    BOOK -2

    STEAM TURBINE TRAINING

    INSPECTION MAINTENANCE

    PREPARED & PRESENTED BY

    DAMARDHONO TASMAN

    Senior Service Engineer / TrainerJAKARTA, SEPTEMBER 25 - 26, 2001

  • 8/10/2019 steam turbine basic training - module 2.ppt

    2/61

    UPAYA MEMPERPANJANG USIA PAKAI DAN PEREMAJAAN

    UNIT STEAM TURBINE

    Introduction Steam turbines are made to be able to achieve the life effetif until 20-30 years.

    Steam turbine operating experience in Indonesia showed a shorter life span than that in Japan

    (Ref. to Mistsubishi Heavy Industries Annual Report October 1, 1997.)

    number of Units

    0 - 10 11- 20 21- 30 3 0 - Years

    48%

    8 %

    30

    20

    10

    0

    PENGARUH JUMLAH ( N )

    START UP DAN SHUT DOWN

    WHY?

    St. Turbines operated in ( N + X )St. Turbines Operated in ( N )

    (TAKEN FROM THE OPERATIONOF COMPARATIVE STUDY OF ST

    MITSUBISHI)

    13%

    12 %

    42%

    33%

    Number of start - upsNumbero

    fUnits

    12%

    44%

    8%

  • 8/10/2019 steam turbine basic training - module 2.ppt

    3/61

    DAMAGE / ACCIDENT ST

    Piping

    &

    Equipment10 %

    Pump

    10 %

    Hreat

    Exchanger

    26 %

    Turbine

    Proper

    54 %

    Accident / damage to the Fossil

    Power Plant( Data 1981 - 1996 ) Accident / damage to the ST( Data 1981 - 1996 )

    Turbine Propoer

    Cylinders

    Rings

    14 %

    Rotor

    &

    Blade 21 %

    Valve

    22 %

    ControlSystem

    22 %

    Pipings

    9 %

    Bearing

    10 %

    Others

  • 8/10/2019 steam turbine basic training - module 2.ppt

    4/61

    Overhaul Inspection

    Inspection Intervals Steam / Gas Turbine

    Years AfterCommissioning 1 2 3 4 5 6 7 8 9 10 11 12

    Steam

    Turbine

    GasTurbine

    Major Overhaul ( Overhaul of Turbine )

    Minor Overhaul ( S/ T : Overhaul of Valves

    G/T : Overhaul of High Temp. Parts )

    Pressure & Temperature pada

    Steam Turbine : 316 kg / cm2 dan 593 0C

    Gas Turbine 1450 0C

  • 8/10/2019 steam turbine basic training - module 2.ppt

    5/61

    Penurunan Usia Pakai St. Turbine must be faced on several circumstances:

    a. Rotating parts: Power and Power Centrifugal stress due to heat

    b. Stationary part: Pressure and thermal stress

    CreepE

    longation

    Rupture (Crushed

    / broken)

    Macro

    Crack

    Cavity

    ChainCavity (Belobang soft)

    Time

    Micro

    Crack

    Diagram of Creep ( merambat ) Life Consumption

    Decrease in the age of

    technical condition ST

    depends on the number ofhours of operation.

  • 8/10/2019 steam turbine basic training - module 2.ppt

    6/61

    Aged - Deterioration Mode and Damage of Steam Turbine

    DETERIORATION

    (defective / damaged)

    CREEP( retak yang tumbuh

    )

    LOW CYCLEFATIGUE

    EMBRITTLEMENT

    CORROSION

    SCC

    CORROSION

    FATIGUE

    CRACKING

    CRACKING

    BRITTLE

    FRACTURE

    CRACKING

    CRACKING

    BLADE TENON

    BLADE GROVE

    HEAT GROOVE

    DISC GROOVE

    ROTOR CENTER BORE

    LOW PRESSURE

    STATIONARY VANE

    DISC GROOVE

    BLADE

    DETERIORATION MODE DAMAGE LOCATION

  • 8/10/2019 steam turbine basic training - module 2.ppt

    7/61

    Creep (Damage grows) Occur in the rotor rotors, casings, blades, bolts bertemperature the nearby areas of high and

    high pressure.

    In the tda -2. Voltage occurs at high temperature. Teru grow elongated and finally broken /

    fracturedMaterial becomes soft and tender holes grow, converge into a large hole and growing.

    Low- Cycle Fatigue ( LCF) occurs due to the effects of repeated stress due to thermal and style changed as a result of

    temperature - robah.Because the change is too often the case load and / or frequent stop / start.

    Cracks occurred on the part of the turbine that often receives load and / or repeated deflection.

    Various Aged Deterioration Modes

  • 8/10/2019 steam turbine basic training - module 2.ppt

    8/61

    HEAT DISTRIBUTION IN BLADES

    HEAT DISTRIBUTION IN BLADES

    Various Aged Deterioration Modes

    DISTRIBUSI STEAM

    FLOW PADA BLADES

    BLADES WEARING

  • 8/10/2019 steam turbine basic training - module 2.ppt

    9/61

    Embrittlement (material damage to the intermolecular,

    weakened due to high heat)

    When ferrite alloy steel (material turbine) saddled for along time at a specific temperature is high,

    consequently the quality will decrease. If it happens on

    the rotor, will mrnjadi problem.

    Inspection and maintenance schedule should be strictly

    implemented.

    Stress Corrosion Cracks ( SCC ) MATERIAL THAT HAPPEN TO RECEIVE THE

    STRESS environment CORROSIVE.

    ESPECIALLY IN AREAS THAT WET / HUMIDCorrosion Fatigue

    RESULT MATEERIAL corrosive decline RESISTANCE

    TO STRESS AND vibration.

    At low temperatures betweenmolecules tersusub each meeting

    and strongly bound

    Due to the high heat, the material

    berexpansi / expands, bonds

    weakened, could deformation or

    fracture

    FOR BONDING BETWEEN MOLECULES weak, tenuous,

    LOADED WITH MOISTURE AND CORROSION

    TTUMBUH (SCC). WHEN OPERATED WITH

    CONTINUOUS HIGH COST, MATERIAL BEING TIRED

    (CF)

    Lif E l ti

  • 8/10/2019 steam turbine basic training - module 2.ppt

    10/61

    Life Evaluation

    Examination of the overhaul is done using NDE methods to obtain the possibility of crack.

    - Non - Destructive Examinations (NDE)

    1. Dye Penetrant Examination (PT) (the liquid will be entered into the soft crack)

    2. Magnetic Particle Examination (MT)3. Ultrasonic Examination (UT)

    - Life Evaluation

    1. Evaluate by calculating the specific formula.

    2. Non - Destructive Evaluation

    3. destructive Evaluation

    Deterioration

    ModeCalculation NDE DE

    Creep FEMFenit Element Method

    Hardness ReplicationA-Parameter Method

    Miniature

    Creep Test

    Low - CycleFatigue FEM

    X-ray Diffraction

    Replication

    ----

    Embrittlement ---- Chemical EtchingSmall Punch

    Test

    Corrosion

    Fatigue SCC---- Replication ----

    E l b C l l i

  • 8/10/2019 steam turbine basic training - module 2.ppt

    11/61

    Evaluate by Calculation

    Finite Element Method (FEM) is used to calculate age

    Maximum Creep Damage

    51

    47

    43

    39

    35

    31

    27

    23

    19

    15

    11

    7

    3

    0

    Creep Damage ( % )

    With a high-tech analysis, creep stress analyzes by comparing the color change and

    difference-2 at start-up and stop, we can estimate the stress distribution caused by creepand / or with a model (simulation) analysis of 3 - dimensional. (With the aid of computers)

  • 8/10/2019 steam turbine basic training - module 2.ppt

    12/61

    Non - Destructive Evaluation

    Used to detect peertumbuhan creep or fatigue damage.

