Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Construction Effluent Guidelines –
Numerical Limits are Coming
April 28, 2011
Stormwater and Transportation Webinar
Thursday, April 28th, 2011 1:30-3:30 PM Eastern Time
Title slide
Moderated by:
Eric Strecker, PE
Geosyntec Consultants, Portland Oregon
Stormwater and Transportation Webinars
Sponsored by:
• Center for Environmental Excellence by
AASHTO
in Cooperation with :
• Federal Highway Administration and
• Federal Transit Administration
Stormwater and Transportation Webinars
• 1st of 3 upcoming Stormwater Webinars
• Others are being organized for June and July
• Tentative topics:
• June: Achieving better environmental performance
through innovation and economically efficient
strategies and techniques
• July: Post-Construction BMP Selection and Design to
Meet Numerical Objectives
Stormwater and Transportation Webinars
Construction Effluent Guidelines – Numerical Limits are
Coming
• Overview of changing Construction site requirements:
• National Effluent Guidelines
• Relevance to and implications for linear systems
• Use of Active Treatment Systems to meet NELs or Benchmarks
• Passive BMPs to meet NELs/Benchmarks
Today’s Seminar
Today’s Speakers/Topics
JESSE PRITTS, P.E., US Environmental Protection Agency and Project Manager, Effluent Limitations Guidelines and Standards for the Construction and Development Point Source Category; Final Rule
Summary of the Construction Effluent Guidelines and Implications for Transportation Agencies
ELSA PIEKARSKI, Washington State Department of Transportation, Environmental Services Office, Statewide Erosion Control Lead
Active Treatment Systems to meet Numerical Water Quality Targets-Chitosan on WSDOT Projects
DAVID HARRIS P.E., North Carolina State Department of Transportation, Roadside Environmental Unit, Roadside Erosion Control & Vegetation Management Engineer
Passive Treatment of Construction Effluent in North Carolina
• Each Speaker will have 20 to 25 minutes for their presentations.
• Followed by a question and answer period at the end.
• Questions can be submitted via the Goto meeting website
• In addition, there are polling questions for your response
• As of today, there are 280 sites registered for this Webinar
Today’s Seminar
Jesse Pritts, P.E. US EPA
Summary of the Construction Effluent Guidelines and Implications for
Transportation Agencies
Background – Construction ELGs
What are they?
• Categorical discharge standards
• Nationally-applicable
• Minimum requirements for all construction stormwater permits
• Minimum BMPs
• Discharge standards and monitoring for turbidity for larger sites
What aren’t they?
• Not risk-based
• Don’t replace water quality standards
• Don’t replace more stringent state standards
• Don’t apply to discharges after construction is complete
Rulemaking History
• EPA first proposed ELGs for construction in 2002
• Decided not to finalize in 2004
• EPA was sued over failure to promulgate a rule
• Court ordered EPA to propose a new rule in 2008 and finalize by December 2009
• EPA sued over 2009 final rule – also received petitions for reconsideration – Main issue was data used to
calculate turbidity limit
• EPA agreed to stay the numeric limit and re-propose
Current Status
Rule (Except Numeric Limit)
• Final rule published December, 2009
• Effective February, 2010
• Any permit issued by EPA or states after February 2010 must include requirements
Numeric Limit
• EPA issued a stay of only the numeric limit in January 2011
• EPA will propose a new limit in 2011
• Public comment period
• EPA will issue a final rule with a new limit (2011 or 2012)
Applicability
Where, when and to what sites does it apply?
• Applies to all construction sites that disturb 1+ acres of land required to obtain NPDES permits
• Applies in all 50 states, tribal areas and U.S. territories
• EPA issues permits in four states (MA, NM, NH, ID), DC, territories and certain tribal areas - all remaining states issue their own construction permits
• Specific applicability dates will vary by state
• Applies to sites covered by general permits as well as individual permits – includes new and existing sites
Effect on State Permits for Construction
What might it change?
• Erosion and sediment controls
• Pollution prevention measures
• Soil stabilization
• Prohibited discharges
• Surface outlets
• Consideration of use of chemical treatment under some conditions
What doesn’t it change?
