Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Rain or ShineWORK
By Kent Pulver
STREET LIGHTING AND ELECTRICAL SYSTEM UNDERGROUNDING
CIP_2015 Title Pages 2016:Layout 1 6/22/15 1:48 PM Page 19
Street Lighting and Electric Undergrounding
Priority Description
AppropriatedThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
FY 2016 - 2020 Capital Improvement Program
Electric System Undergrounding Outside Established Undergrounding District - FY 2016 (74481)
1 100,000 0 100,000 0 00 0
Electric System Undergrounding Outside Established Undergrounding Districts - FY 2017 - 2020
2 400,000 0 0 100,000 100,000100,000 100,000
La Loma Road - Electric System Undergrounding, San Rafael Avenue to Arroyo Boulevard (74484)
3 1,000,000 0 1,000,000 0 00 0
Hill Avenue - Street Lighting and Electric System Undergrounding, Villa St. to North City Limits (74488)
4 11,379,000 11,379,000 0 0 0* 0 0
Alpine Street - Street Lighting and Electrical System Undergrounding, Marengo Avenue to El Molino Avenue (74801)
5 3,923,000 3,923,000 0 0 00 0
Mountain Street - Street Lighting and Electrical System Undergrounding, Lake Avenue to Hill Avenue (74909)
6 5,733,400 5,433,400 0 300,000 00 0
Raymond Avenue - Electric System Undergrounding, Maple Street to North City Limits (74490)
7 14,642,700 13,407,700 0 1,235,000 00 0
Howard Street - Electrical System Undergrounding, Lincoln Avenue to Raymond Avenue (74485)
8 4,081,500 4,081,500 0 0 00 0
Michillinda Avenue - Street Lighting and Electric System Undergrounding, Foothill Blvd. to North City Limits
9 11,583,215 70,000 0 0 11,513,2150 0
1,635,00049,942,815 35,394,600 1,100,000 11,613,215* A portion of project cost not included in summary total. See Special Considerations on project page.
Total 100,000 100,000
4 - Summary
Street Lighting and Electric UndergroundingElectric System Undergrounding Outside Established Undergrounding District - FY 2016
74481
FY 2016 - 2020 Capital Improvement Program
Electric System Undergrounding Outside Established Undergrounding District - FY 2016
74481Priority DescriptionProject No.
1Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund 0 100,000 0 00 0100,0000 100,000 0 0
DESCRIPTION: This project provides for the undergrounding of electrical facilities and the installation of street lighting in conjunction with small undergrounding projects at various locations throughout the City. It also provides refunds to property owners for underground conversions in residential areas.
JUSTIFICATION: This project will enhance the aesthetic quality of the streetscape by removing unsightly utility poles and overhead wires. Undergrounding the utilities will also improve system reliability.
SCHEDULE: This is an ongoing project which is based on small undergrounding projects that are not part of an established underground district.
RELATIONSHIP TO THE GENERAL PLAN: This project is consistent with the Mobility Element/Power Facilities in that to improve the visual environment of the City through improved streetscapes, conversion of existing overhead to underground facilities will be encouraged.
HISTORY: This project was originally created and received initial funding in FY 1983 as project number 74569. It was segmented into a five-year project in FY 2011 as project number 74480. Starting in FY 2016, the name of this project changed and it became an annual project. This project was created and fully funded in FY 2016.
Total 0 0100,000
4.1Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingElectric System Undergrounding Outside Established Undergrounding Districts - FY 2017 - 2020
FY 2016 - 2020 Capital Improvement Program
Electric System Undergrounding Outside Established Undergrounding Districts - FY 2017 - 2020
Priority DescriptionProject No.2
AppropriatedThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund 0 0 100,000 100,000100,000 100,000400,0000 0 100,000 100,000
DESCRIPTION: This project provides for the undergrounding of electrical facilities and the installation of street lighting in conjunction with small undergrounding projects at various locations throughout the City. It also provides refunds to property owners for underground conversions in residential areas.
JUSTIFICATION: This project will enhance the aesthetic quality of the streetscape by removing unsightly utility poles and overhead wires. Undergrounding the utilities will also improve system reliability.
SCHEDULE: This is an ongoing project which is based on small undergrounding projects that are not part of an established underground district.
