Welcome to the new Reading Branch Library

Step-by-Step Look At How We Built The New Reading Branch Library

Embed Size (px)

Citation preview

Page 1: Step-by-Step Look At How We Built The New Reading Branch Library

Welcome to the new Reading Branch Library

Page 2: Step-by-Step Look At How We Built The New Reading Branch Library

Ground was broken on April 21, 2014.

Page 3: Step-by-Step Look At How We Built The New Reading Branch Library

In June, 2014, work officially began. The first job was to drill the geothermal well.

Page 4: Step-by-Step Look At How We Built The New Reading Branch Library

July, 2014 ‒ Workers install reinforcing bars for the branch foundation.

Page 5: Step-by-Step Look At How We Built The New Reading Branch Library

Glass containers were unearthed at the site including (left to right) a 1920 Nu-Grape soda bottle, a WT Wagner bottle, and a cottage cheese container.

Page 6: Step-by-Step Look At How We Built The New Reading Branch Library

August, 2014 ‒ The foundations are finished and the under slab electric and plumbing are nearly complete.

Page 7: Step-by-Step Look At How We Built The New Reading Branch Library

September, 2014 ‒ Steel columns are installed and cranes are used to lift the frame into place.

Page 8: Step-by-Step Look At How We Built The New Reading Branch Library

October, 2014 ‒ Exterior stud walls are installed and sheathing is attached.

Page 9: Step-by-Step Look At How We Built The New Reading Branch Library

November, 2014‒ Masons begin to install brick and stone on the exterior facade.

Page 10: Step-by-Step Look At How We Built The New Reading Branch Library

January, 2015 ‒ The interior walls are taking shape.

Page 11: Step-by-Step Look At How We Built The New Reading Branch Library

February, 2015‒ More

finishing touches are

added to the interior,

including paint, tile and

flooring.

Page 12: Step-by-Step Look At How We Built The New Reading Branch Library

March, 2015 ‒ Glass installation begins and the branch gets new fountains and a refillable water

bottle station.

Page 13: Step-by-Step Look At How We Built The New Reading Branch Library

April, 2015 ‒ The interior is taking shape and work begins on the sidewalks and parking lot.

Page 14: Step-by-Step Look At How We Built The New Reading Branch Library

April, 2015‒ Final touches are made to the drive-thru and book drop area.

Page 15: Step-by-Step Look At How We Built The New Reading Branch Library

May, 2015 ‒ The branch gets carpeting and a sliding glass entry door.

Page 16: Step-by-Step Look At How We Built The New Reading Branch Library

June 18, 2015 ‒ Last minute preparations are made before the opening.

Page 17: Step-by-Step Look At How We Built The New Reading Branch Library

June 18, 2015 ‒ Last minute preparations are made before the opening.

Page 18: Step-by-Step Look At How We Built The New Reading Branch Library

Welcome to the new Reading Branch Library! Please explore the building and enjoy complimentary