Upload
others
View
11
Download
0
Embed Size (px)
Citation preview
November 1, 2014
Dr. Edward Mcmahon
Mr. Trevor Elliott
University of Tennessee at Chattanooga
615 McCallie Avenue
Chattanooga, TN 37403-2598
To whom it may concern,
The Road Design team is presenting a report concerning the proposed redesign of State Route 317
in the Collegedale area. This proposal includes the design plan and evaluation for the storm
drainage system for phase 2 of a 4 phase project, progress made thus far on the design, and the
groups future time line for completion. The team member’s skills and resumes are also included. If
you have any questions or comments regarding the project please contact me at (615) 542-0491.
Sincerely,
Jeremy Moody
Road Design Team Manager
Sponsor: TDOTTeam Members:Jeremy MoodyKyle PhillipsNikita HemnaniDaniel FussellTarek Azzouz
April 21, 2014
Road Design Storm Drainage Report
Executive Summary
This report was created to provide a final design and cost estimate for the design of the storm drainage
system for State Route 317 from the new connector at Interstate 75 Enterprise South Interchange and
extending for approximately 2.1 miles. The design of the storm drainage system will follow the
expansion and widening of the road per TDOT‘s request.
The design of the storm drainage system will include the inlet box locations, outlet box locations, and
piping system between the road and the outflow areas of the drainage area. The expanded road and
surrounding areas will be divided into separate drainage area’s to provide the area flow of water into
each inlet box. With the drainage areas and the estimated intensity values of the area, the flow of water
through the piping system can be calculated to estimate the pipe size required.
To design a new storm drainage system for this road will require that the existing outflow drainage
streams do not see an increase of flow due to the road or drainage system. This is to ensure that the
environment is affected as little as possible.
Table of ContentsExecutive Summary.....................................................................................................................................3
1) Introduction.........................................................................................................................................5
a) Problem Statement..........................................................................................................................5
i. Right of Way................................................................................................................................5
ii. Storm Drainage............................................................................................................................5
b) Project Mission and Goals...............................................................................................................6
c) Design Objectives............................................................................................................................7
d) Benefits to Client.............................................................................................................................7
2) Background..........................................................................................................................................7
1. Right of Way....................................................................................................................................7
2. Storm Drainage..............................................................................................................................10
3) Description of Design.........................................................................................................................13
a) Overall Description........................................................................................................................13
b) Description of Subsystems.............................................................................................................13
c) Detailed Description......................................................................................................................16
4) Detailed Cost Estimate.......................................................................................................................19
5) Conclusions and Recommendations..................................................................................................21
6) References.........................................................................................................................................22
7) Appendix............................................................................................................................................23
1) Introduction
a) Problem Statement
i. Right of Way
This design is being proposed to alleviate traffic demands on State Route 317 beginning at the new
connector from Interstate 75 Enterprise South Interchange and extending for approximately 2.1 miles.
This design is on Phase 2 of a 4 Phase project and Phase 2 encompasses Section 1 of a total of 5 sections.
The substandard two lane road currently being used has no shoulders or sidewalks which in effect limit
pedestrian traffic via bicycles and foot traffic. The route is predicted to surpass its level of service (LOS)
limit and needs to be widened to accommodate a heavier flow of traffic brought about by the expansion
of the McKee Foods Corporation as well as new residential developments that are in the planning
and/or construction phase. One of the busiest general aviation airports in Tennessee, the Collegedale
Municipal Airport, is also located on State Route 317. TDOT has mentioned that along with the widening
of the road a section at one end has an issue with deficient alignments and lane widths that prohibits 18
wheelers from using it safely due to limited sight distance caused by current design.
