach
39.7 election waiver
41 another excuse?
42 perhaps substantial performance
43 evidently most work satisfactory
44 majority: excuse limited to constructive conditions of exchange
45 this condition express?
46 seems to be merely constructive
47 others: limit to constructive conditions in construction contracts
48 if so, inapplicable here
49 still others: not recognize at all
49.1 if so, no excuse here
51 condition #3: “satisfactory” commercial surety
52 interpretation: subjective or objective standard?
53 one factor: who to be satisfied
54 D herself
55 greater risk of false claim of dissatisfaction
56 cuts in favor of objective standard
57 second factor: subject matter
58 commercial
59 also cuts in favor of objective standard
61 if objective standard
62 some reason for doubt, near bankruptcy
59
63 +but 10 years ago
64 - +now largest
65 +now financially sounded
66 if subjective standard.
67 former C of C president
68 know
69 perhaps enough
71 condition #4: provide cash, note, etc.
72 perhaps express duty
73 “promise” absent from this clause
74 but clearly condition
75 purpose
76 at least constructive
77 fulfilled?
78 actually attempted to deliver
79 condition concurrent
79.1 simultaneous exchange
79.2 tender
79.3 sufficient for this type of condition
81 condition #5: provide cash, note, by specific date
82 time of essence issue
83 not ordinarily in non-personality Ks
84 however issue of interpretation
85 text
86 ambiguous
87 “by or on”
88 extrinsic
89 can consider?
89.1 even under objective approach if ambiguous
89.2 certainly under subjective
91 conversation
92 WHEN
93 too late?
94 P had signed already
95 if K formed, D cannot unilaterally change
terms
96 but D had not yet signed
97 “P” Could have objected
98 WHAT was said
99 “once in a lifetime”
99.1 “all” her money
99.2 “need”
99.3 date crucial
99.4 “pronto”
101 if time of essence, condition failed
102 failure final
103 cannot cure
111 if any condition fails and is not excused, no duty of immediate perf
112 D win
(2)
121 general damages
122 benefit of bargain
123 resale?
124 still able to sell at that price?
131 THE $150,000 PROFIT
60
132 foreseeability at the time of contracting
133 special damage
134 ergo must show foreseeability
135 the showing here
136 WHEN
137 did not mention anything until P already signed
138 but D had not yet signed
139 no K at that point
139.1 the time of K formation
141 WHAT was said
142 vague
143 not identify opportunity
144 but “once in a lifetime” opportunity
145 sounds as if major opportunity
146 sense of urgency
147 anticipate that lose profit from opportunity
151 mitigation
152 P argues that D should have tried harder to obtain loan
153 D obviously had collateral
154 D should have started earlier
155 but some effort
156 did not wait until the last minute
157 effort unsuccessful
158 P did not plead D's failure to mitigate
159 P has burden of proof on the issue
159.1 P probably failed to meet burden
161 certainty
162 not merely speculative
163 friend other person capitalized on business opportunity
know the profit they made on resale
61
QUESTION 92
Ms. Ellington owned an old house in Morena. Under the local zoning code, the house was a Type 3
residential building. Ellington decided to convert the building into three commercial rental units. The conversion
required a Type 2 permit; the neighborhood was zoned for both Type 2 and Type 3 buildings, but Type 2 buildings
had higher plumbing and electrical standards.
Mr. Falsetti was a licensed Morena contractor, specializing in remodels. On March 1, 1986, Ellington asked
him to help her convert the building. On March 10, 1986, Ellington and Falsetti signed a written contract.
Paragraphs 5-6 of the contract set out specifications, including reroofing requirements such as the type of tar and
shingles. The contract stated that the deadlines for the various phases of construction were May l, July 1, and finally
September I. Ellington was to make $40,000 progress payments after May 1 and July 1 and a final $20,000 payment.
The contract provided:
7. Contractor expressly covenants that he shall strictly comply with the above specifications.
8. Owner shall make the final payment to Contractor on the understanding that the City of Morena issue
Owner a Type 2 permit for the building no later than September 30, 1986.
9. Contractor must obtain a certificate of compliance from Architect Joyce Grant as a condition to each
payment under the contract.
Falsetti completed the first two stages of the work by June 30. Ellington made the May 1 and July 1
payments without requesting Grant's certificate.
On July 1, Falsetti began the reroofing. When Falsetti stopped by his supplier, Mr. Hummel, Kummel
informed him that the price of the tar he had ordered had declined but that the price of the shingles he had ordered
had skyrocketed. Hummel told him that if Falsetti substituted a better grade of tar and a cheaper shingle, “the roof
will be just as sturdy and cost you a little less.” Without consulting Ellington, Falsetti decided to follow Hummel's
advice.