    Three types of damage

    1. creeps

    - Material that had generally experienced softening creeps.- Evaluation of the Micro-hardness test and inspection structure

    - Violence is reduced at the center of both ends of the rotor.

    2. fatigue Damage

    - Structure Observation (Measurement of Microscopic Crack)

    - X - ray Diffraction

    3. embrittlement- Occurs because of a separate bonding between molecules in different

    materials / metallurgy process is less good

    (Especially on the elements of P and Sn)

    Evaluation by damaging / Destructive Evaluation

    Samples taken from the turbine is examined to determine the quality of the remaining material

    and the rest of the age estimates.

    - By "Small Punch Test Method" for evaluating material properties 2

    - By "Miniature speciment creep" for the evaluation of creep properties 2.

  • 8/10/2019 steam turbine basic training - module 2.ppt

    13/61

    LIVE EXTENSION PROGRAM

    UPAYA MEMPERPANJANG USIA PAKAI ST TURBINE

  • 8/10/2019 steam turbine basic training - module 2.ppt

    14/61

    UPAYA MEMPERPANJANG USIA PAKAI ST. TURBINE

    Damage to KOMPONENT

    Creep

    Fatigue

    Embrittlement

    Corrosion

    Erosion / wearing

    Daily

    Operation

    Result

    Overhaul

    Inspection

    Result

    Life

    Evaluation

    Amended Operating Environment

    Operation in the future by DSS

    Extended intervals between

    overhauls

    The cost of surgery decline

    Economical

    assessment

    Repair

    Renewal

    Plant

    Renovation

    PlantExtension

    Plant Life Extension Program

    PlantLifeExtension

    Menu of Advances Technologies for Steam Turbine

  • 8/10/2019 steam turbine basic training - module 2.ppt

    15/61

    Menu of Advances Technologies for Steam Turbine

    1. Integral Shroud Blade (belt made integrally with the blade tip blades)

    2. 3 - Dimensional Design Reaction Blade

    3. Luggidized Blade Root & Groove Design (

    4. Boron Coated Nozzle

    5. Advanced 12 % Kr HIP ( High - Intermediate Pressure ) Rotor6. Super 9 % Kr Reheat Valves

    shroud

    blade base

    blade

    Integral Shroud Blade

  • 8/10/2019 steam turbine basic training - module 2.ppt

    16/61

    Design yang

    disempurnakan

    design lama

    100% = new condition

    C1

    C2

    to t1 t2 service time

    Service live

    expectancy C1 & C2 = Different status of conditionfound at t1 & t2

    Kr = Condition after repair

    Cm = Condition after modification

    Kr

    Cm

    fault line

    breakdown

    Live curve with preventive maintenance

    Live curve without maintenance

    P d i Lif E t i P i St P

  • 8/10/2019 steam turbine basic training - module 2.ppt

    17/61

    Procedures in Life Extension Program in Steam Program

    Step 1

    1. Learn how the daily operations and the results of the examination at

    the time of overhaul

    2. Plan application. Life Extension on turbine components

    Step 2

    1. Implement Life Extension program on components

    2. Evaluation of the remaining life of the component before Life Extension

    3. Plan Repair, Renewal and Renovation Komponents

    Step 31. Implementation Repair, Renewal and Renovation Works.

    Turbine Life Extension Program will benefit -2 follows. :

    a. Turbine service life is longer than that in the design

    b. Prevent accidents (forced shut - down) at the time of the operation

    c. Savings in maintenance

    I i i t t i t th d f LP bl d

  • 8/10/2019 steam turbine basic training - module 2.ppt

    18/61

    Stationary Vane dengan

    Remover Drain

    rotating blade

    stationary vane

    Drain

    Steam with

    Water droplet

    A A

    A-A

    Turbine installed on LP (Low spht / High saturated steam with condensate

    water point)

    Blades / stator vanes on the LP comes with a specific shape for catching

    channel and issued a point-2 water

    To reduce erosion from water droplets along the edge of the rotary blade

    edges.

    Stationary Vanes dengan Drain Remover

    Increasing resistance to erosion at the end of LP blades

    A A

    Ruggidized Blade Root & Groove design

  • 8/10/2019 steam turbine basic training - module 2.ppt

    19/61

    Ruggidized Blade Root & Groove design

    Damage due to "creep" in the area of high temperature and "corrosion fatigue / SCC in the lower

    temperatures can occur in Blade Root (foot blades) and Blade Grooves (groove on the wheel).

    Derngan root design modifications and improvements, we can reduce the local voltage (local)

    applied eg. Increase the area of contact with the root area of the rotor blades and groves

    Lowering the voltage kponsentrasi

    old design modification /Ruggedized

    STRENGTHENING Blade Root & Groove (SALURAN) Design :

    1. Enlarged Blade Root & Groove

    2. Enlarged Corner Radius

    3. Increase of Durability against SCC and Corrosion Fatigue

    Boron Coated Nozzle

  • 8/10/2019 steam turbine basic training - module 2.ppt

    20/61

    Applied in Control Stage Nozzle vane

    Anti - Particle Erosion Coating

    Boron Diffusion Coating

    Very Hard and Thin Coated Layer

    Higher Durability Nozzle segmentpada first stage

    Boron Coated Blades

    stationary blades

    rotor / cylinder

  • 8/10/2019 steam turbine basic training - module 2.ppt

    21/61

    Mineral dan Silica Deposits pada Steam Turbines

    Cause, Source and Type of Deposit

    Cause:

    Bodies / foreign material carried by the steam flow.

    Origin:

    Tekanam steam turbine in high berexpansi will form a "steam solved" (steam polluted with moisture).

    Type of Deposits:

    2 main groups:

    1. "Water-soluble" or water in the steam (found in the high and intermediate pressure section of theturbine, in the form of mineral deposits).

    2. "Water-insoluble" or no water in the steam / separate encountered at the end of the intermediate

    section and the low pressure in the form of silica sediments

    Prevention of Deposits

    1. Steam purity is influenced by:

    - Feed-water quality,

    - Steam boiler models

    - Boiler design

    - Boiler operation

    2. Boiler with a pressure of more than 40 bars require demineralization process l

    Mineral dan Silica Deposits didalam Steam Turbines

  • 8/10/2019 steam turbine basic training - module 2.ppt

    22/61

    Akibat adanya Deposits

    Deposits are formed mainly in control valves, especially in local (directional steam nozzle into

    turbuine) and moving blades (blade on the rotor).

    This deposit will be changed the shape of the surface becomes rough and the blades are easycorrosion wound surface

    Adverse effect as a result of deposits:

    1. Economic Affects

    - Decreased ability to make changes in steam steam into mechanical tenagga, meaning

    reduced turbine out.