The new design proposed will incorporate curbs and gutters, 6’ shoulders for bicycle use, and sidewalks
on both sides of the route to accommodate pedestrian traffic. It will also widen the existing route to
either four 12’ traffic lanes with a continuous 12’ center turn lane, or four 12’ lanes with a 22’ raised
median with median breaks placed at appropriate locations.
ii. Storm Drainage
To allow for the expansion of the area surrounding state route 317 within phase 2 of the 4 phase
project, a new storm drainage design is required. The current storm drainage system that is in place is
designed to handle the drainage produced by the residential and commercial properties. The design will
include all aspects of the storm drainage including but not limited to detention/retention ponds, catch
basins, the curb and gutter system, storm drain inlets/outlets, ditches, all necessary piping, any pumps,
access holes, and water quality control facilities. The storm drainage system will be designed using a 10
year frequency and a maximum overflow of a 100 year frequency storm event to ensure that the storm
drain will be able to manage the flooding events that can occur. The design of the drainage system must
allow for the drainage of the newly designed 60’ wide four lane roadway that is 2.1 miles in length. The
storm drain system must be able to handle the water flow from surrounding drainage areas and
properly transfer the storm water to existing outlet locations. This will show possible features that will
benefit future designs and benefit the public’s needs.
b) Project Mission and Goals
The first mission for this project is to design a R.O.W that will sufficiently handle the deficient vertical
and horizontal alignments and design an adequate storm drain system that will handle the water runoff
from the new roadway.
The primary goal of the R.O.W design is to determine right of way (R.O.W) path that will minimally affect
the surrounding neighborhood and environment and increase the level of service of the road. In general,
this is accomplished by:
Determine the best path for R.O.W to not disturb current housing
Determine desired cut and fill
Identify construction equipment zones
Determine flow of traffic path during construction
The primary goal of storm drainage design is to limit the depth and spread of water flowing on the
roadway and the ponding at sag points so that it will not interfere with the passage of traffic during the
design frequency storm. In general, this is accomplished by:
Placing inlets at the locations and intervals necessary to control spread by intercepting flows
Providing storm drain pipes adequately sized to transport flows from the inlets to suitable outlet
locations
Determine appropriate drainage areas for the system
Determine newly designed roadway runoff
Determine adequate piping size to handle water runoff
Determine proper location for water inlets
Determine existing rainfall outlets
c) Design Objectives
There are two objectives for this project:
The first objective is to raise the L.O.S. of the road, and to give better accessibility to Mackee
foods corporation factory. The new road design should also be a low cost option, traffic flow not
inhibited, minimal construction time, and low impact on environment.
The second objective is to design a drainage system that supports the excess water flows from
the expansion of the new roadway, the surrounding drainage areas, and the future commercial
and business run off, and transfer this flow to the appropriate water outlets.
d) Benefits to Client
The benefits for the client, TDOT, will be a road construction plan that satisfies the design criteria,
enhanced local and regional accessibility, improved safety and operating conditions along the corridor,
increased traffic capacity, enhancement of future planned growth by local and/or regional land use
planning agencies, a storm drainage system that supports the newly designed 60’ wide roadway, as well
as the water flow that would occur from the population expansion within the area. This R.O.W design
will correct the deficient vertical and horizontal alignments and lane widths. This will allow the route to
better accommodate larger vehicles safely due to increased sight distance. The drainage system will
have less negative environmental impact and properly handle the water rainfall so that there aren’t any
negative impacts on the public.
2) Background
1. Right of Way
Road design is what has provided a thriving foundation for both global and local economies. Roads are
used on a daily basis for us to get from point A to point B. However, their practicality is much more
extensive than given credit for.
The first indications of a constructed road date back to around 4000 BC in modern day Iraq. This road
was constructed of stone and was the first of its kind. In the 1800s, road developers decided that it was
mandatory to include water in the mixture to allow for a smooth unified road surface. The modern style
pavement design as we know it today was developed by a blind man named John Metcalfe. He designed
his pavement out of three layers: large stones, excavated road material, and a layer of gravel. Shortly
after Metcalfe’s death, a pair of Scottish engineers named Thomas Telford and John McAdam developed
Metcalfe’s road design even further and created a raised center to allow water to drain to the outer
edges of the road. Also, they decided that broken stones allowed for better road strength and stability
while creating a smoother surface finish.
The objective of this project is to create a road the will fix the insufficient vertical and horizontal
alignments and lane widths throughout. This is to allow for safer transportation as well as increased
accessibility of goods and people along Apison Pike by allowing for increased sight distance.
To further explain and correctly define the project several key words are involved in the road design
process. Sag vertical curves, crest vertical curves, horizontal alignment, and lane width are all design
standards that govern every road that is built today.
