Upload
robert-roy-nichols
View
35
Download
1
Tags:
Embed Size (px)
Citation preview
| Steward Health Care SystemSuffolk Construction Company, Inc.2
“PARTNERSHIP”
| Steward Health Care SystemSuffolk Construction Company, Inc.3
PRECONSTRUCTION
| Steward Health Care SystemSuffolk Construction Company, Inc.4
TASKS
• Weekly Construction Meetings (A/E/C team only)• Sustainable Design Meetings (if applicable)• Public Approval Meetings (if applicable)• Site Diligence• Existing Condition Report• Subcontractor Development• Regulatory Approval• Design Review
| Steward Health Care SystemSuffolk Construction Company, Inc.5
PROJECT BUDGET
| Steward Health Care SystemSuffolk Construction Company, Inc.6
BUDGET DELIVERABLES
• Order of Magnitude Initial SF or Lump Budget - the rough starting point.
• Conceptual Design Budget with Full Constructability Report – CR#1– Including: Description, Issues, Existing Conditions,
Logistics, Master Campus Schedule, Project Specific Schedule, Conceptual Budget Estimate. Due 2 weeks from issuance of the design team document package.
| Steward Health Care SystemSuffolk Construction Company, Inc.7
BUDGET DELIVERABLES
• Schematic Design Budget with Full Constructability Report – CR#2– Including: Description, Issues, Updated deliverables to
all the above, and the first Engineering Constructability Matrix, with Design Team Input, Building Systems Narrative, and Value Management Log #1 and the official Budget #1 with Suffolk in house quantities in the schedule of values. Due 2 weeks from issuance of the design team document package.
| Steward Health Care SystemSuffolk Construction Company, Inc.8
BUDGET DELIVERABLES
• Design Documents Budget with Full Constructability Report – CR#3– Including: All the above updated deliverables; with new
schedules and logistics, and finer detail Engineering Constructability Matrix, which has been vetted and responded by the Steward Design Team, Value Management Log #2, and Budget #2 that has been sent out to at a minimum of 3 subcontractors; with rough bid tabs, and new updated in-house Suffolk quantities for comparison. With the list of Qualifications and Assumptions and Allowances and Hold Values known or anticipated to date. Due 3 weeks from issuance of the design team document package.
| Steward Health Care SystemSuffolk Construction Company, Inc.9
BUDGET DELIVERABLES
• GMP Contract Value to coincide with a final review of the design team’s 100 CD package that has answered and accounted for all Qualifications and Assumptions and Holds and Allowances from above.
| Steward Health Care SystemSuffolk Construction Company, Inc.10
CONSTRUCTABILITY REPORT
| Steward Health Care SystemSuffolk Construction Company, Inc.11
CONSTRUCTABILITY REPORT
• Description
• Technical Constructability Report
• Detailed Report by Section
• Summary of Phasing
| Steward Health Care SystemSuffolk Construction Company, Inc.12
ATTACHMENTS
• Floor Plans with
Remarks
• Engineering Matrix
• Architectural Drawings
• Fire Protection
Drawings
• Plumbing Drawings
• HVAC Drawings
• Electrical Drawings
• Logistics Plan
• Master Schedule for
the Campus
• Site Project Schedule
• Budget Estimate
• Historical Estimate
• Backup of Quantities
| Steward Health Care SystemSuffolk Construction Company, Inc.13
LOGISTICS PLAN
| Steward Health Care SystemSuffolk Construction Company, Inc.14
LOBBY LOGISTICS PLAN
| Steward Health Care SystemSuffolk Construction Company, Inc.15
SURGERY LOGISTICS PLAN
| Steward Health Care SystemSuffolk Construction Company, Inc.16
SCHEDULE
| Steward Health Care SystemSuffolk Construction Company, Inc.17
MASTER SCHEDULE
| Steward Health Care SystemSuffolk Construction Company, Inc.18
PROJECT SCHEDULE
| Steward Health Care SystemSuffolk Construction Company, Inc.19
BUDGET ESTIMATE
| Steward Health Care SystemSuffolk Construction Company, Inc.20
BUDGET ESTIMATE
| Steward Health Care SystemSuffolk Construction Company, Inc.21
ESTIMATE #1 WITH QUANTITIES
| Steward Health Care SystemSuffolk Construction Company, Inc.22
DISCUSSION
“PARTNERSHIP”
OPERATIONSProject Management
•Project Authorizations•Subcontractor Procurement•PCO’s & Contingency Authorizations•Requisitions•Meeting Minutes and Reports•Submittals/RFI’s•Future Meeting Topics
PROJECT AUTHORIZATIONS
• Should be based on agreed to scope/cost/Q&A’s
• Text and Exhibits generated by Suffolk
• Items requiring discussion, Liquidated Damages, Holiday,
Subguard, CCIP
Click icon to add picturePROJECT AUTHORIZATION
EXHIBIT A
SUBCONTRACTOR PROCUREMENT
• Suffolk “Exhibit B” – Scope of Work– Covers work not specifically shown or additional work
required– Distributed to Suffolk Project Team and Steward PM for
review and comment.• Subcontractor pricing is received, reviewed and tabulated
based on exhibit and distributed to Steward PM prior to “best and final for comment.
• Bid tabs and exhibits are forwarded to Suffolk Purchasing for best and final. Successful bidder is awarded project. Steward PM is notified.
LETTER OF RECOMMENDATION
• Suffolk PM generates Subcontractor award approval letter with Letter of Recommendation, Bid Tab & Exhibit B.
MEETING MINUTESAND PM LOGS/REPORTS
• Meeting Minutes will be broken into standard sections, indicate BIC, and date initiated.
• Minute items should be clear, concise and non-biased.• Meeting Minutes should be distributed within 24-48 hours of
meeting so they can be used as a tool.• Attachments weekly should include the following– 3 Week Look Ahead– Submittals– RFI’s– PCO’s/Contingency Authorization Log
MEETING MINUTES
3 WEEK LOOK AHEAD
SUBMITTALS
PCO AND CONTINGENCY LOG
CONTINGENCY AUTHORIZATIONS
PCO
OWNER CHANGE ORDER
REQUISITIONS
• Pencil Received by 5th of every month to Steward PM
• Comments Due from Steward PM By 10th
• Final Signed Version, Suffolk and Architect Due to Steward PM by 15th of the month– Preconstruction Req are Letter Bills– Construction Reqs (even if work occurs during
Preconstruction) are submitted on AIA G702, G703 & signed by Architect
REQUISITIONSFOR PRECONSTRUCTION
REQUISITIONSFOR PRECONSTRUCTION
REQUISITIONSFOR CONSTRUCTION
REQUISITIONSFOR CONSTRUCTION
FUTURE MEETING TOPICS
• CCIP/Subguard• Logistics• ICRA/ILSM• Scheduling• Signage/Postings• Shut Downs• Scheduling• A & E Deliverables
DISCUSSION