    - Lowering Efficiency (steam consumption, high normal load)

    deposits

    L. k. 500 grams deposits on the entire surface

    of the blades will result in decreased efficiency

    sebedar 1%

    Mineral dan Silica Deposits didalam Steam Turbines

    Mineral and Silica Deposits in Steam Turbines

  • 8/10/2019 steam turbine basic training - module 2.ppt

    23/61

    Mineral and Silica Deposits in Steam Turbines

    Overloading and decreased reliability in operation

    thrust force thrust force

    Ft

    Ft

    source ofvibration

    thrust steam

    from nozzle

    thrust steamfrom nozzle

    clean surface deposited surface(Compare force Ft and Fa)

    Ft

    Ft

    Rough surfaces cause the steam flow turbulence (swirling) to produce turbine output at the

    desired level, means should add pressure steam (the amount of steam needed to grow) the

    other is due to increase pressure thrust (overloading the thrust bearing)

    Bending stress on the blades increasesVibration increases in blades than the natural vibration.

    Uneven distribution on the entire surface of the blades will be rumbling / rough

    Deposits on the valve will reduce the smooth flow of steam

    Fa Fa

    Mineral and Silica Deposits in Steam Turbines

  • 8/10/2019 steam turbine basic training - module 2.ppt

    24/61

    Corrosion Effects

    e a a d S ca epos ts Stea u b es

    Steam basah

    chlorides

    silica other salt

    Corrosion Attack

    1. Pitting (pit-soft 2)2. Corrosion fatigue (decreased endurance / fatigue due to

    rust)

    3. Stress corrosion (due to reduced cross-sectional area due

    to rust blades).

    Damages Decrease Efficiency Vibration

    Shorter Live Time

    High Cost

    Tindakan :

    1. Supervise of Steam Quality

    2. Feedwater Treatment

    3. Detect the Deposits

    Mineral and Silica Deposits in Steam Turbines

  • 8/10/2019 steam turbine basic training - module 2.ppt

    25/61

    Mineral and Silica Deposits in Steam Turbines

    Removing of Deposits

    1. Water - Soluble Deposits ( minerals )

    Cuci dengan menggunakan kondensat

    - Beda temperatur antara cylinder / shell tidak boleh

    mencapai 300C.- Beda temp. antara silinder belahan atas dan sinder

    belahan bawah tidak boleh lebih dari 400C. Kondensat

    jangan sampai masuk ke live steam line.

    - Kondenser harus di prop / sumbat ( diisolasi dari turbin )

    selama 2 - 4 hours

    - pengisian melalui drain . Pengisian awal sampai penuh.

    Pengisian lanjutan cukup sampai shaft .

    - Pengeringan dengan cara steam yang masuk melakui

    back pressure

    Kondensate

    inlet

    Kondenser diisolasi

    Pencucian dengan menggunakan steam 100 0C dan kebasahan ( moisture contents )

    X = 0,90 - 0. 95.

    - Dengan menginjeksikan kondensat dari drain dan/ atau back pressure.

    - Exhaust steam dibuang ke atmosfer melalui gate valve

    - Kondensat ( kotor ) dibuang melalui drain valves- Setelah 2- 3 X isi dan buang, berikutnya turbin isi penuh ,dan diputar dengan kecepatan putar

    max. 20 % dari kecepatan normal.

    2. Water - Insoluble Deposits ( silica )

    - Keluarkan kotoran ( silica berbentuk kristal yang sangat keras ) dibersihkan dengan cara

    mekanis setelah turbin di buka shell nya.

    - Silica deposit tidak larut dalam air

    Washing with Wet steam at 100 0C ( Contd )

  • 8/10/2019 steam turbine basic training - module 2.ppt

    26/61

    Washing with Wet steam at 100 0C ( Cont d )

    Important :

    - Turunkan temp. turbin secara perlahan-lahan, tidak lebih

    dari 1 0C

    - Buka semua cylinder drains

    - Pada saat pengukuran pressure dan temperature, sisi

    dalam turbin kearah control valves dibiarkan dalam

    keadaan basah. Dari drain valve (a ) dan (b ) harus

    mengeluarkan kondensat

    - Untuk mendapatkan hasil pencucian yang baik, naikan

    secara bertahap tekanan didalam turbin selama prosespelaksanaan pencucian.

    - selama proses pencucian, matikan semua gland seal

    steam.

    Pencucian dengan Caust ic Soda

    - Hasil pencucian bagus, tetapi

    potensialmenimbulkan kerusakan lokal didalam turbin

    - Tidak disarankan oleh pabrik pembuatnya.

    Pembersihan Turbine dalam keadaan terbuka (

    shel l bagian atas diangk at )

    - Sedimen dibersihkan dengan tangan / sikat / skrap

    / sand blasting secara manual

    a

    b

    Monitoring of the Washing Process

  • 8/10/2019 steam turbine basic training - module 2.ppt

    27/61

    Setiap kali melaksanaan pencucian turbine, harus terus menerus diadakan analisis

    air bekas pencucian. Dengan mengetahui konduktifitasnya, kita mengetahui kapan

    pencucian dinyatakan selesai.

    Sample dari air ekas pencucian diambil dalam uinterval yang tetap sementarapencucian berlangsung. Bila hasil pegukuran konduktifitas air bekas sama

    dengan konduktifitas di steam pencuci , pencucian dinyatakan selesai.

    Hasil / data konduktifitas yang diperoleh tsb. secara berurutan dicatat.

    St. turbin harus dikeringkan dan restart sesegera munngkin untuk mengetahui

    keberhasilan pencucian turbin.

    Cooling Water Quality

  • 8/10/2019 steam turbine basic training - module 2.ppt

    28/61

    Material untuk cooler dan kondensers dipilih berdasarkan agresifitas coolant.

    Qualitas air pedingin harus memenuhi syarat minimum sbb. :

    1. Cooling water

    - Total salinity max. 1000 PPM.

    - Harus cocok dengan komposisi kimia unuk cooler

    - Ganggang / mikrobiotik dengan larutan chlor ( chlorination )

    - Periksa keseimbangan kimia dalam larutan untuk menghindarkan

    pembentukan gumpalan -2 carbonate. ( kristal seperti kapur / carbonic )

    2. Recirculation Cooling

    - Resirkulasi cooling water harus memenuhi spesifikasi daftar berikut untukmenghindarkan terbentuknya deposit didalam cooler tubes :

    pH - value - > 7

    Free Carbonic Acid PPM < 3

    Carbonate Hardness 0 d H < 6

    Carbonate Hardness at Polly,

    Phosphate 0 d H < 12Non-Carbonate Hardness 0 d H < 80

    Chloride ( Cl ) PPM < 400

    Sulfate ( SO4 ) PPM < 500

    Total Salinity PPM < 3000

    Total alkalinity ( m- value ) mval/L < 15

    Silica PPM < 200

    Suspended Matter PPM < 10

    Qualitas cooling water

    harus di selidiki dengansangat teliti

  • 8/10/2019 steam turbine basic training - module 2.ppt

    29/61

    Irregular Working

    Bagian -2 ber ikut ini termasuk yang di per iksa :

    1. Lubrication and Bearings

    2. Safety Trip and Protective devices

    3. Governing System4. Steam Condition

    5. Blading

    6. Labyrinth seals

    7. Vibration

    1. PENYIMPANGAN DALAM KERJA

  • 8/10/2019 steam turbine basic training - module 2.ppt

    30/61

    Lub r icat ion and Bear ings

    a. TEMPERATUR BEARING NA IK

    a.1 Kesalahan coo l ing water :- Temp. air masuk terlalu tinggi.

    - Deposits di dalam cooler

    - Ventilasi / pembuangan panas sisi air didalam oil cooler tuidak sempurna .

    Semua akan mengurangi proses perpinddahan panas/ thermal - conductivity.

    a.2.Kesaklahan Oil :- Check gelas duga oil level.

    - Check ventilasi pada sisi oil dan filter.