• Who has to get a permit
• Permit application requirements
• Existing monitoring requirements (if any), benchmarks, action levels, etc.
• What you need to do to terminate permit coverage
Specific Requirements
Non-Numeric Requirements
• Vegetated buffers
• Dispersion to vegetated areas
• Initiate soil stabilization immediately when soil disturbance has ceased
• Zero discharge of concrete washout and other wash waters
Surface Outlets
• Final discharge point from basins through surface outlet – Skimmer
– Weir
– Flashboard riser
Key Concept - Feasibility
For many of the non-numeric requirements, regulation requires a particular practice or activity unless infeasible.
This feasibility provision does not, however, apply to the numeric limitation and monitoring requirements.
Turbidity Limitation
What is it?
• Enforceable limitation on the amount of turbidity present in discharges
• Turbidity is a measure of the clarity of the water – proxy for amount of soil present
Where does it apply?
• Applies to all sites that disturb 10+ acres of land at one time
• Anywhere a discharge from your site occurs – Pipes or channels discharging
to storm drains
– Pipes or channels discharging directly to a surface water
Sampling Requirements
What types of discharges?
• Any discharge including – Stormwater runoff
– Dewatering activities
• For linear projects, permitting authority can allow representative sampling instead of sampling at each discharge point
• No need to sample sheet flow
How often and how?
• Frequency is determined by individual states – EPA recommends 3 grab
samples per day at each discharge point
• Type of sample (grab, composite, continuous) and analysis method also determined by state
Calculating the Daily Value and Reporting
How is the limit expressed?
• Turbidity limit is a daily maximum value – it is not tied to background turbidity
• Calculated by averaging all samples collected during a given day at a specific discharge point
• Individual samples can be above limit, as long as daily average is below
Where do I submit data?
• Data reporting requirements up to individual states
• May require electronic reporting
• May have specific reporting requirements if any discharge exceeds the limit
Exceptions and Flexibility
Are there any exceptions?
• Yes - does not apply on days with rainfall exceeding the local 2-year, 24-hour storm depth
• Does not apply to sites larger than 10 acres that phase construction and stay below 10 acres disturbed at one time
Do states have any flexibility?
• Yes – states have flexibility on – Size of vegetated buffers
required around surface waters
– What constitutes adequate stabilization
– Soil stabilization requirements in arid and semi-arid areas
Special Considerations for Linear Projects
Multiple Outfalls
• Given large number of outfalls, concept of representative sampling is encouraged
• Will likely vary by project
• Stabilized areas no longer need to sample
• Consider sampling locations during planning
• Consider ease of access
Unique Challenges
• Available space within ROW may limit technologies
• Consideration of up-slope run-on/diversions
• Construction adjacent to or within waterbodies
• Multiple subwatersheds may require multiple treatment systems
Details on 2011 Rulemaking
2011 Proposed Rule
• Will propose a revised turbidity limitation
• Will propose applicability dates and phase-in period for turbidity limitation – Will initially apply to sites
disturbing 20+ acres at one time
– Will eventually apply to sites disturbing 10+ acres at one time
Next Steps
• Will be a public comment period
• EPA will finalize the turbidity limitation and phase-in schedule
Keys to Compliance
• Source Control
• Phase land disturbing activities
• Minimize footprint of disturbance
• Utilize a treatment train
• Utilize vegetated areas for dispersion
• Stabilize soils
• Retain the water on-site
• Utilize polymers and other flocculants where necessary and according to permitting authority guidelines
• Treat all of the water
• Sample the whole hydrograph
EPA’s Proposed CGP
EPA’s proposed construction general permit is available for comment:
cfpub.epa.gov/npdes/stormwater/cgp.cfm
CGP incorporates all non-numeric requirements of ELG
60 day public comment period
Revised ELG will be available:
http://water.epa.gov/scitech/wastetech/guide/construction/
index.cfm
Active Treatment Systems to meet Numerical Water Quality Targets-
Chitosan on WSDOT Projects
Elsa Piekarski
Statewide Erosion Control Lead
Environmental Services Office
Washington State General Permit: Quick Overview
• Permit reissued by the Department of Ecology on December 1, 2010 –effective as of January 1, 2011
• Benchmarks and trigger values are used to determine level of water quality concern and required level of action:
• 25 NTU turbidity benchmark – action required
• 250 NTU turbidity phone reporting trigger – immediate action required
• Permit does include an option to use a numeric effluent limit (NEL) for determining compliance for discharges to 303(d) listed water bodies:
• 25 NTU NEL at discharge point; or
• Water quality standards
Construction Stormwater General Permit
Why Does WSDOT Use Active Treatment?
