9
Addendum#1 – 14-18 Civic Commons Fountain October 31, 2014 SUBJECT: ADDENDUM #1 Bid 14-18 Civic Commons Fountain This addendum is intended to supplement, clarify, or correct a part of the original specifications for the above referenced bid. It shall become a binding part of the contract documents and shall be taken into account in preparing bid proposals. The following items shall constitute Addendum #1: Item 1: Pre-Bid Meeting Notes and sign-in sheet- Attached Item 2: QUESTIONS: 1. Q. What is the Engineer’s Estimate for the Civic Commons Fountain Improvements? A. $600,000-$700,000 Construction Estimate 2 Q. We were wondering for the project if the Contractor is to have a temporary chain link fence put up for safety purposes? Also, if the chain link fence is put up, would we be able to keep a dumpster on location overnight? A. A 6’-0” High Chain-link fence and dumpster will be allowed, only if you locate the dumpster as defined on the layout below. The chain-link fence must be at minimum in the location shown on the layout adjacent to the dumpster. 75’-0” of 6’-0” High chain-link also needs to be provided around the pit area at all times, until the stairs and pit are secured. Additional chain-link fence is at contractor’s discretion to ensure a safe and secure jobsite. 3 Q. Will Material Testing be under contract with the owner or the General Contractor? A. The owner will directly hire the special testing. 4 Q. Drawing WF2.0 indicates under slab piping in the pipe schedule, these pipes are indicated on the drawings with dashed lines. It is understood that these pipes are underslab. In terms of what is existing, what is to be re-used and what needs to be replaced. What pipes are existing? A. All existing piping is to be removed. All piping on the Pipe Schedule is to be new. Item 3: Technical Specifications and Drawings Clarifications 1. Disregard the reference to Alternate #1 in spec section 131200, part 1.07B. in regards to the LED feature below the waterfall. This work will not be performed. 2. On Dwg C102, Note 9 should be referenced on the drawing in all locations that note 12 is shown. These notes work in conjunction. The entire center of the fountains is to be removed under the details of note 9. The dashed line represents the saw cut line.

SUBJECT: ADDENDUM #1 Item 1...Addendum#1 – 14-18 Civic Commons Fountain 3. Spec for the Waterstop in Section 079100 – Refer to Westec Barrier cut sheets (attached) . Use EB Cap

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Addendum#1 – 14-18 Civic Commons Fountain

    October 31, 2014 SUBJECT: ADDENDUM #1 – Bid 14-18 Civic Commons Fountain This addendum is intended to supplement, clarify, or correct a part of the original specifications for the above referenced bid. It shall become a binding part of the contract documents and shall be taken into account in preparing bid proposals. The following items shall constitute Addendum #1: Item 1: Pre-Bid Meeting Notes and sign-in sheet- Attached Item 2: QUESTIONS:

    1. Q. What is the Engineer’s Estimate for the Civic Commons Fountain Improvements? A. $600,000-$700,000 Construction Estimate 2 Q. We were wondering for the project if the Contractor is to have a temporary chain link

    fence put up for safety purposes? Also, if the chain link fence is put up, would we be able to keep a dumpster on location overnight?

    A. A 6’-0” High Chain-link fence and dumpster will be allowed, only if you locate the

    dumpster as defined on the layout below. The chain-link fence must be at minimum in the location shown on the layout adjacent to the dumpster. 75’-0” of 6’-0” High chain-link also needs to be provided around the pit area at all times, until the stairs and pit are secured. Additional chain-link fence is at contractor’s discretion to ensure a safe and secure jobsite.

    3 Q. Will Material Testing be under contract with the owner or the General Contractor? A. The owner will directly hire the special testing. 4 Q. Drawing WF2.0 indicates under slab piping in the pipe schedule, these pipes are indicated

    on the drawings with dashed lines. It is understood that these pipes are underslab. In terms of what is existing, what is to be re-used and what needs to be replaced. What pipes are existing?

    A. All existing piping is to be removed. All piping on the Pipe Schedule is to be new.

    Item 3: Technical Specifications and Drawings Clarifications

    1. Disregard the reference to Alternate #1 in spec section 131200, part 1.07B. in regards to the LED feature below the waterfall. This work will not be performed.

