Upload
dayou-yang
View
245
Download
10
Embed Size (px)
DESCRIPTION
Citation preview
Company Confidential
Optimising Strategic Improvements
in High Tech Industry
Dr. Dayou YANG
(A simplification to public presentation of PhD dissertation)
http://urn.fi/urn:isbn:9789514293559
PhD dissertation link:
Company Confidential
2
Optimisation of Product Change Process and
Demand-Supply Chain in High Tech Environment
3
• Research Problem Statement & Sub-questions
• Structure of the Thesis
• Research Conditions
• The Details of Action Research Cycles
• Answering Research Questions
• Discussion & Future Research
Presentation Contents
4
Research Problem
- A real challenge from one of the largest telecommunications infrastructure suppliers
Month
Product
Amount Monthly Forecast & True Demand
5
Research Problem
- A real challenge from one of the largest telecommunications infrastructure suppliers
Research Problem Statement:
How should companies optimise the product change
process strategy in a situation where there are simultaneous
and variable pressures to be lean, agile and innovative.
6
Research Sub-questions
1. What are the effects for the product change
process when costs are minimised?
2. What are the effects for the product change
process when order delivery period is minimised?
3. What are the effects for the product change
process when product change time is minimised?
7
Chapter 1: Introduction
• Research background & motivation
• Objectives and scope
• Research process
• Action research
• Research context
• Practical realisation
Structure of the Thesis
Evaluate Diagnose
Plan Act
Action
Research
cycle
8
Chapter 1: Introduction
Chapter 2: Literature review
• Manufacturing philosophies
• Developing demand-supply network
• Product change management
• Special characteristics of high-tech industries
• Theory synthesis
Structure of the Thesis
Structure of the Thesis
9
Chapter 1: Introduction
Chapter 2: Literature review
• Manufacturing philosophies
• Developing demand-supply network
• Product change management
• Special characteristics of high-tech industries
• Theory synthesis
Minimise costs
Quick delivery Rapid change
(lean)
(innovativeness) (agile)
10
Chapter 1: Introduction
Chapter 2: Literature review
Chapter 3: Results of the three action research cycles
• Research cycle 1
– minimising costs
• Research cycle 2
- shortening order delivery time
• Research cycle 3
- shortening product change time
Structure of the Thesis
11
Chapter 1: Introduction Chapter 2: Literature review
Chapter 3: Results of the three action research cycles
Chapter 4: Discussion
• Answering research questions
• Managerial implications
• Scientific implications
• Reliability and validity
• Research contribution & discussion
• Future research
Structure of the Thesis
12
Chapter 1: Introduction Chapter 2: Literature review
Chapter 3: Results of the three action research cycles
Chapter 4: Discussion
Chapter 5: Summary
Structure of the Thesis
13
- The supply complexity is greatly affected by multiple product life-cycles
(Bengtsson et al., 2002)
Research Conditions
14
- The research should provide new scientific contributions at the end
Optimisation of Product Change Process and
Demand-Supply Chain in High Tech Environment
The Research via
“Product change
Management”
R&D product
changes
Customer demand
changes
Supply situation
changes
…
Business process
changes
…
Internal variants External variants
The Thesis
Demand Fulfillment
Process
Product Creation
ProcessProduct Change
Process
CONTEXT ANALYSIS:
EXECUTION PROCESSES:
RESEARCH OUTCOME:
Strategy changes
People affect
operation
Research Conditions
15
Action Research Cycles
- Scientific contributions are from multiple research cycles as a journey
Evaluate Diagnose
Plan Act
Cycle 1
Min. inventory
Evaluate Diagnose
Plan Act
Cycle 2
Quick delivery
Evaluate Diagnose
Plan Act
Cycle 3
Rapid product
change
Final
Conclusions
2003 2004 2005 2006 2010
RESEARCH JOURNEY OVERVIEW:
16
Action Research Cycles (The Cycle 1 as a Sample)
Minimise costs
Quick delivery Rapid change
(lean)
(innovativeness) (agile)
Research cycle 1
– minimising costs
17
Action Research Cycles (The Cycle 1 as a Sample)
Research cycle 1
– minimising costs
Manual synchronisation Into MRP
Last “Proto” BOM Current BOM
Product Change Driver
Weekly Status & Adjust Lists Forecast & Demand
“Possible Scrap” Monitoring
Implementation
Another “Proto” RoundApproval?