• Many water bodies in Western Washington are habitat for threatened or endangered Salmonid populations. Salmonids are sensitive to fine particulates (increases respiration rates, smothers spawning grounds, and lowers feeding success). State water quality standards are low.
• Active treatment lowers water quality risks for work in the wet and winter seasons. This means that projects can be completed faster.
• Benchmarks are very low in Western Washington (25 NTU, 8.5 pH). If the 25 NTU benchmark is exceeded, adaptive management becomes required. Active treatment will lower the need for continual adaptive management.
• Active treatment effectively and efficiently treats turbid water on linear projects where there is not room for large ponds or infiltration.
• Active treatment reliably meets compliance requirements for 303(d) listed water bodies (25 NTU NEL or water quality standards).
Potential Active Treatment Methods
Active Treatment Currently Approved by the Department of Ecology:
• Chitosan Enhanced Sand Filtration (CESF)
4 different treatment methods approved for ‘general use’
2 different treatment methods for ‘conditional use’
• Electrocoagulation
1 treatment method approved for ‘general use’
• Other technologies need to be evaluated by Ecology
Chitosan has been WSDOTs Preferred Choice for Active Treatment
• Local sources and providers
• The Department of Ecology has approved multiple methods for ‘general use’
• Natural, non-toxic, biodegradable biopolymer
e- e-
e- e-
P+
P+
e- e-
e- e-
P+
P+ P+
P+
e- e-
e- e-
P+
P+
P+
Coagulation
Flocculation
Clarification (gravity settle)
e- e-
e- e-
e- e-
e- e-
Negatively Charged Suspension P+
P+
e- e-
e- e-
P+
P+ Rapid Mix Chitosan
Chitosan in Washington
= Low Turbidity Discharge
Key Points for General Use of Approved CESF Methods and Products:
• Request for Chemical Treatment Form or request use in Notice of Intent (NOI)
• Operational monitoring forms: calibrations, treatability tests, total volume treated etc
• Dosing maximum (1mg/L) and residual chitosan testing (below 0.2 ppm)
• Continuous monitoring: influent and effluent pH and turbidity, flow rate
• Source control required to minimize need for pretreatment
• Dedicated pretreatment holding tanks or ponds
• Maximum effluent limit (10 NTU)
• Operated by certified CESF technician
General Use Level Designation
Chitosan Enhanced Sand Filtration (CESF)
Pros
• Compliance assurance
• Lowers risk during over winter work or on high risk projects
• Smart water management
• Increased discharge rates with minimal sediment release
Cons
• Cost
• Increased time commitment to design and planning
• Large footprint needed on-site for systems/ponds
• Systems may need to be moved as construction progresses
• 2 Systems were used about 100 times from 9/2008 – 7/2009
• Total cost about $1,000,000
• Total usage was about 6% of estimated usage (5,100 hrs estimated > 293 hrs used) because the Contractor was able to utilize a sanitary sewer permit.
UW Bothell Campus Access Bothell, WA
• Review geotechnical reports
• Evaluate site specific factors
• Evaluate project specific risks
• Determine treatment needs
• Mobile or stationary systems
• Don’t skip conventional BMPs
• Plan for extreme events
• Have a contingency plan
Planning and Design Basics
Mobile unit used in Renton WA
Contracting/Oversight Approach
• If planned ahead, CESF systems are included in specifications for design-bid-build projects
• We have learned to specify quantitative estimates rather then lump-sum
• Operational estimates can be made based on hydraulic analysis
• Equipment and hourly operational costs are known values
• Historically systems have been installed and operated by specialty sub-contractors (10 - 40% mark-up).
• Recently contractors have been buying, installing and operating their own systems – lowering mark-up cost. These systems may be older, less advanced and run less efficiently – increasing operational costs. Always verify the contractor CESF operators are certified.