After finishing the roofing on August 30, Falsetti told Ellington that he was “going down to the City to get
our permit. I need a copy of your deed.” Ellington said she would mail his a copy the next day. However, Ellington
forgot to do so and went on a two-week vacation the next day. When she returned, she sent Falsetti the deed. In the
interim, the City had put into effect a new building code. Consequently, it issued a Category 2 permit rather than a
Type 2 permit; under the new code, an owner could use a Category 2 building for the same commercial purposes as
a Type 2 building. Category 2 had higher wiring standards than the old Type 2, but the rewiring Falsetti had done
satisfied the new standards.
When Falsetti delivered the permit to Ellington on September 21, Ellington said that “everything seems
O.K.” but refused to pay without an architect's certificate. At Falsetti's request, Grant inspected the premises. She
discovered the use of the different tar and shingles.
Grant informed Ellington of the substituted materials but added that she might issue the certificate, since
“the substituted materials are pretty good.” Ellington told Grant that she, Ellington, wanted Grant to “enforce the
letter of the contract. Remember how much business I send you.” Grant commented that she did “not want to get
involved in any legal hassle between” Ellington and Falsetti. Grant said she would not issue a certificate.
Ellington refused to pay Falsetti. On October 1, 1986, Ellington took possession of the premises and
advertised its availability for rental.
Falsetti sues Ellington. At trial, Falsetti offers expert testimony that the substituted roofing materials
reduced the property's fair market value by, at most, $1,000.
62
QUESTION 92
1 DUTY TO PAY THE $20,000
11 CONDITION #1: COMPLIANCE WITH PLANS AND SPECIFICATIONS
12 express or constructive?
13 “strictly”
14 but “covenant” connoting promise
15 “on the understanding”
16 “as a condition”
17 context
21 if express
22 excused?
23 avoidance of severe forfeiture
24 minor part of the bargain
25 generally yes
26 Hummel, infra
27 Grant, infra
28 substantial forfeiture
29 Restatement test: 15%
29.1 20% here
31 if constructive
32 excused?
33 waiver
34 took possession
35 knowing
36 yes
37 but voluntary?
38 she owned the property
41 substantial performance
42 objectively trivial
43 Hummel
44 expert
45 “justas”
46 Grant
47 expert
48 impartial
49 “pretty good”
49.1 Reduce FMV by only $1,000
51 subjectively innocent
52 intentional
53 to save money
54 not consult Ellington
55 not consult Grant
56 de minimis exception?
61 CONDITION #2: ARCHITECT'S CERTIFICATE
71 excused?
72 domino theory
73 if satisfy substantive condition, this automatically excused as well
74 mere evidentiary function
75 split of authority
81 first certificate
82 estoppel waiver
83 time to obtain?
84 did not demand
91 second certificate
92 estoppel waiver
63
93 time to demand
94 did not demand
101 third certificate
102 estoppel waiver
103 revocable
104 enough time to reinstate condition?
105 September 21
106 September 30
111 prevention
112 Ellington threatens
113 Wrongful?
114 “letter of contract”
115 proper demand
116 “how much business”
117 Causation
118 Timing
121 constructive fraud
122 Proper basis for denial: deviation from plans
123 Deviations
124 Improper basis: cowardice
125 “Legal hassle”
131 election waiver
132 supra
141 avoidance of severe forfeiture
142 supra
151 CONDITION #3: PERMIT FROM CITY
152 express or constructive?
153 material
154 “on the understanding”
161 if express
162 excuses
163 prevention
164 He requested in time
165 She promised
166 She delayed
167 In the interim
171 legal impossibility
172 unforeseeable?
173 enough facts?
174 material part of the bargain
175 minor difference between the two schemes
181 if constructive
182 excuses
183 substantial performance
184 same purposes
185 stricter standards
186 but complied here
191 DAMAGES
192 Contract price minus
193 if rely on substantial performance
194 cost of correcting deficiencies
201 traditional view
202 cost of completion the strong preference
203 always if intentional deviation
204 automatic in some jurisdictions
205 not deviate unless substantial economic waste
64
206 here
207 missing facts
208 obvious here?
211 competing modern view
212 discretionary balancing test
213 missing facts
214 obvious that there would be economic waste?
215 but $1,000 somewhat substantial
65
QUESTION 93
Mr. Aubright owned some realty on which he wanted to build a shopping center. On January 1, 1985, he
entered into a valid and enforceable contract with Mr. Bermudez a general contractor, to build the center. Later the
same day Bermudez signed separate, valid and enforceable contracts with three different businesses to do the
subcontract work. Cahane (excavation and foundation), Deering (the erection of the buildings, plumbing and
electricity), and Eleazor (the roofing).