RELATIONSHIP TO THE GENERAL PLAN: This project is consistent with the Mobility Element/Power Facilities in that to improve the visual environment of the City through improved streetscapes, conversion of existing overhead to underground facilities will be encouraged.
HISTORY: This proejct was originally created and received initial funding in FY 1983 as project number 74569. It was segmented into a multi-year project in FY 2011 as project number 74480. Starting in FY 2016, this project became an annual project for tracking purposes. The next phase of this project will begin in FY 2017 and continue through FY 2020.
Total 100,000 100,000400,000
4.2Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingLa Loma Road - Electric System Undergrounding, San Rafael Avenue to Arroyo Boulevard
74484
FY 2016 - 2020 Capital Improvement Program
La Loma Road - Electric System Undergrounding, San Rafael Avenue to Arroyo Boulevard
74484Priority DescriptionProject No.
3Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund 0 1,000,000 0 00 01,000,0000 1,000,000 0 0
DESCRIPTION: This project provides for the electrical undergrounding work on La Loma Road between San Rafael Avenue and Arroyo Boulevard necessitated by the La Loma Bridge Rehabilitation project.
JUSTIFICATION: The La Loma Bridge Rehabilitation project requires the transfer of electric loads and the replacement of electrical conduit in the bridge and installation of new underground electrical conduit and vaults in La Loma Road. The new electrical conduit and vault system will provide for future electrical 17kV service to replace existing the 4kV system and provide better reliability and quick service restoration.
SCHEDULE: In FY 2016, construction of electrical undergrounding associated with the La Loma Bridge Rehabilitation project will begin. Construction of underground conduit on La Loma Road between San Rafael Avenue and Arroyo Boulevard to transfer the electric load in connections until the completion of the La Loma Bridge project will also be completed.
RELATIONSHIP TO THE GENERAL PLAN: This project is consistent with Land Use Element Policy 5.7 by implementing development that improves the environment for the public; supporting the distinctiveness of the locality and region as well as the special characteristics of the existing fabric of the site’s immediate surroundings.
HISTORY: This project was created and fully funded in FY 2016.
Total 0 01,000,000
4.3Responsible Department:Water and Power Department
Street Lighting and Electric UndergroundingHill Avenue - Street Lighting and Electric System Undergrounding, Villa St. to North City Limits
74488
FY 2016 - 2020 Capital Improvement Program
Hill Avenue - Street Lighting and Electric System Undergrounding, Villa St. to North City Limits
74488Priority DescriptionProject No.
4Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Power Capital Projects Fund (memo) 2,900,000 0 0 00 02,900,000Underground Utilities Fund - Power Facilities 4,822,627 0 0 00 04,822,627Underground Utilities Fund - Public Works 3,656,373 0 0 00 03,656,373
11,379,000 0 0 0Hill Avenue Undergrounding DESCRIPTION: This project provides for the installation of a new street lighting system using
energy efficient lighting and the undergrounding of electrical utilities on Hill Avenue from Villa Street to the north city limits.
JUSTIFICATION: Street lights enhance public safety through improved lighting levels. The energy efficient lights will reduce the City's environmental carbon footprint. The energy efficient street lamps have a longer life than other lamps and consume approximately 50 percent less energy. Undergrounding the power facilities improves streetscape aesthetics and system reliability.
SCHEDULE: Design will be completed in FY 2016 and construction of street lighting will be completed in FY 2017 by the Department of Public Works. In addition, electrical design and construction in streets will be completed in FY 2016 by the Department of Water and Power.
RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Mobility Element/Power Facilities in that to improve the visual environment of the City through improved streetscapes, conversion of existing overhead to underground facilities will be encouraged.
SPECIAL CONSIDERATION: On August 12, 2013, City Council approved a transfer of $2.9 million in Undergrond Surtax to the Power Capital Projects Fund. The $2.9 million is part of the total estimated cost of the project, but not calculated in the section summary totals to avoid duplication.
HISTORY: This project was created in FY 1986, received initial funding in FY 2004, and fully funded in FY 2014. This underground district was established in FY 2005. Design of street lighting was completed in FY 2013. Construction of the underground conduit and vault electric system began in FY 2014 and was completed in FY 2015.