    - Filter buntu / kotor .- Auxiliary oil pump distop terlalu dini sementara temperatur bearing masih tinggi

    Auxiliry pump di start ulang

    a.3. Ada kenaikan temp. mis. :

    - V ibrasi akibat terdapat deposit pada blading

    - Tekanan axial bertambah akibat deposit dalam blades. Hal ini ditunjukkan dengan kenaikan

    pressure pada tingkat pertama setelah control stage- Alignment yang kurang sempurna ( kenaikan panas akibat friksi )

    - Vibration due to deposits on the blading

    - Turbin dibiarkan tetap berputar meskipun tanpa beban, temp. bearing naik

    - Kerusakan pada babbit-lining pada bearing disebabkan pelumasan kurang baik / lapisan film

    lube oil kurang.

    - Kerusakan babbit - lining selama turbin tidak dioperasikan

    - kerusakan pada babbit-lining dan permukaan rotor akibat transportasi.

    b. TEKANAN LUBE OIL DIBAWAH NORMAL

  • 8/10/2019 steam turbine basic training - module 2.ppt

    31/61

    b.1. Out-put Main oil pump tidak mencukupi konsumsi.

    b.2. Main oil pump buntuk sebagian / seluruhnya.

    Filetr dibuka dan beersihkan semua kotorannya.b.3. Tekanan oil berkurang karena kebocoran .

    Atau jumlah lube oil berkurang karena bocor.

    b.4. Temperatur lube oil setelah cooler naik akibat .

    b.5. Lamanya pendinginan turbin setelah shut-down terlalu singkat .

    Lebih baik auxiliary pump berjalan lebih lama daripada terlalu singkat.

    b.6. Hal-hal lain yang sulit di deteksi an sulit diatasi.

    Catatan :

    Dalam keadaan normal, tekanan lube oil akan turun setelah turbin mencapai

    kecepatan normal . Hal ini disebabkan oleh berkurangnya derajat kekentalan minyak

    / viskositas akibat temperatur naik .

    Bila dengan segala cara kita gagal mengatasi masalah lube oil pressure, turbine akandi shut-down dan tidak boleh restart sebelum system lube oil bisa diatasi.

    Kondisi oil yang di supply harus dapat dipercaya ( mutu bagus dan jumlah lebih dari

    cukup )

    Benda-2 asing dan deposit didalam oil system harus dihindari

    C. Deposits didalam Oil System

  • 8/10/2019 steam turbine basic training - module 2.ppt

    32/61

    c.1. Check oil filter setelah turbine dikomisi dan bersihkan filter secara berkala dengan

    teratur

    c.2. Untuk turbin dengan unit oil terpisah :

    Penghisapan dan pengembalian ke tangki terpisah dengan wire mesh.

    Wire mesh dapat di keluarkan untuk dibersihkan .

    c.3. Buanglah kondensat terbawa kedalam lube oil melalui drain valves yang terpasang ditangki setelah turbin tidak bekerja 12 jam

    c.4. Pembersiohan filter minimal sekali setiap tahun pada ke dua sisinya (sisi air dan sisi

    oil )

    drain

    Tangki

    lube oil

    filer filer

    Bearings

    2. Trip dan Protective Devices.

  • 8/10/2019 steam turbine basic training - module 2.ppt

    33/61

    a. Turb ine Trip karena Overspeeda.1. Bisa disebabkan oleh jamming lines dari saluran control valve

    Bisa di check pada valve lift indicator sebelum turbin di start

    a.2. Kenaikan pressure yang mendadak di pipa hisap atau tekanan outlet turun

    pada kompresor atau pompa.b . Turbine Trip disebabkan oleh Pergeseran Ax ial

    b.1. Turbine dapat trip oleh keausan yang melebihi yokleransi pada thrust bearing

    ( Michell bearings ) . Pada umumnya axial thrust yang berlebihan disebabkan oleh

    deposit pada rotor blades

    b.2. Bila keausan pada thrust bearing telah di atasi, langkah berikutnya adalah merekondisi

    turbin sebelum axial shift mencapai batas maximum untuk trip

    c. Sebab-sebab lain Turb in TripSemua komponen yang berkaitan dengan trip system

    d. Emergency Stop Valvesd.1. Penyebab kesalahan

    - Damage sealing faces - Erosion of the sealing faces

    - Foreign matter - Excessive strain

    - loose guide bushes - Vibration of the valve proper

    d.2. Bersihkan deposits yang melekat pada valve dan pada saluran valve dengan carathrottling ( menutup sedikit l.k. 1/4 putaran pada emergency

    stop valve sampai kesuatu posisi dimana nozzle control valves terbuka.

    e. Protect ive devices , agar Pengop erasian Turbin dapat di lanjutk an

    e.1. Automatic starting devices pada motor pump bisa gagal bekerja disebabkan

    oleh beberapa faktor , biasanya disebabkan oleh kesalahan wiring ( kabel-2 )

    atau setting ( penyetelan ).

    3. Governing System

  • 8/10/2019 steam turbine basic training - module 2.ppt

    34/61

    a. Nozzle Contro l Valvesa.1 Jaringan nozzle control valves akan mengalami jam apabila deposits telah terbentuk

    pada valve lines yang menyebabkan kekuatan pegas tidak cukup kuat untuk

    menggerakkan mekanisme valve . Dalam hal control valves tidak mau menutup, pegas

    telah lemah dan harus diganti baru.a.2. Main emergency stop valves di throttled untuk menghilangkan deposits yang melekat

    valve stem.

    b.Speed Gov ernorb.1. Speed Governor akan macet biasanya bila karena deposits dan kotor.

    c.External Causesc1. Tekanan steam mula-2 oscillating atau hunting ( tidak stabil ). Tekanan ini akan

    menyebabkan daya tidak stabil pada reducing valve atau f by-pass controller.

    4. Steam Conditionsa. Deposits

    Deposits yang terbentuk didalam turbine blades akan engurangi merobah countur blades

    dan mengurang luas penampang blades. Effisinsi daya akan berkurang

    4. Steam Conditions

    a Deposits

  • 8/10/2019 steam turbine basic training - module 2.ppt

    35/61

    a. Deposits.

    Menaikkan pressure

    Menaikkan exhaust

    temperature

    - Deposit melapisi permukaan blades, steam yang melewati ruang antar dua blades berkurang, dayaberkurang karena kalor ( kinetic energy ) yang dirobah menjadi daya ( mechanical energy )

    berkurang .

    - Untuk menghasikan daya yang telah ditetapkan, diperlukan Extra thrust yang selanjutnya

    diteruskan ke thrust bearings

    - Idem terjadi extra tegangan di labyrinth seals

    - Idem terjadi tegangan extra diluar tegangan yang telah diperhitungkan pada design blading

    4b. Foreign Matter Carried in the Steam Lines

    4b. FOREIGN MATTER CARRIED IN THE STEAM

  • 8/10/2019 steam turbine basic training - module 2.ppt

    36/61

    ( Bend a-2 asing terbawa dalam steam )

    UNTUK MENCEGAH TURBIN KEMASUKAN BENDA-2 ASING , TURBIN

    DILENGKAPI DENGAN STEAM STRAINER DENGAN UKURAN 2 mm

    SEBELUM STEAM LINES DIPASANG, DI BEERSIHKANM TERLEBIH DAHULU

    DENGAN STEAM FLUSHING. PEMBERSIHAN TERSEBUT DI ULANG TIAP

    KALI KITA MELAKSANAKAN PENGGANTIAN PIPA .