Sag vertical curves are hills when viewed from the side are valleys. These types of curves are important
when designing for night time driving because the driver is limited to see what is visible in front of them
in their headlight beams, and the sag vertical curve cuts that short. An example of sag vertical curves can
be seen in Figure 1.
Figure 1: Picture of Sag Vertical Curve.
Crest vertical curves are simply hills that are convex upward. The main goal when designing for crest
vertical curves is stopping sight distance. Since the hill is typically a blind hill, the roadway must be
designed so that the driver will not hit any unforeseen obstructions in the road such as a stalled vehicle
or animal in the road.
Figure 2: Picture of Crest Vertical Curve.
Horizontal alignments of a roadway consist of straight sections of roadway connected by circular curves
to simply change direction of movement. The main factors in the design of horizontal curves are the
speed of the given roadway and the radius of the curve. If a roadway is designed at high speeds and a
tight radius, vehicles may be more prone to wrecking at the tight curvature. To avoid this, a bank would
be needed to be designed to keep vehicles on the roadway. For this specific project, the goal is to
eliminate any tight radii curves to help flow of traffic and to allow for the movement of transfer trucks
with increased visibility. Figure 3 shows an example of a horizontal alignment.
Figure 3: Picture of Horizontal Alignment.
The width of each individual lane effects functionality of the road as well as cost of building and
maintaining the road. The width of lanes typically falls into the 10’ to 12’ foot range with wider roads
being found primarily on high volume, high speed roads such as highways or interstates and where
restrictions on land are not a factor. For smaller volume roads that move primarily large trucks the 12’
lane would be used. Narrow lanes are cheaper to build and maintain but have a higher number of
vehicles that leave the roadway and higher quantity of head on collisions.
All of these aspects of roadway design have been considered in this project since one goal of this project
is to maximize truck sight distance and safety by eliminating as many vertical and horizontal curves as
possible and by maximizing lane widths.
All of these aspects of roadway design have been considered in this project since one goal of this project
is to maximize truck sight distance and safety by eliminating as many vertical and horizontal curves as
possible and by maximizing lane widths.
1.
2. Storm Drainage
Storm drainage systems for transportation facilities collect stormwater flowing within and along the
highway right-of-way and transfer it to a suitable discharge point. A storm drainage system collects
water either from the road using drainage inlets or from the surrounding drainage area using area
drains. An example of these can be seen in Figure 4 and 5 below.
Figure 4: Picture of a Drainage Road Inlet.
Figure 5: Picture of an Area Drain.
A proper highway drainage design will help to reduce many of the effects of an inadequate road
drainage system, including:
Water flowing from the roadway onto adjacent properties
Water ponding behind the roadway curbs
Hazards and delay to traffic caused by excessive ponding in sag points or excessive spread on
the roadway.
Weakening of the base and subgrade caused by frequent long-duration ponding of water
The purpose of any storm water design should be to make every reasonable effort to promote the safety
of the traveling public by providing adequate drainage performance in the most cost-effective way. The
storm drainage system for a roadway project may be organized based upon outlet points for each
individual segment. Each segment of the roadway drainage system will have an outlet to either a side
ditch or a cross drain. A picture of a storm drain outlet can be seen in Figure 6 below.
Figure 6: Picture of Storm drain Outlet.
A proposed storm drainage system will intercept runoff from off-site drainage areas. The drainage areas
and time of concentration for these off-site areas would be listed in the inlet or other computations.
3) Description of Design
a) Overall Description
The road design process can be broken down into three main systems. The three systems that make up
the design process are drainage, pavement design, and alignment. These three are identified because in
every road design these milestones are necessary to complete the overall project . These systems can be
broken down into their own individual subsystems, with each subsystem containing its own components
which are commonly categorized by function, and objectives needed to complete each individual
process. A breakdown of the primary function, basic functions, and the sub functions in the function
node tree can be seen in the Appendix.
