ARQ. JULIO VILAOBRA 1000 VIVIENDAS SECTOR 636 5/13/2015
PREVENTIVO SALDO MATERIALES 636 VIVIENDASSALDO PARA TERMINAR 102 PLATEAS AL 13/05/2015CANT/P a PR ITEM LOSA UNITARIO/P MAT. TOTAL
P U/PL U/PL102 VIGUETA 3,2 62 6324 UN102 VIGUETA 1,8 6 612 UN102 VIGUETA 1,4 4 408 UN102 MALLA SIMA Q50 10 1020 UN102 HORMIGON H17 14 1428 M3102 LADRILLO SHAPPO 740 75480 UN102 ALAMBRE N°14 10 1020 KG102 ALAMBRE N°17 5 510 KG102 CEMENTO PORTLAND 2 204 BOL
SALDO PARA TERMINAR 69 PLATEAS AL 13/05/2015CANT/P a PR ITEM PLATEA UNITARIO/P MAT. TOTAL
P U/PL U/PL69 KIT PVC 2 138 UN69 CEMENTO PORTLAND 2 138 BOL69 H° H-17 17 1173 M3
SALDO PARA TERMINAR 92 PLATEAS AL 13/05/2015
CANT/P a PR ITEM cap. Aisladora UNITARIO/P MAT. TOTALP y mamposteria h2,5 U/PL U/PL
92 granza 0.8 73.6 m392 arena capa aisladora 0.8 73.6 m392 hidrofugo 40 3680 lts92 cemento portland CA 8 736 bol92 PIEDRA 6-20 5 460 m392 arena col y dinteles 5 460 m392 ladri portante 18*18*33 2200 202400 un92 ladri. No portante12*18*33 160 14720 un92 ladrillon 760 69920 un92 ladrillon chico 90 8280 un92 arena mamposteria 21 1932 m392 alambre n°14 12 1104 kg92 alambre n°17 5 460 kg92 fe 6 mm 4 368 barra92 fe 4,2mm 4 368 barra92 cemento portland 47 4324 bolsa92 hidralit 50 4600 bolsa
SALDO PARA TERMINAR 92 PLATEAS AL 13/05/2015CANT/P a PR ITEM PARAPETOS UNITARIO/P MAT. TOTAL
P U/PL U/PL92 Ladr. No portante 18*18*33 310 28520 un92 arena 2 184 m392 hidralit 4 368 bolsas92 cemento portland 4 368 bolsas
SALDO PARA TERMINAR 190 PLATEAS AL 13/05/2015CANT/P a PR ITEM REVOQUE GRUESO UNITARIO/P MAT. TOTAL
P EXTERIOR U/PL U/PL190 cemento portland 20 3800 bolsas190 arena 13 2470 m3190 hidralit 50 9500 bolsas190 hidrofugo 40 7600 lts
SALDO PARA TERMINAR 221 PLATEAS AL 13/05/2015CANT/P a PR ITEM REVOQUE GRUESO UNITARIO/P MAT. TOTAL
P interior U/PL U/PL221 cemento portland 10 2210 bolsas221 arena 15 3315 m3221 hidralit 60 13260 bolsas
SALDO PARA TERMINAR 297 PLATEAS AL 13/05/2015CANT/P a PR ITEM carga de techo UNITARIO/P MAT. TOTAL
P U/PL U/PL297 pintura asfaltica 40 11880 lts297 c250 8 2376 m3297 isocrete 2 594 bolsas297 cemento portland 3 891 bolsas
SALDO PARA TERMINAR 280 PLATEAS AL 13/05/2015CANT/P a PR ITEM yeso aplic UNITARIO/P MAT. TOTAL
P cielorraso U/PL U/PL280 cemento portland 2 560 bolsas280 yeso 18 5040 bolsas
SALDO PARA TERMINAR 297 PLATEAS AL 13/05/2015CANT/P a PR ITEM REVOQUE FINO UNITARIO/P MAT. TOTAL
P INTERIOR U/PL U/PL297 cemento portland 2 594 bols297 fino interior 40 11880 bols
SALDO PARA TERMINAR 297 PLATEAS AL 13/05/2015CANT/P a PR ITEM REVOQUE FINO UNITARIO/P MAT. TOTAL
P EXTERIOR U/PL U/PL304 cemento portland 2 608 bols304 fino interior 40 12160 bols
SALDO PARA TERMINAR 297 PLATEAS AL 13/05/2015CANT/P a PR ITEM CARPETA UNITARIO/P MAT. TOTAL
P U/PL U/PL312 cemento portland 4 1248 bolsas312 pegamento comun 2 624 bolsas312 adhesivo sika 2 624 bolsas312 c250 4 1248 m3
RESUMEN ARIDOSTOTAL ARENA 8434.6 m3 291
totalPIEDRA 6-30 460 m3 16TOTAL GRANZA 73.6 m3 3
RESUMEN CEMENTO HIDRALIT YESOTOTAL CEMENTO 15681 BOLSAS 26TOTAL HIDRALIT 51768 BOLSAS 86
YESO 5040 BOLSAS 8
RESUMEN HORMIGONES Y C250H-17 2601 M3 372
C-250 3624 M3 518
Nota. LOS ITEMS QUE NO FIGURAN EN ESTA LISTA AUN NO HAN TENIDO EJECUCION POR LO CUAL DEBEN CONSIDERARSE COMO SALDO 318 PLATEAS
mamposteria faltan 92 plateas460 dias 1 cuadrilla
35 cuadrillas para ejecutarlo en13 dias18 existentes17 faltan reasignar cuadrillas
bateas 10.0 BATEAS /DIA por 29 DIAS 6/16/2015bateas 2.0 BATEAS /DIA por 8 DIAS 5/22/2015bateas 1 BATEA CADA 2 DIAS TERMINA EN 6 DIA 5/20/2015
viaj. x 600 b 1.0 viaje/dia durante 26dias 6/13/2015viaj. x 600 b 2.0 viajes/dia durante 43 dias 7/4/2015viaj. x 600 b 1 viaje c/8 dias durante 24 dias 6/11/2015
VIAJES X 7M3 12.4 viajes/dia durante 30 dias 6/23/2015VIAJES X 7M3 8.6 viajes/dia durante 60 dias 7/25/2015
147 m3/dia sin veredas
LOS ITEMS QUE NO FIGURAN EN ESTA LISTA AUN NO HAN TENIDO EJECUCION POR LO CUAL DEBEN CONSIDERARSE COMO SALDO 318 PLATEAS
termina suministro