27
STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA ALDINGA STRUCTURE PLAN Final 65269-1 PREPARED FOR Renewal SA PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya, Principal Civil Engineer TELEPHONE office 61 8 8201 9600 direct 8201 9711 FACSIMILE 61 8 8201 9650 EMAIL [email protected] DATE 24/05/2019 REFERENCE 65269 (Revision D)

STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

STORMWATER MANAGEMENT MASTERPLAN

RENEWAL SA ALDINGA STRUCTURE PLAN

Final

65269-1

PREPARED FOR Renewal SA

PREPARED BY Fyfe Pty Ltd

ABN 57 008 116 130

ADDRESS L1, 124 South Terrace, Adelaide SA 5000

CONTACT Bicky Shakya, Principal Civil Engineer

TELEPHONE office 61 8 8201 9600 direct 8201 9711

FACSIMILE 61 8 8201 9650

EMAIL [email protected]

DATE 24/05/2019

REFERENCE 65269 (Revision D)

Page 2: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

©Fyfe Pty Ltd, 2019

Proprietary Information Statement

The information contained in this document produced by Fyfe Pty Ltd is solely for the use of the Client identified on the cover sheet for the purpose for which it has been prepared and Fyfe Pty Ltd undertakes no duty to or accepts any responsibility to any third party who may rely upon this document.

All rights reserved. No section or element of this document may be removed from this document, reproduced, electronically stored or transmitted in any form without the written permission of Fyfe Pty Ltd.

Document Information

Prepared by: Bicky Shakya Principal Civil Engineer Date: 1 March, 2019

Reviewed by: Joel Stevenson General Manager, Property and Infrastructure

Date: 1 March, 2019

Approved by: Michael Osborn National Planning Manager Date: 1 March, 2019

Client acceptance by: Date:

Revision History

Revision Revision Status Date Prepared Reviewed Approved

A Preliminary 1.03.2019 BS JRS MO

B Preliminary 7.03.2019 BS JRS MO

C Preliminary 8.03.2019 BS JRS MO

D Final 24.05.2019 BS JRS MO

Page 3: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE I

CONTENTS

Page

1. INTRODUCTION 1

1.1 Background 1

1.2 Subject Site 1

1.3 Legal Points of Discharge 2

1.4 Flood Hazard 4

1.5 Design Basis 4

1.6 Council Requirements and Service Standard 4

2. STORMWATER DRAINAGE MODELLING 6

2.1 Data Source 6

2.2 Rainfall Data 6

3. PRE-DEVELOPMENT SCENARIO 8

3.1 DRAINS Modelling 8

3.2 Pre-development Flow Rates 9

4. POST-DEVELOPMENT SCENARIO 10

4.1 Sub-catchment Areas 10

4.2 DRAINS Parameters 11

5. STORMWATER MANAGEMENT STRATEGY 12

5.1 Stormwater Detention System 12

5.2 Series of Smaller Stormwater Detention Basins 14

5.3 Discharge into Willunga Creek 14

6. STORMWATER RUNOFF QUALITY MANAGEMENT 16

LIST OF TABLES

Table 3.1 Pre-development flow rates for 0.2 EY and 1% AEP events 9

Page 4: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE II

Table 4.1 Sub-catchment areas and impervious area 11 Table 5.1 Detention basin volumes 13 Table 5.2 Peak flow reductions 13

LIST OF FIGURES

Figure 1.1 Site Plan 3 Figure 5.1 Topography of the site 15

APPENDICES

Appendix A Catchment Plans Appendix B Catchment Brakdown and weighted Impervious Area

Page 5: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE III

EXECUTIVE SUMMARY

Fyfe was engaged by Renewal SA to undertake a stormwater assessment of the Aldinga Structure Plan located on the north-western side of the intersection between Main South Road and Aldinga Beach Road. Council has stipulated the outflow rates from the site after the development (post-development scenario) shall not exceed the pre-development conditions. The flow rates shall be restricted to both 0.2 Exceedances per Year (EY) and 1% Annual Exceedance Probability (AEP) storm. Fyfe undertook hydrological assessment for the pre-development and post-development scenarios to determine the respective flow rates under a range of design storm events. On site stormwater detention basin are required to restrict the post-development flow rates to the pre-development conditions. The required detention basin storage to throttle back the flow rates to the pre-development conditions are tabulated in Table i.

Table i Detention basin volumes

Sub-catchment Bain location Required detention volume (m3)

P1 and P2 North-eastern side of the intersection between How Road and Aldinga Beach Road

26,000

P3 North-western corner of the triangular portion of the site

3,400

P4 South-eastern side of the triangular portion of the site

660

The footprint of the basins depicted on Drawing 65269-1-1-CV-SK02 indicate the total storage volume for each sub-catchment. However, Council’s preferred stormwater management is through a series of smaller basins (chain of basins) integrated with the design and accessibility of the open space network rather than one single larger area. Smaller basins have not been located and sized as part of this scope of works as there is currently no detailed layout plan of the future development. It is anticipated that smaller basins could be designed during the land division phase where such basins compliment the development outcome being sought. Such an outcome would reduce the size of the larger basins shown in this plan.

Future school site

The Consultant for the future school site on the southern side of Quinliven Road has indicated that the site will have its own stormwater management plan. Post-development flows will be throttled back to the pre-development levels for the 0.2 EY and 1% AEP before releasing out from the site. EPA and Council water quality requirements will also be achieved prior to discharging into the external drainage system (site drainage system).

Page 6: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE IV

Proposed internal stormwater drainage Strategy:

Flood flows are to be controlled to minimise inconvenience to traffic and pedestrian. The internal underground drainage network shall convey 0.2 EY flowrate for roads (minor system). The 1% AEP storm is to be managed within safe flood width and depth limitations through the road network (major system). In locations where no defined overland flowpath exists, the primary underground drainage network shall convey a 1% AEP flowrate. Because of the possible level difference between the site surface level and future rail corridor, Council has requested no underground and permanent drainage system within the rail corridor. However some temporary drainage system and flowpath for major event can be provided.

Water quality

Principles of water sensitive urban design (WSUD) are proposed to ensure that the runoff generated by the proposed development is treated within the site before discharging into the existing Council drainage network. The adoption of WSUD principles will improve amenity while also providing environmental enhancement. The installation of WSUD devices such as rain gardens, road side bio-retention systems, sedimentation basins, swales should be considered in the development of open space areas in order for the proposed development to enhance the amenity for the local community.