A storm drainage system can vary from one jobsite to another. These variances will include different
inlet locations, different outlet locations, different size piping, different water retention devices, and
different culvert slope gradients. These differences are site specific and will be designed before
construction begins but every storm drainage system is designed the in the same manor. The slope of
the road provides an outward sloping gradient from the peak in the center of the lane. This slope will
cause the water rainfall to directed to the curb and gutter system. The curb and gutter system follows
along the entire length of the road and the road is designed to be either at a positive or negative
gradient. The water rainfall will follow along the curb and gutter system along the road until it reaches a
culvert inlet box location. The culvert inlet box will act as a drain for the road. The culvert inlet will be
connected to underground storm drainage piping which is designed on an in ground gradient which
allows the water from the inlet box to travel underground to a culvert outlet box. The outlet box directs
the storm rainfall to existing water outflow areas to either streams or rivers.
b) Description of Subsystems
i) Drainage
The overall drainage system can be separated into two subsystems. These subsystems are generally
called the Major and Minor systems (the Minor system is sometimes referred to as the convenience
system). Historically the Minor system was the only subsystem given attention to in the design process,
with the Major system being overlooked in most cases. Today’s road design projects take into
consideration both Minor and Major systems. As weather patterns become more turbulent and surface
runoff from urban sprawl increases the Major system is becoming increasingly important to the overall
design of any urban roadway project.
Drainage minor System: The Minor system is typically designed to carry runoff from 10 year
frequency storm events and its components make up the majority of what people consider the drainage
system. These components are put into three distinct categories which are dictated by the function of
each component. The three function categories are collection, conveyance, and discharge.
The collection of stormwater runoff from the roadway surface and ROW is a function of the Minor
stormwater drainage system, and is manifested within a road design project in the form of: median and
roadside ditches, gutters, and drainage inlets. The ditches are located and shaped to avoid being a
traffic hazard, and can either have Channel linings to control erosion or vegetative linings when design
velocities permit. The gutters intercept runoff primarily from the roadway surface and, in some
instances, ROW at which point it is carried alongside the roadway shoulder to an adequate storm drain
inlet. Usually curbs are installed with gutters to either help avoid erosion of fill slopes, or where either
ROW or topographical conditions prohibit roadside ditches. The drainage inlets are receptors for the
surface water collected from ditches and/or gutters, and serve as an entrance to the storm drains.
Drainage inlets take on many forms, and when located alongside the roadway shoulders they are
designed in such a way as to limit the spread of surface water onto travel lanes.
The conveyance of stormwater begins when the runoff reaches the main storm drainage system, at
which point it is transported along and through the ROW to the discharge point. The main storm
drainage system begins with storm drains which receive runoff from inlets and convey it to a channel,
body of water, or other piped system; be it closed conduit or open channel. The piping system is
comprised not only of pipes, but also contains access holes, junction boxes, and inlets. These aspects of
the piping system are located at intersections of two or more storm drains, or when there is a change in
pipe size or alignment and are generally dictated by critical design parameters. On occasion, when
gravity drainage is not feasible due to geographic or economic factors a stormwater pump station may
be used during the conveyance process.
Quantity and quality of stormwater is what dictates the discharge function of the Minor system. By
including detention/retention ponds the quantity of runoff discharged into receiving waters can be
controlled. The quality of the runoff can be controlled by: extended detention ponds, wet ponds,
infiltration trenches, infiltration basins, porous pavements, sand filters, water quality inlets, vegetative
practices, erosion control practices, and wetlands. They can help to impede, and/or eliminate:
suspended solids, heavy metals, excessive nutrients, and organics into receiving waters.
Major System: The Major system provides overland relief of stormwater flows that would exceed
those of the Minor system and are normally designed to have a capacity of a 100 year frequency storm
event.
The main function involved with the Major system is flood water relief. It is typically provided by
streets, surface swales, ditches, streams, and/or other flow conduits which provide a relief mechanism
and flow path for flood waters.