    UNTUK MENCEGAH BENDA-2 ASING YANG LEMBUT / PARTIKEL TERBAWA

    MASUK KEDALAM TURBIN, STEAM STRAINER TSB HARUS DI BUNGKUS

    DENGAN LEMBARAN 13 % BAJA CHROM . PENUTUP INI BARU DILEPASSETELAH 4 - 6 MINGGU SETELAH KOMMISSIONING.

    4.C. AIR KONDENSAT TERBAWA MASUK KEDALAM TURBIN

    STEAM SEPARATOR DIPASANG SEBELUM STEAM MASUK KEDALAM MAIN

    STOP VALVE DAN STEAM STRAINER.

    5. Blading

  • 8/10/2019 steam turbine basic training - module 2.ppt

    37/61

    SUMBER KERUSAKAN PADA BLADING:

    - Corrosion

    - Pitting ( Lobang-2 lembut dan dalam )

    - Water droplets ( titik-2 air kondensasi )

    - Deposits- Rubbing of moving parts ( luka akibat gesekan / aus )

    - Foreign matter

    - Water schock/ hammer ( air yang terbawa dalam alitran steam )

    - non - uniform cooling down when turning gear is not in operation. ( pendinginan yang

    tidak merata )

    Protect ive actio n :

    1. Jaga turbin tetap keringbila tidak dioperasikan2. Pendinginan turbin dengan turning gear selama 2-4 jam dan saat warm -up selama

    ( 1/2 - 1 hour ) tergantung ukuran dan dimensi turbin .

    Perlu turning gear dilakukaan harian pada turbin yang tidak dioperasikan dengan

    tujuan untuk menjatuhkan titik kondensasi pada rotor blading dan juga untuk

    menghidarkan bending akibat gravitasi pada posisi rotor konstan.

    3. Segera ambil tindakan koreksi apabila ditemukan ada kesalahan / kerusakan

    6. Labyrinth SealsStationary

  • 8/10/2019 steam turbine basic training - module 2.ppt

    38/61

    stationary

    rotary

    Causes lead to damaged

    knife-edges of the labyrinth

    Steam flow

    6.1. Ujung pisau menyentuh shaft turbine shaft karena expansi yang tidak merata,

    terutama akibat start yang dilakukan terlalu singkat

    6.2. Kesalahan pada saat membika turbin shell dan / atau mengganti atau memperbaiki

    labyrinth seals

    6.3. Tekanan steam pada first-stage terlalu tinggi dan disitu terdapat akumulasi deposit

    akan berakibat keausan yang parah thrust bearings.

    6.4. Rotor melengkung akibat pendinginan danb pemanasan yang terlalu cepat .dan

    restart yang tidak tidak sesuai priosedur.

    6.5. Seal steam supply yang kurang tepat, pressure terlalu tinggi.

    6.6. Seal steam tercampur air

    6.7. Radial and thrust bearings rusak.

    Stationary

    7. Vibration

  • 8/10/2019 steam turbine basic training - module 2.ppt

    39/61

    Vibration

    Vibro - meter

    Alarm

    Sound

    Lamp

    OK

    Shut - down

    Trip

    Excessive Noise

    Excessive Vibration

    After trip / shutdown :

    - Check the balance

    - Check the alignment, bearing,

    labyrinth blading, clearances

    - Check the turnability of the rotor

    restart

    OK

    Excessive

    vibrationDetermin the cause :- ( lihat slide berikut )

    coil

    magnet

    Suspension

    spring

    spring

    rider tip

    7 2 Determin the Cause of the Excessive Vibration

  • 8/10/2019 steam turbine basic training - module 2.ppt

    40/61

    7. 2. Determin the Cause of the Excessive Vibration

    2.a. Imbalance yang bvesar, disebabkan oleh :

    - perobahan imbalance sangat mendadak karena blade patah

    - perobahan kondisi imbalance yang sanfat lamban disebabkan terjadinyapenimbunan deposits, erosion, corrosion, rotor distortion.

    2.b. Gesekan antara rotor ( blades atau seals ) terhadap casings.

    2.c. Bidang natural frequency sdangat rapat denfan bidang bagian -2 yang berputar.

    2.d. Resonansi didalam fondasi atau komponen machine .

    2.e. Kekuatan vibrasi disebabkan oleh :

    - Kesalahan pemasangan kopling atau alignmen yang kurang sempurna.

    - Kekuatan reaksi dari daya mesin penggerak atau yang mesin digerakkan.2.f. Selfexited rotor vibrations ( resonansi akibat tekanan lube oil yang menyentak-sentak

    2.g. Terjadi perbahan amplitudo getaran akibat perobahan load yang mendadak,

    keausan bearing dan / atau shaft , atau perobahan temperature dan / atau

    perobahan sifat-2 lube oil

    7. 3. Vibration Measuring Requirement (pengukuran getaran )

  • 8/10/2019 steam turbine basic training - module 2.ppt

    41/61

    pengukuran getaran )

    3.a. Pengukuran vibrasi poros ( relative measurement ).

    Vibration probes dipasang dengan arah vertical an horizontal atau menyudut

    90 0 pada semua lokasi bearing .

    3.b. Bearing Vibration Pick-up ( absolute measurement )3.c. Multi-channel strip chart recorder

    3.d. Analisa gelombang akibat getaran untuk menentukan frequensi harmonis dari

    vibrasi.

    Test 1

    Pengukuran vibrasi pada semua bearing dan rumah bearing ( dan fondasinya )

    ke semua jurusan

    Pengujian dilakukan pada kecepatan idle terendah dan tanpa load

    Test 2

    Menganalisi susunan semua level frequensi vibrasi dan pada amplitudo terbesar

    berapa terjadi vibrasi.

    Test 1 danTest 2 dapat menghasilan 4 variasi getaran..

    7.4. Vibration Tests and Investigations

    Hanya dilakukan hanya oleh yang akhli

    untuk menebtukan vuibrasi yang besar

    Lihat slide berikutnya

    Test ResultsResult 1 of Test 1

  • 8/10/2019 steam turbine basic training - module 2.ppt

    42/61

    Amplitudo vibrasi diukur kearah horizontal dan vertical dengan lokasi yang

    berbeda-beda.

    Test dilakukan pada bagian yang diduga terjadi resonansi getaran ( foundasi atau

    bearing housing ) .

    Hasil test 1 ini perlu dipastikan dengan dengan hasil test 3

    Result 1 of Test 2

    Vibrasi terutama pada frequensi kenaikan kecepatan

    Getaran terutama yang ditimbulkan oleh daya yang berputar / rotor :

    - Unbalance

    - Rotor distortion- Eccentric shaftatau

    - Reaksi daya dari kopling ( misalignment )

    Result 2 of Test 2

    Vibrasi -2 lain yang berbeda dari frequensi kecepatan

    vibration are different from running speed frequency

    Test 3

  • 8/10/2019 steam turbine basic training - module 2.ppt

    43/61

    INSPECTION

    AND

    MAINTENANCE

    Maintenance

    MaintenanceU j d t h k k di i t i l d ti k t dii i k

  • 8/10/2019 steam turbine basic training - module 2.ppt

    44/61

    Upaya menjaga dan mempertahankan kondisi material pada tingkat yang diinginkan

    Menentukan dan memperkirakan kondisi yang sebenarnya.