The contracts set the following deadlines for work: Cahane January 31, Deering February 28, and Eleazor
March 31. Each subcontract referred to the other two subcontracts and provided that Mr. Bermudez would
“coordinate the work of all three subcontractors on this project.” Eleazor's contract stated that “It is hereby provided
that all work must be completed exactly; the work must be finished precisely on schedule.” The contract called for
Fulton shingles for the roof. The contract stated a total contract price of $200,000 for the roofing; $30,000 was to be
paid when the contract was signed, and Eleazor was to receive the balance on “satisfactory completion” of the work.
When Bermudez and Eleazor signed the contract on January 1, Bermudez paid Eleazor the $30,000.
Cahane began work on January 2, 1985. However, a week later, Cahane was required to pay a fine assessed
by the state environmental protection agency on another project. After paying the fine, Cahane was short on cash.
He was unable to pay for the concrete he had ordered delivered to work site on January 20, 1985. When Cahane
could not pay the concrete company refused to deliver. Cahane obtained a loan from the bank and used the loan
proceeds to order more concrete, but he was unable to complete the foundation until February 10, 1985.
On February 11, Eleazor happened to be driving by the work site. He expected to see Deering's employees
busy at work. Instead, he saw Cahane's employees doing their cleanup. Eleazor stopped and asked them why they
were still on the site. They explained Cahane's problems. Eleazor grabbed his car phone and contacted Deering.
Eleazor asked when he, Deering, intended to begin work. Deering stated that there would be a further delay. When
Deering learned that Cahane was behind schedule, he “looked around for other work for my crew. Deering found a
hotel owner who wanted some rehabilitation work done. Deering's crew began that work on February 1, 1985, and
hoped to complete it by February 16th. Eleazor asked, “Well, when in the hell do you think your guys will get to this
job and then clear out to let my men do the roofing?” Deering responded, “Probably not well into March. Sorry.
There's nothing I can do.”
The next day, February 12, Eleazor drove to Bermudez' office. Eleazor asked Bermudez whether he,
Bermudez, was aware of the delays. Bermudez said that he was unaware; he had been on vacation in Europe and had
not returned to Morena until that very morning. Eleazor complained, “You're supposed to be coordinating this job.
The whole thing is messed up now. I expect you to light a fire under Deering.” Bermudez assured Eleazor that he
would do “everything in my power.”
Later that day Bermudez contacted Deering and urged him to finish up “as fast as you can.” Deering asked
whether Bermudez was threatening to refuse to pay unless Deering met the February 28 deadline. Bermudez said,
“No. I'm not saying that at all Jerry.”
Deering's crew finished work on March 16th. On March 17th, Eleazor's roofers began work. That day they
stopped by their supplier's warehouse to pick up the shingles. They discovered that the day before, their supplier had
sold the last Fulton shingles in stock. The supplier phoned Eleazor, and Eleazor directed the supplier to give the
crew Wiley shingles. Eleazor commented, “They're almost as good, and they're roughly the same price. I can't afford
any more delays now.”
Eleazor completed work on April 15th. On that date, he phoned Bermudez and demanded payment. Eleazor
began the conversation by saying, “No thanks to you, the project is wrapped up. I've never worked with a more
incompetent general in my life.” Bermudez took offense and stated, “You're hardly in any situation to complain.
You were supposed to finish by March 31. Looked at the calendar lately? I wasn't satisfied with your progress.”
Eleazor said, “The whole delay is your damn fault. You wouldn't dare withhold payment now.” Bermudez
concluded, “Oh, wouldn't I? You'll have to sue me if you want to see any of that money. The most incompetent
general you ever dealt with? We'll see who the court thinks is competent.”
66
Eleazor files suit against Bermudez for breach of contract. MAY ELEAZOR RECOVER MONEY
DAMAGES? EVEN IF YOU DECIDE THAT ELEAZOR SHOULD NOT RECOVER, DISCUSS HIS
DAMAGES. It would cost $100.000 to replace the shingles. The use of Wiley shingles reduced the fair market value
of the center by $7,000.
67
QUESTION 93
1 THE DUTY TO PAY
2 CONDITION #1: COMPLETE
3 “Fulcon” shingles
4 “exactly”
5 express condition?