The major system acts as a safety device for the minor system. The minor system is only equipped to
handle a 10 year frequency storm so if a storm comes that would exceed the minor systems capabilities
then the major system would divert the water in a different manor to ensure flooding and ponding are
minimalized.
ii. Pavement Design
The pavement for the specified road will be designed to transfer the loads of vehicles to the sub-grade
while ensuring that passengers’ ride quality is nothing less than smooth. The designed pavement will be
structurally strong so that the pavement will transfer forces to the ground as well as keeping the design
life as long as possible and minimizing post construction maintenance costs.
iii. Alignment
The road design we have chosen eliminates most drastic horizontal and vertical alignments. One of the
main concerns for the project was to ensure that truck drivers from McKee foods are able to drive the
road safely. For example, one curve on the existing road had improper vertical as well as horizontal
alignments leading drivers into a blind right turn atop a hill. This will be fixed with the reconstruction of
the road to the specified design.
c) Detailed Description
The storm drainage system for Apison pike is made up of catch basins, area drains, and the piping
system. The catch basins are limited to no more than 400’ apart to prevent sagging in the piping system
and create a point where the pipe can change direction if desired. The pipe is also limited to the
straightest path to allow for clear flow through the system. With these constraints It was estimated that
between 100 to 140 catch basins will be required along the entire 2 mile stretch of road expansion.
Along with these catch basins the pipe required to move the flow of water will vary as the lengths of
pipe get longer and there are no outflow areas to disperse the water. The piping system will start out at
18” circular reinforced concrete pipe (CRCP) and steadily increase depending on the flow of water.
Figure 7 below shows the entire length of road with some of the drainage areas specified.
Figure 7: Picture of Entire Road.
Figure 8 below shows a section of the road where the drainage area has been delineated and drawn
with the catch basin locations. Between catch basin 16 and 17 it shows the piping system at 42” CRCP,
this is because all the water flowing before this location is all being carried by the piping system and
there is a headwall with outflow drain roughly at catch basin 31. This piping system is not only carrying
all the water off the road and surrounding area but also all the water uphill from it. As the flow of water
gets larger the pipe size will get larger.
Drainage Area
Figure 8: Picture of Section of Road with Drainage Areas.
Based on the drainage areas and where the outflow locations for the drainage system are, the estimated
total pipe can be seen in Table 1 below.
Table 1: Pipe Sizes and Total Lengths.
Pipe Diameter, in's Units, ft Quantity, ft
18 LF 110524 LF 42236 LF 042 LF 150854 LF 75860 LF 468
The outflow area for the piping system will be designed to direct the flow of water to the existing
streams or rivers. This is done by placing an endwall or a headwall at the end of the piping system that
will allow the water in the pipe to be discharged into the local discharge areas. Figure 9 below shows the
headwall near catch basin 31.
Catch Basin
Figure 9: Picture of Endwall or Headwall Outflow Area.
The outflow area must also not discharge the water at a greater velocity than the velocity of water
before construction. This is done to prevent erosion of soil and stabilization and to not affect any wildlife
downstream. To control the velocity of water along the piping system manholes and junction boxes can
be used to drop the elevation of pipe down to a lower elevation to stop the constant velocity along the
pipe. The more water the is introduced to the piping system the greater the flow so more than one
junction box or manhole may be needed along the entire length of the road.
4) Detailed Cost Estimate
The cost analysis for the storm water portion of State Route 317 (Apison Pike) consists of two main
sections: the “Design to Date” Estimate, and the “Total Projected Design” Estimate. Each table will be
composed of these two sections to show both the estimated cost of what has been actually designed to
date, and the estimated cost of the entire “projected” design.
Endwall
Precast concrete components were chosen to be used for the entirety of the project for consistency and
durability. Table 2 below lists the pipe, by size (diameter), to be used within the project.
Table 2: Pipe Sizes and Associated Costs.