    SCOPE MAINTENANCE

    1. INSPECTION

    2. MINOR OVERHAUL3. MAJOR OVERHAUL

    PREVENTIVE MAINTENANCE

    STRATEGY

  • 8/10/2019 steam turbine basic training - module 2.ppt

    45/61

    MONITORING YANG INTENSIF SEMUA BAGIAN YANG DIOPERASIKAN

    LAKSANAKAN OVERHAUL SESUAI EQUIVALENT OPERATING HOURS ( EOH = WAKTU PENGOPERASIAN

    TERMASUK WAKTU SHUTDOWN KAERENA TRIP DAN UNSCHEDULED SHUTDOWN )

    TUJUAN :

    MENEKAN SERENDAH MUNGKIN :

    - OUTAGE

    - OPERATION COST

    - OUTAGE

    SCOOP MONITORING

    1. STEAM PRESSURE

    2. TEMPERATURES

    3. STEAM FLOWS

    PARAMETER :

    1. SPEED / OUTPUT

    2. RADIAL & AXIAL BEARING METAL

    TEMPERATURES

    3. SHAFT VIBRATIONS

    4. AXIAL POSITION OF ROTOR

    TINDAKAN :

    1. INSPECTIONS SETELAH 10 - 12 000 JAM

    KERJA

    2. SERVICING

    3. OVERHAUL / REPAIR

    MENGEMBALIKAN KONDISI

    TINGKAT TERTENTU

    MENGAWAETKAN SAMPAI KONDISI /

    WAKTU TERTENTU

    MENENTUKAN / MENDAPATKAN DATA

    KONDISI YANG ADA

    MINOR OVERHAUL SETELAH 25 000 EOH

    MAJOR OH SETELAH 50 000 EOH

    LAJU KEAUSAN DIPENGARUHI 3 FAKTORS

    1. HASIL PROSES PRODUKSI

  • 8/10/2019 steam turbine basic training - module 2.ppt

    46/61

    2. KEAUSAN

    3. CARA PENGOPERASIAN

    MATERIAL NYANG DIPAKAI

    SAFETY FACTOR YANG DIPILIH ( DALAM

    DESIGN )

    QUALITAS PRODUKSI

    QUALITAS STEAM

    TEMPERATURE KERJA

    PARTIKEL ( BENDA ) ASING DI DALAM

    STEAM

    % KEBASAHAN STEAM

    KECIL ATAU SEBALIKNYA OVERLOAD

    START - SHUTDOWN ATAU NON STOPOPERATING

    C1.C2 KONDISI TERTENTU YANG BERBEDAYANG DITEMUKAN SELAMA ISPEKSI

    PADA t1 , t2

    CR, CM KONDISI SETELAH PERBAIKAN /MODIFIKASI PADA t2

    USIADESIGN

    YANGD

    IHARAPKAN

    TAHUN

    TINGKAT KERUSAKAN

    CM

    CR = KONDISI MENDEKATI BARUSETELAH PERBAIKAN

    C1

    t1t2

    CM= KONDISI SETELAH MODIFIKASI

  • 8/10/2019 steam turbine basic training - module 2.ppt

    47/61

    SETELAH MENCAPAI 100 000 EOH, KERUSAKAN MATERIAL AKIBAT FATIGUE MAKIN BERSAR DAN

    USIA TERSISA SUDAH BISA DIPERHITUNGKAN.

    KONDISI SETELAH 1000.000 EOH INI PERLU DIKONSULTASIKAN SECARA DETAIL KEPADA PABRIK

    PEMBUATNYA

    Te = T eff + NS X TS

    Te = EOH

    Teff = WAKTU PENGOPERASIAN YANG SEBENARNYA

    TS = WAKTU PENGOPERASIAN UNTUK SETIAP KALI START ( MINIMAL

    PERHITUNGAN 30 JAM UNTUK SETIAP KALI START )

    Ns = berapa kali start

    TIDAK DISARANKAN MELAKUKAN LIFE - EXTENSION BILA TURBINE TELAH DIOPERASIKAN LEBIH

    DARI 50. 000 EOH DENGAN PERTIMBANGAN :

    SULIT DIASSEMBLY TIAP KOMPONEN TURBINE

    IKATAN BOUT ( BOLTS ) SUDAH TIDAK ELASTIS LAGI ( RAPUH ). HARUS GANTI / KENCANGKAN

    KEMBALI

    EROSI DAN KOROSI BISA MENJADI SUMBER RETAK / PECAH

    Servicing and Inspection

    Insp ect ions Intervals

  • 8/10/2019 steam turbine basic training - module 2.ppt

    48/61

    5.Overspeed Governor

    Perijksa kemungkinan deposits, terutama deposit dari kerak lube

    oil.

    Test for annually,

    Inspection every 2 years.

    Insp ect ions Intervals

    1. Blading

    Pemeriksaan deposits, mis. Silica ( SiO2 ) dan larutan -2 lain.

    Checking every 2 years

    2. Bear ing faces of the Rotor

    Permukaan rotor harus di periksa kemungkinan terdapat cacat /

    goresan . Permukaan bldes harus di poles sampai cacat / giores

    tsb. Hilang.

    Checking every 2 years

    3. Bear ings

    Perijksa adanya goresan dalam pada white metal lining.

    Biasanbya terjadi pada radial dan thrust bearings.

    Checkng every 2 years

    4.Labyr inth Seals

    Ujung-2 plat tipis labyrinth diperiksa kemungkinan rusakCheckng every 2 years

    6 E R l

    Ins pect io ns Intervals ( contd)

  • 8/10/2019 steam turbine basic training - module 2.ppt

    49/61

    6. Emergency Relay

    Emergency relay dan Lube Oil pe5rlu diperiksa pada :

    - the catch lever

    - the pilot valve

    - the condition of the springsInspection every 2 years

    7. Contr ol Valves

    Valve stems harus diperiksa adanya deposits, corrosion dan erosion.

    Deposits dapat memnyebabkan jam aliran steam pada leher valve

    Checking annually

    8. Servom otor and Oi l Relay

    Periksa penimbunan lotoran . Biasanya terbentuk pada piston valve pada oil

    relay. Terbentuk dari kotoran minyak yang mengkristal .

    Checking every 2 years.

    9. Turbine OilPeriksa kemungkinan adanya kondensat, kotoran yang terkandung dan periksa

    viskositas.

    Checking every day

    10. Emergen cy Stop Valves

    Checking every 2 years

    SCHEDULE for NONDESTRUCTIVE TESTING of

    STEAM TURBINE COMPONENTS

  • 8/10/2019 steam turbine basic training - module 2.ppt

    50/61

    Steam Turbine

    Component

    Bearings

    Blading

    Bolting

    Casings

    Diaphragm

    Disc Hub and Webs

    Disc Bores and Keyways

    Rotor Periphery

    Rotor Bores

    Steam Path as

    Acxcessable

    Normal Inspection

    Frequency

    1 - 2 tahun

    3 - 5 tahun

    3 - 5 tahun

    3 - 5 tahun

    3 - 5 tahun

    3 - 5 tahun

    5 6 tahun

    3 - 5 tahun

    10 tahun

    Shutdown

    NDT

    Inspection Method

    V, UT

    V, MT, ET, MP

    V, MT, UT, PT

    V, MT, PT

    V, MT, PT

    V, MT

    UT

    V, MT

    V, MT, UT

    V, PT

    V = Visual PT = Penetrant Test

    ET = Eddy Current Test MT = Magnetic Particle

    MP = Magnetic Perturbation ( gangguan )

    UT -= Ultrasonic

    CRACKING PROBLEMS 43

  • 8/10/2019 steam turbine basic training - module 2.ppt

    51/61

    Steam turbine rotor cracking problem areas :

