Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

  • Upload
    stefan

  • View
    32

  • Download
    0

Embed Size (px)

DESCRIPTION

Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006. Dipole cold masses. 416th and last BNN dipole (November 2005). Cryodipole overview. Dipole: integral field. Dipole: b3 integral field. Arc quadrupole cold masses. SSS overview. - PowerPoint PPT Presentation

Citation preview

Page 1: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

Status of the LHC ProjectLyndon EvansJournées de Physique ATLAS FranceAutrans, 29 March 2006

Page 2: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 2

Dipole cold masses

Page 3: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 3

416th and last BNN dipole (November 2005)

Page 4: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 4

Cryodipole overview

Page 5: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 5

Dipole: integral field

10.07

10.09

10.11

10.13

10.15

0 100 200 300 400 500 600 700 800 900

Magnet progressive number

Int t

ran

sf fu

nc

(Tm

/kA

)

-40

-20

0

20

40

Un

its

Firm 1

Firm 2

Firm 3

AT-MAS

Cold mass

upper limit for single magnet (3 sigma)

lower limit for single magnet (3 sigma)

Page 6: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 6

Dipole: b3 integral field

-10

-5

0

5

10

0 100 200 300 400 500 600 700 800 900

Magnet progressive number

b3 in

tegr

al (

units

)

Firm 1

Firm 2

Firm 3

Cold mass

upper limit for systematic

lower limit for systematic

AT-MAS & MTM

Cro

ss

-se

cti

on

2

Cross-section 3

Page 7: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 7

Arc quadrupole cold masses

Page 8: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 8

SSS overview

Page 9: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 9

Preparation for installation in SMI2

Hall SMI2

Page 10: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 10

Underground

Page 11: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 11

Cryogenic distribution line

Page 12: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 12

Cryogenics overview

Page 13: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 13

24h endurance test of all power converters in 8-left (13-14 October 2005)

81 power converters in UA83

3 x 13 kA power converters

18 x 4 to 7 kA power converters

31 x 600 A power converters

29 x 120 A power converters

156 kA and 1.2 MW dissipated: PCs and Cables (estimation)

Page 14: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 14

24h endurance test of electrical network(13-14 October 2005)

0.0

200.0

400.0

600.0

800.0

1000.0

1200.0

1400.0kW

Dipole

Other PC

Total

Power measured by TS-EL in SE8

Page 15: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 15

Infrastructure for RF at Point 4

Page 16: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 16

Global requirements

Page 17: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 17

Machine considerations

Page 18: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 18

Performance goals

Page 19: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 19

LHC operational cycle

0

14000

-3000 -2000 -1000 0 1000 2000 3000

Time [s]

MB

cu

rre

nt

0

1

2

3

4

5

6

7

8

9

B [

T]

RAMP DOWNSTART RAMP

PHYSICS

PREPAREPHYSICS

BEAM DUMP

PREINJECTIONPLATEAU

INJECTION

T0 Tinj

SQUEEZE

PHYSICS

Ramp down 18 Mins

Pre-I njection Plateau 15 Mins

I njection 15 Mins

Ramp 28 MinsSqueeze 5 Mins

Prepare Physics 10 MinsPhysics 10 - 20 Hrs

Page 20: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 20

Staged commissioning plan for protonsStaged commissioning plan for protons

25ns ops IInstall Phase II and MKB

25ns ops II

75ns ops

43 bunch operation

Beam commissioning

Machine checkout

Hardware commissioning

Stage I II III

No beam Beam

IV

I.I. Pilot physics runPilot physics run First collisionsFirst collisions 43 bunches, no crossing angle, no squeeze, moderate intensities43 bunches, no crossing angle, no squeeze, moderate intensities Push performance (156 bunches, partial squeeze in 1 and 5, push Push performance (156 bunches, partial squeeze in 1 and 5, push intensity)intensity) Performance limit 10Performance limit 103232 cmcm--22 ss--11 (event pileup)(event pileup)

II.II. 75ns operation75ns operation Establish multiEstablish multi--bunch operation, moderate intensitiesbunch operation, moderate intensities Relaxed machine parameters (squeeze and crossing angle)Relaxed machine parameters (squeeze and crossing angle) Push squeeze and crossing angle Push squeeze and crossing angle Performance limit 10Performance limit 103333 cmcm--22 ss--11 (event pileup)(event pileup)

III.III. 25ns operation I25ns operation I Nominal crossing angleNominal crossing angle Push squeezePush squeeze Increase intensity to 50% nominalIncrease intensity to 50% nominal Performance limit 2 10Performance limit 2 103333 cmcm--22 ss--11

IV.IV. 25ns operation II25ns operation II Push towards nominal performancePush towards nominal performance

Page 21: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 21

Stage I physics runStage I physics run

Start as simple as possibleStart as simple as possible

Change 1 parameter Change 1 parameter (k(kbb N N **1 , 51 , 5)) at a timeat a time

All values for All values for nominal nominal emittanceemittance

7TeV7TeV

10m 10m * in point 2 (luminosity looks fine)* in point 2 (luminosity looks fine)

Rates in 2Rates in 2Rates in 1 and 5Rates in 1 and 5Beam levelsBeam levelsParametersParameters