    2. On Dwg C102, Note 9 should be referenced on the drawing in all locations that note 12 is shown. These notes work in conjunction. The entire center of the fountains is to be removed under the details of note 9. The dashed line represents the saw cut line.

  • Addendum#1 – 14-18 Civic Commons Fountain

    3. Spec for the Waterstop in Section 079100 – Refer to Westec Barrier cut sheets (attached).

    Use EB Cap Profile No. 637 and the full expansion board cap seal installation method detailed within. This includes the Speed Load Sleeve and the Plastic Expansion Board by Westec.

    Item 4: LAYOUT- as referenced in Question and Answer 2.

    A. Dumpster & Chainlink Fence Location

    Please acknowledge receipt of this addendum by your signature on the proposal form, failure to do so may disqualify the Contractor. END OF ADDENDUM # 1

  • Pre-Bid Meeting Notes Bid #14-18 Civic Commons Fountain October 23, 2014 at 1:00pm

    1. Sign–in and Introductions of City Staff Estelle Gibson, City of Kettering

    2. Project and Technical Overview/Description Rob Baker, City of Kettering

    3. Bid/Contractual Requirements Estelle Gibson, City of Kettering

    a. Mandatory Pre-Bid-only those companies that sign-in can submit a bid-this is a single-prime

    contract.

    b. Bids are due November 6, 2014 1:30pm

    i. Submit bids to: City of Kettering Finance Department, Kettering Government Center,

    3600 Shroyer Road.

    ii. Bid Submission Forms – i through vi

    c. Bonding

    i. 5% Bid Bond- submit with bid- SUBMIT IN DOLLAR AMOUNTS ONLY ii. 100% Performance Bond – submit after award notification

    d. Prevailing Wages-Ohio Prevailing Wage rates apply

    e. Addendums

    i. Addendums will be posted online at Blueserv.com and sent to all planholders

    f. Substitutions- Last day for substitutions – No substitution requests will be accepted after

    October 27, 2014 at 5:00pm.

    g. Questions

    i. Last day for questions – No questions will be accepted after October 27, 2014 at 5pm.

    ii. Questions –submit all questions in writing to Rob Baker at:

    [email protected]. No verbal answers will be given.

    h. Documents are viewable online and downloadable for a non-refundable $75 plus tax; shipping

    and handling charges apply if plans are not picked up in person:

    Blueserv Reprographics, 3313 SeaJay Drive, Beavercreek, Ohio 45430, http://www.blueservplanroom.com, Contact: Rob Mantia, at: (937) 426-6410.

    i. Permits – Contractor is responsible to secure and pay for all permits- permit costs can be found

    on the City’s website at: www.ketteringoh.org/newweb/departments/plan_dev/bz_forms.php

    j. Pre-Bid sign-in sheet – will be posted online at blueservplanroom.com under the “view

    specs/addenda” tab.

    mailto:[email protected]�http://www.blueservplanroom.com/�http://www.ketteringoh.org/newweb/departments/plan_dev/bz_forms.php�

  • Pre-Bid Meeting Notes Bid #14-18 Civic Commons Fountain October 23, 2014 at 1:00pm

    4. Construction Management Robert Baker, City of Kettering a. Project must be completed by May 1st, 2015. b. Project can be started upon securing all completed paperwork.

    c. Project clean up and security of area is to be performed at end of each day. You are in a heavily traveled public park.

    d. Contractor will need to be flexible for City functions being held within the park, typically Christmas events.

    e. Work Hours are 7:00 am – 6:00 pm, Monday – Saturday unless otherwise requested.

    f. NO Dumpster is allowed to be within the park overnight. All debris needs removed daily. g. Water and Electric are available within the park, if used responsibly. The City reserves the right

    to restrict usage during construction.

    h. Project Vehicle Parking is allowed only in the lot on Isaac Prugh Way or the Government Center Lot, Northern row of parking.

    i. Deliveries can be made to the job site, but then vehicles will be removed from the Park. Access into the park is from Lincoln Park Blvd East only.