Page 7: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 1

1. INTRODUCTION

1.1 Background

The aim of this report is to undertake a stormwater assessment of the Renewal SA site located on the north-western side of the intersection between Main South Road and Aldinga Beach Road. The stormwater assessment includes the following:

Investigate the pre-development scenario stormwater outflows from the site under a range of design storm events;

Investigate any capacity constraints/ discharge restrictions within the existing stormwater disposal network to support the Structure Plan area and determine the required stormwater detention volume to achieve the restricted flowrates after the development. This also includes the management of post-development runoff from the site;

Investigate the potential to use land within the Structure Plan area for stormwater management, including Water Sensitive Urban Design (WSUD) principles.

1.2 Subject Site

The subject site covers a total area of approximately 94.1 hectares of farm land on the north-western side of the intersection of Main South Road and Aldinga Beach Road (Figure 1.1). A 26 metre wide SAPN easement runs from the west to the east. The site naturally drains towards the south-western corner and discharges into the existing How Road basin. The basin is located on the south-western side of the How Road/Aldinga Beach Road intersection. The inlet to the basin is via a (1200W x 750D) RCBC and a swale. The basin discharges into a smaller basin downstream and into a swale. The swale is in an easement and not within Council owned property. The swale does not have adequate capacity to convey the outflow rates from the basins. Council mentioned that there is no land available for any extension to increase the conveyance capacity of the swale. The How Road basin is also at capacity and cannot accept any addition flows from the site.

The northern side triangular portion of the site drains into Port Road and Quinliven Road. The Council stormwater drainage system was located in Quinliven Road.

Page 8: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 2

1.2.1 Land division

There are likely to be a number of separate land divisions that will not require open space provision. The preliminary analysis as follow:

School 14 ha Private school expansion 3 ha Rail corridor 13.5 ha Park n ride 2.5 ha Bus interchange 1 ha Road widening (30 m Main South Road) 2.78 ha Road widening (13.5 m Aldinga Beach Road) 0.36 ha Road widening (5 m How Road) 0.36 ha Total Excluded Land 38.50 ha Remaining Land (including open space) 56.6 ha

The future school site as required by the Department of Education is on the southern side of Quinliven Road. The site covers a total area of 14 hectares. The concept design of the school site was undertaken by Aurecon, however the concept plan was not made available to Fyfe for the purpose of the Study and therefore the hydrological modelling for the catchment has been proceeded based on the meeting with the Aurecon engineer on 7 February 2019. Aurecon confirmed that the school site will have its own stormwater management plan. Post-development flows will be throttled back to the pre-development levels for the 0.2 EY and 1% AEP before releasing out from the site. EPA and Council water quality requirements will also be achieved prior to discharging into the external drainage system.

1.3 Legal Points of Discharge

The legal points of the discharge are proposed based on the natural topography of the site.

1.3.1 Site on the southern side of Quinliven Road

The proposed stormwater drainage outlet system is to be extended to a large existing junction box located on the south-eastern corner of the intersection between How Road and Aldinga Beach Road. The outlet from the junction box is a (1200W x 750D) RCBC which drains into the How Road basin.

1.3.2 Site on the northern side of Quinliven Road (western side of the railway corridor)

The outlet from the detention basin for the sub-catchment will drain into the Council drainage system in Port Road at the northern corner of the site.

Page 9: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 3

1.3.3 Site on the northern side of Quinliven Road (eastern side of the railway corridor)

The outlet from the detention basin for the sub-catchment will drain into the Council drainage system in Quinliven Road.

Figure 1.1 Site Plan

Page 10: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 4

1.4 Flood Hazard

Whilst floodplain mapping of the subject site is not available, it is not expected that the development would be subject to flood hazard as it is located in naturally higher terrain.

1.5 Design Basis

The stormwater management strategy for the site, as outlined in this document has been developed using guidelines contained in the following documents:

Australian Rainfall and Runoff 2016 Stormwater Management Design Guide, City of Onkaparinga Queensland Urban Drainage Manual (QUDM) 2013 Department of Planning, Transport and Infrastructure (DPTI) Stormwater Design DD300 Using MUSIC in Sydney’s Drinking Water Catchment, A Sydney Catchment Authority Standard Water sensitive urban design-creating more liveable and water sensitive cities in South Australia.

More specifically, the stormwater management plan has been prepared with consideration of the requirements provided by the City of Onkaparinga.

1.6 Council Requirements and Service Standard

Council requirements for stormwater management for the site were based on the meeting between Fyfe and Council engineers on 17 January 2019, and the Council Stormwater Management Design Guide 2017. These are listed below:

Outflow rates from the site after the development (post-development scenario) shall not exceed the pre-development conditions. The flow rates shall be restricted to both 0.2 Exceedances per Year (EY) and 1% Annual Exceedance Probability (AEP) storm.

Flood flows are to be controlled to minimise inconvenience to traffic and pedestrian;

The primary underground drainage network shall convey 0.2 EY flowrate for roads (minor system).

1% AEP storm is to be managed within safe flood width and depth limitations through the road network (major system).

In locations where no defined overland flow path exists, the primary underground drainage network shall convey a 1% AEP flowrate.

No underground and permanent drainage system to be constructed within the rail corridor. The outlet drainage system from the eastern side of the rail corridor can be on the southern side of the site. Temporary drainage system such as overland flow paths and temporary water features can be constructed.

Page 11: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 5

Velocity depth product (V x D) for surface flow shall be less than 0.4 m2/s for pedestrians (footpaths and pedestrian routes) and (V x D) < 0.6 m2/s for vehicles (roadway)

The secondary drainage network comprising overland flow paths in roadways, reserves, open drains and swales, and in combination with the primary drainage network, shall convey a 1% AEP flowrate.

Implement the principles of Water Sensitive Urban Design (WSUD) and stormwater reuse.

Stormwater quality is to be achieved through the use of WSUD principles to meet Council and EPA water quality targets and minimise the impacts of erosion and sedimentation on the environment. Council’s water quality target are:

80% reduction in total suspended solids (TSS) 60% reduction in total nitrogen (TN) 45% reduction in total phosphorus (TP) 90% reduction in gross pollutants

Ensure that the proposed development will not impact adversely on the surrounding environment and existing residences during and after construction.

Page 12: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 6

2. STORMWATER DRAINAGE MODELLING

The aim of the stormwater drainage modelling is to determine the pre-development flow rates, post-development flow rates and to model the detention system required to restrict the post-development flow rates to pre-development conditions. The pre-development scenario is modelled using the initial loss/ continuing loss model and the post-development scenario is modelled in the ILSAX type hydrological model in the DRAINS program. The model combined various sub-catchments flows and routed through a pipe and channel system. Calculations are performed at a specified time after the start of each storm. At each time step, a hydraulic grade line analysis is performed throughout a drainage network, and flow rates and water levels are determined.