Total 0 011,379,000
4.4Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingAlpine Street - Street Lighting and Electrical System Undergrounding, Marengo Avenue to El Molino Avenue
74801
FY 2016 - 2020 Capital Improvement Program
Alpine Street - Street Lighting and Electrical System Undergrounding, Marengo Avenue to El Molino Avenue
74801Priority DescriptionProject No.
5Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund - Power Facilities 2,840,220 0 0 00 02,840,220Underground Utilities Fund - Public Works 1,082,780 0 0 00 01,082,780
3,923,000 0 0 0Alpine Street from Marengo Avenue to El Molino Avenue DESCRIPTION: This project provides for the undergrounding of electrical utilities and the
installation of a new street lighting system using energy efficient lighting on Alpine Street from Marengo Avenue to El Molino Avenue.
JUSTIFICATION: This project will improve street lighting for traffic and pedestrian safety. The energy efficient lights will reduce the City's environmental carbon footprint. The energy efficient street lamps have a longer life than other lamps and consume approximately 50 percent less energy. Undergrounding of electrical facilities will improve streetscape aesthetics and system reliability.
SCHEDULE: In FY 2016, a private property connection will be designed by the Department of Public Works. In addition, installation of underground conduits and vaults in the street right-of-way will be completed by the Department of Water and Power. Electrical construction in streets is expected to be completed in FY 2017.
RELATIONSHIP TO THE GENERAL PLAN: This project is consistent with the Public Facilities Element Objective 2 by providing more efficient development and utilization of public facilities. In addition, the project is consistent with Public Facilities Element Objective 5 by providing a high level of design quality in all public streets.
HISTORY: This project was created in FY 2007, initially funded in FY 2008, and fully funded in FY 2014. The establishment of the district was completed in FY 2008 and the electric system design was completed in FY 2009. Design of the street lighting was completed in FY 2010 and construction was completed in FY 2014.
Total 0 03,923,000
4.5Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingMountain Street - Street Lighting and Electrical System Undergrounding, Lake Avenue to Hill Avenue
74909
FY 2016 - 2020 Capital Improvement Program
Mountain Street - Street Lighting and Electrical System Undergrounding, Lake Avenue to Hill Avenue
74909Priority DescriptionProject No.
6Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund - Power Facilities 4,320,401 0 0 00 04,320,401Underground Utilities Fund - Public Works 1,112,999 0 300,000 00 01,412,999
5,433,400 0 300,000 0Mountain Street from Lake Avenue to Hill Avenue DESCRIPTION: This project provides for the undergrounding of electrical utilities and the
installation of a new street lighting system using energy efficient lighting on Mountain Street from Lake Avenue to Hill Avenue.
JUSTIFICATION: This project will improve street lighting for traffic and pedestrian safety. The energy efficient lights will reduce the City's environmental carbon footprint. The energy efficient street lamps have a longer life than other lamps and consume approximately 50 percent less energy. Undergrounding of electrical facilities will improve streetscape aesthetics and system reliability.
SCHEDULE: Design of electrical system will be completed in FY 2016 by the Department of Water and Power.
RELATIONSHIP TO THE GENERAL PLAN: This project is consistent with the Public Facilities Element Objective 2 by providing more efficient development and utilization of public facilities. In addition, the project is consistent with Public Facilities Element Objective 5 by providing a high level of design quality in all public streets.
HISTORY: This project was created in FY 2007 and initially funded in FY 2014.
Total 0 05,733,400
4.6Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingRaymond Avenue - Electric System Undergrounding, Maple Street to North City Limits
74490
FY 2016 - 2020 Capital Improvement Program
Raymond Avenue - Electric System Undergrounding, Maple Street to North City Limits
74490Priority DescriptionProject No.
7Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund - Power Facilities 8,724,150 0 1,235,000 00 09,959,150Underground Utilities Fund - Public Works 4,683,550 0 0 00 04,683,550
13,407,700 0 1,235,000 0Raymond Avenue DESCRIPTION: This project provides for the undergrounding of electrical utilities and the
installation of a new street lighting system using energy efficient lighting on Raymond Avenue from Maple Street to the north city limits.
JUSTIFICATION: This project will improve street lighting for traffic and pedestrian safety. The energy efficient lights will reduce the City's environmental carbon footprint. The energy efficient street lamps have a longer life than other lamps and consume approximately 50 percent less energy. Undergrounding of electrical facilities will improve streetscape aesthetics and system reliability.