    1. Blade Cracking

    2. Disc Rim / Blade attachment cracking

    3. Disc external surface cracking

    4. Disc imternal bore and keyway cracking

    5. Shaft peeriphery surface transferse cracking

    6. Shaft body and bore connected internal radial / axial cracking

    1

    5

    2

    6

    5

    Inspection and Overhaul Program

  • 8/10/2019 steam turbine basic training - module 2.ppt

    52/61

    I M I G I M I G I M I G I M I M I G

    3 6 9 10 12 15 18 20 22 yrs

    25.000 50.000 75.000 100.000 125.000 150.000 180.000 Max. operating hrs

    T = Equivalent Operating Hours

    G = Major Overhaul

    M = Minor Overhaul

    I = Inspection

    1X stop-start senilai est. 30 hrs

    T equiv = Tact + ns . Ts

    Tequiv = Equivalent Operating Hours

    Tact = Actual Operating Hours

    ns = Number of starts

    Ts = Operating Hours Chargedfor One Start

    Ganti turbin baru

    Preventive Maintenance Concept

    Pemeriksaan dilaksanakan untuk jangka waktu apprx.. 12. 500 O.H atau 1 1/2

  • 8/10/2019 steam turbine basic training - module 2.ppt

    53/61

    tahun antara minor dan major overhauls

    Minor overhauls harus dilaksanakan setelah total 25.000 equivalent O.H atau 3

    tahun paling lambat

    Major overhaul dilaksanakan setelah 50.000 eoh atau 6 tahun paling lambat.

    E.O.H = Equiv alent Operat ing Hou rs = Te

    Te = T eff + nsX Ts

    Teff = jam operasi sebenarnya.

    Ts = Operating hours dihitung untuk 1 X start

    & stop yang senilai dengan 30 jam .ns = Jumlah berapa kali starts tanpa

    memperhatikan hot and cold starts

    Kerusakan yang cukup berat padfa material akibat kelelahan dimulai setelah 100.000

    eoh ( Equivalent Operation Hour ).

    Jangan menunda pemeeriksaan untuk overhaullebih lama dari 50.000 eoh.

    - Membongkar bagian -2 di daerah yang menerima steam panas adalah paling sulit.- Bout-2 pengikat, biasanya rusak pada saat pembongkaran. Harus ganti baru

    atau dikencangkan kembali.

    - Kerusakan akibat Erossion dan Corrosion dapat mengakibatkan kebocoran pada

    shell packing .

    Scope of Inspect ion, Minor and Major Overhauls

  • 8/10/2019 steam turbine basic training - module 2.ppt

    54/61

    Semua harga / angka harus dibandin gkan dengan hasi l

    pengukuran sebelumnya.

    PERIKSA FUNGSI ALAT / PERLENGKAPAN BERIKUT : MONITORING , SAFETY,

    PROTECTION.

    TEST / INSPEKSI SESUAI YANG TERTERA DALAM OPERATIONAL MANUAL

    SELAMA TURBINE BEROPERASI , PEMERIKSAAN MELIPUTI :- UKUR KONSUMSI STEAM .

    - HITUNG INTERNAL EFISIENSI

    - UKUR STAGE PRESSURE dan BANDINGKAN DENGAN PENGUKURAN PERIODE

    SEBELUMNYA DENGAN MENGGUNAKAN DIAGRAM VALUE PADA BEBAN YANG BERBEDA-

    2.

    - BANDINGKAN HASIL PENGUKURAN TEMPERATURE PADA CASINGS.

    - VIBRATION MEASUREM ENT- BEDA ANGKA EXPANSI ANTARA SHAFT dan CASINGS.

    - SUPPORT of THE TURBINE CASING PADA TURBINE PEDESTALS.

    - PERIKSA TEMPERATURE dan TEKANAN PADA BEARINGS.

    - PERIKSA OIL, STEAM dan KEBOCORAN COOLING WATER

    LAKUKAN PEMERIKSAAN PADA SAAT MESIN BEKERJA / RUNNING DOWN dan COOLING

    DOWN.

    - THE COST DOWN TIME- UKUR AMPERE TERPAKAI PADA TURNING GEAR.

    - DENGARKAN KEMUNGKINAN SUARA - 2 GESEKAN, DERIK dan / atau SCRAPPING.

    MINOR OVERHAUL ( 25.000 EQUAL Operating Hours atau 3 years )

    Scope of Inspection, Minorand Major Overhauls

  • 8/10/2019 steam turbine basic training - module 2.ppt

    55/61

    INSPECTION PADA :

    TEST MASING 2 FUNGSI DARI CONTROL dan SAFETY SYSTEMS. ( vocal points :

    Aus dan kotoran pada sensitive components)

    BEARING dan EXTERNAL CHECK PADA RADIAL dan AXIAL ROTOR CLEARANCE.

    TEST KOSENTRIK PADA SAAT TURBINE BERPUTAR

    PERMUKAAN BIDANG SEATING dan GUIDIING dan PEGAS PENUTUP PADAENEERGENCY STOP dan CONTROL VALVES.

    KOPLING dan ALLIGNMENT ANTARA TURBINE dan BAGIAN YANG

    DIGERAKKAN / LOAD

    EXHUST SECTION MELALUI MAN HOLE ( bila dilengkapi )

    SEALING dan DRAINAGE SYSTEM

    SCOPE of INSPECTION , MINOR and MAJOR OVERHAULS

    MAJOR OVERHAUL 50. 000 Equal Operating Hours ( EOH ) atau 6 years

  • 8/10/2019 steam turbine basic training - module 2.ppt

    56/61

    PERIKSA SEMUA KOMPONEN DALAM KEADAAN TERURA (disassembled ) TERUTAMA PADA SEMUA

    SEALING dan PERMUKAAN BIDANG YANG BERHADAPAN DENGAN KISI KISI LABYRINTHS.

    > DAMAGE / RUSAK > WEAR / AUS

    > STEAM CUTS/ SALURAN STEAM BUNTU. > SURFACE RUST / KARAT .> DISTORSION / HAM BATAN , etc

    PERIKSA PADA VALVES , NOZZLES dan BLADING :

    > FOREIGN PARTICLE DAMAGE > STEAM CUTS

    > RUBBING / GORES > Erosion ( especially exhaust section )

    > CRACKS > SURFACE RUST and DEPOSITS

    CRACK TESTING PADA :> STEAM STRAINER > VALVE COMPONENT

    > CASINGS > ROTOR and GUIDE BLADE CARRIER

    > BEARINGS > COUPLINGS

    > INTERNAL STEAM LINES

    PENGAMBILAN SAMPLE dan DEPOSITS

    CLEAING BY SAND BLASTING ( BILA PERLU )

    BALANCING CHECK - PADA ROTOR INTERNAL ALLIGNMENT dan CLEARANCE CHECK

    PERIKSA SEMUA LABYRINTH dan OIL RETAINING RINGS BILA ADA TANDA GOESAN dan DEFORMASI.

    LIFE EXTENSION

  • 8/10/2019 steam turbine basic training - module 2.ppt

    57/61

    UNIT

    SHUTDOWN

    TEMPERATUR UDARA DIBAWAH DEWPOINT,

    MENGAKIBATKAN KONDENSASI

    PROSES ELEKTROCHEMICAL , WATER dan OXYGEN

    MENGAKIBATKAN KOROSI.