• Discharges from CESF must be maintained below 10 NTU
Cost Summary
Systems Cost Vary Widely
• Who owns and operates it (1st, 2nd, 3rd tier contractor - up to 40% mark-up)
• Whether the system was planned for or added after construction starts
• Complexity of the system – piping, number of systems, contamination issues
• How the bid breaks down system operations (pretreatment, maintenance etc)
• Operational efficiency (pretreatment time, experienced operators etc)
• Whether the system needs to be remobilized during construction
• Monthly costs for one system generally range from $10,000 – $30,000
• From 3/2009 – 3/2011 WBNV discharged 36,534,923 gallons of water
• Discharge samples are typically between 1 – 7 NTU
• 8 systems in bid • $560,000 lump sum • $5,000 monthly rentals • 14,400 estimated
operational hrs @ $60 per hour
WB Nalley Valley Tacoma, WA
Totem Lake
Kirkland, WA
• 2 systems • 8/2005 – 6/2006 • $330,000 lump sum • $25,000 pumping costs • $30,000 remob 2 systems • 10,534,953 gal discharged
• Start planning and design early
• Do a project specific risk analysis: soil types, topography, climate
• Specify quantitative estimates rather than lump-sum estimates
• Flow through systems minimize temporary storage needs
• Limit need for pretreatment by employing effective source control (Not PAM)
Summary of Cost Saving Strategies for Active Treatment Systems
See BMP c250 from the Department of Ecology Stormwater Manual http://www.ecy.wa.gov/programs/wq/stormwater/wwstormwatermanual/final_bmp_c250_12_06.pdf See the Use Level criteria for use of approved methods and products http://www.ecy.wa.gov/programs/wq/stormwater/newtech/construction.html
For additional information on use of advanced treatment in Washington:
David B. Harris, PE, CPESC, CPSWQ
North Carolina Department of Transportation
Roadside Environmental Unit
Passive Treatment of Construction Effluent in North Carolina
North Carolina Department of Transportation
• 80,000 Miles of State Maintained Highways • 15,000 Miles of Primary • 65,000 Miles of Secondary
• 13,578 Bridges Statewide
Passive Treatment of Construction Effluent in North Carolina
North Carolina Department of Transportation
• Urban Loop Projects • Widening Projects • Rehabilitation Projects • Bridge/Culvert Replacement Projects • Toll Road Projects • Resurfacing Projects • Secondary Road Construction Projects
Passive Treatment of Construction Effluent in North Carolina
North Carolina Department of Transportation
Delegated Erosion and Sedimentation Control Program • Design
• Implement • Evaluate • Modify
Passive Treatment of Construction Effluent in North Carolina
Passive Treatment of Construction Effluent
in North Carolina
Guiding Regulations
NC Sedimentation Pollution Control Act
NC Water Quality Standard
Passive Treatment of Construction Effluent
in North Carolina
NC Sedimentation Pollution Control Act 1. Identify Critical Areas: Identify site areas subject to severe erosion, and off-
site areas especially vulnerable to damage from erosion and sedimentation.
2. Limit Exposed Areas. Limit the size of the area exposed at any one time.
3. Limit Time of Exposure. Limit exposure to the shortest feasible time.
4. Control Surface Water. Control surface water run-off originating upgrade of exposed areas in order to reduce erosion and sediment loss during exposure.
5. Control Sedimentation. All land-disturbing activity is to be planned and conducted so as to prevent off-site sedimentation damage.
6. Manage Storm Water Runoff. When the increased velocity of storm water runoff resulting from a land-disturbing activity causes accelerated erosion of the receiving watercourse, plans shall include measures to control the velocity to the point of discharge.
Passive Treatment of Construction Effluent
in North Carolina
NC Water Quality
Standard
Turbidity: the turbidity in the receiving water shall not exceed 50 Nephelometric Turbidity Units (NTU) in streams not designated as trout waters and 10 NTU in streams, lakes or reservoirs designated as trout waters; for lakes and reservoirs not designated as trout waters, the turbidity shall not exceed 25 NTU; if turbidity exceeds these levels due to natural background conditions, the existing turbidity level shall not be increased. Compliance with this turbidity standard can be met when land management activities employ Best Management Practices (BMPs)
Solution?