Pipe Diameter,
in's
Units, ft
Quantity, ft
Unit Price (per inch
diameter per lineal foot)
ExtensionQuantity,
ft
Unit Price (per inch
diameter per lineal foot)
Extension
18 LF 1105 $5.00 $99,450.00 8000 $5.00 $720,000.0024 LF 422 $5.00 $50,640.00 1200 $5.00 $144,000.0036 LF 0 $5.00 $0.00 700 $5.00 $126,000.0042 LF 1508 $5.00 $316,680.00 1400 $5.00 $294,000.0054 LF 758 $5.00 $204,660.00 800 $5.00 $216,000.0060 LF 468 $5.00 $140,400.00 500 $5.00 $150,000.00
$811,830.00 $1,650,000
Circular Precast Concrete Storm Drain
Total Projected Cost
Designed to Date Estimated Cost of Complete Design
Cost of Completed Design
The Unit Price (per inch diameter per lineal foot) used in the table was found on the “Urban Drainage
and Flood Control” of Colorado website. It uses data compiled between the years of 2005-2009, and
was developed in 2010 to be used as a cost estimator for master planning. The program is excel based
and gives the user the option to include current, CCI (Construction Cost Index) and Inflation, rates to
adjust the costs of components used within any given project. The unit costs are complete-in-place and
include all associated costs for excavation, bedding, placement, and backfill. These prices will inevitably
be higher than the actual price due to some of the complete-in-place processes happening during, and
for, other phases of the Road Project as a whole.
The component costs were obtained in a similar fashion as the Unit Prices for the pipe. After adjusting
for the CCI and Inflation rates using “Urban Drainage and Flood Control” software the worst case
scenario was used to estimate each component. Table 3 below shows the estimated component list and
associated cost.
Table 3: Component List and Associated Costs.
Component UnitItem Description ft. Quantity Unit Price Extension Quantity Unit Price Extension
Catch Basin (Area Drain) SF 2 $7,500 $15,000 5 $7,500 $37,500.00Catch Basin (Single Grate Inlet) SF 29 $6,000 $174,000 120 $6,000 $720,000.00
Junction Box SF 5 $4,500 $22,500 15 $4,500 $67,500.00Manhole (6' diameter) each 1 $10,500 $10,500 7 $10,500 $73,500.00
Headwall (60" double pipe) $3,500 $0 $3,500 $0.00Wingwall (11' x 11') $5,000 $0 $5,000 $0.00
Curb and Gutter LF 3800 $50.00 $190,000 10,000 $50.00 $500,000.00
$412,000 $1,398,500.00
Component Price EstimateDesign to Date Estimate Projected Design Estimate
Total Projected Component
Estimate
Projected Design to Date Estimate
The cost estimate of the project is located in Table 4 below and as stated above is based on the worst
case scenario due to lack of design data. The “Project to Date” cost estimate will be much closer to the
actual cost than the “Projected Total” due to dimensional assumptions made during Cost Analysis.
Table 4: Total Cost Estimate.
Project to Date Projected TotalUnit Cost Cost
Pipe Total $811,830.00 $1,650,000Component Total $412,000.00 $1,398,500
Total Estimated Cost $1,223,830.00 $3,048,500
Cost Estimate of Project
5) Conclusions and Recommendations
We started this year off with one project and one goal. We were to design a road that would alleviate
traffic demands on state route 317. While working on this project the team was redirected towards
designing the drainage alone for this roadway, because we were led to believe that too much
information had been given to us regarding the roadway design. We began this design of drainage at the
beginning of the fall semester, and have been working consistently to accomplish this. With the amount
of time our group has had to design this system, we will not have the complete drainage system for the
full length of the road within our project area. The Drainage system of this roadway has been designed
up until the catch basin 17 but plan on design up to catch basin 31 this week.
One recommendation that we have in performing this project would be a longer time period for our
group to focus on simply the drainage design of our assigned road. The fact that we had to switch
projects mid-year due to confusion within the project as a whole, has put us back and limited the extent
we can dig into this project.
Also, we feel that easier, more fluid access to the TDOT Microstation program would have substantially
made this project better. Allowing us to receive and give information more easily, as well as receive help
from users who have experience using the Microstation program.
6) References
Transportation Planning Report by Tennessee Department of Transportation, Project Planning Division.
http://inventors.about.com/od/rstartinventions/a/History-Of-Roads.htm
http://www.triplenine.org/articles/roadbuilding.asp
http://www.tdot.state.tn.us/chief_engineer/assistant_engineer_design/design/DesGuide.htm
http://www.tdot.state.tn.us/Chief_Engineer/assistant_engineer_design/design/DrainManpdf/Chapter%203.pdf
http://www.tdot.state.tn.us/Chief_Engineer/assistant_engineer_design/design/DrainManpdf/Chapter%204.pdf
7) Appendix
Storm Drainage Function Tree