11 whiley shingles
12 technical failure
21 excuses
22 substantial performance
23 trivial
24 “almost as good”
25 $7,000 effect
26 innocent
27 deliberate
28 cost little less
29 the test: bad faith
29.1 the delay the reason
29.2 but express condition
29.3 majority not apply substantial performance
31 avoidance of severe forfeiture
32 good faith
33 supra
34 large forfeiture
35 170,000
36 even express conditions
37 but only minority view
41 estoppel waiver
42 earlier conduct
43 did not know of substitution
44 no evidence of notice
51 intentional waiver
52 knowing
53 no evidence of notice
54 failure to mention
55 mentioned only lack of progress
56 distinct minority view
61 CONDITION #2: TIME OF COMPLETION
62 if merely reasonable time
63 arguably fulfilled
64 delay”
65 as soon as possible
71 if time of essence
72 “on schedule”
73 “precisely”
74 normally not
75 language_explicit_enough.
76 condition technically failed
81 excuses
82 impossibility
83 not his fault
84 impossible—roofing
85 but material part of the bargain
91 prevention
92 wrongful
68
93 “coordinate”
94 subsequent assurance
95 subsequent attempt
96 earlier neglect
97 later half-hearted effort
98 factual causation
101 estoppel waiver
102 knew of delay
103 permitted to continue
111 election waiver
112 if time of essence, material breach
113 choice
114 allowed to continue
115 elect to treat as minor breach
121 CONDITION #3: SATISFACTION
122 “satisfactory completion”
123 commercial subject-matter
124 objective test
125 said not satisfied
126 but with progress
127 merely subjective dissatisfaction
128 ulterior motive
129 took offense
129.1 repeated remark about incompetent contractor
131 THE DUTY TO COORDINATE
132 “coordinate”
133 subsequent assurance
134 subsequent attempt
135 breach
136 not withhold payment
137 earlier neglect
138 vacation
139 evidently asked no one to supervise in absence
141 DAMAGES
142 expectation
143 contract price
144 deduct for deficiency
145 substantial performance
151 cost of completion versus diminution in value
152 early view: strong preference for cost of completion
153 bad faith
154 not here
155 physical destruction
156 here
157 special purpose
158 not here
161 modern view: discretionary balancing test
162 7,000
163 100,000
171 restitution
172 “breach of K”
173 only if not in default
174 fair market value
175 no facts
181 reliance
182 “breach of contract” action
70
QUESTION 94
On January 1, 1576, Mr. Zola visited the offices of Ms. Herner, local agent for Bailey Insurance Co., Zola
filled out a disability insurance application and gave Werner $200, the premium for one year. Werner forwarded the
application and money to the insurer's home office. On January 5, Mr. Bailey approved the application, thereby
forming a valid and enforceable contract. Bailey authorized Werner to issue a disability policy to Zola.
On January 10, Zola visited Werner's offices. Werner gave Zola the policy. The policy's COVERAGE
section included the following language:
“3. The Insured must notify the Company in writing within 30 days after the onset of any disability.
4. Within 70 days after the onset of disability, the Insured must furnish the Company with
satisfactory proof of such disability.”
When Werner handed Zola the policy, he inquired about the policy deadlines for notice and proof of loss.
Werner said, “Well, you get about a month for notice and about three months for proof. It's all in your policy's
COVERAGE section.”
On February 1, Zola suffered disability in an accident, Zola spent almost four weeks in the hospital. On
February 28, Zola phoned Werner and told her about the accident. She said, “Sorry about the accident. Let's start
processing your claim. Get the proof of loss in as soon as you can.”
On March 1, Werner informed Bailey that Zola had phoned. Bailey decided to deny liability. On March 2,
he wrote Zola, “We are not liable for your disability. You did not give us the required written notice of loss.”
On March 6, Zola received the letter. Be phoned Ms. Werner and told her that he considered Bailey liable
and would submit proof of loss. Werner told Zola that it would be a waste of time to submit proof. Before closing,
Zola asked for a list of names of doctors who could help prepare the proof. Werner refused to help. She said, “Even
if we were liable, it would be your job to prepare the proof.”
On April 20, Zola delivered satisfactory proof of loss to Werner. As Zola handed her the proof, Werner
said, “I just hope you realize you're wasting your time.”
Werner forwarded the proof to Bailey. On April 25, Bailey sent Zola another letter. The letter stated, “I
must reiterate our position that we are not liable for your disability. You did not give us written notice of your
disability. “
Zola sues Bailey Insurance Company to recover disability benefits.
WILL ZOLA RECOVER DISABILITY BENEFITS FROM BAILEY INSURANCE COMPANY? DO
NOT DISCUSS THE MEASURE OF DAMAGES.
71
QUESTION 94 SAMPLE ANSWER
Zola is suing to enforce the insurer's duty to pay the disability benefits.
