Upload
rowaters
View
254
Download
3
Embed Size (px)
Citation preview
ID 2
55
7
The greatest challenge faced was
that the segments were 20.34m
wide with rather thin concrete
sections. Vibrations during
transportation could cause
cracking and so most required
fitting with temporary props before
setting out on the journey.
Travel was at low speed to
minimise vibration. The segments
adjacent to the pier had to be
strengthened by temporary
strutting and increases to the
bottom slab thickness to allow
nailing of deck to pier during
cantilever construction.
components had been modified,
strengthened and upgraded to suit the
latest project.
VSL Malaysia in joint venture with
precaster Projalma was awarded a
contract for the casting and erection
of 747 precast segments, weighing
between 80t and 120t, and the supply
and installation of 1,100t of post-
tensioning. The segments were cast
in Ipoh – approximately 200km from
the Subang site - and delivered to a
point directly beneath the gantry. The
viaduct was built by the free-cantilever
method and segments were lifted up
in pairs using VSL’s strand lifting
units.
VSL JV’s scope of work included
provision of the casting yard at Jalan
Gopeng, Ipoh, including steel moulds,
the straddle carrier system,
reinforcement jigs and the bar
bending yard for the 747 segments.
The scope also covered provision of
the storage yard to store and cure the
segments, the supply of rebar,
concrete and prestressing
components, and the trailer to deliver
the segments to site.
Scope of works performed
• Design and supply of the launching
gantry
• Segment casting and erection
• Supply and installation of post-
tensioning
Subang Kelana Jaya Link is an
elevated highway in Subang Jaya,
Selangor, Malaysia. At the time of
construction it was the tallest
elevated highway in the region.
The project saw a return to action
for an overhead launching gantry
previously used on the Malaysia-
Singapore Second Crossing
Bridge, the Pakse Bridge in Laos
and the Bayan Baru Viaduct in
Penang. The gantry had first been
used in 1995, before being sent to
Laos in 1998 and returning to
Malaysia for the Bayan Baru
Viaduct in 2002. On the Subang
Kelana Link, it was used to build
the 34 spans of an elevated viaduct
consisting of precast segmental
twin-cell box girders. It was
assembled at the Subang site in
September 2006, after some
Subang Kelana Link – Malaysia
Reuse of a modular launching gantry for the free-cantilever erection
of the segments of a major viaduct
▲ VSL adapted its modular launching gantry to carry out the segment erection.
▲ Falsework was used in erecting the
end spans.
www.vsl.com
Edited
2012
ID 2
55
7
OWNER
Malaysia’s public works department
ENGINEER
Maunsell, Sharma & Zakaria (MSZ)
MAIN CONTRACTOR
Ahmed Zaki Sdn. Bhd (ASZSB)
VSL ENTITY
VSL Malaysia in JV with Projalma
DATE
2006
This ensured that the gantry loads
could be transferred to the
crosshead.
For the post-tensioning, VSL
supplied and installed approximately
1,100t of internal and external
tendons, as well as providing
specific cast-in components for
incorporation into the segments.
Segment erection works covered
the design and supply of the
launching girder, the falsework to
support out of balance part of side
spans and provision of all labour
and supervision for the launching
girder operation and the falsework
installation and dismantling.
VSL was also responsible for all
aspects of the construction
engineering, including the design
of temporary stressing for segment
erection, pre-camber and
alignment calculations, preparation
of the erection kinematics and
calculation of the stressing
elongation for the post-tensioning
tendons.
▲ Casting of segments in Projalma's casting yard approximately 200km from the site.
▲ The segments had to be carefully
prepared for transport.
▲ Deck access at pier locations
▼ Remember to comment the picture