    5. Questions/ Walk Through City Staff

  • Patented

    TPER Expansion Board Cap Seal System

    U.S. Patent No. 5,375,386

    The Patented Expansion Board Cap Seal System, designed by Westec is a complete concrete joint system with a simple installation. The EB Cap System integrates the waterstop, forming system, expansion board, joint seal and load transfer units into a single structure. Just stake down the board, set your screed elevation and that’s it. No stripping forms, no messy sealants, no problems. Installation Benefits: • No split formwork • Fewer installation steps • No poured-in-place sealant required • No remobilization for saw cutting or sealant • Convenient strip pouring possible with Speed Loads • Lower labor and installation costs • No joint finishing required

    Polyboard Westec ¾” HDPE Polyboard is available for 6” and 8” paving applications. Westec ½” Polyboard also available in 4’x8’ sheets. The polyboard is designed to work with the EB Cap and EB Cap Retrofit profiles and serves as both an expansion material and forming system.

    Speed Load Speed Loads are an excellent addition to the Expansion Board Cap Seal and Polyboard. The Speed Load aligns the steel load transfer dowels, eliminates greasing the dowels and are designed specifically for leave-in-place forming systems like the EB Cap System Polyboard and Speed Load

    3400 Tree Court Industrial Blvd. St. Louis, MO 63122 (800) 793-7832 or (636) 225-9400 Email: [email protected]

  • No. 634 No. 637

    No. 638 No. 639

    Standard EB Cap Profiles

    Typical Components for an Expansion Board Cap Seal System

    bakerroPolygon

  • EB CAP SEAL SYSTEM Jobsite Guide The WESTEC EB CAP SEAL SYSTEM is a one step complete concrete joint system. The EB Cap Seal serves as FORM, WATERSTOP, SEALANT and DOWEL GUIDE in a single installation to create a fluid tight, maintenance-free expansion joint.

    The EB CAP Seal System includes the Waterstop/Cap Seal profile, a HDPE Expansion Board / Form Board and Speed Load Dowel Sleeve.

    1. Holes for Speed Load: Drill 1” holes for the ¾” x 9 Speed Load in HDPE Expansion Board. Consult a Greenstreak Group Engineer for other Speed Load Sizes. Treated Lumber and Plywood may also serve as form and expansion material, however typical expansion joint materials (foam, fiber, etc..) are not rigid enough and should not be used without external support.

    2. Tap Speed Load Sleeves through Expansion Board. (rubber mallet works well)

    3. Stake Expansion Board (EB) at regular intervals, Stakes should be 3” below Top of

    Slab (TOS) elevation. Board can be secured with wood screws or ring shank nails.

    4. Leave 1/8” between board ends to allow for any possible thermal expansion

    5. Weld EB Cap Seal waterstop according to Westec TPER/PE Splicing Guide directions. Use prefabricated fittings for all intersections and direction changes.

    NOTE: Welding process will create a bead of material around the ends of the cap.) This bead must be removed from the inside of cap in order for the EB Cap to sit flush on the Expansion Board. (pliers work well for this) The Weld Bead on the top of the cap must also be removed or smoothed with the iron to avoid catching the screed during concrete placement and finishing.

    6. Place EB Cap profile on Expansion Board and secure cap to board with Nails or screws

    through the tabs BELOW the waterstop ribs. No penetrations are allowed through the top or sides of the waterstop above the ribs.

    7. Pour concrete normally and use top of EB Cap as screed guide and finish concrete

    normally.

  • The 687 and 688 waterstops were designed to allow placement of the waterstop over an expansion joint. Excellent for retrofitting around tank foundation or pump pads, or wherever an isolation joint is required. The 687 and 688 can be fabricated with the 638 EB Cap seal for new construction. Westec 687 and 688 profiles are ideal for both circular and angled tank foundations. The profiles can curve around tanks as small as 15’ in diameter without special miter cuts.

    No. 687 No. 688

    Retrofit EB Cap Profiles

    3400 Tree Court Industrial Blvd. St. Louis, MO 63122 (800) 793-7832 or (636) 225-9400 Email:

    [email protected]

    Addendum#1Pre-Bid Meeting NotesPre-Bid Meeting NotesOctober 23, 2014 at 1:00pm

    PRE-BID SIGN IN SHEETWestec TPER Expansion Board Cap Seal System