2.1 Data Source

The data sources used to undertake the hydrological assessment are as follows:

Aerial photography of the site Cadastral map Survey information The Bureau of Meteorology website Australian Rainfall Runoff 2016 Australian Rainfall Runoff (ARR) Data Hub.

2.2 Rainfall Data

2.2.1 Design rainfall

The Australian Rainfall and Runoff (ARR) 2016 rainfall Intensity Frequency Duration (IFD) system is used to estimate the rainfall data. The latest rainfall depths to be used in design and analysis procedures were obtained from the Bureau of Meteorology website (www.bom.gov.au/water/designRainfalls/revised-ifd/?year=2016) and temporal patterns were obtained from the ARR Data Hub. Rainfall IFD data plays an integral part in the design and assessment of hydraulic structures and the Bureau provides this as part of ARR 2016.

IFD data was prepared for Aldinga utilising the tool provided by the Bureau of Meteorology for the preparation of ARR 2016 design rainfalls.

The following rainfall events were considered for the stormwater drainage modelling and assessments of the study area:

Page 13: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 7

1% Annual Exceedance Probability (AEP) event, also commonly referred to as the 100 year Average Recurrence Interval (ARI) event. The rainfall event has a 1% probability of occurring or being exceeded within any given year;

10% AEP, also commonly referred to as the 9.49 years ARI event; 0.2 Exceedances per Year (EY), also commonly referred as the 5 years ARI event.

ARR 2016 nominates up to 10 rainfall patterns for a given AEP event/duration. Storm duration ranging from 5 minutes to 72 hours, each with an ensemble of 10 different rainfall temporal patterns, have been assessed using DRAINS. The peak flows and associated drain sizing correspond to the median storm from the critical rainfall ensemble.

Page 14: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 8

3. PRE-DEVELOPMENT SCENARIO

The pre-development scenario is modelled using the initial loss/continuing loss model and the post-development scenario is modelled in the ILSAX type hydrological model in DRAINS program. The aim of the pre-development hydrological analysis is to determine the 0.2 EY and 1% AEP pre-development flow rates generated from the site. As per the Council requirement, it is proposed to restrict the post-development flow rates to 0.2 EY and 1% AEP pre-development conditions.

3.1 DRAINS Modelling

Initial loss (IL) and continuing loss (CL) model in DRAINS was used to model the pre-development scenario. The initial and continuing loss model in DRAINS uses effective impervious area (EIA) rather than directly connected paved area. EIA is made up of part of the directly connected impervious area and some of the indirectly connected impervious area.

The design rainfall procedures as outlined in ARR recommend using IL and CL model. The IL and CL values selected for pre-development scenario are based on literature from ARR 2016, Book 5, Chapter 3 (Section 3.5.3).

Effective Impervious Area (EIA) Initial Loss 1mm : (ARR Section 3.5.3.1.2) Effective Impervious Area (EIA) Continuing Loss 0 : (ARR Section 3.5.3.1.2) Remaining area Initial Loss 30 mm/hr : (ARR Figure 3.18) Remaining area Continuing Loss 4 mm/hr : (ARR Section 3.5.3.2.2)

3.1.1 Overland flow travel time

Kinematic wave equation is used to calculate the sheet flow travel time for flow length of 200 metre (maximum) as recommended by QUDM for 0-1% bushland or grassland. It is assumed that the flow will be concentrated after this point and will no longer be a sheet flow. The remaining distance of assumed concentrated overland flow from the end of the adopted sheet flow to the downstream end is calculated using Figure 4.8 of QUDM (Flow travel time in pipes and channel). The obtained flow travel time from the chart was multiplied by 3, as recommended by QUDM for natural channel. Sheet flow travel time is shorter for the northern side triangular portion of the site because of the site gradient.

The Manning’s n-value (retarding coefficient) selected for the existing condition is 0.17. The site is a cultivated soils and is assumed that the residue is greater than 20% (soil covered by crop residue after field operations).

Page 15: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 9

3.2 Pre-development Flow Rates

The subject site is sub divided into three main sub-catchments (A1, A2 and A3) based on the discharge locations. Refer Drawing 65269-1-1-CV-SK01 in Appendix A for pre-development catchment. The pre-development flow rates generated by the site are tabulated in Table 3.1.

Table 3.1 Pre-development flow rates for 0.2 EY and 1% AEP events

Sub-catchment Discharge location Pre-development flow rate (m3/s)

0.2 EY 1% AEP

A1

South-western corner of the site (How Road basin)

0.400 2.79

A2 Northern corner of the site (Port Road drainage system)

0.042 0.357

A3 Quinliven Road drainage system 0.035 0.241

Page 16: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 10

4. POST-DEVELOPMENT SCENARIO

The post-development scenario was modelled in the ILSAX type hydrological model in DRAINS program. The aim of the modelling was to determine the detention storage volume required to restrict the post-development flow rates to the pre-development conditions as stipulated by Council.

4.1 Sub-catchment Areas

The proposed development has been divided into two broad sub-catchments based on the discharge locations. The catchment to the south of the future school site will drain into the How Road stormwater basin and the site on the northern side of Quinliven Road will drain into the watercourse on the north.

If the land (excluding site and rail corridor) was used exclusively for residential purposes, it is estimated that this would result in a potential yield of 1000 new dwellings, assuming housing densities in the order of 15 dwellings per hectare.

Refer Drawing 65269-1-CV-SK01 in Appendix A for post-development catchment plan.

The impervious and pervious area percentage for the ILSAX hydraulic modelling is based on the following assumptions:

4.1.1 Development Site

As per the Council requirement, for the post-development modelling, the impervious area and pervious area for the development (excluding open space, railway corridor, existing road widening) are:

Minimum Residential impervious area = 75% Pervious area = 25% (No supplementary area considered as per Council requirement)

4.1.2 Rail Corridor

The proposed site comprises of a 100 metre wide corridor (equating to 14 hectares) for the purpose of accommodating a future rail line. It is assumed that 10% of the area within the corridor will be impervious.

4.1.3 Open Space

Open space contribution is assumed to be minimum 12.5% of the site. It is assumed that 20% of the open space including basin(s) area will be impervious.

Page 17: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 11

4.1.4 Road Widenings

Main South Road, Aldinga Beach Road and How Road need to be widened. Main South Road needs to be widened by 30 metres in accordance with the Department of Planning, Transport and Infrastructures requirements, and Aldinga Beach Road and How road by 13.5 metres and 5 metres respectively.

4.1.5 Catchments contributing to the internal drainage system

All 4 sub-catchments are sub-divided based on the land use as mentioned in Section 1.2.1. The detailed breakdown of the sub-catchments is attached in Appendix B. The summary of the contributing sub-catchment areas and impervious percentages are tabulated in Table 4.1.