    CORROSION PITTING

    SHUT DOWN CLASSIFICATION :

    1. SHORT SHUTDOWN SAMPAI 4 HARI

    2. SHUTDOWN DENGAN MENJAGA UNIT

    TURBINE SIAP UNTUK DIOPERASIKAN LAGI ,

    SETELAH BEBERAPA JAM PERSIAPAN.

    3. SHUTDOWN 68 BULAN ( mis. sugar millplant )

    4. SHUTDOWN LEBIH Lama dari 68 bulan.

    TINDAKAN UNTUK MEMPERPANJANG USIA PAKAI TURBINEPLANT PADA SAAT SHUTDOW

    TINDAKAN PENCEGAHAN untuk TURBINE PLANT

    (Preventive Measures for Turbine Plants located Indoors ( no danger of frost )

  • 8/10/2019 steam turbine basic training - module 2.ppt

    58/61

    1. SHORT SHUT-DOWN up to 4 DAYS :( DIMULAI SETELAH UNIT SELESAI PENDINGINAN )

    - TIDAK ADA TINDAKAN KHUSUS PERLU DIAMBIL- BILA TURBINE DILENGKAPI DENGAN PERLENGKAPAN UDARA PENGERING,

    JALANKAN SETELAH TURBINE PROSES COOLING DOWN.

    2. TURB INE SHUT-DOWN TETAPI HARUS TETAP SIAP UNTUK DIOPERASIKAN

    SETIAP SAAT ( STAND BY PLANTS )

    a. TURBINE

    b.OIL SYSTEM

    a.1.SEMUA VALVES TUTUP RAPAT UNTUK M MENCEGAH UDARA MASUK KEDALAM BADANTURBINE. TURBINE TERISOLASI SEMOURNA TERHADAP STEAM SYSTEM dan

    CONDENSATE SYSTEM.

    a.2.TETAP MENJAGA BAGIAN DALAM TURBINE TETAP KERING . KELEMBABAN UDARA

    ATMOSFER < 60 % DI DALAM GEDUNG TURBINE. .

    b1.- JALANKAN OIL PUMP SETIAP 2 MINGGU SELAMA 1 JAM. SELAMA POMPA BERJALAN,

    SEMUA KONTROL DEVICES HARUS DIGERAKKAN PENUH MEMBUKA atau PENUHMENUTUP

    - PUTARLAH TURBINE SECARA MANUAL MINIMAL 2 PUTARAN .

    PRESERVATION of SHUTDOWN TURBINE PLANT ( contd )

    2.b. 2. - AMBILLAH SAMPLOE LUBE OL DARI TANGKI dan DARI TITIK DRAIN LAIN. -

  • 8/10/2019 steam turbine basic training - module 2.ppt

    59/61

    4. MISCELLAENOUS

    > JALANKAN TERUS OIL PUMP

    > PANASKAN TERLEBIH DULU OIL LUBE ( untuk daerah dingin ) dan JAGA LUBE

    OIIL PADA TEMPERATURE KONSTAN

    > PANASKAN TERLEBIH DULU TURBINE M ELALUI BACK PRESSURE SYSTEM

    DENGAN CARA MEMBUKA SEDIKIT DRAIN VALVES

    - BILA MUNGKIN , TAMOUNG KONDENSAT YANG DIAMBIL DARI TANGKI LUBE OIL.

    2. b. 3. KOSONGKAN COOLING WATER DARI COOLER dan KERINGKAN PERMUKAAN BIDANG

    BAGIAN DALAMNYA BILA SHUT-DOWN BERLANGSUNG UNTUK WAKTU LEBIH DARI 1

    MINGGU- UNTUK AUXILIARY OIL PUMP TIDAK ASDA TINDAKAN KHUSUS YANG PERLU DIAMBIL.

    3. GEAR UNIT

    TIDAK ADA TINDAKAN KHUSUS YANG PERLU DIAMBIL.

    PRESERVATION of SHUTDOWN TURBINE PLANT ( contd )

    3 SHUT DOOWN 6 8 MONTHS

  • 8/10/2019 steam turbine basic training - module 2.ppt

    60/61

    a. TURBINE

    3. SHUT DOOWN 6 8 MONTHSUNIT TURBINE YDM. BIASANYA TERPASANG PADA UNIT YANG DIOPERASIKAN MUSIMAN

    ( mis. Pabrik Gula )

    a.3. PERIKSA EXTERNAL COATING dan RECOATING BILA PERLU DENGAN VALVOLINE OIL

    TECTYLE 506 . . ( DILAkukan terutama sebelum konisioning dengan menggunakan minyak /

    petrol atau paraffine pembersih ) .

    a.1. CEGAH KEBOCORAN STEAM JANGAN SAMPAI MASUK KEDALAM STEAM SYSTEM DENGAN

    CARA MEMASANG SLIP PLATE :

    INLET STEAM, BLEED STEAM, PASS OUT STEAM, FOREIGN SEAL STEAM , STARTING

    STEAM and SECONDARY STEAM CONNECTIONS.

    a.2. UNTUK PERLINDUNGAN BAGIAN DALAM TURBINE, PILIHLAH SALAH SATU CARA BERIKUT :

    1). OVERHAUL DENGAN CARA BONGKAR TOTAL.

    2). JAGA TURBINE TETAP KERING DENGAN CARA BLOWING UDARA YANG SUDAHDIKERINGKAN atau UDARA YANG TELAH DIPANASKAN TERLEBIH DULU.

    3). KELUARKAN SEMUA PENYEBAB KOROSI DARI DALAM STEAM SYSTEM SERGERA

    SEBELUM SHUT-DOWN DILAKSANAKAN. . CARANYAA DENGAN MENGINJEKSIKAN

    SUATA CAMPURAN OLI- STEAM DENGAN ALAT PORTABLE KHUSUS UNTUK ITU.

    SETELAM CAMPURAN OIL-STEAM DIINJEKSIKAN KEDALAM TURBINE, OIL DIHARAPKAN

    MEMBENTUK LAPISAN PELINDUNG PADA PERMUKAAN SETIAP SAAT MENERIMA

    PANAS.

    4). PROSEDUR NITROGEN. BILA DIPERLUKAN UNTUK EKXPANSI KE UDARA ATMOSFERSETELAH SHUT-DOWN dan DIINJEKSIKAN UDARA KERING. SEGERA DISUSUL DENGAN

    MENGISOLASI TURBINE DENGAN CARA MENUTUP SEMUA VALVES

    4. SHUTDOWN UNTUK WAKTU TIDAK TERBATAS

  • 8/10/2019 steam turbine basic training - module 2.ppt

    61/61

    ( lebih lama dari 6-8 bulan )

    MEMERLUKAN COST CUKUP TINGGI dan VOLUME PEKERJAAN PREVENTIVE YANG LEBIH LUAS

    DILAAKSANAKAN BERKAITAN DENGAN PROGRAM OVERHAUL MENYELURUH YANG SEGERAHARUS DILAKSANAKAN TURBO SET LENGKAP DETELAH SHUT-DOWN .

    SEMUA KOMPONEN DALAM KEADAAN TERURAI PER KOMPONEN , MASING- 2 DIBUNGKUS /

    SIISOLASI TERHADAP UDARA ATMOSFER.

    PERIKSA KWMBALI SETIAP INYERVAL 2 TAHUN dan BILA PERLU LEMASAN DIGANTI BARU.

    SEBELUM DIKOMISI KEMBALI UNTUK PEMASANGAN ( assembling ) SEMUA CORROSION HARUS

    DI BERSIHKAN DENMGAN STEAMJET, PETROL atau PARAFIN.