Sterlite Industries V. Union of India,

Embed Size (px)

DESCRIPTION

By Dafy George, 4thYear, B.A LL.B (Hons.), Amity Law School Delhi

Citation preview

  • LAW MANTRA THINK BEYOND OTHERS (National Monthly Journal, I.S.S.N 2321 6417)

    Sterlite Industries V. Union of India

    Introduction

    Indian Supreme Court recently took a very important environment related decision in Sterlite

    Industries case, relating to running of industries which lead to environmental degradation.

    Sterlite Industries is a public listed company which operates a copper smelting plant since 1996

    at SIPCOT Industrial complex, Thoothukudi, Tamil Nadu. This case came up in the Supreme

    Court because of the contradicting claims by Sterlite Industries and the National Green

    Tribunal decision. Sterlite Industries had been following all prescribed conditions for running

    such an industry but due to the complaints by the public of that area enquiry was conducted

    and after an initial okay action was taken against it due to the huge adverse impact, of

    manufacturing process undertaken for production, on the environment. Consequently Supreme

    Court has imposed a penalty of Rs. 100 Crore but has allowed continued operations, with

    regular checks. Findings of the Court needs to be looked into to see why exactly the Bench

    came to such a conclusion and how. Also keeping in mind the past environmental

    jurisprudence which has come under the limelight due to the recent mining case controversy

    the somewhat lenient stand needs to be understood in its all entirety.

    First, the Court had to decide whether the High Court had the authority to interfere in the

    environment clearance processes provided by the Ministry of Environment and Forests. High

    Court reference to decisions of Supreme Court on Sustainable Development, Precautionary and

    Polluter Pays Principles and Public Trust Doctrine was seen to be futile as it failed to see

    decision like the three judge bench in Lafarge Umiam Mining (P) Ltd. v. Union of India & Ors.

    Where tests to be based on anvil of well recognized principles of judicial review. It was said if

    the environmental clearance granted by the competent authority is clearly outside the powers

    given to it by the Environment (Protection) Act, 1986, the Environment (Protection) Rules,

    1986 or the notifications issued there under, the High Court could quash the environmental

    clearance on the ground of illegality. If the environmental clearance is based on a conclusion

    so unreasonable that no reasonable authority could ever have come to the decision, the

    environmental clearance would suffer from Wednesbury unreasonableness and the High Court

    could interfere on the ground of irrationality. And, if the environmental clearance is granted in

  • breach of proper procedure, the High Court could review the decision of the authority on the

    ground of procedural impropriety. Decision of the Central Government to grant the

    environmental clearance can see to be reasonable as same was provided after detailed

    examination of rapid EIA/EMP, NOC, and proper qualifications was ensured for operation. It

    was noted that authorities under the Environment Protection Act, 1986 and Rules, notification

    are to determine scope of project, extent of screening and assessment of cumulative effects.

    Also, as long as the prescribed statutory process for clearance is followed and EIA isn't found

    to be irrational to frustrate its very purpose the Court is not to interfere with the decision of the

    prescribed authorities under the veil of judicial review. The examination of the implications of

    Supreme Courts innovations for environmental jurisprudence reveals that the application of

    innovative methods to resolve environmental disputes and implement Court orders is certainly

    a deviation from the usual adjudication function of the Court. While the procedural innovations

    have widened the scope for environmental justice through recognition of citizens right to

    healthy environment, entertaining petitions on behalf of affected people and inanimate objects

    and creative thinking of judges to arrive at a decision by making spot visit, substantive

    innovations have redefined the role of Court in the decision-making process through

    application of environmental principles and expanding the scope of environmental

    jurisprudence. Given the crisis within the executive and legislature in discharging their