Table 4.1 Sub-catchment areas and impervious area

Sub-catchments Contributing catchment area

(Ha)

Weighted impervious area percentage (Ha)

Discharge location

P1 38.71 64% How Road basin

P2 23.29 47% How Road basin

P3 7.8 68% Port Road drainage system (northern corner of the site)

P4 3.8 54% Quinliven Road drainage system

4.2 DRAINS Parameters

4.2.1 Depression Storage

Depression storage is typically used to account for the initial loss in depth of rainfall that is assumed to be retained in depression on a catchment surface and is subject to evaporation. In the ILSAX hydrological model, this loss is subtracted after continuing infiltration losses because it is assumed to occur after infiltration. All remaining rainfall is considered to runoff.

The depression storages considered for the project are as follows:

Paved (impervious) area depression storage = 1mm Supplementary area depression storage = 1mm Grassed (pervious) area depression storage = 5mm Grassed (pervious) area depression storage – reserves = 10 mm

4.2.2 Antecedent moisture content (AMC)

The AMC is used in loss calculations by the ILSAX type hydrology model, specifying the wetness or dryness of soils in a catchment at the start of a storm. The AMC is determined based on the expected rainfall in the 5 days prior to a storm. AMC of 2.5 was used in the model, as recommended by Council.

Page 18: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 12

5. STORMWATER MANAGEMENT STRATEGY

Stormwater drainage system of the site shall be constructed according to the Council stormwater drainage guidelines and the EPA water quality requirement. The drainage system of the site is proposed to consist of a combination of minor drainage system (0.2 EY) and the major drainage system (1% AEP). The gap flow rate between the major and the minor system is accommodated safely within the road reserve and overland flow paths. No overflows and upwelling from pits are permitted for minor event. All low points on the road surface shall be designed for a 1% AEP flow rates. Because of the possible level difference between the site surface level and future rail corridor, Council has requested no underground and permanent drainage system within the rail corridor. However some temporary drainage system and flowpath for major event can be provided.

Council has stipulated the outflow rates from the site after the development (post-development scenario) shall not exceed the pre-development conditions. On site stormwater detention basins are required to restrict the post-development flow rates to the pre-development conditions.

Options to manage the post-development flows includes:

Stormwater detention system, Series of smaller stormwater detention basins, and Discharge into Willunga Creek.

5.1 Stormwater Detention System

Council has stipulated the outflow rates from the site after the development (post-development scenario) shall not exceed the pre-development conditions. On site stormwater detention basins are required to restrict the post-development flow rates to the pre-development conditions.

The topography of the site indicates that majority of the land on the southern side of Quinliven Road drains toward the south-western corner of the site. One of the options to manage the post-development flows is to construct a large stormwater detention basin on the south-western side of the site.

On-site stormwater detention systems are proposed to restrict the post-development flow rates to the prescribed conditions. The detention basins depths will be governed by the existing drainage outlet invert levels and new inlet pipes. To determine the approximate surface area required for detention basins, it is assumed that the detention basins will be a maximum 1.5m deep with 1(V):5(H) side batter. Vehicular access shall be provided to basins for maintenance purposes. The stormwater detention basins are to be designed according to Council’s Stormwater Management Design Guide. Due to the natural topography of the northern side of the sub-catchment P3, the detention basin in the area will require mounding to retain water above the existing ground level.

Page 19: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 13

5.1.1 Basin Seepage

Hydraulic conductivity adopted in DRAINS modelling of basins assumed the native soil is of heavy clay. Heavy clay soils show hydraulic conductivity values in the range 1 x 10-8 to 1 x 10-6 m/s.

For the detention basin in this study, a hydraulic conductivity of 3.5 x 10-7 m/s has been adopted.

5.1.2 Basin Storage Volume

The detention basin storage capacities for the sub-catchments to restrict the post-development flow rates to the pre-development conditions are shown in Table 5.1.

Table 5.1 Detention basin volumes

Sub-catchment Location Required detention volume (m3)

P1 and P2 North-eastern side of the intersection between How Road and Aldinga Beach Road

26,000

P3 North-western corner of the triangular portion of the site

3,200

P4 South-eastern side of the triangular portion of the site

660

The peak flow reductions are provided in Table 5.2

Table 5.2 Peak flow reductions

Sub-catchment Pre-development flow rate Post-development flow rate

0.2EY (m3/s) 1% AEP (m3/s) 0.2EY (m3/s) 1% AEP (m3/s)

P1 and P2 0.400 2.79 0.308 2.604

P3 0.042 0.357 0.040 0.290

P4 0.032 0.241 0.225

The basin will discharge via underground pipes/orifices and weir/spillway. However for the minor event, the basin shall not discharge on the surface via weir/spillway. A series of orifices will be required at the basin outlets to restrict the flow rates for both minor and major events.

Stormwater detention basins for the sub-catchments are depicted on Drawing 65269-1-1-CV-SK02 in Appendix A. The footprints of the basins indicate the total required storage volume for each sub-catchment.

Page 20: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 14

5.2 Series of Smaller Stormwater Detention Basins

Council’s preferred stormwater management is through a series of smaller basins (chain of basins) integrated with the design and accessibility of the open space network, rather than one single larger area. Smaller basins have not been located and sized as part of this scope of works as there is currently no detailed layout plan. It is anticipated that smaller basins could be designed during the land division phase where such basins compliment the development outcome being sought. Such an outcome would reduce the size of the larger basins shown in this plan.

5.3 Discharge into Willunga Creek

Desktop assessment was undertaken to investigate whether the post-development runoff from the southern side of Quinliven Road can be drained into Willunga Creek on the northern side of the site. The proposed large detention basin could be reduced by directing site runoff towards the north and discharging into the creek. The investigation indicates that the creek should have the capacity to cater for the flows from the site. The time of concentration of the flow arriving to the creek is a lot longer than the flow travel distance from the site. The peak of the hydrograph from the site will pass well before the peak from the upstream catchment arrives. Therefore, it can be said that the runoff from the site will have minimal contribution on the creek peak flow. Further hydrological study is required to determine the flows in the creek, creek capacity and impact due to site runoff.

The topography of the site indicates that the site catchment on the southern side of the future school site drains towards the south. It is a possible option to convey the runoff from the catchment towards the northern side and discharge into the creek via underground drainage system. However the drainage system would be at significant depth and the costs associated with it would need to be investigated against the additional land that could be made available with this option

Refer Figure 5.1 for the profile of the site between the creek and Aldinga Beach Road. The ridge line on the site is approximately where the red arrow is.