0.770.77

0.150.15

0.150.15

0.150.15

<< 1<< 1

<< 1<< 1

Events/Events/

crossingcrossing

2.2 102.2 1031313.93.91.1 101.1 10323216161.4 101.4 1013132299 10101010156156

4.4 104.4 1030300.760.762.2 102.2 103131776.2 106.2 101212224 104 101010156156

1.2 101.2 1030300.760.766.1 106.1 103030221.7 101.7 101212224 104 1010104343

1.2 101.2 103030<< 1<< 16.8 106.8 102929221.7 101.7 10121218184 104 1010104343

7.7 107.7 102828<< 1<< 14.2 104.2 1028280.50.54.3 104.3 1011111818101010104343

1.8 101.8 102727<< 1<< 1101027271010--221 101 10101018181010101011

LuminosityLuminosity

(cm(cm--22ss--11))

Events/Events/

crossingcrossing

LuminosityLuminosity

(cm(cm--22ss--11))

EEbeambeam

(MJ)(MJ)

IIbeambeam

protonproton

* 1,5* 1,5

(m)(m)

NNkkbb

FfkN

Ln

b*

2

4

fk

LCrossEventrate

b

TOT/

Protons/beam ? 1013

(LEP beam currents)

Stored energy/beam ? 10MJ(SPS fixed target beam)

Page 22: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 22

Stage II physics runStage II physics run FfkN

Ln

b*

2

4

Rates in 2 and 8Rates in 2 and 8Rates in 1 and 5Rates in 1 and 5Beam levelsBeam levelsParametersParameters

0.760.76

0.150.15

0.150.15

0.150.15

Events/Events/

crossingcrossing

1.3 101.3 103232771.2 101.2 10333394948.4 108.4 1013131199 10101010936936

2.6 102.6 1031311.41.42.5 102.5 10323242423.7 103.7 101313114 104 101010936936

2.6 102.6 1031310.730.731.3 101.3 10323242423.7 103.7 101313224 104 101010936936

2.6 102.6 103131<< 1<< 11.5 101.5 10313142423.7 103.7 10131318184 104 101010936936

LuminosityLuminosity

(cm(cm--22ss--11))

Events/Events/

crossingcrossing

LuminosityLuminosity

(cm(cm--22ss--11))

EEbeambeam

(MJ)(MJ)

IIbeambeam

protonproton

* 1,5* 1,5

(m)(m)

NNkkbb

Relaxed crossing angle (250 Relaxed crossing angle (250 radrad)) Start unStart un--squeezedsqueezed Then go to where we were in stage IThen go to where we were in stage I All values for All values for

nominal nominal emittanceemittance 7TeV7TeV 10m 10m * in points 2 and 8* in points 2 and 8

Protons/beam ? few 1013

fk

LCrossEventrate

b

TOT/

2

*21/1

zcF

Stored energy/beam ? 100MJ

Page 23: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 23

Stage III physics runStage III physics run FfkN

Ln

b*

2

4

0.240.241.2 101.2 1032323.63.61.9 101.9 1033331571571.4 101.4 1014140.550.555 105 10101028082808

1.21.26.5 106.5 1032321919101034343623623.2 103.2 101414NominalNominal

0.240.241.2 101.2 1032321.11.15.9 105.9 1032321571571.4 101.4 1014142255 1010101028082808

0.240.241.2 101.2 1032322.12.11.1 101.1 1033331571571.4 101.4 101414115 105 10101028082808

Rates in 2 and 8Rates in 2 and 8Rates in 1 and 5Rates in 1 and 5Beam levelsBeam levelsParametersParameters

0.150.15

0.150.15

Events/Events/

crossingcrossing

7.9 107.9 1031310.720.723.8 103.8 1032321261261.1 101.1 101414224 104 10101028082808

7.9 107.9 103131<< 1<< 14.4 104.4 1031311261261.1 101.1 10141418184 104 10101028082808

LuminosityLuminosity

(cm(cm--22ss--11))

Events/Events/

crossingcrossing

LuminosityLuminosity

(cm(cm--22ss--11))

EEbeambeam

(MJ)(MJ)

IIbeambeam

protonproton

* 1,5* 1,5

(m)(m)

NNkkbb

fk

LCrossEventrate

b

TOT/

Nominal crossing angle (285 Nominal crossing angle (285 radrad)) Start unStart un--squeezedsqueezed Then go to where we were in stage IIThen go to where we were in stage II All values for All values for

nominal nominal emittanceemittance 7TeV7TeV 10m 10m * in points 2 and 8* in points 2 and 8

Protons/beam ? 1014

2

*21/1

zcF

Stored energy/beam = 100MJ

Page 24: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 24

Breakdown of a normal year

Page 25: Status of the LHC Project Lyndon Evans Journées de Physique ATLAS France Autrans, 29 March 2006

L.R. Evans 25

Conclusions

• All key objectives have been reached for the end of 2005

and installation is now proceeding smoothly.

• Half of the machine has been liberated for magnet

installation and is proceeding in 3 octants in parallel.

Magnet installation is now steady at 20/wk and will ramp

up to 25/wk next month. Installation will finish end

February 2007.

• Interconnect must now ramp up to plateau of 30/wk for

the ring to be closed by spring 2007.

•We will make every effort to have a first run in 2007.