Status Report # 3 Commhut – Home Security Wire Protection System Team 7 Ronald, Orlando, Robert, Jaime An interfacing module to communicate with previously.

  • Published on
    17-Jan-2016

  • View
    214

  • Download
    0

Transcript

Status Report # 1 Home Security Wire Protection System Ronald, Robert, Orlando, Jaime An interfacing module to communicate with previously designed protective case.

Status Report # 3Commhut Home Security Wire Protection System

Team 7Ronald, Orlando, Robert, JaimeAn interfacing module to communicate with previously designed protective case.OVERALL NEED: To protect the communication lines of home security systems by detecting intrusion.

DESIGN MILESTONES:Develop Detailed Schematics for interface (On going)Receive sample code and sample products from Mr. Poston (Mid February)Interface modem with the PIC Microcontroller (2/20/09) Continue constructing source code for PIC (2/20/09)

Overall Need and Design MilestonesTeam meeting to discuss different methods of implementing sensors and further discussion of the case. (2/11/09)

Began organizing sections of sample code into main program.(2/13/09)

Began construction on power phase of design. (2/13/09)

Completed Tasks Develop Functional Code to link modem with microcontroller.

Test protective case in all possible environments it might encounter.

Finalize design of modem/PIC interface.

Finalize and upload fully functional website.

Pending/Ongoing TasksContinue building the project test site. (2/18/09)

Complete case design and contact machine shop. (2/20/09)

Begin interfacing PIC and modem. (2/20/09)

Complete power phase including back up power. (2/20/09)Tasks to Begin Next WeekCommHut DesignMicrocontrollerModemMagnetic SensorBack up BatteriesEmergency AlertAC PowerAC/DC ConverterRoberto RosasOrlando PinaJaime GomezRon BarnesAnalog AC SignalAnalog DC SignalDigital Sensor OutputBackup Analog DC SignalDigital Modem Activation SignalPhone Line CommunicationPenetration SensorBackup Analog DC SignalAnalog DC Signal20%25%13%25%25%40%Current Schedule