Page 21: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 15

Source: Google Earth

Figure 5.1 Topography of the site

Page 22: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

65269-1 FINAL RENEWAL SA ALDINGA STRUCTURE PLAN STORMWATER MANAGEMENT MASTERPLAN

65269 (REVISION D) 24/05/2019 PAGE 16

6. STORMWATER RUNOFF QUALITY MANAGEMENT

The application of water sensitive urban design (WSUD) principles comprises an approach to urban planning and design that provides sustainable solutions for integrating land development and the natural water cycle. In its broadest context, WSUD includes all aspects of integrated urban water cycle management such as the harvesting and/or treatment of stormwater and wastewater treatment and re-use with the view of minimising the dependency of the community on mains water. In many cases WSUD stormwater measures can enhance a landscape while providing treatment and flood conveyance. The intent is to reduce flow rates, provide filtration and provide sedimentation of stormwater that will prevent the majority of stormwater pollutants from leaving the study area.

The stormwater management systems shall minimise the discharge of sediments, suspended solids, organic matter, nutrients, bacteria, litter and other contaminants to the stormwater system. This can be achieved through demonstrating how particular water quality requirements will be achieved.

It is a Council requirement that outflows from new developments has a pollution load reduction as outlined in Section 1.6.

These water quality improvements can be achieved through the application of WSUD concepts in conjunction with more conventional stormwater management strategy such as temporary storage detention basins, swales, bio-retention systems, raingardens, vegetative buffer strips, gross pollutant traps etc.

The installation of rainwater tanks for all newly built houses is mandatory in South Australia. Runoff generated from the roof area of each dwelling will be harvested and stored in rainwater tanks for non-potable uses such as toilet flushing. The use of rainwater tanks will help in reducing the stormwater pollutants and reduce the mains water demand.

Page 23: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

APPENDIX A CATCHMENT PLANS

Page 24: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

WM

E

E

E

E

E

E

E

EE

E

E

65269-1-1-CV-SK01.DWG

PRELIMINARY COPYNOT TO BE USED FOR

CONSTRUCTION PURPOSES

ALDINGA FRAMEWORK PLANALDINGA

PRE-DEVELOPMENT SCENARIOSTORMWATER CATCHMENT 65269-1-1-CV-SK01 B

PRELIMINARY

CITY OF ONKAPARINGA

A 25.01.19 PRELIMINARY BXSB 7.03.19 CATCHMENT BOUNDARY REVISED BXS

P:\A

DE

LAID

E\6

0000

\650

00\6

5269

\652

69-1

ALD

ING

A S

TRU

CTU

\09_

CA

D\0

902_

CV

ST\

0902

03_W

OR

KIN

G\D

RA

WIN

GS

\652

69-1

-1-C

V-S

K01

.DW

G7/

03/2

019

4:08

:34

PM

DESCRIPTIONDATEREV. APP'D.

STATUS

DRAWING No.

DRN.

REV

CAD. REF

DRAWN

SURVEYED COUNCIL

DESIGNED

APP'D. APP'D. DATE

CLIENT:

DEV. NO.

DRAFTING CHECK

DESIGN CHECK FYFE PTY LTDABN 57 008 116 130LEVEL 1, 124 SOUTH TERRACEADELAIDE SA 5000GPO BOX 2450 ADELAIDE SA 5001

[email protected]