    Constitutional duties, the Supreme Courts innovative methods have attempted to arrest the

    dysfunctional trend of other organs and enable the effective enforcement of environmental

    laws. However, in reminding other organs about their Constitutional duties and enforcing

    fundamental right of citizens, the Supreme Court has at times, crossed its boundaries and

    started interfering in the very basic affairs of environmental management. In resolving more

    than 100 environmental cases since 1980, the Supreme Court has continuously engaged itself

    in the management and resolution of environmental conflicts and thereby increased the

    countrys dependence on the Court for environmental protection. This dependence on a judicial

    institution that has already exceeded the boundaries of its responsibilities has been further

    complicated by the lack of monitoring of the Supreme Courts orders and the vagueness of the

    legislative and executive roles regarding environmental issues. With its intervention in the

    interpretation of environmental policy and implementation process, the potential for resolving

    environmental conflict is hardly over. The review of environmental cases shows that there has

    been no uniform cooperation from the implementing agencies to effectively implement the

    Court directions. It is also observed that most of the innovative methods introduced by the

    Court have neither been followed consistently nor been institutionalised to make a long term

    impact for the environmental jurisprudence process.

  • Secondly, the point of contention with respect to the location of the Industry and closure due to

    its proximity with population was taken into consideration. The reason given by the High Court

    in coming to conclusion was that the TNPCB had stipulated in the Consent Order that the

    appellant-company has to ensure that the location of the unit should be 25 kms. away from

    ecologically sensitive area and as per the report of NEERI, the plant of the appellants was

    situated at a distance of 6 kms. Of Vanthivu, 7 kms. Of Kasuwar and 15 kms. Of Karaichalli

    and Villanguchalli and these four villages is part of the twenty one islands in the Gulf of

    Munnar. Hence, the High Court directed closure of the plant because the appellant-company

    has violated the condition of the Consent Order issued by the TNPCB under the Water Act.

    Extract from the Consent Order dated 22.05.1995 of the TNPCB issued under the Water Act

    makes it clear that the appellant-company was given consent to establish its plant in the

    SIPCOT Industrial Complex, Melavittan Village, Tuticorin Taluk.Therefore, the appellants

    were given consent to establish their plant in the SIPCOT Industrial Complex, which as per the

    NEERI report is within 25 kms. Of four of the twenty one islands in the Gulf of Munnar. On

    the other hand, a condition was stipulated in the consent order that the appellants have to

    ensure that the location of the unit is 25 kms. away from ecological sensitive area. It thus

    appears that the TNPCB while granting the consent under the Water Act for establishment of

    the plant of the appellants in the SIPCOT Industrial Complex added the above requirement

    without noting that the SIPCOT Industrial Complex was within 25 kms. From ecological

    sensitive area. Since, however, the Consent Order was granted to the appellant-company to

    establish its plant in the SIPCOT Industrial Complex and the plant has in fact been established

    in the SIPCOT Industrial Complex, the High Court could not have come to the conclusion that

    the appellant-company had violated the Consent Order and directed closure of the plant on this

    ground. But the Supreme Court observed that for the preservation of ecology the plant could be

    asked to be shifted in some future time. Especially because concerned area, Gulf of Munnar, as

    per State statutes and material evidences are noted to be ecologically sensitive areas. Central

    Government being the prescribed authority may under Environment Protection Rules, 1986

    prohibit or restrict of such area.

    Finally the order of closure of Industry by the High Court was decided upon and as to whether

    the same could be done even after receiving NOC from Tamil Nadu Pollution Control Board

    for continued operation. There were certain conditions prescribed by the TNPCB which were

    later on relaxed but then same can't be contested against as it has been already seen earlier that

    over judicial activism would result in dilution of the powers of other organs of government.

  • But then we are at a loss to the fact as to why exactly could it not be enquired as to why this

    exemption from 250 m. to minimum 25 m. was allowed by the SPCB.