Research
Richard A. McLaughlin, PhD.
Soil Science Department
North Carolina State University
Passive Treatment of Construction Effluent in North Carolina
Traditional Erosion and
Sedimentation Control Practices
Less then 60%
efficient
Passive Treatment of Construction Effluent in North Carolina
How Do We
Improve BMPs?
Start at the discharge points
Passive Treatment of Construction Effluent in North Carolina
Improve Basin Efficiency Step 1:
Reduce Turbulence
Porous Baffles
Passive Treatment of Construction Effluent in North Carolina
Improve Basin Efficiency Step 1:
Reduce Turbulence
Porous Baffles
Passive Treatment of Construction Effluent in North Carolina
Improve Basin Efficiency
Step 2: Reduce Potential
Erosion
Stabilize Entrance
& Sides
Of Devices
Passive Treatment of Construction Effluent in North Carolina
Improve Basin Efficiency Step 2: Reduce Potential
Erosion
Stabilize Entrance
& Sides
Of Devices
Passive Treatment of Construction Effluent in North Carolina
Improve Basin Efficiency
Step 3: Surface Outlet
Skimmers
Passive Treatment of Construction Effluent in North Carolina
Step 3: Surface Outlet
Skimmers
Improve Basin Efficiency
Passive Treatment of Construction Effluent in North Carolina
Step 4: Improve
Stabilization
Improve Basin Efficiency
Passive Treatment of Construction Effluent in North Carolina
Step 4: Improve
Stabilization
Improve Basin Efficiency
Passive Treatment of Construction Effluent in North Carolina
Improved Efficiency
95+%
Improve Basin Efficiency
Passive Treatment of Construction Effluent in North Carolina
Improve Basin Efficiency
95+% Efficient at Trapping Sediment
Now what about Turbidity
Passive Treatment of Construction Effluent in North Carolina
More Research
NC State Department of Soil
Science
Rich McLaughlin, PhD &
Melanie McCaleb, MS &
Scott King, LSS
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Turbidity
How Do You Reduce
Turbidity?
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Flocculate the suspended
particles
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Polyacrylamide – Is a Water Soluble
Synthetic Powder that is used to flocculate suspended sediment
from water runoff
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Polyacrylamide
• Is known to be relatively non-toxic as measured by acute LD50 test.
• Chronic test on fish also show low toxicity.
• Chronic effects on smaller species less well known, but toxicity appears to be very low for these as well.
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Polyacrylamide • When introduced to the
effluent and mixed properly, the results can be very beneficial.
8,010 NTU 62 NTU 376 NTU
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
How do you introduce polyacrylamide into the effluent?
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Apply polyacrylamide to the wattles or other fiber type material.
Passive Treatment of Construction Effluent in North Carolina
Turbidity Reduction
Success has been achieved.
Passive Treatment of Construction Effluent in North Carolina
Wattles and Polyacrylamide
When sprinkled onto a wattle at 4 oz. per wattle after 0.5 inch rainfall event
Passive Treatment of Construction Effluent in North Carolina
Wattles and Polyacrylamide
Turbidity Reduction Improved
Passive Treatment of Construction Effluent in North Carolina
To Be Successful: Training Design Implementation Monitoring
Training
Design
Passive Treatment of Construction Effluent in North Carolina
To Be Successful Training Design Implementation Monitoring
Implementation
Monitoring
Passive Treatment of Construction Effluent in North Carolina
Passive Treatment of Construction Effluent
in North Carolina
For More Information Research Information
http://www.soil.ncsu.edu/lockers/McLaughlin_R/Webstuff/SECREF/
NCDOT Roadside Environmental
http://www.ncdot.org/doh/operations/dp_chief_eng/roadside/soil_water/erosion_control/
Email Address
Concluding Remarks
• Please fill in and submit the simple on-line questionnaire (e-mail will provide directions)
• The webinar will be available for on-demand viewing and pdf of the presentation for download at the Center website:
– http://environment.transportation.org/
• Look for future announcements about upcoming Webinars
• Thank you for your attention and participation