T (08) 8201 9600F (08) 8201 9650

AutoCAD SHX Text
ALDINGA BEACH ROAD
AutoCAD SHX Text
ALDINGA BEACH ROAD
AutoCAD SHX Text
ALDINGA BEACH ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
HOW ROAD
AutoCAD SHX Text
HOW ROAD
AutoCAD SHX Text
HOW ROAD
AutoCAD SHX Text
QUINLIVEN ROAD
AutoCAD SHX Text
QUINLIVEN ROAD
AutoCAD SHX Text
PORT ROAD
AutoCAD SHX Text
PORT ROAD
AutoCAD SHX Text
OLD COACH ROAD
AutoCAD SHX Text
PORT ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
ALDINGA ROAD
AutoCAD SHX Text
ALDINGA ROAD
AutoCAD SHX Text
PLAINS ROAD
AutoCAD SHX Text
LACEY DRIVE
AutoCAD SHX Text
RAINBIRD COURT
AutoCAD SHX Text
DOLPHIN BLVD
AutoCAD SHX Text
MEADOW BANK WAY
AutoCAD SHX Text
BLUEPOINT WAY
AutoCAD SHX Text
26
AutoCAD SHX Text
27
AutoCAD SHX Text
28
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
29
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
28
AutoCAD SHX Text
28
AutoCAD SHX Text
28
AutoCAD SHX Text
27
AutoCAD SHX Text
27
AutoCAD SHX Text
27
AutoCAD SHX Text
26
AutoCAD SHX Text
26
AutoCAD SHX Text
26
AutoCAD SHX Text
25
AutoCAD SHX Text
25
AutoCAD SHX Text
24
AutoCAD SHX Text
24
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
22
AutoCAD SHX Text
22
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.93
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.94
AutoCAD SHX Text
30.96
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.93
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.94
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.86
AutoCAD SHX Text
30.86
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.85
AutoCAD SHX Text
30.82
AutoCAD SHX Text
30.84
AutoCAD SHX Text
30.86
AutoCAD SHX Text
30.82
AutoCAD SHX Text
30.80
AutoCAD SHX Text
30.82
AutoCAD SHX Text
30.78
AutoCAD SHX Text
30.74
AutoCAD SHX Text
30.70
AutoCAD SHX Text
30.73
AutoCAD SHX Text
30.70
AutoCAD SHX Text
30.67
AutoCAD SHX Text
30.65
AutoCAD SHX Text
30.66
AutoCAD SHX Text
30.62
AutoCAD SHX Text
30.61
AutoCAD SHX Text
30.57
AutoCAD SHX Text
30.57
AutoCAD SHX Text
30.55
AutoCAD SHX Text
30.54
AutoCAD SHX Text
30.51
AutoCAD SHX Text
30.52
AutoCAD SHX Text
30.49
AutoCAD SHX Text
30.47
AutoCAD SHX Text
30.46
AutoCAD SHX Text
30.45
AutoCAD SHX Text
30.45
AutoCAD SHX Text
30.41
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.52
AutoCAD SHX Text
30.47
AutoCAD SHX Text
30.44
AutoCAD SHX Text
30.45
AutoCAD SHX Text
30.44
AutoCAD SHX Text
30.47
AutoCAD SHX Text
30.36
AutoCAD SHX Text
30.33
AutoCAD SHX Text
30.34
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.41
AutoCAD SHX Text
30.36
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.41
AutoCAD SHX Text
30.38
AutoCAD SHX Text
30.38
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.36
AutoCAD SHX Text
30.38
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.35
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.33
AutoCAD SHX Text
30.33
AutoCAD SHX Text
30.31
AutoCAD SHX Text
30.26
AutoCAD SHX Text
30.24
AutoCAD SHX Text
30.27
AutoCAD SHX Text
30.26
AutoCAD SHX Text
30.25
AutoCAD SHX Text
29.98
AutoCAD SHX Text
30.25
AutoCAD SHX Text
30.24
AutoCAD SHX Text
30.19
AutoCAD SHX Text
30.19
AutoCAD SHX Text
30.17
AutoCAD SHX Text
30.18
AutoCAD SHX Text
30.15
AutoCAD SHX Text
30.15
AutoCAD SHX Text
30.11
AutoCAD SHX Text
30.08
AutoCAD SHX Text
30.08
AutoCAD SHX Text
30.01
AutoCAD SHX Text
30.01
AutoCAD SHX Text
29.97
AutoCAD SHX Text
29.99
AutoCAD SHX Text
29.95
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.92
AutoCAD SHX Text
29.93
AutoCAD SHX Text
29.92
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.89
AutoCAD SHX Text
29.88
AutoCAD SHX Text
29.77
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.88
AutoCAD SHX Text
29.86
AutoCAD SHX Text
29.88
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.84
AutoCAD SHX Text
29.89
AutoCAD SHX Text
29.81
AutoCAD SHX Text
29.77
AutoCAD SHX Text
29.76
AutoCAD SHX Text
29.80
AutoCAD SHX Text
29.74
AutoCAD SHX Text
29.68
AutoCAD SHX Text
29.66
AutoCAD SHX Text
29.63
AutoCAD SHX Text
29.60
AutoCAD SHX Text
29.56
AutoCAD SHX Text
29.53
AutoCAD SHX Text
29.75
AutoCAD SHX Text
29.51
AutoCAD SHX Text
29.47
AutoCAD SHX Text
29.44
AutoCAD SHX Text
29.46
AutoCAD SHX Text
29.47
AutoCAD SHX Text
29.44
AutoCAD SHX Text
29.44
AutoCAD SHX Text
29.47
AutoCAD SHX Text
27.26
AutoCAD SHX Text
22.24
AutoCAD SHX Text
21.91
AutoCAD SHX Text
21.90
AutoCAD SHX Text
29.40
AutoCAD SHX Text
29.46
AutoCAD SHX Text
29.14
AutoCAD SHX Text
29.15
AutoCAD SHX Text
29.06
AutoCAD SHX Text
29.09
AutoCAD SHX Text
28.89
AutoCAD SHX Text
28.74
AutoCAD SHX Text
28.61
AutoCAD SHX Text
28.62
AutoCAD SHX Text
28.61
AutoCAD SHX Text
28.56
AutoCAD SHX Text
28.50
AutoCAD SHX Text
28.42
AutoCAD SHX Text
28.34
AutoCAD SHX Text
28.25
AutoCAD SHX Text
28.21
AutoCAD SHX Text
28.14
AutoCAD SHX Text
28.03
AutoCAD SHX Text
27.88
AutoCAD SHX Text
27.81
AutoCAD SHX Text
27.77
AutoCAD SHX Text
27.78
AutoCAD SHX Text
27.80
AutoCAD SHX Text
27.84
AutoCAD SHX Text
27.84
AutoCAD SHX Text
27.94
AutoCAD SHX Text
27.94
AutoCAD SHX Text
SP
AutoCAD SHX Text
SP
AutoCAD SHX Text
SP
AutoCAD SHX Text
SP
AutoCAD SHX Text
27.73
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.84
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.35
AutoCAD SHX Text
30.26
AutoCAD SHX Text
29.93
AutoCAD SHX Text
29.70
AutoCAD SHX Text
29.78
AutoCAD SHX Text
30.04
AutoCAD SHX Text
30.13
AutoCAD SHX Text
28.73
AutoCAD SHX Text
28.77
AutoCAD SHX Text
27.66
AutoCAD SHX Text
27.06
AutoCAD SHX Text
25.74
AutoCAD SHX Text
24.06
AutoCAD SHX Text
22.81
AutoCAD SHX Text
22.15
AutoCAD SHX Text
22.80
AutoCAD SHX Text
22.23
AutoCAD SHX Text
22.11
AutoCAD SHX Text
A12 DP94045
AutoCAD SHX Text
A2 DP71576
AutoCAD SHX Text
A61 DP81273
AutoCAD SHX Text
RAIL CORRIDOR EXTENT
AutoCAD SHX Text
PROPOSED RAILWAY
AutoCAD SHX Text
RAIL CORRIDOR EXTENT
AutoCAD SHX Text
ALDINGA CFS
AutoCAD SHX Text
D47144
AutoCAD SHX Text
D81273
AutoCAD SHX Text
D58709
AutoCAD SHX Text
D71576 GALILEE CATHOLIC SCHOOL
AutoCAD SHX Text
CATCHMENT AREA (A1) = 68.50 Ha CULTIVATED SOIL
AutoCAD SHX Text
FUTURE SCHOOL 5.7 Ha
AutoCAD SHX Text
CATCHMENT AREA (A2) = 5.25 Ha
AutoCAD SHX Text
EXISTING SYSTEM
AutoCAD SHX Text
CATCHMENT BOUNDARY
AutoCAD SHX Text
CATCHMENT AREA (A2) = 6.35 Ha
AutoCAD SHX Text
FUTURE SCHOOL 6.33 Ha
AutoCAD SHX Text
HOW ROAD BASIN
AutoCAD SHX Text
0
AutoCAD SHX Text
100
AutoCAD SHX Text
200
AutoCAD SHX Text
250m
AutoCAD SHX Text
1 : 10000 (A3)
AutoCAD SHX Text
1 : 5000 (A1)
Page 25: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

WM

E

E

E

E

E

E

E

EE

E

E

65269-1-1-CV-SK02.DWG

PRELIMINARY COPYNOT TO BE USED FOR

CONSTRUCTION PURPOSES

ALDINGA FRAMEWORK PLANALDINGA

POST-DEVELOPMENT SCENARIOSTORMWATER CATCHMENT 65269-1-1-CV-SK02 B

PRELIMINARY

CITY OF ONKAPARINGA

A 25.01.19 PRELIMINARY BXSB 7.03.19 CATCHMENT BOUNDARY FOR P1 REVISED BXS

P:\A

DE

LAID

E\6

0000

\650

00\6

5269

\652

69-1

ALD

ING

A S

TRU

CTU

\09_

CA

D\0

902_

CV

ST\

0902

03_W

OR

KIN

G\D

RA

WIN

GS

\652

69-1

-1-C

V-S

K02

.DW

G7/

03/2

019

4:03

:59

PM

DESCRIPTIONDATEREV. APP'D.