R&D“Planning BOM”
Synchronising Pace = “Dynamic Cut-off Window” / Weekly
0 Series Result
Optimisation of Product Change in The Cycle 1
18
Action Research Cycles (The Cycle 1 as a Sample)
Research cycle 1
– minimising costs
Product change implementation result
19
Answering Research Questions
Question 1:
What are the effects for the product change process when costs are minimised?
Positive impact:
• Accept inaccurate forecast
• Operate as weekly base
• Minimise costs even including the liability
Minimise costs
(lean)
Optimisation
Negative impact:
• Need IT (Information
Technology) to support as a
lesson learnt
20
Answering Research Questions
Question 2:
What are the effects for the product change process when order delivery period
is minimised?
Quick delivery
(agile)
Optimisation
Positive impact:
• Enlarge operational tolerance to “extreme”
• Synchronise even with R&D
Negative impact:
• Understand the liability
• Understand the forecast as a
reference
21
Answering Research Questions
Question 3:
What are the effects for the product change process when product change time
is minimised?
Rapid change
(innovativeness)
Optimisation
Positive impact:
• Make product change beyond the limits
(OK to a bigger scrapping cost)
• Promote radical innovation (to reduce the
liability in an unusual way)
Negative impact:
• Learn the difficulties of
revolutionary solution
22
Minimise costs
Quick delivery Rapid change
(lean)
(innovativeness) (agile)
Optimisation
Optimisation with multi-strategies:
Not only the extremes but also the choices in the between !
Discussion
23
Future Research
“Total Synchronisation” concept with IT solutions:
(A time based optimisation not only in product change period but also as anytime
and anywhere in the operation)
How to apply
the principles
to normal
operation?
How to solve
research
problem and
questions?
(Anytime, Anyw here, ……= Total Synchronisation)
Case 1
Case 2
Case 3
Product change implementation result
24
中文简洁版本
杨大猷 博士
博士论文的链接:
http://urn.fi/urn:isbn:9789514293559
(基于博士论文公开答辩时所用的演讲材料)
Company Confidential
25
• 所研究问题的声明及详细分题
• 论文结构
• 研究条件
• 行动研究法的应用
• 研究问题的回答
• 深入讨论和将来的研究方向
博士论文公开答辩 —— 陈述提纲
Company Confidential
26
研究问题
- 最大的电信基础设施供应商之一在需求供应实践中,也是高科技行业里所普遍面临的一个真实挑战!
Month
Product
Amount Monthly Forecast & True Demand 产品数量 按月所做的预测和真实需求的对比
月份 2 月 3 月 4 月 5 月 6 月 7 月 8 月 9 月 10 月 11 月 12 月 1 月 2 月
产品需求预测——2 个月前
产品需求预测——1 个月前
实际生产量
Company Confidential
27
研究问题的声明:
企业应如何优化而使产品变化流程可以贯彻公司的战略意图,
在整个需求供应的运营中同时或者分别地达到精益、 敏捷和
差异化创新的期望。
研究问题
- 最大的电信基础设施供应商之一在需求供应实践中,也是高科技行业里所普遍面临的一个真实挑战!
