14. Steel sheet pile driving flowchart
1) Individual driving/without existing steel sheet pile
Carrying-in of driving machine,material, and steel sheet pile
Installation of machine and material atspecified location
Setting of the reaction stand horizontallyon the driving normal line and installation
of pile driver and weight
Driving reaction steel sheet pileTrial operation and adjustment of Still
Worker
Start of driving reaction steel sheet pile(3 sheets for 90t and 4 sheets for 100-150t
class)
Completion of driving reaction steel sheetpile
Removal of reaction stand and weight
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclinationDriving 1st steel sheet pile
Completion of steel sheet pile up to theplanned top
Driving steel sheet pile Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclination
Driving steel sheet pile until self-driving ispossible
Forward self-traveling of Still Worker
Repetition from the 2nd pileonward
Completion of driving steel sheet pile upto the planned top
Collection of driving machineand material
Removal of driving machineand material
- 27 -
2) Individual driving/with existing steel sheet pile
Carrying-in of driving machine,material, and steel sheet pile
Installation of machine and material atspecified location
InstallationInstallation of pile driver on existing steel
sheet piles
Trial operation and adjustment of StillWorker
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclinationDriving 1st steel sheet pile
Completion of steel sheet pile up to theplanned top
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclination
Driving steel sheet pile until self-driving ispossible
Forward self-traveling of Still Worker
Driving steel sheet pile
Repetition from the 2nd pileonward
Completion of driving steel sheet pile upto the planned top
Collection of driving machineand material
Removal of driving machineand material
- 28 -
3) Driving together with water jet/without existing steel sheet pile
Carrying-in of driving machine,material, and steel sheet pile
Installation of machine and material atspecified location
Setting of the reaction stand horizontallyon the driving normal line and installation
of pile driver and weight
Trial operation and adjustment of StillWorker and water jet pump
Driving reaction steel sheet pileStart of driving reaction steel sheet pileusing water jet (3 sheets for 90t and 4
sheets for 100-150t class)
Completion of driving reaction steel sheetpile
Removal of reaction stand and weight
Attaching water jet pipe to steel sheet pile
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclination
Completion of driving steel sheet pile upto the planned top
Stopping water jet pump
Driving 1st steel sheet pile
Removal of water jet pipeDriving steel sheet pile
Attaching water jet pipe to steel sheet pile
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclination
Driving steel sheet pile until self-driving ispossible
Forward self-traveling of Still Worker
Completion of driving steel sheet pile upto the planned top
Stopping water jet pump
Repetition from the 2nd pileonward
Removal of water jet pipe
Removal of driving machineand material
Carrying-out of drivingmachine and material
- 29 -
4) Driving together with water jet/with existing steel sheet pile
Carrying-in of driving machine,material, and steel sheet pile
Installation of machine and material atspecified location
InstallationInstallation of pile driver on existing steel
sheet piles
Trial operation and adjustment of StillWorker and water jet pump
Attaching water jet pipe to steel sheet pile
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclination
Completion of driving steel sheet pile upto the planned top
Stopping water jet pump
Driving steel sheet pile
Driving 1st steel sheet pile
Removal of water jet pipe
Attaching water jet pipe to steel sheet pile
Clamping steel sheet pile with chuck
Driving start after confirmation of drivingnormal line and right-left/forward-
backward inclination
Driving steel sheet pile until self-driving ispossible
Forward self-traveling of Still Worker
Completion of driving steel sheet pile upto the planned top
Stopping water jet pump
Repetition from the 2nd pileonward
Removal of water jet pipe
Removal of driving machineand material
Carrying-out of drivingmachine and material
- 30 -
15. Dimensional drawing of trench excavation
Dimensional drawing of trench excavation
W2Dimensions
Machine typeW1
① ②H
80t class 1,040 540 940 450
90t class 1,080 540 940 450
100t class 1,080 800 1,200 450
150t class 1,140 800 1,200 450
150t class machine dedicated to wide steel sheet piles 1,250 750 1,350 460
Notes: 1. (1) Hoisting by crane after driving the 2nd pile/(2) Self-traveling2. “F” in the cross section of trench excavation is the thickness of the cover plate.
Plain view of trench excavation
Cross section of trench excavation
Shaft (start/finish)
Still Worker
Steel sheet pile
80t class
Major specificationsDriving force (t) 80Extracting force (t) 85Stroke (mm) 700Driving rate (m/min) 3.7-22.0Extracting rate (m/min) 3.3-27.0Applicable type of steel sheet pile SP IA-IVA
Operation method Radio controlMast tilting angle 5° forward/backwardPile driver moving method Self-travelingWeight of pile driver (kg) 4,500Motive power (PS) 125
Str
oke
90t class
Major specificationsDriving force (t) 90Extracting force (t) 100Stroke (mm) 800Driving rate (m/min) 2.7-18.0Extracting rate (m/min) 2.4-20.0Applicable type of steel sheet pile SP IA-IVA
Operation method Radio controlMast tilting angle 5° forward/backwardPile driver moving method Self-travelingWeight of pile driver (kg) 5,500Motive power (PS) 125
Str
oke
100t class
Major specificationsDriving force (t) 100Extracting force (t) 110Stroke (mm) 800Driving rate (m/min) 2.3-18.0Extracting rate (m/min) 2.0-20.0Applicable type of steel sheet pile SP IA-IVA
Operation method Radio controlMast tilting angle 5° forward/backwardPile driver moving method Self-travelingWeight of pile driver (kg) 5,900Motive power (PS) 125
Str
oke
150t class
Major specificationsDriving force (t) 150Extracting force (t) 170Stroke (mm) 800Driving rate (m/min) 1.6-11.0Extracting rate (m/min) 1.5-16.0Applicable type of steel sheet pile SP IA-IVA
Operation method Radio controlMast tilting angle 5° forward/backwardPile driver moving method Self-travelingWeight of pile driver (kg) 7,900Motive power (PS) 125
Str
oke
150t class machine dedicated to wide steel sheet piles
Major specificationsDriving force (t) 150Extracting force (t) 160Stroke (mm) 800Driving rate (m/min) 1.8-20.0Extracting rate (m/min) 1.9-16.0Applicable type of steel sheet pile SPII-IV W・FSP5・6L・SM-J
Operation method Radio controlMast tilting angle 5° forward/backwardPile driver moving method Self-travelingWeight of pile driver (kg) 10,400Motive power (PS) 200
Str
oke