I. THE EXISTENCE OF ANY CONDITIONS TO THE DUTY
The first issue is whether there are any conditions to the duty. The courts generally do not apply the
constructive condition doctrine to insurance contracts; the courts treat insurance agreements as aleatory contracts.
Hence, we must determine whether there are any express conditions to the duty. The insurer will argue that the third
and fourth clauses, quoted in the problem, constitute express conditions. On the one hand, the clauses are in the
COVERAGE section rather than a CONDITIONS section. However, the clauses will serve a useful purpose only if
we construe them as conditions, Moreover, since the language is attributable to the promisor and refers to acts to be
performed by the insured, the court will probably conclude that the clauses are two express conditions precedent to
the insurer's duty to pay the benefits.
II. EXCUSES FOR THE FAILURE OF THE FIRST CONDITION PRECEDENT The third clause
required written notice, and the insured gave only oral notice. The condition failed, and we must now determine
whether the failure was excused.
A. Impossibility. Zola might argue that it was impossible for him to file the proper notice because he
was ill during most of the notice period. The court will almost assuredly reject the argument, Zola had 30 days in
which to file the notice. When Zola left the hospital, he still had two days in which to file notice. It would have been
a simple matter to file written notice of loss.
B. Prevention of Forfeiture. Zola might argue that the court should excuse the failure because the
court's refusal to do so would impose a severe forfeiture upon him. First, it is doubtful whether he would suffer the
type of extreme forfeiture necessary to trigger the doctrine, Moreover, prevention of forfeiture as an excuse doctrine
is a distinct minority view. The court would probably refuse to follow the minority view.
C. Intentional Waiver. The courts are especially eager to find intentional waivers in insurance cases.
In the instant case, however, Werner really did not intend to waive the written notice provision; she evidently
thought that oral notice was sufficient. Yet, in spite of her ignorance of the provision, some courts would
undoubtedly “imply” a fictitious intent to waive from her act of accepting notice. While most courts would not
excuse the failure on this theory, some would.
D. Estoppel Waiver. Zola has a strong argument that there is an estoppel waiver, Werner's conduct
reasonably led Zola to believe that his notice was deficient. If Werner had said that point that Zola had to file written
notice, he could easily have filed the writing within the remaining two days.
E. Conclusion. While a few courts would excuse the failure on an intentional waiver rationale, most
would excuse the failure of an estoppel waiver theory.
III. EXCUSES FOR FAILURE OF THE SECOND CONDITION PRECEDENT
The fourth clause required that Zola file proof within 70 days. The condition failed, and we must now
determine whether the failure was excused.
A. Intentional Waiver. Zola can present three arguments.
1. He can argue that Werner's statement on January 10 was a waiver. While Werner mentioned three
months, her last sentence made it clear that she was merely describing the policy provisions. I doubt whether any
court would find an intentional waiver in her statement.
72
2. He might argue that Werner's statement on February 1, “as soon as you can,” was a waiver. A
court probably would not read the statement that broadly. Werner was encouraging Zola to submit proof promptly
rather than waiving any condition.
3. Zola's weakest argument would be that Werner waived the condition by physically accepting the
proof. However, as she accepted the proof, she made it clear that the insurer did not consider itself liable. Again, the
court probably would not find a waiver.
B. Estoppel Waiver. Zola will argue that he relied upon Werner's statement on January 10. However,
to invoke an estoppel theory, the promise must show that his or her reliance was reasonable. Since, in the same
breath, Werner referred Zola to the policy provisions, I do not think that Zola's reliance was reasonable.
C. Prevention. Zola might argue that Werner prevented the condition's fulfillment by refusing to give
Zola a list of names of doctors. The argument fails for two reasons. First, it is difficult to believe that Werner's act
substantially hindered Zola. It is a relatively easy matter to contact a physician to obtain proof of loss. Second,
Weimer's refusal probably was not wrongful. Werner voiced parties' common understanding when she said, “Even if
we were liable, it would be your job to prepare the proof.”
D. Forfeiture, supra.
E. Failure to Mention the Condition. A minority of courts would excuse the failure because Bailey
did not mention the failure of the second condition on the April 25th letter. However, most courts would not excuse
the failure in the absence of facts amounting to an estoppel.
F. Prospective Failure of the Conditioned Duty. The insurer repudiated the contract in the March 2nd
letter. The letter reasonably led Zola to believe that whatever he did, Bailey would not perform the duty. Bailey did
not retract the statement prior to the proof period's expiration. I think that almost all courts would excuse the failure
on this theory.
IV. CONCLUSION
Zola can recover. The court will excuse the first condition's failure on an estoppel waiver theory and the
second condition's failure on the ground of prospective failure of the conditioned duty.