SCHEDULE: In FY 2016, design of the electrical system will begin and will be completed in FY 2017 by the Department of Water and Power.
RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Public Facilities Element Objective 5 of the General Plan by encouraging a high level of maintenance of existing facilities to ensure public safety. It is also consistent with Land Use Element Objective 13 by providing adequate support for institutions that serve the needs of Pasadena's diverse residents and families.
IMPACT ON THE NORTHWEST: This project is located in Northwest Pasadena which is an area that has been targeted for revitalization.
HISTORY: This project was created and received initial funding in FY 2004. The underground district was established in FY 2006.
Total 0 014,642,700
4.7Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingHoward Street - Electrical System Undergrounding, Lincoln Avenue to Raymond Avenue
74485
FY 2016 - 2020 Capital Improvement Program
Howard Street - Electrical System Undergrounding, Lincoln Avenue to Raymond Avenue
74485Priority DescriptionProject No.
8Appropriated
ThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund - Power Facilities 2,402,204 0 0 00 02,402,204Underground Utilities Fund - Public Works 1,679,296 0 0 00 01,679,296
4,081,500 0 0 0Howard Street from Lincoln Avenue to Raymond Avenue DESCRIPTION: This project provides for the undergrounding of electrical utilities and the
installation of a new street lighting system using energy efficient lighting on Howard Street from Lincoln Avenue to Raymond Avenue.
JUSTIFICATION: This project will improve street lighting for traffic and pedestrian safety. The energy efficient lights will reduce the City's environmental carbon footprint. The energy efficient street lamps have a longer life than other lamps and consume approximately 50 percent less energy. Undergrounding of electrical facilities will improve streetscape aesthetics and system reliability.
SCHEDULE: No work is scheduled for FY 2016.
RELATIONSHIP TO THE GENERAL PLAN: This project is consistent with the Public Facilities Element Objective 2 by providing more efficient development and utilization of public facilities. In addition, the project is consistent with Public Facilities Element Objective 5 by providing a high level of design quality in all public streets.
IMPACT ON THE NORTHWEST: This project is located in Northwest Pasadena which is an area that has been targeted for revitalization.
HISTORY: This project was created in FY 2007 and fully funded in FY 2015.
Total 0 04,081,500
4.8Responsible Department:Public Works Department
Street Lighting and Electric UndergroundingMichillinda Avenue - Street Lighting and Electric System Undergrounding, Foothill Blvd. to North City Limits
FY 2016 - 2020 Capital Improvement Program
Michillinda Avenue - Street Lighting and Electric System Undergrounding, Foothill Blvd. to North City Limits
Priority DescriptionProject No.9
AppropriatedThroughFY 2015
AdoptedFY 2016
ProposedFY 2017
ProposedFY 2018
ProposedFY 2019
ProposedFY 2020
and Beyond
TotalEstimated
Costs
Underground Utilities Fund - Power Facilities 0 0 0 8,249,7840 08,249,784Underground Utilities Fund - Public Works 70,000 0 0 3,263,4310 03,333,431
70,000 0 0 11,513,215Michillinda Avenue Undergrounding DESCRIPTION: This project provides for the installation of a new street lighting system (west
side only) using energy efficient lighting and the undergrounding of electrical utilities on Michillinda Avenue from Foothill Boulevard to the north city limits.
JUSTIFICATION: This project will improve street lighting for traffic and pedestrian safety. The energy efficient lights will reduce the City's environmental carbon footprint. The energy efficient street lamps have a longer life than other lamps and consume approximately 50 percent less energy. Undergrounding the power facilities improves streetscape aesthetics and system reliability.
SCHEDULE: The establishment of the district and design of the street lighting system and underground factilities is currently on hold pending an agreement between Southern California Edison, Time Warner Cable, and the cities of Sierra Madre and Arcadia.
RELATIONSHIP TO GENERAL PLAN: This project is consistent with the Mobility Element/Power Facilities in that to improve the visual environment of the City through improved streetscapes, conversion of existing overhead to underground facilities will be encouraged.
SPECIAL CONSIDERATIONS: This project will require the cooperation of two other cities since the eastern half of the street is located within the cities of Arcadia and Sierra Madre.
HISTORY: This project was created in FY 1986 and received initial funding in FY 2004.
Total 0 011,583,215
4.9Responsible Department:Public Works Department