Structures Management Unit
David Stutts, Project Management
Bridges – From “Cradle to Grave”Structures Management Unit
2
Bridge Replacement ProgramStructures Management Unit
3
The “B” Projects2017 – Under New Management150 +/- Current ProjectsTierre Peterson – Team LeaderJacquelyn Bowles – Project Coordinator
Bridge Replacement ProgramStructures Management Unit
4
SMU CoordinationDesign Firm – Turnkey ProjectGEC Review FirmIn-house Coordination with all
other Units
Bridge Replacement ProgramStructures Management Unit
5
PrescreeningNovember thru January – 53 ProjectsFebruary thru May - Scoping & NTPSummer 2018 – 50 More Projects
Structures Management Unit
6
Bridge Replacement Program
Bridge Replacement ProgramStructures Management Unit
7
Coordination with Divisions
• Prescreening• Scoping• FSM and CFI•ROW•Municipal Involvement
Bridge Replacement ProgramStructures Management Unit
8
SHAREPOINT / CONNECT NCDOT PRECONSTRUCTION
• Submittals – Reviews - Design Files -Final Plans
•No more SrvConn / R:drive / ProjStore•Guidelines: Bridge Program & Structures Design Library – available(???)
Division Managed ProjectsStructures Management Unit
9
Plan Review Coordination with Divisions
David Stutts – PEF CoordinatorHoang Dieu – Plan Review
Coordinator
Division Managed ProjectsStructures Management Unit
10
Plan Review Coordination with Divisions
• PGD Review:Current BSR, Roadway Plans
• Final Plan Review:Current Foundation Recs, BSR, Roadway
Plans
Division Managed ProjectsStructures Management Unit
11
Plan Review Coordination with Divisions
• 10 Day Review Time• Provide Let Schedule for prioritization
Division Managed ProjectsStructures Management Unit
12
Division Design – Raleigh Let (DDRL)
•Central Letting• SMU PS&E Group – Hoang Dieu• Provide Final Plans, PSP, Estimate, Working Days
Questions?Structures Management Unit
13