STATUS

DRAWING No.

DRN.

REV

CAD. REF

DRAWN

SURVEYED COUNCIL

DESIGNED

APP'D. APP'D. DATE

CLIENT:

DEV. NO.

DRAFTING CHECK

DESIGN CHECK FYFE PTY LTDABN 57 008 116 130LEVEL 1, 124 SOUTH TERRACEADELAIDE SA 5000GPO BOX 2450 ADELAIDE SA 5001

[email protected]

T (08) 8201 9600F (08) 8201 9650

AutoCAD SHX Text
ALDINGA BEACH ROAD
AutoCAD SHX Text
ALDINGA BEACH ROAD
AutoCAD SHX Text
ALDINGA BEACH ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
HOW ROAD
AutoCAD SHX Text
HOW ROAD
AutoCAD SHX Text
HOW ROAD
AutoCAD SHX Text
QUINLIVEN ROAD
AutoCAD SHX Text
QUINLIVEN ROAD
AutoCAD SHX Text
PORT ROAD
AutoCAD SHX Text
PORT ROAD
AutoCAD SHX Text
OLD COACH ROAD
AutoCAD SHX Text
PORT ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
MAIN SOUTH ROAD
AutoCAD SHX Text
ALDINGA ROAD
AutoCAD SHX Text
ALDINGA ROAD
AutoCAD SHX Text
PLAINS ROAD
AutoCAD SHX Text
LACEY DRIVE
AutoCAD SHX Text
RAINBIRD COURT
AutoCAD SHX Text
DOLPHIN BLVD
AutoCAD SHX Text
MEADOW BANK WAY
AutoCAD SHX Text
BLUEPOINT WAY
AutoCAD SHX Text
26
AutoCAD SHX Text
27
AutoCAD SHX Text
28
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
29
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
30
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
28
AutoCAD SHX Text
28
AutoCAD SHX Text
28
AutoCAD SHX Text
27
AutoCAD SHX Text
27
AutoCAD SHX Text
27
AutoCAD SHX Text
26
AutoCAD SHX Text
26
AutoCAD SHX Text
26
AutoCAD SHX Text
25
AutoCAD SHX Text
25
AutoCAD SHX Text
24
AutoCAD SHX Text
24
AutoCAD SHX Text
23
AutoCAD SHX Text
23
AutoCAD SHX Text
22
AutoCAD SHX Text
22
AutoCAD SHX Text
29
AutoCAD SHX Text
29
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.93
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.94
AutoCAD SHX Text
30.96
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.93
AutoCAD SHX Text
30.92
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.94
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.86
AutoCAD SHX Text
30.86
AutoCAD SHX Text
30.91
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.85
AutoCAD SHX Text
30.82
AutoCAD SHX Text
30.84
AutoCAD SHX Text
30.86
AutoCAD SHX Text
30.82
AutoCAD SHX Text
30.80
AutoCAD SHX Text
30.82
AutoCAD SHX Text
30.78
AutoCAD SHX Text
30.74
AutoCAD SHX Text
30.70
AutoCAD SHX Text
30.73
AutoCAD SHX Text
30.70
AutoCAD SHX Text
30.67
AutoCAD SHX Text
30.65
AutoCAD SHX Text
30.66
AutoCAD SHX Text
30.62
AutoCAD SHX Text
30.61
AutoCAD SHX Text
30.57
AutoCAD SHX Text
30.57
AutoCAD SHX Text
30.55
AutoCAD SHX Text
30.54
AutoCAD SHX Text
30.51
AutoCAD SHX Text
30.52
AutoCAD SHX Text
30.49
AutoCAD SHX Text
30.47
AutoCAD SHX Text
30.46
AutoCAD SHX Text
30.45
AutoCAD SHX Text
30.45
AutoCAD SHX Text
30.41
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.52
AutoCAD SHX Text
30.47
AutoCAD SHX Text
30.44
AutoCAD SHX Text
30.45
AutoCAD SHX Text
30.44
AutoCAD SHX Text
30.47
AutoCAD SHX Text
30.36
AutoCAD SHX Text
30.33
AutoCAD SHX Text
30.34
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.41
AutoCAD SHX Text
30.36
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.41
AutoCAD SHX Text
30.38
AutoCAD SHX Text
30.38
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.36
AutoCAD SHX Text
30.38
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.35
AutoCAD SHX Text
30.39
AutoCAD SHX Text
30.37
AutoCAD SHX Text
30.33
AutoCAD SHX Text
30.33
AutoCAD SHX Text
30.31
AutoCAD SHX Text
30.26
AutoCAD SHX Text
30.24
AutoCAD SHX Text
30.27
AutoCAD SHX Text
30.26
AutoCAD SHX Text
30.25
AutoCAD SHX Text
29.98
AutoCAD SHX Text
30.25
AutoCAD SHX Text
30.24
AutoCAD SHX Text
30.19
AutoCAD SHX Text
30.19
AutoCAD SHX Text
30.17
AutoCAD SHX Text
30.18
AutoCAD SHX Text
30.15
AutoCAD SHX Text
30.15
AutoCAD SHX Text
30.11
AutoCAD SHX Text
30.08
AutoCAD SHX Text
30.08
AutoCAD SHX Text
30.01
AutoCAD SHX Text
30.01
AutoCAD SHX Text
29.97
AutoCAD SHX Text
29.99
AutoCAD SHX Text
29.95
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.92
AutoCAD SHX Text
29.93
AutoCAD SHX Text
29.92
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.89
AutoCAD SHX Text
29.88
AutoCAD SHX Text
29.77
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.88
AutoCAD SHX Text
29.86
AutoCAD SHX Text
29.88
AutoCAD SHX Text
29.90
AutoCAD SHX Text
29.84
AutoCAD SHX Text
29.89
AutoCAD SHX Text
29.81
AutoCAD SHX Text
29.77
AutoCAD SHX Text
29.76
AutoCAD SHX Text
29.80
AutoCAD SHX Text
29.74
AutoCAD SHX Text
29.68
AutoCAD SHX Text
29.66
AutoCAD SHX Text
29.63
AutoCAD SHX Text
29.60
AutoCAD SHX Text
29.56
AutoCAD SHX Text
29.53
AutoCAD SHX Text
29.75
AutoCAD SHX Text
29.51
AutoCAD SHX Text
29.47
AutoCAD SHX Text
29.44
AutoCAD SHX Text
29.46
AutoCAD SHX Text
29.47
AutoCAD SHX Text
29.44
AutoCAD SHX Text
29.44
AutoCAD SHX Text
29.47
AutoCAD SHX Text
27.26
AutoCAD SHX Text
22.24
AutoCAD SHX Text
21.91
AutoCAD SHX Text
21.90
AutoCAD SHX Text
29.40
AutoCAD SHX Text
29.46
AutoCAD SHX Text
29.14
AutoCAD SHX Text
29.15
AutoCAD SHX Text
29.06
AutoCAD SHX Text
29.09
AutoCAD SHX Text
28.89
AutoCAD SHX Text
28.74
AutoCAD SHX Text
28.61
AutoCAD SHX Text
28.62
AutoCAD SHX Text
28.61
AutoCAD SHX Text
28.56
AutoCAD SHX Text
28.50
AutoCAD SHX Text
28.42
AutoCAD SHX Text
28.34
AutoCAD SHX Text
28.25
AutoCAD SHX Text
28.21
AutoCAD SHX Text
28.14
AutoCAD SHX Text
28.03
AutoCAD SHX Text
27.88
AutoCAD SHX Text
27.81
AutoCAD SHX Text
27.77
AutoCAD SHX Text
27.78
AutoCAD SHX Text
27.80
AutoCAD SHX Text
27.84
AutoCAD SHX Text
27.84
AutoCAD SHX Text
27.94
AutoCAD SHX Text
27.94
AutoCAD SHX Text
SP
AutoCAD SHX Text
SP
AutoCAD SHX Text
SP
AutoCAD SHX Text
SP
AutoCAD SHX Text
27.73
AutoCAD SHX Text
30.40
AutoCAD SHX Text
30.84
AutoCAD SHX Text
30.88
AutoCAD SHX Text
30.35
AutoCAD SHX Text
30.26
AutoCAD SHX Text
29.93
AutoCAD SHX Text
29.70
AutoCAD SHX Text
29.78
AutoCAD SHX Text
30.04
AutoCAD SHX Text
30.13
AutoCAD SHX Text
28.73
AutoCAD SHX Text
28.77
AutoCAD SHX Text
27.66
AutoCAD SHX Text
27.06
AutoCAD SHX Text
25.74
AutoCAD SHX Text
24.06
AutoCAD SHX Text
22.81
AutoCAD SHX Text
22.15
AutoCAD SHX Text
22.80
AutoCAD SHX Text
22.23
AutoCAD SHX Text
22.11
AutoCAD SHX Text
A12 DP94045
AutoCAD SHX Text
A2 DP71576
AutoCAD SHX Text
A61 DP81273
AutoCAD SHX Text
RAIL CORRIDOR EXTENT
AutoCAD SHX Text
PROPOSED RAILWAY
AutoCAD SHX Text
RAIL CORRIDOR EXTENT
AutoCAD SHX Text
ALDINGA CFS
AutoCAD SHX Text
D47144
AutoCAD SHX Text
D81273
AutoCAD SHX Text
D58709
AutoCAD SHX Text
D71576 GALILEE CATHOLIC SCHOOL
AutoCAD SHX Text
FUTURE SCHOOL 6.33 Ha
AutoCAD SHX Text
CONNECT TO THE EXISTING SYSTEM.
AutoCAD SHX Text
GPT
AutoCAD SHX Text
CATCHMENT BOUNDARY
AutoCAD SHX Text
AREA (P1) 41.85 Ha
AutoCAD SHX Text
AREA (P3) 7.80 Ha
AutoCAD SHX Text
AREA (P4) 3.80 Ha
AutoCAD SHX Text
INTERNAL STORMWATER DRAINAGE
AutoCAD SHX Text
INDICATIVE DETENTION BASIN FOR SUB-CATCHMENTS P1 & P2
AutoCAD SHX Text
INDICATIVE DETENTION BASIN FOR SUB-CATCHMENTS P3
AutoCAD SHX Text
INDICATIVE DETENTION BASIN FOR SUB-CATCHMENTS P4
AutoCAD SHX Text
GROSS POLLUTANT TRAP
AutoCAD SHX Text
INTERNAL STORMWATER DRAINAGE
AutoCAD SHX Text
NATURAL FLOW DIRECTION
AutoCAD SHX Text
FUTURE SCHOOL SITE
AutoCAD SHX Text
SAPN EASEMENT
AutoCAD SHX Text
AREA (P2) 26.65 Ha
AutoCAD SHX Text
HOW ROAD BASIN
AutoCAD SHX Text
0
AutoCAD SHX Text
100
AutoCAD SHX Text
200
AutoCAD SHX Text
250m
AutoCAD SHX Text
1 : 10000 (A3)
AutoCAD SHX Text
1 : 5000 (A1)
Page 26: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