    The High Court in the impugned judgment has not recorded any finding that there has been any

    breach of the mandatory provisions of the Air Act or the Rules there under by the TNPCB by

    reducing the green belt to 25 meters. Nor has the High Court recorded any finding that by

    reducing the width of the green belt around the battery limit of the industry of the appellants

    from 250 meters to 25 meters, it will not be possible to mitigate the effects of fugitive

    emissions from the plant. The High Court has merely held that the TNPCB should not have

    taken such a generous attitude and should not have in a casual way dealt with the issue

    permitting the appellant-company to reduce the green belt particularly when there have been

    ugly repercussions in the area on account of the incidents which took place on 05.07.1997

    onwards. It was for the TNPCB to take the decision in that behalf and considering that the

    appellants plant was within a pre-existing industrial estate, the appellant could not have been

    singled out to require such a huge green belt. Out of the 30 directions issued by the TNPCB,

    the appellant-company has complied with 29 directions and only one more direction under the

    Air Act was to be complied with. As the deficiencies in the plant of the appellants which

    affected the environment as pointed out by NEERI have now been removed, the impugned

    order of the High Court directing closure of the plant of the appellants is liable to be set aside.

    The NEERI reports of 1998, 1999, 2003 and 2005 show that the plant of the appellant did

    pollute the environment through emissions which did not conform to the standards laid down

    by the TNPCB under the Air Act and through discharge of effluent which did not conform to

    the standards laid down by the TNPCB under the Water Act. On account of some of these

    deficiencies, TNPCB also did not renew the consent to operate for some periods and yet the

    appellants continued to operate its plant without such renewal.

    For such damages caused to the environment from 1997 to 2012 and for operating the plant

    without a valid renewal for a fairly long period, the appellant-company obviously is liable to

    compensate by paying damages. In M.C. Mehta and Another vs. Union of India and Others, a

    Constitution Bench of this Court held:

    The enterprise must be held to be under an obligation to provide that the hazardous or

    inherently dangerous activity in which it is engaged must be conducted with the highest

    standards of safety and if any harm results on account of such activity, the enterprise must be

    absolutely liable to compensate for such harm and it should be no answer to the enterprise to

  • say that it had taken all reasonable care and that the harm occurred without any negligence on

    its part.

    The Constitution Bench in the aforesaid case further observed that the quantum of

    compensation must be co-related to the magnitude and capacity of the enterprise because such

    compensation must have a deterrent effect and the larger and more prosperous the enterprise,

    the greater must be the amount of compensation payable by it.

    Considering the magnitude, capacity and prosperity of the appellant- company, Supreme Court

    was of the view that the appellant-company should be held liable for a compensation of Rs.

    100 crores for having polluted the environment in the vicinity of its plant and for having

    operated the plant without a renewal of the consents by the TNPCB for a fairly long period and

    according to us, any less amount, would not have the desired deterrent effect on the appellant-

    company. The aforesaid amount will be deposited with the Collector of Thoothukudi District,

    who will invest it in a Fixed Deposit with a Nationalized Bank for a period of five years. The

    interest there from will be spent for improving the environment, including water and soil, of

    the vicinity of the plant after consultation with TNPCB and approval of the Secretary,

    Environment, and Government of Tamil Nadu.

    The very main point of concern after this particular case can be seen as to the limitation which

    the judiciary is imposing on itself. For separation of powers yes it is true that there should be

    minimum overlapping and clashes but then judiciary is the sole organ of government which

    can ensure the citizens their basic rights. In light of recent events where at one hand people are

    ensured right to unadulterated food through article 21 and such an instance where the very

    living condition of people was in plight the needs to be acknowledged. Valuation of loss to the

    environment caused is contestable for once our callous attitude gets imprinted on nature its

    very hard to set it right. Especially in light of the urgent relieve required as degradation of

    nature here in India has reached to very maximum and stringent measures are required to

    preserve I, even if not in its once pristine form. If political motivations are guiding these now

    then yet again loss would be suffered by us only as we would be the ones walking on barren

    lands, surrounded by metal pieces, looking for that last piece of shade and water eventually.

    By: - Dafy George, 4thYear, B.A LL.B (Hons.) Amity Law School Delhi