Company Confidential
28
- 众多产品生命周期之间交替互动,而大大地增加了供应链运营的复杂性
(Bengtsson et al., 2002)
研究条件
新产品或者版本变化的”起飞”阶段 大批量生产阶段 减产退出阶段
Company Confidential
29
- 研究的最终目的是提供新的科学贡献
Optimisation of Product Change Process and
Demand-Supply Chain in High Tech Environment
The Research via
“Product change
Management”
R&D product
changes
Customer demand
changes
Supply situation
changes
…
Business process
changes
…
Internal variants External variants
The Thesis
Demand Fulfillment
Process
Product Creation
ProcessProduct Change
Process
CONTEXT ANALYSIS:
EXECUTION PROCESSES:
RESEARCH OUTCOME:
Strategy changes
People affect
operation
研究条件
商务流程的变更
(研发)产品的变化
内部的变量 外部的变量 公司战略变更
市场需求的变化
供应状况的变化
人为的影响因素
通过产品变化管理的案例进行研究
产品开发的流程 产品变化的流程 产品需供的流程
公司生态系统的分析
公司运营流程的分析
Company Confidential
30
行动研究法的应用
- 多个研究周期以形成一个勇于攀登科学高峰的旅程
评估 诊断
计划 行动
第 1 期
精益实践 第 2 期
敏捷实践 第 3 期
创新实践
研究总结
2003 2004 2005 2006 2010
RESEARCH JOURNEY OVERVIEW: 研究历程的回顾
评估 诊断
计划 行动
评估 诊断
计划 行动
Company Confidential
31
行动研究法的应用 (以第 1 个周期为例子)
更专注于控制开支
(精益实践)
研究周期 1
– 精益实践
尽量快地供货
(敏捷实践)
突破产品更新的常规
(创新实践)
Company Confidential
Manual synchronisation Into MRP
Last “Proto” BOM Current BOM
Product Change Driver
Weekly Status & Adjust Lists Forecast & Demand
“Possible Scrap” Monitoring
Implementation
Another “Proto” RoundApproval?
R&D“Planning BOM”
Synchronising Pace = “Dynamic Cut-off Window” / Weekly
0 Series Result
Optimisation of Product Change in The Cycle 1
行动研究法的应用 (以第 1 个周期为例子)
研究周期 1
– 精益实践
产品新版本材料的”计划明细表”
MRP系统中进行手工调衡
产品变化的关键件 版本切换前的动态”空窗”期
如何优化和控制产品版本变化?
32
Company Confidential
33
产品版本变化的最终结果
行动研究法的应用 (以第 1 个周期为例子)
研究周期 1
– 精益实践
所涉及的产品类别
需用
的星
期数
工厂 2
工厂 1
工厂 2 的目标值 = 11个星期
工厂 1 的目标值 = 7个星期
Company Confidential
34
研究问题的回答
问题 1:
公司的精益战略会对产品变化的流程产生什么样的影响?
正面影响:
• 接受需求预测总犯错的情况
• 改进运营以星期为供需调衡的节奏
• 控制开支并包括呆滞欠料的部分
优化
侧重点
反面影响:
• 从教训中认识到需要信息技
术支持的迫切性
更专注于控制开支
(精益实践)
Company Confidential
35
正面影响:
• 能实现公司运营最大的韧性(产能最大化)
• 有可能与公司研发部门很好地调衡配合
反面影响:
• 通过教训而深刻理解呆滞欠料
的本质
• 理解需求预测作为参考的重要
性
研究问题的回答
问题 2:
公司的敏捷战略会对产品变化的流程产生什么样的影响?
优化
侧重点
尽量快地供货
(敏捷实践)
Company Confidential
36
正面影响:
• 打破产品更新的常规 (甚至于接受较大的
材料浪费)
• 推动非常规创新的尝试
反面影响:
• 对于某些失败吸取教训,更理
解用成品作为运营缓冲的弊病
研究问题的回答
问题 2:
公司的非常规创新战略会对产品变化的流程产生什么样的影响?
优化
侧重点
突破产品更新的常规
(创新实践)
Company Confidential
37
多元化战略的优化运营:
不仅得考虑独立或极端化的情形,而且更要概括所有选项及互动,而成为一个整体的
动态涉及范围!
深入讨论
更专注于控制开支
(精益实践)
尽量快地供货
(敏捷实践)
突破产品更新的常规
(创新实践)
优化
侧重点
Company Confidential
38
将来的研究
“全面地同步均衡运营” 的概念以及相关信息技术,作为一个整体解决方案的开发:
(由此去发展一种即时优化的理念,不局限于产品变化的时期,而是进一步拓展到公
司运营的任何时间和各个环节)
How to apply
the principles
to normal
operation?
How to solve
research
problem and
questions?
(Anytime, Anyw here, ……= Total Synchronisation)
Case 1
Case 2
Case 3
Product change implementation result
(任何时间和环节 ... = 全面地同步均衡运营)
Company Confidential
39