APPENDIX B CATCHMENT BRAKDOWN AND WEIGHTED IMPERVIOUS AREA

Page 27: STORMWATER MANAGEMENT MASTERPLAN RENEWAL SA … · 2019-05-24 · PREPARED BY Fyfe Pty Ltd ABN 57 008 116 130 ADDRESS L1, 124 South Terrace, Adelaide SA 5000 CONTACT Bicky Shakya,

Catchment P1Assumed Impervious %

Total area 41.85 haMain South Road widening 2.78 haAldinga Beach Road widening 0.36 ha

Sub-catchment draining into internal drainage systemRailway Corridor 2.42 ha 10%Remining site area 36.29 haOpen sapce (12.5% of total site area) 4.54 ha 20%Land division area 31.75 ha 75%

Total catchment 38.71 ha

Weighted impervious area for catchment P1 64%

Catchment P2Assumed Impervious %

Area of western side to rail corridor 26.65 haPrivate school expansion 3 haHow Road widening 0.36 haSub-catchment draining into internal drainage systemRailway Corridor 9.04 ha 10%Park and Ride 2.5 ha 80%Remaining site area 11.75 haOpen sapce (12.5% pf total site area) 1.47 ha 20%Land division area 10.28 ha 75%

Total catchment 23.29 ha

Weighted impervious area for catchment P2 47%

Catchment P3Assumed Impervious %

Total area 7.8 haOpen sapce (12.5% pf total site area) 0.98 ha 20%Development site area 6.83 ha 75%

Total catchment 7.80 ha

Weighted impervious area for catchment P3 68%

Catchment P4Assumed Impervious %

Total area 3.8 haRailway Corridor 2 ha 10%Remaining site area 1.8 haOpen sapce (12.5% pf total site area) 0.23 ha 20%Development site area 1.58 ha 75%

Total catchment 3.80 ha

Weighted impervious area for catchment P4 38%